MESSENGER: Mission Operations in Orbit at Mercury

Size: px
Start display at page:

Download "MESSENGER: Mission Operations in Orbit at Mercury"

Transcription

1 A. B. Calloway, R. G. Shelton, and E. D. Melin MESSENGER: Mission Operations in Orbit at Mercury Andrew B. Calloway, Richard G. Shelton, and Eric D. Melin ABSTRACT The orbital operations phase of the MErcury Surface, Space ENvironment, GEochemistry, and Ranging (MESSENGER) mission was stunningly successful, with >4 Earth years or nearly 18 Mercury years of uninterrupted activities without a single safing event in arguably one of the harshest operational environments in the solar system. The spacecraft returned >277,000 camera system images and millions of spectra and laser altimetry measurements, all while safely conducting 19 orbit-correction maneuvers, including a two-part adjustment in orbit period from 12 to 8 h. The team s long list of achievements included actively managing solar-array positions, heater settings, and spacecraft pointing on a weekly basis as well as conducting trailblazing helium-pressurantonly maneuvers at the end of the mission, plus an onboard clock rollover, >200 ephemeris builds, and 180 propulsive commanded reaction-wheel momentum unloading sequences over the 4105 orbits. This remarkable success can be attributed to the combination of substantial preparations and practice during the cruise phase of the mission, close collaboration and continuous communication among all of the project team members, and establishment of a reliable and repeatable cadence of flight activities and deliverables with few deviations except as required to work around geometry-driven events such as superior solar conjunctions and the evolving thermal challenges of each successive Mercury year. INTRODUCTION The MErcury Surface, Space ENvironment, GEochemistry, and Ranging (MESSENGER) mission, the first spacecraft orbital mission to the innermost planet, was known for safe and efficient operations from orbit. We provide here an overview of the preparations, processes, tools, and philosophies that enabled successful orbital mission operations. Topics include the pro active readiness approach taken during the 6.6-year cruise phase, ranging from the experience and practice of the six planetary flybys, to the building-block approach of day-in-the-life to week-in-the-life (WITL) to multi- WITL workshops that incrementally expanded objectives, to in-flight proof-of-concept tests. We also focus on the communications that were crucial to mission success, including weekly meetings and the products that were produced, reviewed, and disseminated among the team members, as well as the dual preliminary design review/critical design review approach to critical event 14

2 MESSENGER: Mission Operations in Orbit at Mercury planning. Most importantly, we describe what recurring activities were performed from the perspectives of real-time and mission planning operations. The MESSENGER team met all these challenges by maintaining consistency and rigor while not shying away from continually implementing innovations, revising techniques, enhancing reports with content and format, and updating ground system tools and scripts that together increased science return safely as resources were reduced through the extended mission phases. CRUISE-PHASE PREPARATIONS FOR THE ORBITAL PHASE The operations team worked closely with the science planning team and the ground system and software development teams to implement the tools and procedures for Mercury orbit, including interface control document revisions. The team also took full advantage of the three Mercury flybys and proactively pursued flight software upgrades for the instruments and the main processor (MP) that would benefit orbit-phase operations. A key component to orbit readiness involved a comprehensive building-block test program that broadened from days in the life to WITLs, culminating in a 4-consecutive-WITL test. These tests confirmed plans and readiness for the weekly cadence, and the orbital phase was in many respects treated as an entirely new mission from the cruise phase. The science team also generated 52 weekly test command loads that were gradually run through the operations faster-than-real-time StateSim constraint checking tool in what the team dubbed year-in-the-life validation testing. Lastly, to ensure readiness after Mercury orbit insertion, a series of orbit-phase concept-of-operations reviews were held for each spacecraft subsystem. These reviews were complemented by detailed planning for the first two command loads after orbit insertion and contingency planning for dealing with potential differences in post-insertion orbit parameters from those planned, including quickturnaround rebuild options and time-biasing strategies. Several in-flight tests were conducted in the later stages of the cruise phase to ensure readiness for orbit operations and adequacy of the tools and planned staffing levels. This testing was above and beyond the development and fine-tuning of instrument operations concepts and sequence building blocks on the basis of lessons learned from the three Mercury flybys. Many projects shy away from conducting such flight tests, but the MESSENGER team felt that specific tests would benefit from actual flight conditions in situations where hardware simulator runs could not provide sufficient confidence because of reduced fidelity or emulated behaviors. A good example was a progression of battery performance flight tests that culminated in a long eclipse/hot-pole flyover/highest charge rate end-to-end test, modeling an orbit at Mercury. Such tests helped ensure that there were no late surprises to operations planning that could have significantly changed thermal and power management, including instrument power cycling. A new automated strategy for conducting commanded momentum dumps (CMDs) had also been identified, and it was essential to verify that process in flight because the procedure would be used weekly through the orbital phase. Another orbit concept that benefited from in-flight testing was a new scheme involving downlink rate stepping during Deep Space Network (DSN) tracking passes. When the concept was first envisioned in the cruise phase, it was unclear whether downlink interruptions at the steps would last seconds or minutes. By conducting flight tests in 2010, the team was ready to optimize the downlink during the orbital phase, tracking the DSN antenna elevation profiles. Details were ironed out before orbit operations thanks to those flight tests, including the number of steps needed to institute, how close to the end of a track to place them, and how to tune the CCSDS (Consultative Committee for Space Data Systems) File Downlink Protocol (CFDP) settings to minimize data-gap retransmissions. An Earth acquisition rotation RF characterization test was also conducted to ensure that the team practiced and knew what to expect for demotion contingency situations. The most significant flight test was conducted in the final week of August This was a composite test compressing WITL activities in time, including solar array, heater, and power setting management. The team opted to trick the onboard software with a modified ephemeris to simulate a spacecraft orbiting Mercury in a manner that was realistic yet would not impose undue risk to the spacecraft. The team also opted to institute planned orbital phase states while still in the cruise phase for trending and experience. For example, in November 2010 the accelerometers were powered on and left running for the remainder of the mission, and the cadence of weeklong command loads began before orbit insertion. Each of the instruments was updated at least once with a flight software load, enhancing the capabilities for orbit-phase operations in some way. For example, the data processing unit (DPU) was updated with new command capabilities for image snaps and pivot steps, considerably reducing the overall number of commands that would be required in orbit. Even the MP software was updated with a crucial load in The MP memory map was originally partitioned with 256 time-tag bins, 900 small macros, and 124 large macros. The number of time-tag command slots was increased to 512 because testing revealed that 256 would be insufficient. An additional 20 large macros were also added by taking memory space from unused autonomy bin space. These changes increased the effective size of each command load resident in the MP, a step that was essential to the success of the orbital phase. 15

3 A. B. Calloway, R. G. Shelton, and E. D. Melin COMMUNICATIONS: MEETINGS AND REPORTING PRODUCTS Timely and effective communications were one of the primary keys to the success and safe operations of the MESSENGER mission. This task was accomplished by the institution of several key recurring meetings, a rigorous preliminary design review/critical design review template approach to critical events planning, and quick responsiveness whenever any issue came up that affected the contents or schedule of a weekly command load. The four primary team meetings during the orbital phase were the weekly mission status meetings run by the mission operations manager (MOM), the Science Planning Group meetings led by the payload operations manager (POM), the power and thermal Mercury season planning meetings led by the operations power lead, and the command load review meetings led by the mission planners from the operations team. Secondary meetings included anomaly review and closure meetings co-led by the MOM and mission systems engineer, Configuration Change Board meetings led by the mission systems engineer, and planning meetings between the POM and the development and implementation team for the SciBox science acquisition planning tool (reference the Related Literature section), plus many other intra-team-level meetings. Every nonroutine, first-time, or critical event was assigned a preliminary design review/critical design review schedule, and all element leads were tasked to provide applicable charts for detailed walk-throughs in an internal peer review forum, including actions and test plan review. This adherence to process and schedule was a key component to safely conducting so many nonroutine events in orbit such as propulsive maneuvers, an onboard clock rollover, special calibration activities, and end-of-mission activities, to name a few. Several important products were used for team-wide communications and information exchange, some of which were manually maintained and some of which were distributed by software such as cron jobs. These products included a daily mission timeline and a timetag bias notification with historical trends and look-ahead predictions maintained by the MOM, file directory snapshots and hourly downlinked file lists, DSN track working schedules, as well as weekly reports and monthly presentations. The monthly reports captured information from all of the element leads, including propellant consumption statistics and solar-array degradation trends. Seasonal boundaries for solararray offset positioning changes and instrument state changes were also publicized in table form, partitioned by dates and by high and low Mercury true anomaly thermal seasons. Other products included clock drift history and prediction plots (which eventually incorporated relativistic effects accounting for proximity to the Sun), Spacecraft Planet Instruments C-matrix Events (SPICE) meta-kernel trajectory update notifications with priority ordering overlay specifications, and attitude prediction and history reports. The latest attitude data status was defined in a SPICE meta-kernel and composed of attitude history from downlinked engineering files, short-term weeklong attitude predictions based on StateSim output reports, and long-term predictions based on the most recent science planning outputs from guidance and control (G&C) and SciBox. The navigation team required the weekly attitude updates for orbit determination. Every week a predicted solid-state recorder (SSR) file playback list was delivered to and ingested at the Science Operations Center so that alarm messages would go out if a file was flagged as missing 72 h after the predicted downlink time. Orbit event files produced by the mission design team were ingested by the operations planning system to populate the command loads properly. Periapsis crossing time tables were provided by the navigation team for operations time-tag biasing calculations. DSN station allocation files were sent to the science developers for re-optimization runs along with recorder space snapshots to improve predictions of onboard SSR loading. The science developers, in turn, delivered optimal DSN track requests that the MOM tried to match as closely as possible. Command and data handling engineers were notified of onboard correctable single-bit errors. The operations team notified instrument teams when instrument memory dumps revealed comparison mismatches to correct potential single-event upsets via patch or power cycle. ListServs were created, including an overall operations distribution list and a SPICE users list. REAL-TIME OPERATIONS AT MERCURY Mission operations is the hub of any planetary space mission, interfacing with all team members on a project, including navigation, mission design, subsystem engineering, science planning, science operations, ground systems engineering, the DSN link controllers and engineering support, and project management, among others. The MESSENGER operations team was divided into three focus areas: real-time flight control operators, mission planners, and spacecraft/payload systems engineering analysts. With a lean core team of just 15 personnel, several of whom were part-time later in the mission, the operations team members continuously cross-trained so that every role and deliverable procedure had a fully trained backup who periodically practiced the primary cross-training tasks to ensure currency. A steady progression of task streamlining and automation implementation was also conducted over the course of the 4 years to accommodate extended mission downsizing. 16

