World Academy of Science, Engineering and Technology International Journal of Geotechnical and Geological Engineering Vol:11, No:9, S.

Similar documents
Saving on the Geotechnical Investigation A False Economy

Engineeringmanuals. Part2

Chapter 12 Subsurface Exploration

Liquefaction Induced Negative Skin Friction from Blast-induced Liquefaction Tests with Auger-cast Piles

Lesson 25. Static Pile Load Testing, O-cell, and Statnamic. Reference Manual Chapter 18

Cone Penetration Testing in Geotechnical Practice

CPT Guide 5 th Edition. CPT Applications - Deep Foundations. Gregg Drilling & Testing, Inc. Dr. Peter K. Robertson Webinar # /2/2013

Discussion: behaviour of jacked and driven piles in sandy soil

Deep Foundations 2. Load Capacity of a Single Pile

Interpretation of Pile Integrity Test (PIT) Results

DRILLED DISPLACMENT PILE PERFORMANCE IN COASTAL PLAIN AND RESIDUAL SOILS

OP-023. INTERPRETATION OF INSTRUMENTED TEST PILE RESULT

14 Geotechnical Hazards

(C) Global Journal of Engineering Science and Research Management

INTRODUCTION TO STATIC ANALYSIS PDPI 2013

Measurement of effective stress shear strength of rock

ISC 5 SELF-BORING PRESSUREMETER TESTS AT THE NATIONAL FIELD TESTING FACILITY, BALLINA 5 9 SEPT 2016

Boreholes. Implementation. Boring. Boreholes may be excavated by one of these methods: 1. Auger Boring 2. Wash Boring 3.

Analysis of a single pile settlement

Neutral Plane Method for Drag Force of Deep Foundations and the AASHTO LRFD Bridge Design Specifications

AN ABSTRACT OF THE THESIS OF

NEW DOWN-HOLE PENETROMETER (DHP-CIGMAT) FOR CONSTRUCTION APPLICATIONS

Conventional Field Testing & Issues (SPT, CPT, DCPT, Geophysical methods)

THE STRUCTURAL DESIGN OF PILE FOUNDATIONS BASED ON LRFD FOR JAPANESE HIGHWAYS

The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

Soil Behaviour Type from the CPT: an update

SITE INVESTIGATION 1

TC211 Workshop CALIBRATION OF RIGID INCLUSION PARAMETERS BASED ON. Jérôme Racinais. September 15, 2015 PRESSUMETER TEST RESULTS

Theory of Shear Strength

Landslide FE Stability Analysis

S E C T I O N 1 2 P R O D U C T S E L E C T I O N G U I D E - H E L I C A L S C R E W P I L E F O U N D A T I O N S

LRFD Calibration of Axially-Loaded Concrete Piles Driven into Louisiana Soils

Analysis of Load Carrying Capacity of a Single Pile in Weathered Rock

Soil Mechanics Brief Review. Presented by: Gary L. Seider, P.E.

Cavity Expansion Methods in Geomechanics

SHEAR STRENGTH OF SOIL

STUDY ON CONSOLIDATION OF ALLUVIAL CLAY IN NORTHERN QUEENSLAND

Chapter (11) Pile Foundations

IN SITU TESTING TECHNOLOGY FOR FOUNDATION & EARTHQUAKE ENGINEERING. Wesley Spang, Ph.D., P.E. AGRA Earth & Environmental, Inc.

PILE LOAD TEST IN OLD ALLUVIUM

Geotechnical Engineering Report

Soil type identification and fines content estimation using the Screw Driving Sounding (SDS) data

LECTURE 10. Module 3 : Field Tests in Rock 3.6 GEOPHYSICAL INVESTIGATION

Piles and Pile Foundations

Modelling installation of helical anchors in clay

Improving site specific modified driving formulae using high frequency displacement monitoring

Minnesota Department of Transportation Geotechnical Section Cone Penetration Test Index Sheet 1.0 (CPT 1.0)

Clayey sand (SC)

ENCE 3610 Soil Mechanics. Site Exploration and Characterisation Field Exploration Methods

Geotechnical issues in seismic assessments: When do I need a geotechnical specialist?

