Progress on FACET Commissioning. U. Wienands Director, Linac S0-20 Division for the FACET Commissioning Team

Similar documents
Tuning Techniques And Operator Diagnostics for FACET at SLAC National Accelerator Laboratory. Chris Melton SLAC Accelerator Operations

SPPS: The SLAC Linac Bunch Compressor and Its Relevance to LCLS

First results from the plasma wakefield acceleration transverse studies at FACET

II) Experimental Design

SABER Optics. Y. Nosochkov, K. Bane, P. Emma, R. Erickson. SABER Workshop, SLAC, March 15-16, /25

Chromatic Corrections for the LCLS-II Electron Transport Lines

ILC Beam Dynamics Studies Using PLACET

Beam Dynamics. Gennady Stupakov. DOE High Energy Physics Review June 2-4, 2004

LCLS Accelerator Parameters and Tolerances for Low Charge Operations

FACET-II Design Update

Studies of Emittance Bumps and Adaptive Alignment method for ILC Main Linac

X-band RF driven hard X-ray FELs. Yipeng Sun ICFA Workshop on Future Light Sources March 5-9, 2012

Low alpha mode for SPEAR3 and a potential THz beamline

LOLA: Past, present and future operation

6 Bunch Compressor and Transfer to Main Linac

Beam Physics at SLAC. Yunhai Cai Beam Physics Department Head. July 8, 2008 SLAC Annual Program Review Page 1

Lattice Design and Performance for PEP-X Light Source

Low slice emittance preservation during bunch compression

PEP-II Lattices. U. Wienands for many others from AD, ARD, NLC. U. Wienands, PEP-II MAC

FURTHER UNDERSTANDING THE LCLS INJECTOR EMITTANCE*

The TESLA Dogbone Damping Ring

What have we learned from the LCLS injector?*

A Meter-Scale Plasma Wakefield Accelerator

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

PIP-II Injector Test s Low Energy Beam Transport: Commissioning and Selected Measurements

FACET-II Design, Parameters and Capabilities

Generation and characterization of ultra-short electron and x-ray x pulses

FY04 Luminosity Plan. SAG Meeting September 22, 2003 Dave McGinnis

Update on Optics Modeling for the ATF Damping Ring at KEK Studies for low vertical emittance

Steering Simulation Studies

Novel diagnostics and beam phase space recovery

LHC operation in 2015 and prospects for the future

ThomX Machine Advisory Committee. (LAL Orsay, March ) Ring Beam Dynamics

Future Light Sources March 5-9, 2012 Low- alpha mode at SOLEIL 1

S2E (Start-to-End) Simulations for PAL-FEL. Eun-San Kim

ILC Laser-wires. G A Blair, RHUL Snowmass 17 th August 2005

Lattice Design for the Taiwan Photon Source (TPS) at NSRRC

Accelerators and Lasers In Combined Experiments Susan Smith Daresbury Laboratory

IP switch and big bend

Linac Design for the LCLS Project at SLAC*

X-Ray Diagnostics Commissioning at the LCLS

2.6 Electron transport lines

First propositions of a lattice for the future upgrade of SOLEIL. A. Nadji On behalf of the Accelerators and Engineering Division

Update on Development of High Current Bunched Electron Beam from Magnetized DC Photogun

Femto-second FEL Generation with Very Low Charge at LCLS

ILC Spin Rotator. Super B Workshop III. Presenter: Jeffrey Smith, Cornell University. with

LCLS Injector Straight Ahead Spectrometer C.Limborg-Deprey Stanford Linear Accelerator Center 8 th June 2005

New Tweaker Quadrupole Magnets for the LCLS LTU

Measurements of Short Bunches at SPPS and E-164X

Transverse Beam Optics of the FLASH Facility

LCLS-II Beam Stay-Clear

Commissioning of the SNS Beam Instrumentation

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

Outlook for PWA Experiments

COMMISSIONING AND STATUS OF THE DIAMOND STORAGE RING

Short Pulse, Low charge Operation of the LCLS. Josef Frisch for the LCLS Commissioning Team

Accelerator Physics. Accelerator Development

COMBINER RING LATTICE

Start-to-end beam optics development and multi-particle tracking for the ILC undulator-based positron source*

LCLS Injector Prototyping at the GTF

Operational Performance of LCLS Beam Instrumentation. Henrik Loos, SLAC BIW 2010, Santa Fe, NM

Diagnostics at the MAX IV 3 GeV storage ring during commissioning. PPT-mall 2. Åke Andersson On behalf of the MAX IV team

Beam dynamics measurement during ALBA commissioning

Storage Ring Optics Measurement, Model, and Correction. Yiton T. Yan SLAC, 2575 Sand Hill Road, Menlo Park, CA 94025, USA.