4 MESSENGER: Mission Operations in Orbit at Mercury The flight control team consisted of a lead flight controller (FC) and individuals who worked in shifts of two, aligned with the DSN track schedule. Support was eventually reduced to single-person coverage for the extended missions, and the operations team analysts served as the second set of eyes for all nonroutine subsystem-led activities. The flight control team interfaced with the DSN personnel for communications and troubleshooting when necessary; to monitor spacecraft health and produce logs, reports, and plots; and to send commands for planned tasks. There was little turnover over the years, but any new flight control team member had to undergo a training and checkout period culminating in a series of proficiency demonstrations charted by a detailed training checklist. The lead FC was responsible for maintaining the shift and coverage schedule and training for the flight control team. The flight control team was also responsible for setting up the Mission Operations Center (MOC) whenever there was a planned critical event such as a maneuver, and for maintaining the MOC equipment and facilities. This role included performing voice checks of all MOC communications boxes before arrival of all of the support engineers, configuring each workstation for telemetry flow with a load-balancing checklist, and setting up the overhead screens with appropriate displays and timelines. The operations team also relied on ground monitoring software to ensure reliability and send alerts for thresholds on disk space, central processing unit usage, and related tasks. A backup MOC was configured in a separate building and was periodically used for real-time supports in order to maintain currency. As automation tools were incrementally brought online, including limit-violation s and texts, flight control team members eventually developed a rotating schedule that allowed them to observe night and weekend tracks from home. Experience and reliability eventually allowed the MOM to be comfortable with automated commanding on unattended weekend tracks by enabling CFDP concurrent with turning on the transmitter at the DSN so that file delivery protocol handshaking would close out transactions onboard throughout those tracks rather than letting the transactions accumulate until Mondays. Flight control team members were always ready to travel in should any glitch affect the uplink or downlink on a case-by-case basis. Such events happened infrequently, and the benefits of automation far outweighed those rare instances, particularly as flight control team members began to support other projects part-time. All of the flight control team members were cross-trained to fill supplemental roles for the mission analysts. For example, one of the FCs was responsible for command and telemetry database management. Another FC eventually became the command and data handling and CFDP lead for the operations team. Another was in charge of automation development and maintenance. These added responsibilities and cross-training were essential for keeping such a small team experienced and focused. RECURRING ACTIVITIES DURING THE ORBITAL PHASE Configuration control was a major factor in the success of the mission. Every new or revised procedure or display page underwent a testing and review process by a second person before MOM approval for placement into the production system. Standardized forms and databases were a key part of this control process, including MOCRs (mission operations change requests). Every command to the spacecraft underwent similar scrutiny, with two-person validation followed by questioning by the MOM. These commands were handled by MURFs (MESSENGER uplink request forms). In addition, a table of preapproved maintenance commands and procedures was maintained in the MOC for routine activities to be referenced as needed. Most orbit-phase tasks were performed on a recurring weekly cadence. For example, every Monday a G&C parameter block was delivered to the operations team, tested, and loaded to uniquely prepare for and target each Tuesday s weekly CMD. Mondays were also the weekly load transition days on the last hour of each DSN support, and confirmation of that transition was closely monitored. Tuesdays were not only the CMD days for reaction-wheel desaturation but were also the primary opportunities for loading the second half of each weekly command load. Wednesdays and Thursdays were the backup opportunities for loading the second half of the sequences. The weekly ephemerides were delivered on Thursdays, days when the following week s time-tag bias values were chosen by the MOM. Fridays were busy uplink days. The weekly spacecraft ephemerides were tested and loaded, along with the first half of the following week s command load. Fridays were also a second placeholder to conduct a CMD as needed. Each week, the MOM had to determine the order in which these critical long-duration uplinks should occur in order to maximize the use of the available DSN time. Saturdays and Sundays were backup days for the command load uplinks. All days included recorder playback with CFDP and routine maintenance activities such as refreshing the onboard command loss timer and conducting and reviewing engineering dumps and SSR directory listings. There were important activities that were less frequent or asynchronous, led by the mission analysts, such as solar-array off-pointing battery discharge characterization activities, G&C and power system parameter block updates, and activities associated with the orbit-correction maneuvers, such as the external precise oscillator deselections and reselections. Other examples included the memory object cyclical redundancy check and full dumps for ensuring that the hardware simulator was always synchronized with flight. 17

5 A. B. Calloway, R. G. Shelton, and E. D. Melin Command Load Uplinks The most important flight control task was to uplink each new command load twice a week for >4 years, nominally on Tuesdays and Fridays. Because each segment took h to radiate and the process had to be started from the beginning if even one uplink frame was dropped because of a transmitter or antenna pointing glitch, this activity was far from routine. This activity became even more complex when the segments were split into parts A, B, and C and had to be loaded across multiple DSN supports, to accommodate shorter tracks associated with the 8-h orbits. Each weekly sequence contained commands to off-point the spacecraft appropriately during each orbit while crossing over the hot planet, to avoid an autonomous safing and command load halting response to a hot-pole keep-out violation from thermal spikes off the sunlit side of the planet. If a command load ran out and the next half-load was not onboard and ready for the automatic hand-over, then the hot-pole keep-out condition would be violated during the very next orbit when the G&C and fault-protection tandem detected the hot planet crossing in the unsafe orientation. Similarly, a weekly ephemeris had to be loaded every Friday (with the weekends as backup opportunities) before the onboard ephemeris expired on Mondays, which would have caused the G&C system to throw a flag and request a safing mode demotion from the fault-protection system. Time-tag Biasing Each weekly command load uplink occurred 4 weeks after the science inputs were first compiled for that week. The orbit determination solution over those 4 weeks drifted and changed with perturbations, in particular the timing of predicted versus actual periapsis crossing times. As a result, a time-tag biasing strategy was developed to optimize command timing for improved instrument pointing that accounted for those multi-week drift conditions. The operations team worked with the navigation team to develop and receive a weekly summary of orbit periapsis crossing times spanning 5 previous weeks, parsed in a columnar fashion. By subtracting the most recent periapsis crossing times with that of 3 and 4 weeks prior and then calculating an average change over the course of a calendar week of orbits, two biases were calculated and published on a weekly basis. These biases could be either positive or negative integer seconds. The first bias value covered the Friday through Monday of the currently executing load, which was a week older than the one that would take over on that subsequent Monday. Those Friday biases were loaded in real time once the new ephemeris was confirmed onboard. The Monday bias adjustment would be valid Monday through the following Friday. That bias was always loaded on Friday in the form of a macro to be called on board at the start of each new command load. Instrument commands executing out of the DPU were not subject to the biasing shift, however. As a result, the DPU memory space was used only when necessary for MP command volume reasons, and there was heightened awareness to place those commands at times when it was unlikely that a real-time bias change could affect an observation in undesirable ways, such as changing the relative timing or order between MP and DPU commands from the same observation activity. Timetag biasing also had a major impact on management of the DSN key word files. Because the biasing affected only onboard commands, DSN key word files had to be actively managed to ensure that each week s biases were properly captured with the interleaving of ground-relevant commands that were not affected by the bias and those that were directly tied to spacecraft RF commands, to ensure that the proper order was always maintained. This task could be particularly tricky when there were large negative time-tag biases. Large biases did occur around major events such as superior solar conjunctions and orbit-correction maneuvers; otherwise, values were typically only in the tens of seconds rather than minutes. Telecommunications Planning Tailoring the RF communications system was also a large part of recurring orbit operations. Placeholder downlink rates were provided well in advance to the mission planners for the command load builds. As actual DSN tracks firmed up, the placeholder downlink rates were replaced with optimized rates tailored for each specific DSN antenna, some of which were significantly better than others. The RF lead would also analyze whether downlink rate stepping should be applied to any tracks in that command load sequence, on a seasonal basis, and would sit down side by side with the mission planners when it came time to insert all of that information into the baseline sequences. CFDP allowed for a more aggressive downlink margin posture, enabling the operations team to reduce the required downlink margin from 3 db to nearly 0 db. This change alone nearly doubled the downlink capacity of the mission overall. CFDP was an enabler for the rate-stepping strategy because it automatically requested retransmissions of the dropped data during the brief rate-change dropouts. The RF lead also needed to determine uplink rate and, in particular, the specific track on which that rate should change between 125 and 500 bps. There were also orbit geometries when the 70-m antennas could not be used because of solar aberration, and the RF lead had to keep track of those seasons as well. In addition, there were seasons when the solid-state power amplifiers on board had to be powered off for power and thermal management reasons, and the RF lead worked closely with the power and thermal engineers to coordinate the timing of such changes and ensure the proper configurations. 18

6 The RF lead also worked very closely with the radio science team members. The radio science team provided seasonal requirements to the MOM regarding when to collect additional per-orbit data by scheduling DSN tracks in alignment with periapsis crossings and Earth occultation ingress and egress times. The RF lead then had to determine when to place low-gain antenna (LGA) switching commands outside of high-gain antenna (HGA) times as the spacecraft slewed collecting science data, to best ensure a retention of signal lock during the additional LGA DSN coverage. Depending on geometry, some seasons required only one LGA configuration, but other seasons required multiple LGA swaps between a single pair of HGA tracks. Those seasons were more complex not only because of the additional analysis required but also because of the added command volume and the much larger and more involved DSN key word file builds and quality checking reviews. The RF lead worked closely with the G&C team and the DSN network operations engineers as the Sun probe Earth angle changed with time. On a seasonal basis, the onboard phased-array model parameter block had to be toggled in coordination with spacecraft rotation to the opposite quadrant for Earth-pointing communications with the electronically steerable phased-array antenna, and a specific pre-track time had to be proposed and agreed upon. The DSN also then had to be notified about that timing and told to expect a different frequency consistent with the opposite transponder characteristics for the next track after the change. The RF lead also worked with the DSN in support of maneuvers, to choose appropriate carrier loop bandwidth settings for the receivers to best maintain lock through the maneuver. The RF lead also notified the DSN when thermal environmental effects changed the best-lock frequency beyond a predefined threshold, typically ±1000 Hz, to warrant an update at the DSN. This strategy was used so that the MESSENGER team did not need to conduct RF sweeps to reacquire OPENED on SC signal after occultations or outages. As long as the best-lock frequency was tightly maintained as described, then the no-sweep concept of operations could be used, greatly simplifying operations in support of MESSENGER automation and reliability. MESSENGER: Mission Operations in Orbit at Mercury fast and a slow rate at known points in each orbit, should an Earth acquisition demotion occur. The fast rate was implemented for thermal mitigation reasons, and the slower rates were the windows where operations could intervene and recover the spacecraft back to operational mode. The placement of those rule triggers had to be modified after each orbit-correction maneuver because the orbit parameters had just changed. This activity was performed throughout the primary mission after maneuvers. Fortunately, the team never had to exercise a recovery from Earth acquisition in orbit, even though the team continually planned for and was ready to do so at any time. Other fault-protection changes were tailored for orbit as well, including automatic star tracker reset recovery commanding and thermal and power threshold monitoring response rules that adjusted solar-array positions, as well as autonomous mid-maneuver fuel tank switching logic. CFDP AND FILE SYSTEM USE IN ORBIT The MESSENGER spacecraft was the first developed by the Johns Hopkins University Applied Physics Laboratory (APL) to use an onboard file system for data collection. APL spacecraft prior to MESSENGER stored data sequentially to a random-access memory-based SSR and then downlinked blocks of memory using read/ write pointers. Transmission dropouts or communication errors in those spacecraft were manually corrected (when they could not be tolerated) by commanding the recorder to replay the section of missing data. The decision to adopt a file-based system for MESSENGER was driven by predictions of a limited downlink bandwidth from the spacecraft, limited onboard processing power (insufficient central processing unit available to compress images during data capture), and the need to compress images to meet data-return requirements. An additional rationale for using a file system was the need 1. Metadata information (trans ID, size, etc.) 3. EOF PDU 2. Data PDUs EOF received PDU (ACK) 5. Missing PDUs, including metadata (NAK) OPENED on ground MOC Fault Protection An operational fault-protection scheme was devised for orbit operations that triggered Fault Protection Processor (FPP) autonomy rules at designated orbit true anomaly points in order to change the spacecraft rotation rate between a CLOSED on SC 5a. Retransmissions (if any) 6. File finished PDU (FIN) Only sent after file successfully assembled 7. FIN acknowledgment CLOSED on ground Figure 1. MESSENGER deferred NAK CFDP transaction. ACK, acknowledgment; PDU, protocol data unit. 19