Performance and Post Earthquake Assessment of CFA Pile Ground Improvement 22 February 2011 Christchurch, New Zealand Earthquake

UNIVERSITY OF BOLTON WESTERN INTERNATIONAL COLLEGE FZE BENG (HONS) CIVIL ENGINEERING SEMESTER TWO EXAMINATION 2016/2017 GROUND AND WATER STUDIES 2

Geotechnical Indications Of Eastern Bypass Area In Port Harcourt, Niger Delta

SIMULATION OF AUGER DISPLACEMENT PILE INSTALLATION

Bored Sockets in weathered Basalt

Liquefaction and Foundations

The attitude he maintains in his relation to the engineer is very well stated in his own words:

Calibration of Resistance Factors for Drilled Shafts for the 2010 FHWA Design Method

APPENDIX A. Borehole Logs Explanation of Terms and Symbols

Geotechnical verification of impact compaction

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

GEOTECHNICAL ENGINEERING II. Subject Code : 06CV64 Internal Assessment Marks : 25 PART A UNIT 1

Minnesota Department of Transportation Geotechnical Section Cone Penetration Test Index Sheet 1.0 (CPT 1.0)

SHEAR STRENGTH OF SOIL

Axially Loaded Piles

Pile Foundation Bearing Capacity Characteristics of Volcanic Ash in Hokkaido, Japan

Collapsible Soils Definitions

Jose Brito, Cenor, Portugal

A presentation of UniPile software for calculation of Capacity, Drag Force, Downdrag, and Settlement for Piles and Piled Foundations

Evaluation of the Liquefaction Potential by In-situ Tests and Laboratory Experiments In Complex Geological Conditions

General. DATE December 10, 2013 PROJECT No TO Mary Jarvis Urbandale/Riverside South Development Corporation

Harmonized European standards for construction in Egypt

Back-analysis and interpretations of driven and bored pile tests data in Bangkok sub-soils

IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6

From - To 0,00-4,90 4,90-6,40 6,40-8,60 8,60-9,60 9,60-10,50 10,50-12,00 12,00-14,80 14,80-15,80 15,80-19,30 19, ,00

Role of the Geotechnical Consultant in Design Build Projects a General Contractors Geotechnical Engineer s Perspective

Shear Strength of Soils

Prof. Dr.-Ing. Martin Achmus Institute of Soil Mechanics, Foundation Engineering and Waterpower Engineering. Offshore subsoil investigations

Modified Dry Mixing (MDM) a new possibility in Deep Mixing

USE OF CPT/CPTU FOR SOLUTION OF

Numerical modelling of tension piles

Use of Recharge Impulse Technology in Deep Foundations Set-up Wafi Bouassida1, a, Essaieb Hamdi1, b, Mounir Bouassida1, c and Youri Kharine2, d

Bored and driven pile testing in Bangkok sub-soils

Theory of Shear Strength

PERFORMANCE OF BITUMINOUS COATS IN REDUCING NEGATIVE SKIN

LRFD Application in Driven Piles (Recent Development in Pavement & Geotech at LTRC)

Geotechnical Engineering Report

Geotechnical Engineering Study, Conifer Senior High School Football Field Improvements, Conifer, Colorado

Drawing up of a geotechnical dossier for the stabilization of historical quay walls along the river Scheldt in Antwerp

SOME GEOTECHNICAL PROPERTIES OF KLANG CLAY

INVESTIGATION OF SATURATED, SOFT CLAYS UNDER EMBANKMENTS. Zsolt Rémai Budapest University of Technology and Economics Department of Geotechnics

Geotechnical Subsoil Investigation for the Design of Water Tank Foundation

Table 3. Empirical Coefficients for BS 8002 equation. A (degrees) Rounded Sub-angular. 2 Angular. B (degrees) Uniform Moderate grading.

TRANSPORTATION RESEARCH BOARD. Static and Seismic Design of Piles for Downdrag. Thursday, October 4, :00-3:30 PM ET

Cone Penetration Test (CPT) Interpretation

EXTENSION OF A HOTEL IN POIANA BRASOV ON AN INCLINED SLOPE

Mitigation of Liquefaction Potential Using Rammed Aggregate Piers

Manual on Subsurface Investigations National Highway Institute Publication No. FHWA NHI Federal Highway Administration Washington, DC

GEOTECHNICAL INVESTIGATION REPORT

SOME OBSERVATIONS RELATED TO LIQUEFACTION SUSCEPTIBILITY OF SILTY SOILS

Transcription:

