A new design approach for highway rock slope cuts based on ecological environment protection

Similar documents

CONTROLLING FACTORS BASIC ISSUES SAFETY IN OPENCAST MINING WITH SPECIAL REFERENCE TO SLOPE STABILITY

Introduction and Background

The Mine Geostress Testing Methods and Design

Underground Excavation Design Classification

Rock slope rock wedge stability

COMPARING THE RMR, Q, AND RMi CLASSIFICATION SYSTEMS

Rock slope failure along non persistent joints insights from fracture mechanics approach

Landslide FE Stability Analysis

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Further Research into Methods of Analysing the October 2000 Stability of Deep Open Pit Mines EXECUTIVE SUMMARY

Table of Contents Development of rock engineering 2 When is a rock engineering design acceptable 3 Rock mass classification

NNN99. Rock Engineering for the Next Very Large Underground Detector. D. Lee Petersen CNA Consulting Engineers

CHAPTER FIVE 5.0 STABILITY OF CUT SLOPES IN THE STUDY AREA. them limited by a thick canopy of vegetation and steep slope angles.

Correlation of Revised BQ System in China and the International Rock Mass Classification Systems

Building on Past Experiences Worker Safety

MEMORANDUM SUBJECT: CERTIFICATE IN ROCK MECHANICS PAPER 1 : THEORY SUBJECT CODE: COMRMC MODERATOR: H YILMAZ EXAMINATION DATE: OCTOBER 2017 TIME:

EOSC433: Geotechnical Engineering Practice & Design

The effect of discontinuities on stability of rock blocks in tunnel

Curriculum Document Mining Technician: Strata Control Practitioner (Surface) Occupational Curriculum

Module 9 : Foundation on rocks. Content

Chapter 6 Bearing Capacity

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS

Session 3: Geology and Rock Mechanics Fundamentals

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309

TWO DIMENSIONAL MODELING AND STABILITY ANALYSIS OF SLOPES OVERLAYING TO SHAHID RAGAEE POWER PLANT

Construction Technical Specifications on Rock-Foundation Excavating Engineering of Hydraulic Structures

1 of 46 Erik Eberhardt UBC Geological Engineering ISRM Edition

An introduction to the Rock Mass index (RMi) and its applications

August 10, 2007 File:

ROCK SLOPE STABILITY ANALYSES

J. Paul Guyer, P.E., R.A.

End-wall Slope Stability Analysis of Surface Coal Mine under the Combined Open-pit Mining with Underground Mining

Structurally controlled instability in tunnels

A Unique Metro Accident in Brazil Caused by Multiple Factors

Appendix 6 Geotechnical report

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE. METALLIFEROUS MINING OPTION Updated November 1998

FIELD MONITORING OF STABILITY OF DUMP A CASE STUDY

1. Rock Mechanics and mining engineering

Study of Soft Rock Roadway Support Technique

Quantitative Classification of Rock Mass

Ground support modelling involving large ground deformation: Simulation of field observations Part 1

INFLUENCE OF AIR-DECK LENGTH ON FRAGMENTATION IN QUARRY BLASTING

CHRACTERISTICS OF LANDSLIDE OCCURRED IN LOPARE, BOSNIA AND HERZEGOVINA

Kinematic Analysis Underground Wedges

Effect of Displacement Loading Rate on Mechanical Properties of Sandstone

Empirical Design in Geotechnical Engineering

3/8/17. #20 - Landslides: Mitigation and Case Histories. Questions for Thought. Questions for Thought

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE COAL MINING OPTION

Unloading Phenomena Characteristics in Brittle Rock Masses by A Large- Scale Excavation in Dam Foundation

Stability Assessment of a Heavily Jointed Rock Slope using Limit Equilibrium and Finite Element Methods

Instructional Objectives. Why use mass classification? What is rock mass classification? 3 Pillars of empirical design and rock mass classification