Experience on Coupling Correction in the ESRF electron storage ring

Two Beamline Ground Motion Simulation for NLC

On-axis injection into small dynamic aperture

Diagnostics Requirements for the ARIEL Low Energy Beam Transport

Design Status of the PEFP RCS

Transverse Field Profile of the NLC Damping Rings Electromagnet Wiggler

SRF GUN CHARACTERIZATION - PHASE SPACE AND DARK CURRENT MEASUREMENTS AT ELBE*

S. Guiducci. Table 1 PADME beam from Linac. Energy (MeV) 550. Number of positrons per pulse Pulse length (ns)

12 GeV CEBAF Beam Parameter Tables

Cornell Injector Performance

Plasma Wakefield Accelerator Experiments and their Diagnostics Patric Muggli University of Southern California

Present Capabilities and Future Concepts for Intense THz from SLAC Accelerators

Overview of accelerator science opportunities with FACET ASF

Front end, linac upgrade, and commissioning of J-PARC. Y. Liu KEK/J-PARC, Japan

Presented at the 5th International Linear Collider Workshop (LCWS 2000), Oct 24-28, 2000, Batavia, IL

Accelerator Design and Construction Progress of TPS Project

Longitudinal Top-up Injection for Small Aperture Storage Rings

Status of Optics Design

LCLS Start-Up Test Plan

Laser Heater: Scaling of Laser Power with Undulator Period and Laser Wavelength

TTF and VUV-FEL Injector Commissioning

CEPC Linac Injector. HEP Jan, Cai Meng, Guoxi Pei, Jingru Zhang, Xiaoping Li, Dou Wang, Shilun Pei, Jie Gao, Yunlong Chi

Simulation of Optics Correction for ERLs. V. Sajaev, ANL

Status of linear collider designs:

STATUS OF E-157: METER-LONG PLASMA WAKEFIELD EXPERIMENT. Presented by Patrick Muggli for the E-157 SLAC/USC/LBNL/UCLA Collaboration

Plasma Wakefield Acceleration Presented by: Bob Siemann On behalf of: The E157, E162, E-164, E-164X, E167 Collaborations

Upstream Polarimetry with 4-Magnet Chicane

Optics considerations for

Linear Collider Collaboration Tech Notes

Accelerator R&D Opportunities: Sources and Linac. Developing expertise. D. Rubin, Cornell University

OPTIMIZATION OF COMPENSATION CHICANES IN THE LCLS-II BEAM DELIVERY SYSTEM

Demonstration of Energy-Chirp Control in Relativistic Electron Bunches at LCLS Using a Corrugated Structure. Karl Bane, 7 April 2017,, KEK

LCLS-II SCRF start-to-end simulations and global optimization as of September Abstract

7th IPAC, May 8-13, 2016, Busan, Korea

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

CesrTA Status Report Mark Palmer for the CesrTA Collaboration March 4, 2009 ESR

Transcription:

Progress on FACET Commissioning U. Wienands Director, Linac S0-20 Division for the FACET Commissioning Team 1

Outline * Introduction to FACET * Hardware commissioning * Beam commissioning * Operational issues * FACET Commissioning Workshop * Plan ahead * Summary 2

FACET Beamline Map 3

FACET Design Parameters Energy 23 GeV Charge per pulse 0.5 2.0 x 10 10 e or e + Pulse length at IP ( z ) 15 40 µm Typical spot size at IP ( x,y ) 10 20 µm Repetition rate Momentum spread Momentum dispersion at IP ( and ) 1 30 Hz 4 0.5% full width < 10-5 m 4

FACET Installation 5

FACET Hardware Commissioning * FACET Readiness Review on 6-May-11 most Action Items as expected * Magnet power supply commissioning verify configuration check polarity fix issues & retest * Controls Commissioning run supplies through SCP check vacuum controls check diagnostics controls * Complete safety barriers * Complete ALARA shield wall at dump table 6

