Project Title: Eleven Point River Streambank Erosion Assessment

Similar documents
Birch Creek Geomorphic Assessment and Action Plan

Project Leader: Project Partners:

Project Budget: State Wildlife Grant Requested: $16,412 Project Match (UARK in kind services): $5,744 Total Project Cost: $22,156

Lower South Fork McKenzie River Floodplain Enhancement Project

Assessment. Assessment

Columbia Estuary Province

Watershed Assessment of River Stability and Sediment Supply: Advancing the Science of Watershed Analysis

PROJECT PARTNER: PROJECT PARTNER:

Subcommittee on Sedimentation Draft Sediment Analysis Guidelines for Dam Removal

GENERAL SUMMARY BIG WOOD RIVER GEOMORPHIC ASSESSMENT BLAINE COUNTY, IDAHO

NATURE OF RIVERS B-1. Channel Function... ALLUVIAL FEATURES. ... to successfully carry sediment and water from the watershed. ...dissipate energy.

Mobrand to Jones and Stokes. Sustainable Fisheries Management Use of EDT

Geomorphology Studies

Best Management Practices for Coldwater Fisheries Enhancement and Restoration

San Joaquin River Tributary Sediment Transport and Geomorphology Study

The Effects of Geomorphology and Watershed Land Use on Spawning Habitat

United States Department of the Interior NATIONAL PARK SERVICE Northeast Region

Wetland & Floodplain Functional Assessments and Mapping To Protect and Restore Riverine Systems in Vermont. Mike Kline and Laura Lapierre Vermont DEC

NORTHUMBERLAND COUNTY, PA

Natural Shoreline Landscapes on Michigan Inland Lakes

Griswold Creek August 22, 2013

Use of benthic invertebrate biological indicators in evaluating sediment deposition impairment on the Middle Truckee River, California

EAGLES NEST AND PIASA ISLANDS

Spring Run Spawning Habitat Assessment Sediment Mobility

Coarse Sediment Augmentation on Regulated Rivers. Scott McBain McBain & Trush, Inc.

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

Dam Removal Analysis Guidelines for Sediment

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

Fluvial Geomorphic Guidelines

Why Geomorphology for Fish Passage

SEARCHING FOR SEDIMENT SOURCES IN SPRING CREEK

ADDRESSING GEOMORPHIC AND HYDRAULIC CONTROLS IN OFF-CHANNEL HABITAT DESIGN

Bank Erosion and Morphology of the Kaskaskia River

Ecological Land Cover Classification For a Natural Resources Inventory in the Kansas City Region, USA

RAILWAYS AND FISH: HOW TO PROTECT AND ENHANCE FISH HABITAT VALUES AT STREAM CROSSINGS THROUGH PROJECT DESIGN AND CONSTRUCTION

Swift Creek Sediment Management Action Plan (SCSMAP)

Step 5: Channel Bed and Planform Changes

When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill

Limitation to qualitative stability indicators. the real world is a continuum, not a dichotomy ~ 100 % 30 % ~ 100 % ~ 40 %

Solutions to Flooding on Pescadero Creek Road

Session C1 - Applying the Stream Functions Pyramid to Geomorphic Assessments and Restoration Design

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013

Design of Levee Breaches in Sheltered Water for Flood Risk Reduction & Marsh Restoration ASFMP; June 5, 2014 Presented By:

Geomorphology Of The Chilliwack River Watershed Landform Mapping At North Cascades National Park Service Complex, Washington By National Park Service

Avoiding Geohazards in the Mid-Atlantic Highlands by Using Natural Stream Principles

Mapping Watershed-scale Streambank Erosion Using EPA- BANCS for Determining TMDLs

EXECUTIVE SUMMARY (Continued)

Title of the Project: Distribution and population status of Arkansas bumble bees

Fish Passage and Abundance around Grade Control Structures on Incised Streams in Western Iowa

APPENDIX A REACH DECRIPTIONS. Quantico Creek Watershed Assessment April 2011

Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018

Sediment Deposition LET THE RIVER RUN T E A C H E R. Activity Overview. Activity at a Glance. Time Required. Level of Complexity.

Roger Andy Gaines, Research Civil Engineer, PhD, P.E.