PLANES OF WEAKNESS IN ROCKS, ROCK FRCTURES AND FRACTURED ROCK. Contents

Drainage Used to Control Movements of a Large Rock Slide in Canada

SITE INVESTIGATION 1

Open Access Support Technique of Horse Head in Weakly Cemented Soft Rock

CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM

GEO The Åknes rock slope. Content. Dr. Vidar Kveldsvik NGI

Test Study on Strength and Permeability Properties of Lime-Fly Ash Loess under Freeze-Thaw Cycles

The stability of a large slope after impoundment by using 3D numerical modeling at the reservoir

Slope stability analysis and prediction based on the limit equilibrium method of Luming Molybdenum Mine's West-I and North Region

TINTAGEL CASTLE FOOTBRIDGE OPTIONS APPRAISAL. Feasibility Report July 2014

Open Pit Rockslide Runout

Slope Stability. loader

Landslide Granice in Zagreb (Croatia)

Prevention and remediation of rockslide at left portal of north tunnel of Da Nang Qu ang Ngai expressway in Quang Nam, Vietnam

Behaviour of Blast-Induced Damaged Zone Around Underground Excavations in Hard Rock Mass Problem statement Objectives

Mass Wasting. Requirements for Mass Wasting. Slope Stability. Geol 104: mass wasting

A STUDY ON THE BLASTING VIBRATION CONTROL OF CREEP MASS HIGH SLOPE

Experimental Research on Ground Deformation of Double Close-spaced Tunnel Construction

Deformation And Stability Analysis Of A Cut Slope

Mass Wasting. Revisit: Erosion, Transportation, and Deposition

LANDSLIDES IN THE WHITE MOUNTAIN (GEOTECHNICAL STUDIES AND ENGINEERING TESTS)

Geotechnical & Mining Engineering Services

Methods of Interpreting Ground Stress Based on Underground Stress Measurements and Numerical Modelling

Influence of foliation on excavation stability at Rampura Agucha underground mine

Analysis stability of rock slope at left bank of South portal of North tunnel Da Nang Quang Ngai expressway

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

7. Foundation and Slope Stability

Need of Proper Development in Hilly Urban Areas to Avoid

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

Geotechnical Monitoring for Safe Excavation of Large Rock Cavern: A Case Study

January 17, 2008 File:

GROUND RESPONSE AND SUPPORT MEASURES FOR PIR PANJAL TUNNEL IN THE HIMALAYAS

Shear strength model for sediment-infilled rock discontinuities and field applications

Numerical Study of Relationship Between Landslide Geometry and Run-out Distance of Landslide Mass

Numerical modelling for estimation of first weighting distance in longwall coal mining - A case study

Module 6: Stresses around underground openings. 6.2 STRESSES AROUND UNDERGROUND OPENING contd.

Risk assessment of collapse in shallow caverns using numerical modeling of block interactions with DDA: Suggested approach and case studies

LICENTIATE THESIS. Evaluation of rock mass strength criteria. Catrin Edelbro

Module 9 : Foundation on rocks

ENGINEERING GEOLOGY AND ROCK ENGINEERING ASPECTS OF OPERATION AND CLOSURE OF KBS-3

ON THE FACE STABILITY OF TUNNELS IN WEAK ROCKS

The results of KCB s site inspection observations and our recommendations for further work are presented herein.

Stability Analysis of Hongsa Coal Mine s Pit Walls, Xaignabouli Province, Laos PDR. Thanachot Harnpa* Dr.Schradh Saenton**

Research on the Concrete Dam Damage and Failure Rule under the Action of Fluid-Solid Coupling

ENGINEERING GEOLOGY AND ROCK ENGINEERING

Collapse Analysis of Jointed Rock Slope Based on UDEC Software and Practical Seismic Load

Roadway Support Technology with Sliding Cracking Surrounding Rock under Tectonic Stress

ROCK EXCAVATION (GRADING) OPSS 206 INDEX

Transcription:

A new design approach for highway rock slope cuts based on ecological environment protection T. Lian-jin, Z. Li, W. Yunjie, W. Guang-yuan & Z. Yin-tao College of Architecture and Civil Engineering, Beijing University of Technology, Beijing, China S. Zhihui Zhong Zi Hua Ke Traffic Construction Techonolgy Co.Ltd. ABSTRACT: With China's fast development, especially that of highways in mountainous areas, there are many unavoidable high cut rock slopes. Specifications for the design of highways in China prescribe that the design of any slope with a height of more than 30m should be compared with bridge and tunnel design schemes, economically. Despite existing guidelines, many high slopes are designed as equally high cuts based on traditional design methods, due to the engineering geological conditions and highway alignment. Actually, these excessively high cuts relative to the natural slope height seriously damages the original ecological environment and groundwater systems, in some cases irreversibly. With the aim of reducing ecological damage, we propose a new design approach which minimizes the ecological and environmental disturbance by decreasing the amount of cut slope through a steep excavation scheme. This approach requires that: (1) the geological conditions are good and the rockmass is self stable; (2) damage to the rock is minimized through use of controlled blasting (buffers, pre-splits); (3) a 20-m high bench be introduced if the local geological conditions are not very good; (4) reinforcement is added where needed to ensure stability during construction; and (5) deformation of the slope and working condition of the reinforcement be monitored to ensure stability. This new design is demonstrated through its application to a cut slope along the provincial trunk highway S223 in Guangdong province. Results from numerical modeling using UDEC reveal that compared with a traditional design scheme for which the cut would be 90 m high, a steeper cut limiting the height to 23.5 m, with the remaining height following its natural profile, would generate a comparable stability state. With cable reinforcement, the stability of slope excavated steeply can be further assured. 1 INTRODUCTION With China's fast growing economy, numerous road construction projects have obtained great achievements. However, with highway construction, especially in mountainous areas, there are many unavoidable high cut slopes. Specifications for the design of highway subgrades prescribe that the design scheme of slopes with heights greater than 30m should be compared with bridge and tunnel schemes, economically (JTGD-30 2004). Despite existing guidelines, it is still quite common to see many high slopes being designed as high cuts due to the engineering geological conditions, highway alignment, costs and issues related to traditional design ideas. In some cases, the traditional design method of high backfill, high cut for mountainous highways seriously damages the original ecological environment and groundwater systems, especially to those areas that are ecologically sensitive where damage is often irreversible. It is quite common practice to add vegetation to greenify a cut slope, however this still has problems such as low survival ratios, high maintenance costs and lack of species diversity. With increased awareness of the importance of the ecological environment, it becomes more urgent to decrease the damage to the ecological environment while ensuring stability during the engineering of high cut slopes. PAPER 4420 1