Early Beam through FACET on FACET Dump on Exit Window 7

Hardware Issues * PS: Breakers popped B1,B2,B3 Zero flux transductors/bitbus ground loop MCORs reversed voltage all soon fixed (but a B3 mystery remains) * BPMs and Toroids TMITs not consistent for BPMs Toro TMIT seem ~25% low in comparison with linac toroids: 9-turn versus 13-turn? Rotation, orientation, PCMM: fixed in 2 nd week (or so Missing two BPMS, smaller than necessary beam pipe, misaligned beam pipe much improved, but work remains * Moving Wire causes vacuum gauge glitch (fixed)

FACET Beam-Commissioning * Beam to dump 23-June immediately clear that dipole calibration was not accurate also, relatively heavy beam loss, not easily tuned out. * Relaxed lattice with much less phase advance in x allowed steering, aperture scans, reduction of beam loss revealed serious aperture restriction near center of W * Survey of center of W found vac. chamber in Q5E-R dislocated by 1/2 inch (7-July). supported properly => this restriction no longer present. * Back to full-strength lattice Some beam loss showed up again; getting about 90% through. * More work on dipole settings PCD did find issues with the transductor electronics, fixed the BACT BMON diff (28-July). 9

* Phase jump across center XCOR 2326 strongly negative again, shoot beam across pipe? but aperture on the + side (1 mm) not consistent. (xcor 2236 not scanned :-( +1.5 mm +1 mm 10

QF5E#2 Chamber Offset 11

Vertical Aperture * Aug 4 data 12

Energy aperture * Aug 4 data 13

Chicane Lattice Work * Response measurements were used to assess the state of the beam optics in the chicane Dispersion: focusing but also the central energy Results in general good agreement with the model prediction Beam energy determined to be 19.65 GeV Dispersion is quite sensitive to even small errors, and even small leakage ( 1 cm) is enough to significantly enlarge the beam size. R 12 : measures focusing * BBA is necessary to fully straighten out the beam path The Chicane is challenging due to very strong focusing and not enough correctors or BPMs in the horizontal plane Limits the number of quads/bpms amenable to straight-forward BBA 14

15 Woodley

Dispersion for adjusted Focusing * Note the rather large vertical dispersion. Comparison to MAD results (Nosochkov) indicates S2E Woodley 16

17 Woodley

The Linac * Re-commissioning of front-end and NDR lots of hardware issues, but no show stoppers largest time-sink was TIU problems * Beam emittance initially quite large, significant tuning effort fix correctors so local bumps actually work match issue in S02 resolved. nowadays we get 3 by 0.3 in S02 with little mismatch fairly routinely * S10 chicane recommissioned without much trouble * Linac emittance in S11 still relatively large * Linac beam into chicane not yet what we need 18

Sector 02 Emittance 19

Sector 11 Emittance Scan 20

Beam Incoming (PMON) 21

Understanding FACET Beam Sizes * Best emittance: 7 by 1 m-rad (meas in S11) * E/E 1 % (SYAG, PR185) * x 0.015 m; y 0.015 m (measured) * [ß x 0.03 m; ß y 0.3 m (design)] * So the dispersive beamsize alone 150 m(!) we have seen beamsizes considerably smaller than this down to 30 by 32 m @ IPWIRE likely the tuning reduces the dispersion leakage (zero crossing) * Longitudinal THz indicates bunch length may be near 65 m. E203 has little signal for 50 grating => bunch >> 17 m long Wakeloss scans about 120 MeV: consistent with SppS data. 22

Wirescans @ IP * Note: the best ones were 30 m by 32 m some inconsistency to nearby BPMs, but WS calibration checked with dial gauge => WS should be correct. 23

Beam emittance in S20 (DSOTR) 24

Michelson Interferometer Z. Wu 25

Bunch Length Signals * Pyro Q 2 /l, YARNorm = Pyro/Q 2 1/l 26

Wake loss Scan E loss 120 MeV -22.5 Pyro -23.5 27

Availability Colocho 28

Operational Issues * One (dedicated) operator/shift initially mostly the ones with SLC experience, now bringing in younger ones as well, cross training during quieter times operate near LCLS => better integration some EOIC s spend time @ FACET beyond their direct shifts * A set of SOPs is being generated (Schuh, Stanek, Yocky) Save-the-(FACET-)World macro Standard characterizations to be done at beginning of shift Tuning & measurement procedures (e.g. wakeloss scan, front-end tuning, etc.) Configurations for different experiments, knobs for waist shifts 29