7 A. B. Calloway, R. G. Shelton, and E. D. Melin to record contingency housekeeping information with the intention to rarely or never downlink it. The file system architecture selection drove the need to define a protocol for downlinking files and managing the file system. In orbital operations, there was typically a range of 5- to 12-min one-way light-time delays between the ground stations and the spacecraft. The CCSDS developed a protocol called CFDP to specifically address single-endpoint file transfer needs for deepspace missions. The CFDP provides capabilities for file transfer and file system management commands such as delete, move, and copy similar to File Transfer Protocol. It is designed to minimize bandwidth usage and round-trips between communicating entities and is fully configurable to support different mission phases or operations concepts. MESSENGER used the reliable (Class 2) communications with deferred negative acknowledgment (NAK) shown in Fig. 1. In this configuration, metadata information about a transaction is sent, followed by the file data and an end-of-file (EOF) indication. If any data were missed, the ground system issued a NAK request to retransmit the missing chunk of data. A transaction was completed when both the flight and ground system confirmed successful delivery. The protocol also includes timers to resend EOF, NAK requests, and finished (FIN) messages to guarantee efficient reliable delivery with the minimal amount of messaging. Only reliable deferred NAK transactions were implemented, and file system operations were handled externally to the protocol. The MOC ground software team originally chose to incorporate a CFDP implementation from the Jet Propulsion Laboratory. Years later during flight operations, the MOC software team replaced the Jet Propulsion Laboratory CFDP executable implementation with a C language CFDP library provided by NASA Goddard Space Flight Center (GSFC), which was more manageable and conducive to orbit operations. Some extensions to the base CFDP functionality were made to better support MOC operations as enhancements to the GSFC library. All ground-software modifications were developed by APL and provided to GSFC for potential inclusion in future releases. One key need was the ability to ensure that transaction states across a MOC command workstation reboot or even a failover to the backup MOC command workstation persisted. APL also implemented a pause-and-resume timer functionality to avoid sending unnecessary NAKs due to active timers outside of DSN tracks. This step enabled tighter timer settings for more expedient file deliveries. Lastly, a light-time setting was added to the CFDP library. This addition allowed the base transaction timers to have a consistent value but allowed the actual time between retransmission requests to vary on the basis of current light-time values. The operation of the protocol lent predictability and timeliness to the data downlink and made it easier for the science teams to track their data status. SPECIAL ACTIVITIES DURING THE ORBITAL PHASE Although the team strove to maintain consistency and repeatability during the orbital phase as much as possible, MESSENGER was a mission of exploration, and it was understood that new information and new questions drove changes, especially for the extended missions. As such, special requests and accommodations were considered. Some were rejected, but most were approved. The orbit-phase concept-of-operations architecture was designed with flexibility so as to accommodate such requests, including specialized command sequences and changes in recorded data volume handling. Good examples of this flexibility included the ability to observe comets Encke and ISON, to collect Faraday rotation data from radio transmissions through the solar corona during solar conjunctions, and to conduct a delta-differential one-way ranging DSN observation request by NASA Headquarters near the end of the mission. Other accommodations included a substantial modification of the downlink priority scheme for the last extended mission and a request by the radio science team to add a multi-week campaign of short DSN supports aligned with Mercury periapsis crossings, which required broad negotiations with other missions across the DSN community. MISSION PLANNING IN ORBITAL OPERATIONS Command Load Building The ultimate goal each week for the mission planners was to produce a safe and optimized command load that merged spacecraft engineering and housekeeping activities with payload data acquisition. Table 1 depicts a typical command load build schedule, with a three-person staggered rotation for shepherding those loads through the 2-week pipeline from build to merge to uplink. The load names were defined in a yyddd format. The command loads were nominally compiled as one Monday-to- Monday week, transitioning daisy-chain style in the last HGA hour of the Monday DSN tracks. Unfortunately, the weekly loads had to be split into two half-week upload segments because there were far too many commands in 1 week to fit in onboard memory, even after pre-orbit software enhancements. The location of the split was defined to be Thursdays or Fridays, chosen to balance, at least approximately, the number of commands in each half and to allow at least two real-time opportunities to load each segment to the spacecraft, avoiding weekends. The mission planners chose the split location on the basis of the actual track lengths and half-load sizes. The split choice was usually straightforward but occasionally had to be made in consultation with the MOM, who made the final call on the basis of whether other activities planned for uplink days could be in conflict or a particular week was very close to uplink availability margins regardless 20

8 Table 1. MESSENGER representative 2014 mission planner command load build schedule Week YYDDD Mon Tue Wed Wed Wed Thu/Fri Fri Build Load Finish Load CLR SPG of choice. With this vulnerability and concern in mind, the MOM worked closely with the DSN scheduler weeks in advance on a weekly basis to minimize those tough choices. The MOM negotiated with other missions to gain the best combination of daily tracks, track lengths, and station antenna diversity to ensure a successful load segment uplink before the current load segment ran out. As shown by a representative week in Table 1, the operations team built the initial schedules each week on Wednesdays, incorporating the finalized DSN tracks. The planners also added in engineering activity blackout placeholders for science to work around and defined one of the double Tuesday and Friday tracks to be that week s blackout track for CMDs. Science operations was notified of initials readiness via the JIRA software tool. By Friday of the following week, the science and G&C teams delivered their constraint-checked and error-free instrument and G&C sequences to the planners. Occasionally G&C analysis showed that a science slew should be decomposed into two smaller slews for safety to avoid potential thermal keep-in zone overshoot. The instrument teams and G&C engineers also updated their review and notification steps in JIRA. The planner then started the command load build process by merging the initials and all of the science (one per instrument) and G&C inputs. The following Monday and Tuesday were then used to finish building that command load and to check the results using a suite of reports from mission operations software, including StateSim, a software simulator, and custom scripts. A second planner always performed independent checks on the load. The POM MOps Initials Re-Run SS Start Load 6 Oct Oct Oct Oct Nov Nov Nov Nov Dec Dec Dec Dec Dec Yellow, planner 1; green, planner 2; blue, planner 3. CLR, command load review; SPG, Science Planning Group; SS, StateSim. MESSENGER: Mission Operations in Orbit at Mercury served as the liaison between the operations and payload teams to keep the pipeline flowing and help resolve any delays or issues. Fridays through Tuesdays provided sufficient margin for the few cases in which the science input deliveries had to be delayed to keep the pipeline moving. When the operations team finalized a load, the science teams and G&C were tasked to review a set of reports, and a mission analyst would perform the uplink on the hardware simulator to ensure there were no issues with the product itself or the load splitting. The following Wednesday, the operations team gathered for the official command load review for that load, led by that load s shepherding mission planner. This meeting was the last opportunity for the team to review the comprehensive set of reports in a consistent way each week and for any final questions or discussions before the MOM would approve and sign the uplink form for that load or, on rare occasions, send it back for a modification. Wednesdays were also Science Planning Group meeting days, led by the POM, where future command load decisions and data-retrieval issues would be discussed and worked out. The operations team was well represented at those meetings. Lastly, on Thursdays or Fridays, the mission planner resynchronized the StateSim SSR model with the onboard SSR state each week. The mission planner reviewed the downlinked directory listing files and made adjustments to the StateSim model to agree with the real SSR when necessary, such as accounting for a DSN pass outage or images that were larger than predicted because of elevated temperature fluctuations in a charge-coupled device. Planning the Command Loads The mission operations team used the MESSENGER DSN track schedule to build the sequence generation software (SeqGen, from the Jet Propulsion Laboratory) requests for the HGA passes. These requests included maintenance activities and placeholders for burn events. The maintenance requests were validated by SeqGen flight rules and models and by a second-person manual verification checklist procedure. Once the initial requests were verified, a mission operations initial request file was delivered and a notification was sent to the POM and the science teams via JIRA. 21

9 A. B. Calloway, R. G. Shelton, and E. D. Melin Each science team s SciBox output was run through SeqGen with the flight rules and behavior models in order to validate the science requests. The valid science request files from each instrument sequencer were then passed on to the POM. The POM took the initial request file and all the science request files and merged them in SeqGen, looking for conflicts between the operations team requests and the overall science team requests plus conflicts between the science team requests, as early in the process as possible. The POM was provided preapproved shared-resources details such as SSR allocations and attitude ownership timing. Resource conflicts were resolved by returning requests to the instrument team for corrective action and resubmission. Once all conflicts were resolved and the merged requests were validated using SeqGen flight rules and models, those requests were then reviewed by the instrument engineers for health and safety verification. If any problems were discovered, the instrument requests were returned to the appropriate team for correction. The process repeated until all instrument engineers and the POM were confident they had a safe and clean product. It was seldom required, but the POM and MOM had authority to pull a problematic sequence from a load altogether if a timely resolution could not be achieved, so as not to risk delaying the process to the point of a missed uplink, because that was a spacecraft demotion risk. The approved science request files were delivered to the operations directories. The mission planners merged each week in SeqGen the delivered requests with the latest version of the initial requests. Those updates typically included any late changes to the DSN track schedule and updated burn requests from mission design. The planners occasionally had to adjust science requests in coordination with the POM in order to conduct the activities within the revised spacecraft resources (e.g., memory, power, SSR space, spacecraft attitude). Once a set of requests passed the SeqGen system-level verification, the mission planner built the command load in the uplink format and subsequently performed a second level of verification. MP macro memory (900 small, 144 large) Onboard blocks Weekly load N Weekly load N + 1 Weekly load N Weekly load N + 1 Building the Stored Command Sequences SeqGen produced the ASCII spacecraft sequence file (SeqGen output, or SeqOut), which was the translation of the canned sequences into individual commands in time order. Next, the APL SeqPost program grouped the commands into transient macros and stored time-tag DPU macro memory (256 bins) Onboard blocks Weekly load N Weekly load N + 1 EPU macro memory (256 bins) Onboard blocks Figure 2. MESSENGER onboard memory allocations for mission planning. commands. SeqPost constructed macros on the basis of commands listed in time order for both the spacecraft and the instruments, and it eliminated duplicate macros for efficient use of onboard memory. A command load driver file was created to define the macros and time-tag commands, and a load script was created for use with the binary portion of the command load, which was created later in this process. MP macros, commonly referred to as onboard blocks, were divided into two groups: semipermanent and transient. Semipermanent macros were loaded once to random-access memory and electrically erasable programmable read-only memory and used many times (with infrequent updates) for routine operations, including DSN track support and SSR operations. Transient macros were used and replaced with each active spacecraft load. Memory allocated for transient macros was divided in half so one range was updated while the other was in use with the active command load. DPU memory had a similar architecture. For each command load, the mission planner decided whether or not to create DPU transient macros. This decision was based on the size of the command load. If the commands would not all fit into MP macros, a large part of the Mercury Dual Imaging System commands would be packaged into DPU transient macro space instead. The planning team had to keep track of the DPU transient memory and clear out the memory if the DPU transient macros were to be reused in a subsequent load. The loaded time-tags executed the transient macros at absolute times. There were 512 available time-tagged command slots for the orbital phase. When the current half-week set of timetags was exhausted, onboard autonomy loaded the next set of time-tag commands and expanded them into the bins for the next half-week of execution. Figure 2 shows the high-level onboard memory map allocations. 22