Design and Construction Validation of Pile Performance through High Strain Pile Dynamic Tests for both Contiguous Flight Auger and Drilled Displacement Piles S. Pirrello Abstract Sydney s booming real estate market has pushed property developers to invest in historically no-go areas, which were previously too expensive to develop. These areas are usually near rivers where the sites are underlain by deep alluvial and estuarine sediments. In these ground conditions, conventional bored pile techniques are often not competitive. Contiguous Flight Auger (CFA) and Drilled Displacement (DD) Piles techniques are on the other hand suitable for these ground conditions. This paper deals with the design and construction challenges encountered with these piling techniques for a series of high-rise towers in Sydney s West. The advantages of DD over CFA piles such as reduced overall spoil with substantial cost savings and achievable rock sockets in medium strength bedrock are discussed. Design performances were assessed with PIGLET. Pile performances are validated in two stages, during constructions with the interpretation of real-time data from the piling rigs on-board computer data, and after construction with analyses of results from high strain pile dynamic testing (PDA). Results are then presented and discussed. High Strain testing data are presented as Case Pile Wave Analysis Program (CAPWAP) analyses. Keywords Contiguous flight auger, case pile wave analysis, high strain pile, drilled displacement, pile performance. I. INTRODUCTION HE increasing rise in house pricing within Sydney has T driven property developers in investing in what used to be expensive areas to develop. These areas are usually underlain by deep soft soils for which conventional piling technique, such as bored piles, do not perform well. On the other hand, CFA and DD Pile techniques are more appropriate for these ground conditions. Also, DD piles results in a substantial reduced spoil quantity compared to CFA piles. This paper will discuss the design and construction challenges encountered with both piling techniques, their limitations and advantages within the same ground conditions. Estimated design loads settlements curves are validated by means of PDA testing and results are discussed. II. GEOLOGICAL AND GEOTECHNICAL CHARACTERIZATION OF THE SITE The Sydney 1:100 000 Geological Series Sheet shows that the site is underlain by man-placed filling and S. Pirrello is with Keller Australia, Sydney, NSW 2100 Australia (phone: +61 2 8866-1100; e-mail: stefano.pirrello@ keller.com.au). alluvial/estuarine sediment. The sediment comprises silty to peaty sand, silt and clay. Shell layers are also expected to be present within the soil profile. The Prospect/Parramatta River 1:2500 Acid Sulphate Soil Risk Map shows the site as Disturbed Terrain in which soil investigations are required to assess acid sulphate soil potential. Several Cone Penetration Tests and Boreholes were carried out during the geotechnical investigation. All boreholes were extended to bedrock and NMLC-sized diamond core drilling was used to obtain 50-mm continuous core of the rock, enabling unconfined compression strength testing to be carried out on selected samples. A summary of the ground conditions encountered on this site and inferred from the CPTs can be described as follows: FILL (Unit A) concrete, bitumen, sand, gravel and clayey filling to depths between 0.3 m to 1.8 m; ALLUVIUM (Units B and C) clayey and sandy soils to depths of between 16m and 23m. The soils became firm to stiff (clays) and dense to medium dense (sands) with depth. Occasionally soft and loose layers were also encountered; SANDSTONE BEDROCK (Unit D) encountered from depths of between 16 m and 23 m. The bedrock had typically a weathered layer low strength (LS, defined as having typical UCS values of 2 to 6 MPa) up to 1m thick over medium strength (MS, UCS 6 to 20 MPa) to high strength to the base of the cores at 22 m to about 30 m. Stiff clay/dense sand (i.e. Unit C) variability can be appreciated on the two cross sections of the site given in Figs. 2 and 3, below. The locations of the cross sections along with the borehole locations are shown in Fig. 1. III. PRACTICAL CONSIDERATIONS ON THE PILE TYPES ADOPTED FOR THIS SITE CFA piles are a non-displacement form of cast in situ piles. Theoretically, the volume of spoil coincides with the volume of the auger. DD piles on the other hand seek to laterally displace the soil and consequentially improve the latter, with the advantage of having virtually no spoil. Fig. 4 below shows schematically the conceptual difference between CFA and DD penetration. A summary of the most popular displacement heads is presented in Fig. 5. 759