MEANDER MIGRATION MODEL ASSESSMENT FOR THE JANUARY 2005 STORM, WHITMAN PROPERTY, SAN ANTONIO CREEK, VENTURA COUNTY, CALIFORNIA

Summary Description Municipality of Anchorage. Anchorage Coastal Resource Atlas Project

Rapid Geomorphic Assessments: RGA s

Massachusetts Rivers & Roads Training

Background. North Cascades Ecosystem Grizzly Bear Restoration Plan/ Environmental Impact Statement. Steve Rochetta

Appendix I: The Summit-at-Snoqualmie Master Development Plan Proposal FEIS Physical and Biological Resource Data Tables

In-channel coarse sediment trap Best Management Practice

low turbidity high turbidity

Overview of fluvial and geotechnical processes for TMDL assessment

Validation of BEHI Model through Field Generated Data for Assessing Bank Erosion along the River Haora, West Tripura, India

Learning Objectives: I can identify and interpret river flows and directions.

The Refugia Concept: Using Watershed Analysis to Prioritize Salmonid Habitat for Conservation and Restoration

Dolores River Watershed Study

How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin?

Woodstock, Route 26 Stream Relocation Project

FOREST RESEARCH INSTITUTE, DEHRADUN

Ways To Identify Background Verses Accelerated Erosion

Savannah District s Revised SOP: Moving Towards A Functional Approach. US Army Corps of Engineers BUILDING STRONG

Working with Natural Stream Systems

Hannah Moore CEE Juvenile Bull Trout Distribution in the South Fork Walla Walla River, Oregon

Case Study 2: Twenty-mile Creek Rock Fords

APPLIED FLUVIAL GEOMORPHOLOGY

PolyMet NorthMet Project

Upper Manistee River Instream Fish Habitat Assessment

Opportunities to Improve Ecological Functions of Floodplains and Reduce Flood Risk along Major Rivers in the Puget Sound Basin

Measuring Streambank Erosion Bank Profiles to more Robustly Estimate Recession Rates and Calibration of the AnnAGNPS-CEAP Model

A GEOMORPHOLOGICAL APPROACH TO RESTORATION OF INCISED RIVERS. David L. Rosgen 1

Restoring the Napa River:

Conceptual Model of Stream Flow Processes for the Russian River Watershed. Chris Farrar

Why Stabilizing the Stream As-Is is Not Enough

Four Mile Run Levee Corridor Stream Restoration

YUBA COUNTY WATER AGENCY

The last three sections of the main body of this report consist of:

Date of Report: EPA agreement number: Center Name and Institution of Ctr. Director: Identifier used by Center for Project: Title of Project:

Kootenai River Habitat Restoration Program Update

SEDIMENT BENEFICIAL USE SUPPORT ASSESSMENT FOR OTTER CREEK

Biological Response to the Gold King Mine Release in the Animas and San Juan Rivers

PHASE 1 STREAM GEOMORPHIC ASSESSMENT. Castleton River, Rutland County Vermont. Final Report

HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE

What is a watershed or landscape perspective?

WATERSHED RESTORATION PLANNING AND PRIORITY SETTING. An Emphasis on Fish Habitat

Goundwater Seepage Mechanisms of Streambank Erosion and Failure

Little Blackfoot TPA 2009 Sediment and Habitat Assessment QAQC Review March 9, 2010

Important Copyright Information

Use of Bioengineering Techniques for Revegetation of Riparian Areas: Colomac Mine Remediation Project, NWT

CASE STUDIES. Introduction

Integrated methodology for assessing the effects of geomorphological river restoration on fish habitat and riparian vegetation

Transcription:

Project Title: Eleven Point River Streambank Erosion Assessment Project Summary: The project seeks to formally assess streambank erosion along the Eleven Point River in Arkansas, where sedimentation from streambank erosion is threatening extirpation of the endangered Ozark Hellbender. The assessment would include an investigation into historical land uses, a Bank Erosion Hazard Index survey and Near Bank Shear Stress survey to assess bank conditions and predict erosion rates. These actions would identify areas of greatest concern impacting a Species of Greatest Conservation Need within a priority watershed. The resulting data and information will be crucial to implementing conservation activities necessary to ensure long-term survival of the Ozark Hellbender. Project Leader: John Chapman, Watershed Conservation Program Director The Nature Conservancy 38 W. Trenton Blvd., Ste. 201 Fayetteville, AR 72701 john.chapman@tnc.org 479-422-4759 Project Partners: Melissa Lombardi, Biologist US Fish and Wildlife Service, Ecological Services Arkansas Field Office Melissa_lombardi@fws.gov 501-513-4488 Sean Saunders, Region 1 Stream Team Coordinator Arkansas Game and Fish Commission Sean.saunders@agfc.ar.gov 501-765-9208 Kelly Irwin, Herpetologist Arkansas Game and Fish Commission Kelly.Irwin@agfc.ar.gov 501-539-0431 Project Budget: SWG amount request: $21,660 Match provided: $11,727 Total project costs: $33,386