10 MESSENGER: Mission Operations in Orbit at Mercury Verifying the Stored Command Sequences After the conversion to uplink format, the command macros and time-tagged commands were loaded into the MESSENGER software simulator (StateSim). This process permitted an early faster-than-real-time checkout of the merged command sequence as it would be loaded and executed. StateSim modeled the loading of command macros and their time-tagged calls. Any problems in the command processing would be caught and reported via error and warning reports. An autonomy history report showed which autonomy rules tripped. StateSim modeled the spacecraft attitude on the basis of the attitude commands. StateSim computed attitude relative to the Sun line and targets of interest. Such a calculation was useful as a way to assess power and thermal conditions that the spacecraft would experience when executing the command load. The weekly ephemeris had to be loaded into StateSim for the proper Sun position computations. Command Load Sizes: Uplink Time Limitations and Splitting Each half-week command load could take 3 4 h to load depending on the Earth-range season, and operators had to start from the beginning if there was a transmission glitch. This happened several times during the cruise phase of the mission, when timing was more forgiving than in orbit. Therefore, the mission planning team designed a utility that could split a half-week further into parts A and B, to mitigate the need to complete a full uplink should there be a dropped frame or DSN error. If a frame was dropped during a part B load, then at least the reload would only have to start at part B and not all the way back at part A, potentially saving 2 h and eliminating the need to risk the uplink on the final load opportunity. This also happened several times in the orbital phase, justifying the utility s development. The real-time team was trained to run a special macro clear script for the specific case of loading a part B a second time because part A nominally contained all the precursor macro clear commands for the entire segment. To maximize the chance of success, the MOM published planning week 15123_1 (4 days long); 15123_2 (3 days long) Piece A Piece B 15123_1A and 15123_1B Weekly CMD load Part 1 Part 2 Piece A Piece B Piece C 15123_2A,15123_2B, and 15123_2C Figure 3. MESSENGER command load splitting strategy. a ratio directive each week on how large each A/B piece should be; the weekly was tailored to the specific DSN track durations and placement of flight activities within tracks that week. An additional complication was foreseen when the MESSENGER orbit period was reduced from 12 to 8 h. The HGA portion of the DSN tracks became shorter because of thermal constraints for Earth pointing in proximity to periapsis. Splitting a half-week into parts A and B was no longer sufficient for all cases. A modification had to be coded and tested to split a half-week load into three parts, A, B, and C. Using custom utilities and subjective experience, the MOM determined when a part C was warranted, as shown in Fig. 3; the MOM also determined the size of each segment and the times across multiple tracks during which the segments should be loaded, how they should be customized to fit within those tracks, and how to work around flight activities where commanding was not allowed, such as DSN station hand-overs and CMDs. Command Volume Efficiency Depending on the Mercury year and season, certain instruments, such as the Mercury Atmospheric and Surface Composition Spectrometer (MASCS), had to be powered off and on for thermal reasons during each orbit. Therefore, the mission operations team developed semipermanent MP and DPU macros for powering each instrument on and off. Each power on/off would cost only one command (an MP macro execute command) rather than bundling the equivalent number of commands per orbit for uplink within each command load. The operations team also developed a variable looping science macro strategy for two instruments. Those onboard macros could be repeated multiple times from one command, thereby realizing considerable uplink command volume savings. Custom reports were created to strip out the redundant loops for easier human review. The operations team also reviewed all of the subsystem commanding to determine whether repetitive commands could be identified and potentially replaced by semipermanent macros in the MP. For example, a macro was created to open the suite of daily files with just one execute command instead of 20 file-open commands. The operations and instrument teams similarly reviewed instrument command sequences to build macros, which worked well for the DPU and MASCS commanding. The instrument teams also looked for other ways to reduce command volume by small amounts, in situations where the sum total of small contributions was quite helpful. For example, several of the spectrographic instruments changed data-collection rates routinely at discrete parts of each orbit. Those teams were able to reduce the number of changes per day by having their instruments remain in coarser or finer data-sampling modes through- 23

11 A. B. Calloway, R. G. Shelton, and E. D. Melin out an orbit, thereby reducing the number of commands without degrading the science and without recording significant amounts of additional data. Telemetry Pipeline Management Onboard packet and image files were stored in 10 directories, P0 P9. Files were closed and new files were opened once per day via the command loads to keep file sizes manageable for reasonable playback durations. These openings were tied to tracks but were manually inserted in the rare cases when there was no track on a calendar day. Files that had been successfully downlinked were moved to the TRASH directory automatically. To recover space for new data, the command loads deleted trashed files that were older than 5 days, along with un-promoted P7 P9 files, daily. A file filter table managed by the operations team was used to map the spacecraft application IDs (APIDs) to the files. Each APID represented a different data type for the instruments and the spacecraft subsystems. The file filter table maintained a row for each APID, and each APID could be routed to two files. For each file, the priority, instance, and data-sampling rate were defined by operations. The two-file definition allowed for a small subset of data to be given high priority to support health and safety spot checks, while the larger data set would be given lower priority. The file filter table changed over the course of the mission, with major changes occurring when transitioning from the cruise phase to the orbital phase and from primary orbital phase to extended mission phases. File directory priority P0 P9 determined the order of file playback to the ground, as shown in Fig. 4, and was managed by the operations team in coordination with the science planning team. Default image locations were changed from P4 and split into P5 and P6 when data-collection science priorities changed. Files MESSENGER file system directories /REC: Files currently opened for recording /OPNAV: Critical OpNav images ready for compression /IMG: Images ready for compression /DNL: Files being downlinked /TRASH: Files ready to be deleted /P0: Critical OpNav images /P1: High-priority health and safety data /P2: Propulsion event data /P3: High-priority science and images /P4: Medium-priority science and images /P5: Medium-priority science and images /P6: Low-priority science and images /P7: Payload contingency data /P8: Autonomy spawned contingency data /P9: Subsystem contingency data Next track Future track No downlink guarantee Figure 4. MESSENGER onboard file priority scheme. from within the same priority directory played back by oldest onboard creation time first protocol. Mission planners were able to model the order and amount of SSR playback via StateSim and passed this information to the Science Operations Center for file downlink tracking purposes. Managing the data volume on the SSR was a continual process. The operations team (using StateSim) and the science team (using SciBox) independently modeled the volume of data on the SSR. The science allocation was conservative in the prime mission phase at 70% but was relaxed to >80% for the extended missions, when the risk of recorder saturation could be better tolerated. When the StateSim model predicted that the SSR might exceed 90%, the MOM conferred with the science team to obtain a second opinion and work out the mitigation strategy. If the onboard SSR ever reached 95%, it would stop recording until the percentage dropped again below that threshold. For long solar conjunctions of 5 days, when there would be no reliable contact with the spacecraft because of Sun interference, mission operations proactively worked with the science team and POM weeks in advance to reduce the number of images that would be taken and/or to selectively throttle the rate of the nonimage data collection in order to avoid the chance of recorder saturation. The science team implemented these data-reduction strategies into the science inputs for the loads that would execute during the conjunction periods. CONCLUSION Practice, communication, continual vigilance, optimization, and dedication were the hallmarks of each team within the overall MESSENGER project. In some respects, operating in such a hostile environment with an orbit that progressively changed in altitude and periapsis latitude in both sunlight and shadow worked to the team s benefit, because the team lived under heightened awareness at all times and complacency was never an issue. Because no two Mercury years were alike, all team members regarded each 88-day Mercury year as a new challenge, to be scrutinized and planned uniquely and in great detail, while maintaining consistency in processes and communications. That is a far different paradigm than operating in Earth orbit, for example, where environmental conditions tend to be similar from orbit to orbit, day to day, and year to year. As a result, the MESSENGER mission is considered by many to have one of the best returns on investment of the Discoveryclass missions. It is indeed hard to argue with that, given the data-return metrics, on-time Planetary Data System deliveries, the level of public engagement, the revised textbooks, and even a Mercury globe, none of which would have been possible without MESSENGER and the team s operational safety record. 24