E1 5m Unit C Fig. 1 Test locations E4 E8 E10 E13 E15 Unit A Unit D Fig. 2 Cross-section A-A' Unit C 760

E4 E8 E5 E2 E6 E3 E7 Unit A 5m Unit C Fig. 4 Wood drill vs screw analogy as in [8], [9] Unit D A detailed explanation of these two piling systems is outside the scope of this paper with the focus being the advantages and disadvantages of the respective pile types. CFA piles can be used in most soil conditions. Modern piling rigs have sufficient power and torque that can deliver a reasonably high production rate while achieving considerable depths with rock socket lengths often sufficient to satisfy design requirements. On the other hand, DD piles have the limitation of not being able to displace the soil when the soils are too stiff/hard or too dense. DD augers can be successfully employed when there is limited thickness of stiff soil over bedrock. For this project, a stiff clay contour map was developed for this site, aiding with the assessment of identifying areas where one piling technology could be used over the other. This assessment was carried out using the available geotechnical data presented in Figs. 2 and 3. The Fig. 3 Cross section B-B' results of the inferred Unit C contour map are presented in Fig. 6. APGD ATLAS DE WALL FUNDEX OLIVIER OMEGA Fig. 5 Most popular full displacement augers [3] As can be seen from the contour map shown above, the area with no or little stiff clay (zero-meter contour line) is limited to a small area compared to the overall site area. If traditional DD heads presented in Fig. 5 were used, this would result in CFA Piles being used for 80% of the project piles because the DD piles could not achieve the required socket lengths in the rock. The high costs of spoil removal resulting from a predominantly CFA solution on this project would have a detrimental effect on project costs. As a consequence, every SVB SVV 761

effort was made to reduce the volume of spoil generated by piling. A displacement auger capable of drilling through thicker layers of stiff clay and founding in the rock extends the chances of its applications within this site. Fig. 7 shows the modified DD head custom made for this site. Fig. 6 Unit C thickness contours map Fig. 7 Keller s modified DD drilling head The DD head adopted was a hybrid of the Omega and De Waal heads, utilizing an Omega-type head with a 3-m to 6- m auger extension. This guaranteed extending the application of the DD piles within layers up to 6 m of Unit C, while still delivering the required designed minimum pile sockets of up to 1-m length in the MS Sydney Sandstone. Pile design and settlement estimate were carried out in accordance with limit state procedures as outlined in the Australian Standard AS2159-2009 [1], which requires piles to fulfil both serviceability and strength requirements. The geotechnical reduction factor adopted for low and high redundancy piles was 0.65 and 0.71, respectively. The foundation design for this project comprised the design and construction of over 800 piles, the final scheme comprising 55% CFA piles and 45% DD. Pile diameters were 600 mm and 750 mm, with all piles being socketed up to 1 m into MS Sandstone to meet design requirements. The proposed development extends to an area greater than 24 football fields. Different design zones were developed, targeting any significant variability of the soil and bedrock profile. Differences such as thicknesses of soft soil (i.e. ), Unit C, and levels of the MS Sandstone had to be assessed and considered in the design. A typical geotechnical soil profile for this site is presented in Table I. Geotechnical Unit TABLE I GEOTECHNICAL PARAMETERS Unit Base of Unit Thickness RL(m) AHD (m) Ultimate Shaft Adhesion (kpa)* Ultimate End Bearing (kpa)* B 10-8 15 - C 8-16 40 - D (LS Sandstone) 2-18 120 - D (MS Sandstone) N/A N/A 450 30000 Note: (*) LS and MS Sandstone parameters were based as in [4], [5] As all piles were founded in bedrock, any potential ground improvement in the case of the DD piles was ignored, so technically these piles were designed as CFA piles. Structural capacity of the piles was dictated by Clause 5.3.4 AS2159-2009 [1], which states that for partially reinforced piles the maximum structural load allowed is essentially 0.3f cag. Table II shows the maximum design loads for 600-mm and 750-mm piles. TABLE II MAXIMUM STRUCTURAL DESIGN FOR PARTIALLY REINFORCED PILES ON THIS SITE Diameter (mm) f c(mpa) Eds(kN)* Ed(kN)* 600 65 3040 4140 750 65 6667 9000 Note (*) Eds = serviceability load; Ed = Factored design load. Eds Ed/1.35 Negative skin friction, assessed to be 20 kpa, resulting from the consolidation of the compressible layer,, provided an additional load to be considered for both the structural pile design and for serviceability assessment. Pile settlement predictions under ultimate and working load were assessed 762