FY 2017 State Wildlife Grant Project Proposal Need: The endangered Ozark Hellbender is a large, strictly aquatic salamander endemic to streams of the Ozark Plateau in southern Missouri and northern Arkansas. Due to the species specialized habitat and diet requirements, changes to the aquatic environment have led to a significant reduction in hellbender populations. The Eleven Point River is a priority watershed in the Arkansas Wildlife Action Plan (AWAP) and is considered to be the last viable population of Ozark Hellbenders in the state. As noted in the AWAP, land use within the Eleven Point River watershed is rapidly changing and actions to survey physical habitat conditions within the watershed are needed to identify major threats and support conservation actions. Sediment inputs from land use activities significantly contribute to habitat degradation for a number of Species of Greatest Conservation Need in the Eleven Point River. Degraded riparian conditions and unpaved roads are presumably the two largest sources of sediment loading in the Eleven Point River. Since 2005, USFWS and Arkansas Game and Fish Commission have documented changes to habitat quantity and quality in the Eleven Point River due to sedimentation. Cover rocks necessary for Ozark Hellbenders have been embedded or completely buried at numerous sites. During monitoring efforts, artificial nest boxes have been documented to fill with fine sediment in less than three months, thereby hindering recovery efforts. This rapid siltation potentially provides insight into recruitment failure if similar siltation occurs under native cover rocks when egg clutches and larvae are present. While empirical data to document loss of cover rocks due to sedimentation are lacking, biologists with both agencies have visually observed increased fine sediments filling interstitial spaces and embedding (with fines and gravel) cover rocks at numerous sites occupied by Ozark Hellbender between the Missouri/Arkansas state line and Arkansas Highway 90. The effects of sedimentation become increasingly prominent as the Eleven Point extends downstream. An initial desktop review of historical and current aerial photography confirms channel widening due to stream bank erosion at over thirty sites between the state line and Arkansas Hwy 90. As the river channel widens and shallows, water velocity slows, leading to greater sedimentation and the shallow, slow moving water then warms. Biologists also have observed increases in aquatic macrophytes and large deposits of gravel near the confluence of tributaries following storm events, both indicators of bank erosion and resulting sedimentation throughout the reach. Purpose and Objectives: Identify and prioritize impaired reaches for potential streambank restoration in the Arkansas portion of the Eleven Point River with suitable habitat for Ozark Hellbender. This will be accomplished by completing a reconnaissance level survey of stream bank conditions, accompanied by validation of predicted erosion rates/sediment loads. A Bank Erosion Hazard Index (BEHI) survey will be conducted, which involves collecting streambank characteristics and conditions which affect bank erosivity. Near Bank Shear Stress (NBSS) will be estimated for each bank and, in conjunction with BEHI data, used to predict annual erosion rates for each impaired reach. Lateral erosion rates will be measured over a one-year period at the highest ranking reaches to validate the predicted values.