12 MESSENGER: Mission Operations in Orbit at Mercury ACKNOWLEDGMENTS: We acknowledge all of the MESSENGER teams that supported operations. We extend a special thank you to our core operations team, including our mission planners, mission analysts, and superb realtime flight team. They all contributed in some way to the content of this article. We further extend a thank you to our ground system and network engineers, our navigation and mission design engineers, our mission systems engineer and subsystem engineers, our APL and NASA project management, our principal investigator and our science planning and instrument operations colleagues, our DSN partners, our media and public outreach members, safety and mission assurance team members, and of course the public; we truly accomplished something special the exploration of our innermost planet together as one family. McAdams, J. V., Solomon, S. C., Bedini, P. D., Finnegan, E. F., McNutt, R. L. Jr., Calloway, A. B., Moessner, D. P., Wilson, M. W., Gallagher, D. T., Ercol, C. J., and Flanigan, S. H., MESSENGER at Mercury: From Orbit Insertion to First Extended Mission, in Proc. 63rd International Astronautical Congress, Naples, Italy, paper IAC12-C1.5.6, pp (2012). Ord, K. J., and Hibbard, K. E., MESSENGER Power and Thermal Systems Operations, in Proc. SpaceOps 2010 Conf., Huntsville, AL, paper AIAA , pp (2010). Page, B. R., Bryan, C. G., Williams, K. E., Taylor, A. H., Stanbridge, D. R., Wolff, P. J., and Williams, B. MESSENGER Navigation Operations During the Mercury Orbital Mission Phase, Adv. Astronautical Sci. 148, (2013). RELATED LITERATURE Bedini, P. D., Solomon, S. C., Finnegan, E. J., Calloway, A. B., Ensor, S. L., McNutt, R. L., Anderson, B. J., and Prockter, L. M., MESSENGER at Mercury: A Mid-term Report, Acta Astronaut. 81(1), (2012). Berman, A. F., Domingue, D. L., Holdridge, M. E., Choo, T. H., Steele, R. J., and Shelton, R. G., Orbital Operations Planning and Scheduling for the MESSENGER Mission, in Proc. Sixth International Workshop on Planning and Scheduling for Space, Pasadena, CA, pp (2009). Choo, T. H., Murchie, S. L., Bedini, P. D., Steele, R. J., Skura, J. P., Nguyen, L., Nair, H., Lucks, M., Berman, A. F., McGovern, J. A., and Turner, F. S., SciBox, an End-to-End Automated Science Planning and Commanding System, Acta Astronaut. 93, (2014). Cooper, S. B., A Practical Application of Relativity to Observation and Control of MESSENGER Timekeeping, Johns Hopkins APL Tech. Dig. 32(1), (2013). Cooper, S. B., From Mercury to Pluto: A Common Approach to Mission Timekeeping, IEEE Aerosp. Electron. Syst. Mag. 21, pp , (2006). Flanigan, S. H., O Shaughnessy, D. J., and Finnegan, E. J., Guidance and Control Challenges to the MESSENGER Spacecraft in Achieving and Operating from Orbit at Mercury, in Proc. 35th Annual AAS Guidance and Control Conf., Breckenridge, CO, paper AAS (2012). Holtzman, G. A., Begley, S. M., and Ercol, C. J., Return to Mercury: An Overview of the MESSENGER Spacecraft Thermal Environmental Predictions and Analysis Process, in Proc. International Conf. on Environmental Systems, Bellevue, WA, paper ICES , pp (2015). Hudson, J. F., and Colwell, E. J., Spacecraft Clock Maintenance for MESSENGER Operations, in Proc. AIAA Space 2011 Conf. & Exposition, Long Beach, CA, paper AIAA , pp (2011). Kochte, M. C., Sepan, D. M., and Shelton, R. G., Getting the Message to MESSENGER: Overview of the Weekly Planning and Sequencing of MESSENGER Orbital Activities, in Proc. SpaceOps th International Conf. on Space Operations, Pasadena, CA, paper AIAA , pp (2014). Krupiarz, C. J., Heggestad, B. K., and Carper, R. D., Flying CFDP on MESSENGER, International Telemetering Conf. Proc., San Diego, CA, paper , pp. 1 8 (2004). Krupiarz, C. J., Burleigh, S. C., Frangos, C. M., Heggestad, B. K., Holland, D. B., Lyons, K. M., and Stratton, W. C., The Use of the CCSDS File Delivery Protocol on MESSENGER, in Proc. SpaceOps 2002 Conf., Houston, TX, paper T5-35, pp. 1 8 (2002). Krupiarz, C. J., Artis, D. A., Calloway, A. B., Frangos, C. M., Heggestad, B. K., Holland, D. B., and Stratton, W. C., File-Based Data Processing on MESSENGER, Acta Astronaut. 59, (2006). Mackey, D. P., and Calloway, A. B., Planning and Operations for Superior Solar Conjunctions During the MESSENGER Mission, in Proc. Institute of Electrical and Electronic Engineers (IEEE) Aerospace Conf., Big Sky, MT, paper , pp. 1 6 (2012). Andrew B. Calloway, Space Exploration Sector, Johns Hopkins University Applied Physics Laboratory, Laurel, MD Andrew B. Calloway is a member of the Principal Professional Staff in APL s Space Exploration Sector. He has 24 years of experience in space operations as of 2017, including geostationary Earth orbit, low Earth orbit, and planetary missions. He was the mission operations manager for MESSENGER from 2007 through end of mission in April 2015 and a core team member of New Horizons through the Pluto flyby encounter. He continued exploring the solar system when he joined the OSIRIS-REx (Origins, Spectral Interpretation, Resource Identification, Security, Regolith Explorer) team in April 2016, supporting the mission to return samples from asteroid Bennu as the mission operations manager. His address is andrew.calloway@jhuapl.edu. Richard G. Shelton, Space Exploration Sector, Johns Hopkins University Applied Physics Laboratory, Laurel, MD Richard G. Shelton of APL s Space Exploration Sector has been a mission operations analyst for the MSX (Midcourse Space Experiment) spacecraft and NASA s NEAR (Near Earth Asteroid Rendezvous), MESSENGER, and New Horizons missions. For MESSENGER, he was responsible for the operations for four of the seven science instruments, including the Mercury Dual Imaging System, and maintained key components of the mission operations software. His address is richard.shelton@jhuapl.edu. Eric D. Melin, Space Exploration Sector, Johns Hopkins University Applied Physics Laboratory, Laurel, MD Eric D. Melin of APL s Space Exploration Sector is currently the ground software lead for NASA s Parker Solar Probe mission. He was previously the ground software lead for NASA s New Horizons and MESSENGER missions. Eric has also developed ground software for NASA s Van Allen Probes mission. His address is eric.melin@jhuapl.edu. 25

SciBox, a Proven Automated Planning and Commanding System

SciBox, a Proven Automated Planning and Commanding System SciBox, a Proven Automated Planning and Commanding System Teck Choo, Edward Russell, Michael Kim February 25, 2014 2014 by The Johns Hopkins University/Applied Physics Laboratory. Published by The Aerospace

More information

Science planning and operations for Mars Express

Science planning and operations for Mars Express Science planning and operations for Mars Express René Pischel and Tanja Zegers ESA/ESTEC, Research and Scientific Support Department, Postbus 299, 2200 AG Noordwijk, The Netherlands I. Introduction The

More information

DARE Mission and Spacecraft Overview

DARE Mission and Spacecraft Overview DARE Mission and Spacecraft Overview October 6, 2010 Lisa Hardaway, PhD Mike Weiss, Scott Mitchell, Susan Borutzki, John Iacometti, Grant Helling The information contained herein is the private property

More information

SP-1291 June Mars Express. The Scientific Investigations

SP-1291 June Mars Express. The Scientific Investigations SP-1291 June 2009 Mars Express The Scientific Investigations Operations and Archiving Mars Express Science Planning and Operations R. Pischel & T. Zegers ESA/ESTEC, Research and Scientific Support Department,

More information

Use of STEREO High Gain Antenna s Sidelobes at low SPE Angles

Use of STEREO High Gain Antenna s Sidelobes at low SPE Angles SpaceOps Conferences 16-20 May 2016, Daejeon, Korea SpaceOps 2016 Conference 10.2514/6.2016-2403 Use of STEREO High Gain Antenna s Sidelobes at low SPE Angles Matthew W. Cox 1 Johns Hopkins University

More information

New Worlds Observer Operations Concept NEW WORLDS OBSERVER OPERATIONS CONCEPT (OPSCON)

New Worlds Observer Operations Concept NEW WORLDS OBSERVER OPERATIONS CONCEPT (OPSCON) NEW WORLDS OBSERVER OPERATIONS CONCEPT (OPSCON) 1 Table of Contents 1.0 Mission Overview... 1 1.1 NWO scope... 1 2.0 System Overview... 2 2.1 System constituents... 2 2.2 system functional architecture...

More information

MESSENGER Operational Influences and Environment

MESSENGER Operational Influences and Environment MESSENGER Operational Influences and Environment MESSENGER Operational Influences and Environment G. Allan Holtzman, Andrew B. Calloway, Stephen E. Jaskulek, and Daniel T. Gallagher ABSTRACT After a busy

More information

PRELIMINAJ3.:( 6/8/92 SOFTWARE REQUIREMENTS SPECIFICATION FOR THE DSPSE GUIDANCE, NAVIGATION, AND CONTROL CSCI. Prepared by

PRELIMINAJ3.:( 6/8/92 SOFTWARE REQUIREMENTS SPECIFICATION FOR THE DSPSE GUIDANCE, NAVIGATION, AND CONTROL CSCI. Prepared by PRELIMINAJ3.:( SOFTWARE REQUIREMENTS SPECIFICATION FOR THE DSPSE GUIDANCE, NAVIGATION, AND CONTROL CSCI Prepared by Space Applications Corporation 6/8/92.. 1 SCOPE 1.1 IDENTIFICATION 1.2 OVERVIEW This

More information

MESSENGER Onboard Timekeeping Accuracy during the First Year in Orbit at Mercury

MESSENGER Onboard Timekeeping Accuracy during the First Year in Orbit at Mercury MESSENGER Onboard Timekeeping Accuracy during the First Year in Orbit at Mercury Stanley B. Cooper, J. Robert Jensen, and Gregory L. Weaver The Johns Hopkins University Applied Physics Laboratory, Laurel,

More information

Reduction and analysis of one-way laser ranging data from ILRS ground stations to LRO

Reduction and analysis of one-way laser ranging data from ILRS ground stations to LRO Reduction and analysis of one-way laser ranging data from ILRS ground stations to LRO S. Bauer 1, J. Oberst 1,2, H. Hussmann 1, P. Gläser 2, U. Schreiber 3, D. Mao 4, G.A. Neumann 5, E. Mazarico 5, M.H.

More information

Orbital Operations Planning and Scheduling for the MESSENGER Mission

Orbital Operations Planning and Scheduling for the MESSENGER Mission Orbital Operations Planning and Scheduling for the MESSENGER Mission Alice F. Berman, Deborah L. Domingue, Mark E. Holdridge, Teck H. Choo, R. Joshua Steele, Richard G. Shelton The Johns Hopkins University

More information

Time and Frequency Activities at the JHU Applied Physics Laboratory

Time and Frequency Activities at the JHU Applied Physics Laboratory Time and Frequency Activities at the JHU Applied Physics Laboratory Mihran Miranian, Gregory L. Weaver, Jeffrey F. Garstecki, and Richard A. Dragonette Johns Hopkins University Applied Physics Laboratory,

More information

Predicting Long-Term Telemetry Behavior for Lunar Orbiting, Deep Space, Planetary and Earth Orbiting Satellites

Predicting Long-Term Telemetry Behavior for Lunar Orbiting, Deep Space, Planetary and Earth Orbiting Satellites Predicting Long-Term Telemetry Behavior for Lunar Orbiting, Deep Space, Planetary and Earth Orbiting Satellites Item Type text; Proceedings Authors Losik, Len Publisher International Foundation for Telemetering

More information

LOW-COST LUNAR COMMUNICATION AND NAVIGATION

LOW-COST LUNAR COMMUNICATION AND NAVIGATION LOW-COST LUNAR COMMUNICATION AND NAVIGATION Keric Hill, Jeffrey Parker, George H. Born, and Martin W. Lo Introduction Spacecraft in halo orbits near the Moon could relay communications for lunar missions

More information

Figure 1. View of ALSAT-2A spacecraft

Figure 1. View of ALSAT-2A spacecraft ALSAT-2A TRANSFER AND FIRST YEAR OPERATIONS M. Kameche (1), A.H. Gicquel (2), D. Joalland (3) (1) CTS/ASAL, 1 Avenue de la Palestine, BP 13, Arzew 31200 Oran, Algérie, email:mo_kameche@netcourrier.com

More information

New Worlds Observer Final Report Appendix J. Appendix J: Trajectory Design and Orbit Determination Lead Author: Karen Richon

New Worlds Observer Final Report Appendix J. Appendix J: Trajectory Design and Orbit Determination Lead Author: Karen Richon Appendix J: Trajectory Design and Orbit Determination Lead Author: Karen Richon The two NWO spacecraft will orbit about the libration point created by the Sun and Earth/Moon barycenter at the far side