With the aim of reducing ecological damage, we propose a new design approach which helps reduce ecological and environmental damage by reducing the height of a cut for a high rock slope by steepening the angle of the cut, while ensuring that the slope is both safe and economically feasible. 2 ANALYSIS OF STEEP SCHEME 2.1 Conditions required for steep scheme Although the proposed design scheme results in a reduction in the height of the cut slope, it calls for steepening of the cut, which requires that the geological conditions are favorable, the rock strength high, and the rock mass massive (few joints) and no more than slightly weathered. The rock at the toe of the slope must be stable and self supporting. 2.2 Construction considerations Before construction of slope, it is necessary to construct a surface drainage system (e.g. drainage ditch, intercepting ditch, etc.), as well as incorporate other drainage measures (drain holes, underground drainage tunnel, etc.) as the local groundwater conditions require. During construction, excavation, reinforcement and monitoring should be integrated together, and monitoring should be started even during construction. If the local geological conditions and rock mass quality are not very good, the excavation should incorporate benching, with the advised spacing of 20 m. The steep scheme is based on the rock mass strength being high. If the rock mass is damaged because of uncontrolled blasting, it will be more difficult to ensure stability even if reinforcement measures are taken. Thus, the excavation process should be controlled using buffer blasting, smooth blasting and pre-split blasting. Because rainfall usually postpones construction and causes high water pressures to build up along potential sliding surfaces, decreasing the material strength, it is advised that construction be avoided during rainy seasons when implementing the steep scheme. 2.3 Stability evaluation The stress distribution within the slope can be easily determined using numerical methods like distinct element modeling, with results showing the maximum principal stress being parallel to the slope, with a stress concentration developing at the toe. The iso-line of the maximum shear stress is near circular at the slope toe and the rest almost parallel to the slope surface (Zhang et al. 1994). If the rock strength is low, this shear stress concentration may result in the generation of a plastic zone at the toe and tensile cracks behind the slope crest. The deformation in the horizontal direction caused by the excavation is a key index of slope stability. Given the steeper cut in the steep scheme, upon excavation the redistribution of stresses at the slope's toe will be more significant than that implementing slope angles following traditional design schemes. If reinforcement is not strong enough and in time, these have high stress concentrations may result in excessive yielding and the slope may become unstable. 2.4 Advantages of steep scheme Compared with common cut slope designs, the steep scheme is ecological environmentally more friendly because it decreases the cut slope height, the excavated quantity of rock and soil, the amount of slope surface disturbed and engineering cost. Most importantly, the steep scheme results in less natural vegetation being removed. Figure 1 shows the difference in cut slope profile between the common and steep schemes. Because the slope height is remarkably decreased, difficulties associated with construction and maintenance of the slope is reduced greatly. PAPER 4420 2

110 100 90 80 Nat ur al sl ope sur f ace 70 60 50 40 30 Sl ope sur f ace wi t h common scheme Sl ope sur f ace wi t h st eep scheme 20 10 0 0 10 20 30 40 50 60 70 80 90 100 110 120 Figure 1. Illustration comparing the cut slope profiles for the common and steep design schemes. 3 CASE STUDY To illustrate the application of the new design approach, a case study is provided including a detailed analysis using the steep scheme design method. The slope is a typical roadside cut slope along the provincial trunk highway S223 in Guangdong province. The road is on the right side of Meijiang River, the width of subgrade is 22.5m and the natural slope is relatively steep. 3.1 Engineering geological conditions Four test exploration holes extending under the base of the slope were drilled to obtain information on the strata. At the top of the slope is a fully weathered sandstone and mudstone 1.5-3 m thick. Below this, in the middle of slope, is a strongly weathered sandstone with a thickness of 3-6 m. At the bottom of slope is a slightly weathering sandstone with a thickness of 6-12 m. The uniaxial compressive strength of the bottom unit varies ranges from 24.9-49.6 MPa, so the rock falls in the category of hard rock with a RQD equal to 50-90% (Zuyin 2006). Based on the intensive site investigation undertaken before excavation and construction, a detailed engineering geological map was constructed incorporating discontinuity and other geological structure statistics. The rock mass is bedded and locally fissile. The RQD index is mainly 65, so the rock mass is relatively intact. The strata reversely dips into slope, with layer thicknesses of the strata varying between 0.3-0.9 m. There is a group of conjugated shear joints with spacing 0.2-0.7 m and a small fault which dips steeply out of the slope with little influence on the slope stability. The nature of rock deformation may be controlled by the joint orientation, joint spacing and persistence. A summary of the main discontinuity data is shown in Figure 2. The nature of the discontinuity surfaces, such as infill, roughness and weathering are important factors. The infill materials in the discontinuities are characterized as sandy clay and remolded clay, containing fragments of sandstone, which is very significant for stability. The Slope Mass Rating (SMR) classification system is a potentially very useful tool in the preliminary assessment of slope stability, providing information about instability modes and required support measures (Banks 2005). For the case study, the rock is intact and sound, and there is no disadvantageous intersecting structures. The RMR for this slope rates in category III, and the steep slope ratio is considered in the classification. PAPER 4420 3