with aid of the commercial program RATZ, written and developed as in [6]. Table III provides the settlement estimates, including both pile shortening and negative skin friction effects, for the piles loaded in accordance with Table II. TABLE III SETTLEMENT ESTIMATE UNDER SERVICEABILITY Diameter (mm) f c(mpa) Eds(kN)* d(mm) 600 65 3040 6 750 65 6667 8 IV. CONSTRUCTION ASPECTS QA & QC Two major construction aspects were concerning the designers while opting for the revised DD head. These were: 1. The uncertainties related to the performance of this new auger drilled through an unusually thicker Unit C layer. In particular, in case of slow penetration, a combined effect of a prolonged penetration and high torque could lead to the side loading (also known as flighting or soil decompression ) effect for the non-cohesive component of Unit C. This would make the soil surrounding the auger collapse onto the auger. 2. Consideration was also given to the potential within Unit C layer of built up pore pressures due to the displacement effect within the clay potentially causing squeezing of newly formed adjacent pile shafts. 3. Another aspect that demanded care was the possibility of potential necking in the very soft clay layer UNIT B, where bulges could be generated despite the concrete oversupply. Pile bulging would potentially cause increase in the downdrag forces on the pile [2] within UNIT B. The CFA and DD piling rigs were all equipped with onboard computers (PL3000) which allow the site personnel and the designer access to continuous monitoring of the all aspects of pile construction in real time. This my information includes: Boring rate (m/min); Penetration rate(mm/rev); Extraction rate (m/min); Torque (% of maximum); Concrete pressure (bar); Concrete oversupply (% above theoretical) and Ideal pile shape The penetration rates and torque from the PL3000 records served to provide confirmation of rock head levels and socket lengths. This information is essential for a quick assessment of the constructed pile. However, care needs to be taken in the way the data are interpreted especially when a reduced section of the flow profile due to a change in layer s stiffness for example from a low to high stiffness is misinterpreted with a pile necking. This would simply be the case of a larger section back to a nominal section [7]. The analysis of the above information, along with the validation of the rationalised design profile assumed, provided the designers with the confidence required for successful penetration of the Unit C layer in a timely manner. V. EFFECTS OF DD INSTALLATION The opportunity was taken to carry out an additional geotechnical investigation involving CPTu probes aimed to assess pore pressure prior and after installation of DD piles. The CPTu s were carried out prior and after construction of piles. The results showed that the water pressure rarely increased due to the installation process and where increases occurred; those increases were modest and always less than the concrete pressure during which the piles were built. Fig. 8 shows the CPTu testing arrangement prior to and after installation of the piles. Fig. 8 Keller s CPTu test rational CPTu tests were positioned at concentric distances of 1d, 2d, and 3d from the middle of the twin pile configuration. The testing sequence was carried out as follow: Day 1 #4 CPTu test were carried out (i.e. 1 to 4) prior installation of the first pile (i.e. green pile); Day 2 - #3 CPTu were carried out (i.e. 5 to 7). Then the second pile (i.e. blue pile) was installed; Day 3 - # CPTu were carried out (i.e.8 to 10). Typical CPtu results prior and after the installation are given in Fig. 9. 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Typical Pore Pressures Prior and After Installation 0 50 100 150 200 250 300 350 400 450 500 u2 from CPTU7 u u2 from CPTU9 Concrete pressure Fig. 9 Pore pressure results from CPTu7 and CPTu9, prior and after installation 763