More information

Improvement of Hubble Space Telescope subsystems through data mining

Improvement of Hubble Space Telescope subsystems through data mining Improvement of Hubble Space Telescope subsystems through data mining S. Skias, M. Darrah & M. Webb Institute for Scientific Research Inc., USA Abstract The Hubble Space Telescope continues to increase

More information

BepiColombo. Project and MPO Status. Comprehensive Explora1on of Planet Mercury

BepiColombo. Project and MPO Status. Comprehensive Explora1on of Planet Mercury BepiColombo Project and MPO Status Comprehensive Explora1on of Planet Mercury Joe Zender BepiColombo Deputy PS, ESA/ESTEC BepiColombo Previously: Ø Proba2 Science Coordinator, until 12/2013 Ø ProbaV, Project

More information

A Concept of Nanosatellite Small Fleet for Earth Observation

A Concept of Nanosatellite Small Fleet for Earth Observation A Concept of Nanosatellite Small Fleet for Earth Observation Prof. Janusz Narkiewicz jnark@meil.pw.edu.pl Sebastian Topczewski stopczewski@meil.pw.edu.pl Mateusz Sochacki msochacki@meil.pw.edu.pl 10-11

More information

THE VOYAGER-2 NEPTUNE ENCOUNTER

THE VOYAGER-2 NEPTUNE ENCOUNTER THE VOYAGER-2 NEPTUNE ENCOUNTER William J. Kosmann The Astronautics Company The Jet Propulsion Laboratory, The California Institute of Technology 4800 Oak Grove Drive Pasadena, California 91109 ABSTRACT

More information

AN INTERNATIONAL SOLAR IRRADIANCE DATA INGEST SYSTEM FOR FORECASTING SOLAR POWER AND AGRICULTURAL CROP YIELDS

AN INTERNATIONAL SOLAR IRRADIANCE DATA INGEST SYSTEM FOR FORECASTING SOLAR POWER AND AGRICULTURAL CROP YIELDS AN INTERNATIONAL SOLAR IRRADIANCE DATA INGEST SYSTEM FOR FORECASTING SOLAR POWER AND AGRICULTURAL CROP YIELDS James Hall JHTech PO Box 877 Divide, CO 80814 Email: jameshall@jhtech.com Jeffrey Hall JHTech

More information

MULTI PURPOSE MISSION ANALYSIS DEVELOPMENT FRAMEWORK MUPUMA

MULTI PURPOSE MISSION ANALYSIS DEVELOPMENT FRAMEWORK MUPUMA MULTI PURPOSE MISSION ANALYSIS DEVELOPMENT FRAMEWORK MUPUMA Felipe Jiménez (1), Francisco Javier Atapuerca (2), José María de Juana (3) (1) GMV AD., Isaac Newton 11, 28760 Tres Cantos, Spain, e-mail: fjimenez@gmv.com

More information

Team X Study Summary for ASMCS Theia. Jet Propulsion Laboratory, California Institute of Technology. with contributions from the Theia Team

Team X Study Summary for ASMCS Theia. Jet Propulsion Laboratory, California Institute of Technology. with contributions from the Theia Team Team X Study Summary for ASMCS Theia Jet Propulsion Laboratory, California Institute of Technology with contributions from the Theia Team P. Douglas Lisman, NASA Jet Propulsion Laboratory David Spergel,

More information

New Approaches to the Development of GC/MS Selected Ion Monitoring Acquisition and Quantitation Methods Technique/Technology

New Approaches to the Development of GC/MS Selected Ion Monitoring Acquisition and Quantitation Methods Technique/Technology New Approaches to the Development of GC/MS Selected Ion Monitoring Acquisition and Quantitation Methods Technique/Technology Gas Chromatography/Mass Spectrometry Author Harry Prest 1601 California Avenue

More information

STAR CATALOGUE FACILITY

STAR CATALOGUE FACILITY STAR CATALOGUE FACILITY Alan Batten Science Systems (Space) Ltd., 23 Clothier Road, Bristol BS4 5SS Phone: +44 117 9717251. Fax: +44 117 9711125 E-mail: Alan.Batten@scisys.co.uk ABSTRACT The provision

More information

XR Analog Clock - Manual Setting Model Troubleshooting Guide

XR Analog Clock - Manual Setting Model Troubleshooting Guide Primex XR 72MHz Synchronized Time Solution XR Analog Clock - Manual Setting Model Troubleshooting Guide 2018 Primex. All Rights Reserved. The Primex logo is a registered trademark of Primex. All other

More information

Satellite Components & Systems. Dr. Ugur GUVEN Aerospace Engineer (P.hD) Nuclear Science & Technology Engineer (M.Sc)

Satellite Components & Systems. Dr. Ugur GUVEN Aerospace Engineer (P.hD) Nuclear Science & Technology Engineer (M.Sc) Satellite Components & Systems Dr. Ugur GUVEN Aerospace Engineer (P.hD) Nuclear Science & Technology Engineer (M.Sc) Definitions Attitude: The way the satellite is inclined toward Earth at a certain inclination

More information

Improving Space Surveillance with Space-Based Visible Sensor

Improving Space Surveillance with Space-Based Visible Sensor Improving Space Surveillance with Space-Based Visible Sensor Jayant Sharma, Andrew Wiseman, and George Zollinger MIT Lincoln Laboratory Abstract The Midcourse Space Experiment satellite was launched in

More information

PROBA 1. F. Teston ESA/ESTEC D/TEC-EL

PROBA 1. F. Teston ESA/ESTEC D/TEC-EL PROBA 1 F. Teston ESA/ESTEC D/TEC-EL Frederic.Teston@esa.int PROBA 1 launch PROBA 1 has been launched on 21 October 2001 Orbital parameters: Altitude: 681-561 km Near polar (inclination of 97.9 ) Sun-synchronous

More information

A SELF-TUNING KALMAN FILTER FOR AUTONOMOUS SPACECRAFT NAVIGATION

A SELF-TUNING KALMAN FILTER FOR AUTONOMOUS SPACECRAFT NAVIGATION A SELF-TUNING KALMAN FILTER FOR AUTONOMOUS SPACECRAFT NAVIGATION Son H. Truong National Aeronautics and Space Administration (NASA) Goddard Space Flight Center (GSFC) Greenbelt, Maryland, USA 2771 E-mail:

More information

GLAST Large Area Telescope Monthly Mission Review

GLAST Large Area Telescope Monthly Mission Review GLAST Large Area Telescope Monthly Mission Review Gamma-ray Large Area Space Telescope LAT Flight Software Status May 2, 2007 Jana Thayer Stanford Linear Accelerator Center 1 FSW Status B0-10-1 available

More information

Oakland County Parks and Recreation GIS Implementation Plan

Oakland County Parks and Recreation GIS Implementation Plan Oakland County Parks and Recreation GIS Implementation Plan TABLE OF CONTENTS 1.0 Introduction... 3 1.1 What is GIS? 1.2 Purpose 1.3 Background 2.0 Software... 4 2.1 ArcGIS Desktop 2.2 ArcGIS Explorer

More information

Small Satellite Aerocapture for Increased Mass Delivered to Venus and Beyond

Small Satellite Aerocapture for Increased Mass Delivered to Venus and Beyond Small Satellite Aerocapture for Increased Mass Delivered to Venus and Beyond Adam Nelessen / Alex Austin / Joshua Ravich / Bill Strauss NASA Jet Propulsion Laboratory Ethiraj Venkatapathy / Robin Beck

More information

Time in Distributed Systems: Clocks and Ordering of Events

Time in Distributed Systems: Clocks and Ordering of Events Time in Distributed Systems: Clocks and Ordering of Events Clocks in Distributed Systems Needed to Order two or more events happening at same or different nodes (Ex: Consistent ordering of updates at different

More information

THE APL TIME AND FREQUENCY LAB

THE APL TIME AND FREQUENCY LAB THE APL TIME AND FREQUENCY LAB R. A. Dragonette, M. Miranian, and M. J. Reinhart Johns Hopkins University, Applied Physics Laboratory Laurel, MD 20723-6099, USA Abstract The APL Time and Frequency Laboratory

More information

Complexity Metrics. ICRAT Tutorial on Airborne self separation in air transportation Budapest, Hungary June 1, 2010.

Complexity Metrics. ICRAT Tutorial on Airborne self separation in air transportation Budapest, Hungary June 1, 2010. Complexity Metrics ICRAT Tutorial on Airborne self separation in air transportation Budapest, Hungary June 1, 2010 Outline Introduction and motivation The notion of air traffic complexity Relevant characteristics

More information

2024 Mars Sample Return Design Overview

2024 Mars Sample Return Design Overview 2024 Mars Sample Return Design Overview Andrew Hoffman sentinel72@gmail.com Abstract Scheduled for two launches set during two consecutive launch windows with the first launch occurring in 2024, the landmark

More information

The time period while the spacecraft is in transit to lunar orbit shall be used to verify the functionality of the spacecraft.

The time period while the spacecraft is in transit to lunar orbit shall be used to verify the functionality of the spacecraft. ASE 379L Group #2: Homework #4 James Carlson Due: Feb. 15, 2008 Henri Kjellberg Leah Olson Emily Svrcek Requirements The spacecraft shall be launched to Earth orbit using a launch vehicle selected by the

More information

Herschel Science/Instrument Planning and Scheduling. Jon Brumfitt (ESAC) SCIOPS September 2013

Herschel Science/Instrument Planning and Scheduling. Jon Brumfitt (ESAC) SCIOPS September 2013 Herschel Science/Instrument Planning and Scheduling Jon Brumfitt (ESAC) SCIOPS-2013 11 September 2013 Herschel Space Observatory Far infrared & sub-mm Telescope diameter Instruments Launch date End of

More information

End of Life Re-orbiting The Meteosat-5 Experience

End of Life Re-orbiting The Meteosat-5 Experience End of Life Re-orbiting The Meteosat-5 Experience Milan EUMETSAT, Darmstadt, Germany This article illustrates the orbit maneuver sequence performed during Meteosat- 5 End of Life (EOL) re-orbiting operations

More information

System engineering approach toward the problem of required level of in-orbit autonomousoperation of a LEO microsatellite mission

System engineering approach toward the problem of required level of in-orbit autonomousoperation of a LEO microsatellite mission System engineering approach toward the problem of required level of in-orbit autonomousoperation of a LEO microsatellite mission H.Bonyan Amirkabir University of Technology (AUT) H.Bonyan@dena.aut.ac.ir

More information

BepiColombo MPO Science Operations Planning Drivers IWPSS-2013

BepiColombo MPO Science Operations Planning Drivers IWPSS-2013 BepiColombo MPO Science Operations Planning Drivers IWPSS-2013 Sara de la Fuente sfuente@sciops.esa.int BepiColombo MPO Science Ground Segment ESA, ESAC, Villanueva de la Cañada, Madrid, 28691, Spain Summary

More information

Maximizing MESSENGER s Science Return with Technologies and Innovation

Maximizing MESSENGER s Science Return with Technologies and Innovation Maximizing MESSENGER s Science Return with Technologies and Innovation Maximizing MESSENGER s Science Return with Technologies and Innovation Robert. E. Gold, Stewart S. Bushman, Andrew B. Calloway, James

More information

ENVISAT - AATSR CYCLIC REPORT #63

ENVISAT - AATSR CYCLIC REPORT #63 ENVISAT - AATSR CYCLIC REPORT #63 START END DATE 29 OCT 2007 03 DEC 2007 TIME 21:59:29 21:59:29 ORBIT # 29614 30114 Himalayas, 18 November 2007 Daytime visible image showing snow on the Western Himalayas.