Figure 2. Main joints relative to slope surface for the case study. 3.2 Original common scheme The original design followed that using typical design approaches, and is referred here as the common scheme. The common scheme design would call for a cut slope height of 90 m with 12 benches. The height of each bench is 8m, with bench widths of only 1 m. The slope ratio of the three benches at the bottom of the slope is 1:0.5. These are reinforced with 20m long cable anchors designed with a working tension of 500 kn. The remaining benches follow a slope ratio of 1:0.75 and are only protected with spray-on grass seeding (Li 2007). A typical slope section is shown in Figure 1. The design is that typically applied to such slopes, with a gentle excavated slope ratio and light reinforcement. Obviously more soil and rock has to be removed as well as the natural vegetation on top, which is environmentally unfriendly. Because the natural mountain slope is quite steep and stable, if adopted, the cut slope would be less steep than the natural slope resulting in a cut height of more than 90m. This means that the cut slope would require most of the natural slope to excavated, disturbing and removing most of the natural vegetation that grows on it. 3.3 New method: The steep scheme The structural stability of slope was evaluated using the stereonet projection based on rock mass mapping and discontinuity analysis from the boreholes. It is concluded that the geological condition is rather good and satisfies the requirements of the steep scheme. Thus, the steep scheme is put forward as shown in Figure 1: (1) The total height of the slope is 23.5 m, and the ratio of the steep scheme is 1:0.2. There is one bench with a height of 10 m and width of 2 m. The cut slope height above the bench is 13.5 m. (2) The bench at the bottom is reinforced with anchor bolts with 8 m length and 60 kn design load. Their spacing in the vertical direction is 3.5 m and in the horizontal direction 3 m. The upper cut slope above the bench is reinforced with cable anchors, with 18 m lengths and a designed load of 500 kn. The spacing is the same as the anchor bolts. PAPER 4420 4

3.4 Parameter analysis The limit equilibrium method was used to understand the principal factors involved for estimating the factor of safety. The potential failure surface is assumed to be a compound slide based on the site investigation, so we chose the Bishop method in accordance with the site conditions. Because the rock classification index RMR for this slope is III, the equivalent angle of internal friction may be estimated as 45-55 based on the Technical Code for Building Slope Engineering (GB-50330 2002). A sensitivity analysis was performed for key input parameters such as the angle of internal friction and orientation of cable installation. The analysis results are summarized in Figure 3. We can infer from Figure 3a that if the equivalent angle of internal friction is set to 50, the anchor force almost decreases with the cable angle linearly. In contrast, Figure 3b shows that if the cable angle is set at 15, the greater the friction angle, the snaller the anchor force provided from the cable anchors. The cable angle and angle of internal friction both influence the anchor force considerably, especially the latter. The angle of internal friction of 50 o and cable angle of 20 o based on the geological conditions and numerical results, produces a safety factor of 1.3, which satisfies the requirement of the design code. 75 The equat i ve angl e of i nt er nal friction φ =50 The anchor age f or ce( T) 74 73 72 71 (a) 70 8 10 12 14 16 18 20 22 24 26 Cabl e angl e( ) 100 cabl e angl eβ = 15 The anchor age f or ce( T) 90 80 70 60 50 (b) 40 44 46 48 50 52 54 56 The equat i ve angl e of i nt er nal f r i ct i on φ ( ) Figure 3. Relationships between: a) anchor force and cable angle; and b) anchor force and friction angle. PAPER 4420 5