Geographic location: The Eleven Point River starting at the Arkansas/Missouri line and extending down river approximately 23 river miles to Arkansas Highway 90 (suitable habitat reach). See attached map. Approach: Record BEHI and NBSS data using a mapping grade GPS. This involves recording measurements of bank heights, angles, materials, presence of soil layers, rooting depth, rooting density, and percent of bank protection. These variables will be used to develop a streambank erodibility index and create a map using ESRI s ArcGIS. On this map, the attribute values of each section of stream are assigned an output risk rating from 1 to 10 indicating corresponding adjective values of risk as very low, low, moderate, high, very high, and extreme potential erodibility. A NBSS estimation will also be completed to predict total bank erosion, based on stream bank erodibility curves. The project would be expected to start in October 2017 with a reconnaissance level assessment, followed by BEHI and NBSS surveys in winter 2017/2018. Lateral erosion at high-risk reaches will be measured over the following year. All objectives should be accomplished within 2 years of start date, depending on flow characteristics. Results or benefits expected: The data produced from this study will identify the most critical reaches contributing sediment to the Arkansas portion of the Eleven Point River containing populations of the Ozark Hellbender. This data will help guide future streambank restoration priorities for improving riparian and instream conditions. Budget narrative: The total requested amount for this project is $21,660. TNC will provide match through supplies. Additional match will be provided by AGFC through staff time and travel to assist with the project. The combined match sources will provide $11,727, for a total project cost of $33,836. See Table 1 for estimated budget. Category Table 1: ESTIMATED BUDGET Salaries and Benefits $13,250 Travel $4,328 Supplies Other $0 Subtotal $ 17,578 Indirect Cost * $4,082 TOTAL $21,660 * TNC's indirect cost rate in its FY 18 NICRA is 23.22%. TNC's indirect rate is negotiated annually, and TNC will charge indirect at the federally approved rate each year.

Staff Qualifications: John Chapman, TNC - Watershed Restoration Program Director Responsible for overseeing the project. He is a graduate of the University of Arkansas at Monticello with a B.S. in Spatial Information Systems. He specializes in watershed and geomorphic assessments and design and implementation of stream restoration projects using natural channel design techniques. He has completed four intensive courses in Applied Fluvial Geomorphology and Natural Channel Design led by instructor Dave Rosgen, Ph.D., conducted numerous geomorphic surveys, and worked to implement stream restoration projects on the West Fork of the White River, Kings River, and Little Osage Creek. He also has 15 years of experience in the Geographic Information Systems (GIS) field. Chas McCoy, TNC Stream Restoration Technician Chas will provide support for various aspects of the project. He has a B.S. in Environmental Science from the University of Portland, Oregon and 8 years of experience in watershed management and stream restoration. He has completed Introduction to Applied Fluvial Geomorpholgy (Rosgen 1) by Dave Rosgen, Ph.D., and coursework in river restoration processes and design from Portland State University to receive a River Restoration Certificate. Chas has conducted BEHI and NBSS assessments in the Kings River watershed and is knowledgeable about stream processes. Dr. Melissa Lombardi, USFWS Endangered Species Biologist Dr. Lombardi is a veterinarian with the U.S. Fish and Wildlife Service. Her education includes: M.Sc. Fisheries and Wildlife Science, Arkansas Tech University (2014); DVM, Louisiana State University School of Veterinary Medicine (2000); B.A., Hendrix College (1995). Dr. Lombardi has worked with the Ozark hellbender at the St. Louis Zoo Ron Goellner Center for Hellbender Conservation and in interagency surveys and habitat enhancement projects on the Eleven Point River in Arkansas. Sean Saunders Sean Saunders graduated from the University of Arkansas at Little Rock in 2008 with a B.S. in Wildlife Management with an Emphasis on Fisheries. Upon graduation he worked as an intern for the AGFC under Stream Team Coordinator Stephen O Neal where he began his training in stream restoration. When the internship ended Sean took a position with the AGFC at the Jim Hinkle Spring River Hatchery and volunteered his free time to work with now retired Stream Team Coordinator Dave Evans and the Trout Habitat Manager Tim Burnley to increase his knowledge in stream restoration. In 2012 he took a position with the Arkansas Department of Environmental Quality (ADEQ) as a Water Inspector. This position allowed him to receive vast training and knowledge in water regulations and erosion. In 2015 Sean left ADEQ and took a Stream Team Coordinator position with the AGFC. Since returning to the AGFC as the Stream Team coordinator Sean has gone through Dr. Newbury s riffle training and Dr. Dave Rosgen s Level 1-3 training with plans to attend level 4 in September 2017.

Kelly Irwin, AGFC - Herpetologist Kelly Irwin began work as the first herpetologist for the Arkansas Game & Fish Commission in 2000. He is responsible for the conservation and management of the ~130 species of native amphibians and reptiles of Arkansas. In 2005, he initiated a long-term monitoring program on the Ozark Hellbender population in the Eleven Point River. Since 2012, he has been involved in the construction and maintenance of artificial shelters/ nest boxes in the river as a means to augment habitat and provide a possible source of egg clutches for captive propagation efforts at the St Louis Zoo Hellbender Conservation Center.