More information

Feasible Mission Designs for Solar Probe Plus to Launch in 2015, 2016, 2017, or November 19, 2008

Feasible Mission Designs for Solar Probe Plus to Launch in 2015, 2016, 2017, or November 19, 2008 Feasible Mission Designs for Solar Probe Plus to Launch in 2015, 2016, 2017, or 2018 2007 Solar Probe Study & Mission Requirements Trajectory study and mission design trades were conducted in the fall

More information

WISE Science Data System Single Frame Position Reconstruction Peer Review: Introduction and Overview

WISE Science Data System Single Frame Position Reconstruction Peer Review: Introduction and Overview WISE Science Data System Single Frame Position Reconstruction Peer Review: Introduction and Overview R. Cutri and the WSDC Team @ IPAC 1 Review Panel Rachel Akeson (IPAC/MSC) Gene Kopan (IPAC retired)

More information

Enabling Success in Enterprise Asset Management: Case Study for Developing and Integrating GIS with CMMS for a Large WWTP

Enabling Success in Enterprise Asset Management: Case Study for Developing and Integrating GIS with CMMS for a Large WWTP Enabling Success in Enterprise Asset Management: Case Study for Developing and Integrating GIS with CMMS for a Large WWTP Allison Blake, P.E. 1*, Matthew Jalbert, P.E. 2, Julia J. Hunt, P.E. 2, Mazen Kawasmi,

More information

From Mercury to Pluto: A Common Approach to Mission Timekeeping

From Mercury to Pluto: A Common Approach to Mission Timekeeping From Mercury to Pluto: A Common Approach to Mission Timekeeping Stanley B. Cooper The Johns Hopkins University Applied Physics Laboratory ABSTRACT The successful launch of the New Horizons spacecraft for

More information

THE MICRO ADVANCED STELLAR COMPASS FOR ESA S PROBA 2 MISSION

THE MICRO ADVANCED STELLAR COMPASS FOR ESA S PROBA 2 MISSION THE MICRO ADVANCED STELLAR COMPASS FOR ESA S PROBA 2 MISSION P.S. Jørgensen (1), J.L. Jørgensen (1), T. Denver (1), Pieter van den Braembuche (2) (1) Technical University of Denmark, Ørsted*DTU, Measurement

More information

Saving NASA's STEREO-B the 189-millionmile road to recovery 14 December 2015, by Sarah Frazier

Saving NASA's STEREO-B the 189-millionmile road to recovery 14 December 2015, by Sarah Frazier Saving NASA's STEREO-B the 189-millionmile road to recovery 14 December 2015, by Sarah Frazier On Oct. 1, 2014, NASA mission operations lost communication with one of the two spacecraft of the Solar and

More information

Mars Sample Return Mission

Mars Sample Return Mission Mars Sample Return Mission Ryan Supler Saylor.org: SSE101 MSRM Project April 15, 2014 2 Table of Contents The Scoping Elements of the Mars Sample Return Mission page 3 The High-Level Concept of Operations

More information

Supplemental info for MCR : Change Science Orbit Period from 11 Days to 14 Days

Supplemental info for MCR : Change Science Orbit Period from 11 Days to 14 Days This document was reviewed and approved for export, see Juno-14-016. : Mission Engineer 6 May 2015 This document has been reviewed and determined not to contain export controlled technical data. Contents

More information

Venus Express: Results, Status and Future Plans

Venus Express: Results, Status and Future Plans Venus Express: Results, Status and Future Plans Håkan Svedhem ESA/ESTEC Present Status The spacecraft and its payload in general is in a good condition, with the following remarks: One of the two coolers

More information

MISSION ENGINEERING SPACECRAFT DESIGN

MISSION ENGINEERING SPACECRAFT DESIGN MISSION ENGINEERING & SPACECRAFT DESIGN Alpbach 2007 - D.J.P. Moura - CNES MISSION ENGINEERING (1) OVERALL MISSION ENGINEERING IS A COMPLEX TASK SINCE AT THE BEGINNING THE PROBLEM IS GENERALLY BADLY EXPRESSED

More information

The post launch assessment review confirmed the following previous assertions about the mission status:

The post launch assessment review confirmed the following previous assertions about the mission status: 1 GRACE Newsletter No. 2 August 15, 2003 Topics: http://www.csr.utexas/grace/ http://www.gfz-potsdam.de/grace 1. Editorial 2. Major events in Mission Operations since last Newsletter 3. Current status

More information

Project Plan for the City of Philadelphia Pole and Pole Attachment Geodatabase Design Project

Project Plan for the City of Philadelphia Pole and Pole Attachment Geodatabase Design Project Project Plan for the City of Philadelphia Pole and Pole Attachment Geodatabase Design Project Project Overview: The City of Philadelphia is experiencing data integrity problems caused by data format issues.

More information

BUILDING LOW-COST NANO-SATELLITES: THE IMPORTANCE OF A PROPER ENVIRONMENTAL TESTS CAMPAIGN. Jose Sergio Almeida INPE (Brazil)

BUILDING LOW-COST NANO-SATELLITES: THE IMPORTANCE OF A PROPER ENVIRONMENTAL TESTS CAMPAIGN. Jose Sergio Almeida INPE (Brazil) BUILDING LOW-COST NANO-SATELLITES: THE IMPORTANCE OF A PROPER ENVIRONMENTAL TESTS CAMPAIGN Jose Sergio Almeida INPE (Brazil) 1 st International Academy of Astronautics Latin American Symposium on Small

More information

Lightcloud Application

Lightcloud Application Controlling Your Lightcloud System Lightcloud Application Lightcloud Application Navigating the Application Devices Device Settings Organize Control Energy Scenes Schedules Demand Response Power Up State

More information

Announcement of Opportunity AKARI (ASTRO-F)

Announcement of Opportunity AKARI (ASTRO-F) Announcement of Opportunity AKARI (ASTRO-F) CALL FOR OBSERVING PROPOSALS for the AKARI Post-Helium (phase 3) mission 2 nd year of Operations (October 2009 October 2010) Policies and procedures 27 May 2009

More information

J. G. Miller (The MITRE Corporation), W. G. Schick (ITT Industries, Systems Division)

J. G. Miller (The MITRE Corporation), W. G. Schick (ITT Industries, Systems Division) Contributions of the GEODSS System to Catalog Maintenance J. G. Miller (The MITRE Corporation), W. G. Schick (ITT Industries, Systems Division) The Electronic Systems Center completed the Ground-based

More information

FIRE SAIL: MESSENGER S USE OF SOLAR RADIATION PRESSURE FOR ACCURATE MERCURY FLYBYS

FIRE SAIL: MESSENGER S USE OF SOLAR RADIATION PRESSURE FOR ACCURATE MERCURY FLYBYS AAS 09-014 FIRE SAIL: MESSENGER S USE OF SOLAR RADIATION PRESSURE FOR ACCURATE MERCURY FLYBYS Daniel J. O Shaughnessy *, James V. McAdams, Kenneth E. Williams and Brian R. Page MESSENGER (MErcury Surface,

More information

JWST Overheads. Jeff Valenti S&OC Mission Scientist

JWST Overheads. Jeff Valenti S&OC Mission Scientist JWST Overheads Jeff Valenti S&OC Mission Scientist Topics JWST observations APT timing model Observing efficiency 2 Flow of a program through the system Proposal and Planning Subsystem Operations Script

More information

State Vector Reference Body Transformations Throughout The Solar System

State Vector Reference Body Transformations Throughout The Solar System Introduction One of the more mind-boggling programming challenges encountered during interplanetary trajectory design software development is how to transform a specified inertial position and velocity

More information

AIM RS: Radio Science Investigation with AIM

AIM RS: Radio Science Investigation with AIM Prepared by: University of Bologna Ref. number: ALMARS012016 Version: 1.0 Date: 08/03/2017 PROPOSAL TO ESA FOR AIM RS Radio Science Investigation with AIM ITT Reference: Partners: Radio Science and Planetary

More information

LANDSAT DATA CONTINUITY MISSION (LDCM) ORBIT DETERMINATION

LANDSAT DATA CONTINUITY MISSION (LDCM) ORBIT DETERMINATION LANDSAT DATA CONTINUITY MISSION (LDCM) ORBIT DETERMINATION Lauren Chung (1), Ann Nicholson (2), Susan Good (3) and Mark Woodard (4) (1)(2)(3) a.i. solutions, Inc. 10001 Derekwood Lane, Suite 215 Lanham,

More information

Benefits of Applying Predictive Intelligence to the Space Situational Awareness (SSA) Mission

Benefits of Applying Predictive Intelligence to the Space Situational Awareness (SSA) Mission Benefits of Applying Predictive Intelligence to the Space Situational Awareness (SSA) Mission Abstract Ben Lane and Brian Mann Military Civil Space and Ground (MCS&G) Northrop Grumman Electronic Systems

More information

A DISPLAY CONCEPT FOR STAYING AHEAD OF THE AIRPLANE

A DISPLAY CONCEPT FOR STAYING AHEAD OF THE AIRPLANE A DISPLAY CONCEPT FOR STAYING AHEAD OF THE AIRPLANE Eric N. Johnson, Lockheed Martin Aeronautical Systems, Marietta, Georgia David C. Hansen, Lockheed Martin Aeronautical Systems, Marietta, Georgia Abstract

More information

Mission Overview. EAGLE: Study Goals. EAGLE: Science Goals. Mission Architecture Overview

Mission Overview. EAGLE: Study Goals. EAGLE: Science Goals. Mission Architecture Overview Mission Overview OPAG Meeting November 8 th, 2006 Ryan Anderson & Daniel Calvo EAGLE: Study Goals Develop a set of science goals for a flagship mission to Enceladus Investigate mission architectures that

More information

EBS IT Meeting July 2016

EBS IT Meeting July 2016 EBS IT Meeting 18 19 July 2016 Conference Call Details Conference call: UK Numbers Tel: 0808 238 9819 or Tel: 0207 950 1251 Participant code: 4834 7876... Join online meeting https://meet.nationalgrid.com/antonio.delcastillozas/hq507d31

More information

CIMA Professional 2018

CIMA Professional 2018 CIMA Professional 2018 Interactive Timetable Version 16.25 Information last updated 06/08/18 Please note: Information and dates in this timetable are subject to change. A better way of learning that s

More information

ISIS Impactor for Surface and Interior Science

ISIS Impactor for Surface and Interior Science ISIS Impactor for Surface and Interior Science ISIS Mission Concept!! Send an independent, autonomous impactor spacecraft to the target of the OSIRIS-REx mission!! Launch as secondary payload with InSight!!