3.5 Monitoring of the steeply cut slope Deformations at depth and those on surface were monitored by borehole inclinometer and a high-precision total station. The results from the latter are summarized in Figure 4. The working condition of the reinforcement was monitored by cable force gauges, with the results summarized in Figure 5. Note that because of the influence of excavation sequencing, the data plotted in the two figures are not identically corresponding. The monitored force on the cable did not satisfy the demands of the design load at the beginning, so the cable was re-tensioned. The deformation of the slope decreases gradually and the final deformation is very small based on the monitoring data. The change in cable tensions were likewise small after the cables were re-tensioned. No open tension crack behind the cut crest was observed during excavation and after construction had finished. Monitoring is still ongoing and the data shows that the steep slope should be stable during its operational life. 0 Deformation (mm) -2-4 -6 0 20 40 60 80 100 Time (Day) Figure 4. Horizontal deformation response of cut slope. 520 500 480 Cable force (kn) 460 440 420 400 380 Cable 1 Cable 2 360 340 320 0 20 40 60 80 100 120 140 Time (Day) Figure 5. Histories of cable force response. PAPER 4420 6

3.6 Economic comparison between the two schemes Compared with the common scheme, the steep scheme saves 540,000 RMB (US$80,000) in cost. The detailed breakdown in the excavation amount and cost is summarized in Table 1. Compared with the common scheme, the steep scheme is both economical and ecological environmentally friendly. In general, the steep excavation approach decreases slope height, the excavated volume, disturbance of the natural slope surface and engineering cost. In addition, due to the decreasing slope height, construction difficulties and future maintenance is greatly reduced. Table 1. Comparison of the two excavation methods. Slope height (m) Excavated volume (m 3 ) Surface area of excavated slope (m 2 ) Engineering cost (RMB * ) Common scheme 90.2 7.57E+05 8.11E+05 1,780,000 Steep scheme 23.5 1.64E+05 9.50E+04 1,240,000 * RMB = China Yuan. 4 CONCLUSIONS By introducing the steep excavation scheme to the case study, the following conclusions may be drawn: (1) The steep excavation scheme requires that the engineering geological conditions are good, the rockmass self-stable; if the local geological conditions are not very sound, the excavation should be benched. (2) The steep scheme also requires that the excavation process should not badly damage the rock. To do so controlled blasting measures may be required and/or the cut slope should be reinforced more strongly than usual. (3) The deformation of the slope and the working conditions of the reinforcement should be monitored to see how the slope responds. (4) The steep excavation is better than the traditional scheme in terms of ecological environmental effect, slope height, the excavated amount of rock and soil, the amount of disturbed area on the slope surface, and engineering cost. (5) If the geological conditions permit, the steep cut scheme, which can ensure that slopes are both safe and economically sustainable, should be used preferentially. With cable reinforcement, the stability of the steeply excavated slope can be guaranteed. Deformation of the slope and the cable force are monitored in detail during the construction period. The deformation data showed that slope movements decreased gradually with the final deformation being very small. The cable tensions indicated the need to re-tension the anchors, with subsequent tensions being small. It is optimistically estimated that the steep slope should be stable during operation. Comparison between the steep and common schemes affirms that the steep excavation is better than the traditional scheme in terms of ecological environmental impact, cut slope height, the excavated volume, the disturbed slope surface area, and engineering cost. It is concluded that if geological conditions permit, the steep cut scheme should be used given its benefits ACKNOWLEDGEMENTS This research is sponsored by the project: Mountainous village and small town geohazard prevention technology, National Key Technology R&D Program, and Guangdong Transportation Research Fund. PAPER 4420 7

REFERENCES Banks, D. 2005. Rock mass rating (RMR) predicted from slope angles of natural rock outcrops. International Journal of Rock Mechanics & Mining Science 42:440-449. GB-50330 2002. Technical Code for Building Slope Engineering. (in Chinese). JTGD-30 2004. Specifications for Design of Highway Subgrades. (in Chinese). Li, Z. 2007. Numerical analysis and monitoring for stability evaluation of roadside cut rock slopes. Master s Thesis, Beijing University of Technology. Zhuoyuan, Z., Shitian, W. & Lansheng, W. 1994. Fundamentals of engineering geological analysis. Geological Publishing House. Zuyin, Z. 2006. Stability analysis on high cut slopes along riverside highway. Master s thesis, Beijing University of Technology. (in Chinese). PAPER 4420 8