Commissioning mini Workshop * On 16-Aug, we used a 3-day exp. installation period to take a step back & look at what we have achieved & where we are going => half-day mini workshop Open workshop Invited guests not usually much involved in FACET commissioning Emma, Seeman, Raubenheimer, Safranek, Colby, England, Cai, Iverson, Corbett, Frisch, Hast, Erickson, Presentations, discussions, suggestions Web site: https://slacspace.slac.stanford.edu/sites/s0-20facetcore/startup/facet%20commissioning%20mini%20work shop/default.aspx?instanceid=1 30

Agenda 31

Workshop Outcome 50 Action Items A number of commissioning activities suggested: pencil beam studies standard operating procedures Importance of 2nd- and higher-order aberrations ways to study sextupole issues more structured planning look-ahead planning for downtime 32

Beam Parameters Achieved to Date Energy 23 GeV 19.65 GeV Charge per pulse 0.5 2.0 x 10 10 e - or e + 2.0 x 10 10 e - Bunch length at IP ( z ) 15 40 µm 65 m (THz), wakeloss similar to FFTB Typical spot size at IP ( x,y ) 10 20 µm >30-50 m on IPWIRE Repetition rate 1 30 Hz 10 Hz Momentum spread 4 0.5% 3% fw PR185, SYAG Momentum dispersion at IP ( and ) < 10-5 m achieved 0.014 m 33

The Plan Ahead * I have asked to extend the commissioning run until 15- Sept. I am optimistic this will come through Focused on beam commissioning but will allow for some user time as well. * We operate under a Rolling 7-day Plan that facilitates planning without being unduly inflexible. introduced after the mini workshop * Beam commissioning will continue to focus on reducing the beam size in all dimensions: Transverse: linac emittance, FACET final focus, IP dispersion, 2nd- and higher order effects, diagnostics Longitudinal: reliable and quantitiative bunch length measurement, linac tuning, vary R 56 in chicane (?) 34

Details * Linac tuning for PMON image & FACET spot size interleaved with user shifts (present) * Low-energy spread pencil beam studies discussed at mini workshop requires setup time, incompatible with user shifts expect to be in this mode for up-to 3 days questionable whether e.g. IPWIRE can see this beam * Sextupole effects study (coupling, aberrations) compare with simulations * Reduce beam loss activation is a real issue, potentially increasing cool-down time already we attempt to minimize the charge going through FACET * BBA program not yet complete, esp. at center of W * Calibration of diagnostics (e.g. IPWIRE, OTRs) 35

Goals (Sept. 14) * Beam size: 25 by 25 m or less (IPWIRE or OTR) * BLEN: 2000 * Calibrate BLEN/Q2 & wakeloss in m (vs THz) * Resolve IPWIRE calibration issues 36

Downtime work * We will be down mid-september until mid February Install Sector 10 e + chicane AIP Project now under L. Bentson s leadership Ready e + system e + source, PRL etc. SDR Work to begin Oct. 1st Identified need for several improvements in the linac: S19 wirescanner + quad supply to facilitate quad emittance scans S11 bunch-length monitor S02 bunch-length monitor Various software upgrades * There was an expectation to upgrade the PPS for a dedicated S20 zone Cost estimate came in @ M$ 1.4... (not incl. dark-current stoppers) Need to regroup & see how this can be done. Actual impact less than might be thought 1-hr cool-down will remain independent of this 37

Summary * FACET commissioning has been a challenging experience * The chicane optics we believe is mostly understood dispersion, aberrations still need work * We are re-learning how to minimize wakefield effects in the linac will be continuing challenge * The frontend, incl. NDR, produce the required intensity & phase-space density * As we continue making progress with beam sizes and halo, beam loss in the chicane will diminish * e + next year will provide additional challenge 38

Thank You to all Involved in getting FACET off the Ground! FACET Construction Mgt. Team: N. Phinney, J. Q. Chan, J. Sheppard, U. W. Commissioning team: next page 39

Commissioning team T. Smith W. Colocho S.P. Weathersby M. Stanek J. Nelson J. Turner H.V. Smith U. Wienands C. Clarke S. Kalsi plus AARD-PWFA members: M. Hogan S. Li E. Adli S. Gessner J. Frederico 40