More information

DISTRIBUTED COMPUTER SYSTEMS

DISTRIBUTED COMPUTER SYSTEMS DISTRIBUTED COMPUTER SYSTEMS SYNCHRONIZATION Dr. Jack Lange Computer Science Department University of Pittsburgh Fall 2015 Topics Clock Synchronization Physical Clocks Clock Synchronization Algorithms

More information

CIMA Professional

CIMA Professional CIMA Professional 201819 Birmingham Interactive Timetable Version 3.1 Information last updated 12/10/18 Please note: Information and dates in this timetable are subject to change. A better way of learning

More information

CIMA Professional

CIMA Professional CIMA Professional 201819 Manchester Interactive Timetable Version 3.1 Information last updated 12/10/18 Please note: Information and dates in this timetable are subject to change. A better way of learning

More information

Paper Session III-B - Mars Global Surveyor: Cruising to Mars

Paper Session III-B - Mars Global Surveyor: Cruising to Mars The Space Congress Proceedings 1997 (34th) Our Space Future - Uniting For Success May 1st, 1:00 PM Paper Session III-B - Mars Global Surveyor: Cruising to Mars Glenn E. Cunningham Project Manager Mars

More information

Advance signals that can be used to foresee demand response days PJM SODRTF - March 9, 2018

Advance signals that can be used to foresee demand response days PJM SODRTF - March 9, 2018 Advance signals that can be used to foresee demand response days PJM SODRTF - March 9, 2018 1 OVERVIEW BGE s load response programs are split between two programs Peak Rewards and Smart Energy Rewards

More information

Artificial Intelligence at the Jet Propulsion Laboratory. Jakub Hajic AI Seminar I., MFF UK

Artificial Intelligence at the Jet Propulsion Laboratory. Jakub Hajic AI Seminar I., MFF UK Artificial Intelligence at the Jet Propulsion Laboratory Jakub Hajic 3. 12. 2013 AI Seminar I., MFF UK Talk outline Included: Overview of JPL Current planning systems ASPEN (batch) CASPER (continuous)

More information

CIMA Professional 2018

CIMA Professional 2018 CIMA Professional 2018 Newcastle Interactive Timetable Version 10.20 Information last updated 12/06/18 Please note: Information and dates in this timetable are subject to change. A better way of learning

More information

Clojure Concurrency Constructs, Part Two. CSCI 5828: Foundations of Software Engineering Lecture 13 10/07/2014

Clojure Concurrency Constructs, Part Two. CSCI 5828: Foundations of Software Engineering Lecture 13 10/07/2014 Clojure Concurrency Constructs, Part Two CSCI 5828: Foundations of Software Engineering Lecture 13 10/07/2014 1 Goals Cover the material presented in Chapter 4, of our concurrency textbook In particular,

More information

Telemetry Anomaly Detection System using Machine Learning to Streamline Mission Operations

Telemetry Anomaly Detection System using Machine Learning to Streamline Mission Operations 6th IEEE International Conference on Space Mission Challenges for Information Technology Telemetry Anomaly Detection System using Machine Learning to Streamline Mission Operations Michela Muñoz Fernández

More information

The Vaisala AUTOSONDE AS41 OPERATIONAL EFFICIENCY AND RELIABILITY TO A TOTALLY NEW LEVEL.

The Vaisala AUTOSONDE AS41 OPERATIONAL EFFICIENCY AND RELIABILITY TO A TOTALLY NEW LEVEL. The Vaisala AUTOSONDE AS41 OPERATIONAL EFFICIENCY AND RELIABILITY TO A TOTALLY NEW LEVEL. Weather Data Benefit For Society The four most important things about weather prediction are quality, reliability,

More information

Using the International Space Station as an Engineering Technology Research Laboratory for Space Based Telescopes

Using the International Space Station as an Engineering Technology Research Laboratory for Space Based Telescopes Using the International Space Station as an Engineering Technology Research Laboratory for Space Based Telescopes David W. Miller Director, Professor, MIT Dept. of Aeronautics and Astronautics Javier de

More information

GEOGRAPHIC INFORMATION SYSTEMS Session 8

GEOGRAPHIC INFORMATION SYSTEMS Session 8 GEOGRAPHIC INFORMATION SYSTEMS Session 8 Introduction Geography underpins all activities associated with a census Census geography is essential to plan and manage fieldwork as well as to report results

More information

Science Scenario Modeling

Science Scenario Modeling Science Scenario Modeling Rob Lock, Erick Sturm, Tracy Van Houten Presented to OPAG Satellite Break-out Group February 2010 Introduction Scenario Strategy For Europa Explorer and Jupiter Europa Orbiter

More information

The New Horizons OpNav Switch

The New Horizons OpNav Switch The New Horizons OpNav Switch Helen Hart & Karl Whittenburg APL SES SIO This presentation contains no US Export Controlled (ITAR) information. New Horizons OpNav Switch - Outline Mission Overview Optical

More information

Juno Status and Earth Flyby Plans. C. J. Hansen

Juno Status and Earth Flyby Plans. C. J. Hansen Juno Status and Earth Flyby Plans C. J. Hansen July 2013 Juno will improve our understanding of the history of the solar system by investigating the origin and evolution of Jupiter. To accomplish this

More information

Swift Mission Requirements Document

Swift Mission Requirements Document Version 2.4 November 14, 2002 NASA Goddard Space Flight Center TABLE OF CONTENTS Page REVISION HISTORY 4 DOCUMENT TREE 5 INTRODUCTION 6 APPLICABLE DOCUMENTS 6 SCIENCE REQUIREMENTS 7 MISSION REQUIREMENTS

More information

Transition from GVAR to GOES-R GRB Service Continuity

Transition from GVAR to GOES-R GRB Service Continuity Transition from GVAR to GOES-R GRB Service Continuity Presented to CGMS-43 Plenary session, agenda item F.2.3 CGMS-43-NOAA-WP-02 GOES-R at Test Location First 12 Months CGMS-43-NOAA-WP-02 Slide: 2 Transitioning

More information

I N T R O D U C T I O N : G R O W I N G I T C O M P L E X I T Y

I N T R O D U C T I O N : G R O W I N G I T C O M P L E X I T Y Global Headquarters: 5 Speen Street Framingham, MA 01701 USA P.508.872.8200 F.508.935.4015 www.idc.com W H I T E P A P E R I n v a r i a n t A n a l y z e r : A n A u t o m a t e d A p p r o a c h t o

More information

I n the early morning of 9 November 2005, Reaching our Sister Planet

I n the early morning of 9 November 2005, Reaching our Sister Planet From Earth to Venus Venus Express Andrea Accomazzo, Peter Schmitz & Ignacio Tanco Mission Operations Department, Directorate of Operations and Infrastructure, ESOC, Darmstadt, Germany I n the early morning

More information

SYMBIOSIS CENTRE FOR DISTANCE LEARNING (SCDL) Subject: production and operations management

SYMBIOSIS CENTRE FOR DISTANCE LEARNING (SCDL) Subject: production and operations management Sample Questions: Section I: Subjective Questions 1. What are the inputs required to plan a master production schedule? 2. What are the different operations schedule types based on time and applications?

More information

Mass Asset Additions. Overview. Effective mm/dd/yy Page 1 of 47 Rev 1. Copyright Oracle, All rights reserved.

Mass Asset Additions.  Overview. Effective mm/dd/yy Page 1 of 47 Rev 1. Copyright Oracle, All rights reserved. Overview Effective mm/dd/yy Page 1 of 47 Rev 1 System References None Distribution Oracle Assets Job Title * Ownership The Job Title [list@yourcompany.com?subject=eduxxxxx] is responsible for ensuring

More information

New Worlds Observer Final Report Appendix E. Section E: Starshades Subsection E.6: Starshade Spacecraft Lead Author: Amy Lo

New Worlds Observer Final Report Appendix E. Section E: Starshades Subsection E.6: Starshade Spacecraft Lead Author: Amy Lo Section E: Starshades Subsection E.6: Starshade Spacecraft Lead Author: Amy Lo Introduction Starshade Spacecraft Functional Requirements The main function of the starshade spacecraft is to: 1) support

More information

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 Peterborough Distribution Inc. 1867 Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5 November 15, 2017 Ontario Energy Board PO Box 2319 27 th Floor, 2300 Yonge St Toronto ON M4P 1E4

More information

ASTEROID IMPACT MISSION: AIM3P MISSION AND PAYLOAD OPERATIONS SCENARIO

ASTEROID IMPACT MISSION: AIM3P MISSION AND PAYLOAD OPERATIONS SCENARIO estec European Space Research and Technology Centre Keplerlaan 1 2201 AZ Noordwijk The Netherlands T +31 (0)71 565 6565 F +31 (0)71 565 6040 www.esa.int ASTEROID IMPACT MISSION: AIM3P MISSION AND PAYLOAD

More information

Today s Lecture. Mars Climate Orbiter. Lecture 21: Software Disasters. Mars Climate Orbiter, continued

Today s Lecture. Mars Climate Orbiter. Lecture 21: Software Disasters. Mars Climate Orbiter, continued Today s Lecture Lecture 21: Software Disasters Kenneth M. Anderson Software Methods and Tools CSCI 3308 - Fall Semester, 2003 Discuss several different software disasters to provide insights into the types

More information

LUMINARY Memo #214 Revision 1

LUMINARY Memo #214 Revision 1 Massachusetts Institute of Technology C. S. Draper Laboratory Cambridge, Massachusetts LUMINARY Memo #214 Revision 1 To: Distribution From: Luminary Test Group Date: 6 April 1971 Subject: Level 6 for Luminary

More information

HICO Mission Planning and Operations

HICO Mission Planning and Operations HICO Mission Planning and Operations Ellen J. Wagner and Marcos Montes Naval Research Laboratory ellen.wagner@nrl.navy.mil Oregon State Selecting Targets: Part 1 Request through OSU web site Choose coordinates

More information

FIBER OPTIC GYRO-BASED ATTITUDE DETERMINATION FOR HIGH- PERFORMANCE TARGET TRACKING

FIBER OPTIC GYRO-BASED ATTITUDE DETERMINATION FOR HIGH- PERFORMANCE TARGET TRACKING FIBER OPTIC GYRO-BASED ATTITUDE DETERMINATION FOR HIGH- PERFORMANCE TARGET TRACKING Elias F. Solorzano University of Toronto (Space Flight Laboratory) Toronto, ON (Canada) August 10 th, 2016 30 th AIAA/USU

More information

AUTOMATED FLIGHT DYNAMICS SYSTEM FOR THAICHOTE SATELLITE

AUTOMATED FLIGHT DYNAMICS SYSTEM FOR THAICHOTE SATELLITE IAA-AAS-DyCoSS2-14-11-07 AUTOMATED FLIGHT DYNAMICS SYSTEM FOR THAICHOTE SATELLITE Manop Aorpimai, * Pornthep Navakitkanok and Sujate Jantarang INTRODUCTION In this paper, we present the development of

More information