The increase of pore pressure after installation can be appreciated in CPTu7 at 8-m and 9.5-m depth. However, this increase is very close to the concrete head pressure at the same depth in the worst case or less, and therefore the integrity of the newly formed pile shafts is not a concern. A substantial increase in pore pressure with depth greater than the concrete head pressure would be a potential indicator of damage to the pile, e.g. pile necking at the depths where the pore pressures exceeded concrete pressures. VI. PILE TESTING Dynamic pile testing was carried out on 18 piles, of which eight of the more heavily loaded piles are presented. Dynamic pile testing is widely accepted in the Australian piling industry as an alternative to conventional static tests. The test is regarded as being sufficiently accurate but at a much lower cost than alternative load tests and regarded as an excellent tool for assessing pile performances economically. The total number of tests performed represented 2.3% of the total number of piles installed, but this was considered satisfactory given previous extensive experience from adjacent sites, supplemented by data from the PL3000 monitoring that confirmed socket length requirements. Unit pile loads and settlement criteria were satisfied in accordance with AS2159-2009 [1]. Settlement due to negative skin friction was also considered in accordance with clause 4.6.3 of AS2159-2009 [1]. Analysis of wave equation did not highlight any necking or bulging of the piles within UNIT B, so no increase on the already estimated negative skin friction on the piles was assessed. All piles tested were production piles socketed into the sandstone bedrock. A potential disadvantage of dynamic testing of reasonably highly loaded piles is that the hammer drop height must be sufficient to deliver enough energy on the pile to mobilise and prove the required pile resistance whilst not damaging the pile. None of the piles were damaged during the tests as the developed stresses within the piles due to the dynamic impact were continuously monitored. Test signals were recorded on site by means of PDA monitoring and testing devices. Table IV reports the test results. Pile test analyses were carried with CAPWAP, from which the interpreted load displacement curves at construction stage are given in Figs. 10 and 11. Pile ID ᶲ TABLE IV SUMMARY OF DYNAMIC PILE TEST RESULTS Pile Type Pile Depth (m) N* (kn) Pg (kn) Eds (kn) δ 1 δ 2 (mm) 4077 750 DD 20 10984 9951 5110 6 15 4052 750 DD 19 11674 9637 4940 6 15 C74 750 CFA 19 12898 12676 6667 8 17 3064 750 DD 20 11447 10098 5150 6 17 2131 750 DD 25 9961 4435 2110 3 17 2111 600 CFA 20 8425 5595 3040 6 18 1093 600 DD 20 7350 3775 1900 3 16 1150 600 DD 24 8220 1929 960 2 20 Note: E ds -Design Serviceability Load. P g -Maximum Test Load. N*-Total Mobilised Resistance. d 1 -Settlement under SLS. d 2 -Settlement under N*. Pile head load (kn) Pile head load (kn) 12000 10000 8000 6000 4000 2000 600mm Pile Test Results 0-0,005 0,005 0,015 0,025 0,035 Pile displacement (m) HB - Estimated Load/Settlement Curve 1150 - DD 1093 - DD 2111 - CFA LB - Estimated Load/Settlement Curve Fig. 90 600-mm estimated vs test load settlement curve 20000 18000 16000 14000 12000 10000 8000 6000 4000 2000 750mm Pile Test Results 0 0 0,005 0,01 0,015 0,02 0,025 0,03 0,035 Pile displacement (m) HB - Estimated Load/Settlement Curve C74 - CFA 4077 - DD 4052 - CFA 2131 -DD 3064 - DD LB - Estimated Load/Settlement Curve Fig. 101 750-mm estimated vs test load settlement curve VII. SUMMARY AND CONCLUSIONS Technical differences between CFA and DD piles were briefly discussed. The main focus of this paper is to explain the rationale of selecting one method over the other and its application and limitations within different ground conditions. DD pile augers were adopted to offset construction limitations, so they could be employed in stiff soil layers. The quality control during construction was also discussed focusing on two major aspects such as side loading and 764

pore pressure increase. Design load settlement predictions were validated by means of comparison with PDA testing carried out on the same piles. The work was completed on time and on budget. ACKNOWLEDGEMENT The author would like to thank all colleagues involved in the project from conception to delivery. A special mention goes to the construction team on delivering a state of the art product, which enabled designers to push the design envelope. REFERENCES [1] Australian Standard, AS2159-2009. Piling- Design and installation. [2] Brown, D.A, 2005. Practical considerations in the selection and use of continuous flight auger and drilling displacement piles. American Society of Civil Engineers, ASCE J. Geotechnical special publication No.132, pp.1-11. [3] Larish, M. D, 2014. Behaviour of stiff, fine-grained soil during the installation of screw auger displacement piles. PhD Thesis, The University of Queensland, Australia. [4] Pells, P. J. N, Dougals, D. J. Rodway, B., Thorne, C., McMahon, B. K., 1978. Design loadings for foundations on shale and sandstone in the Sydney region. Australian Geomechanics J. Vol.G8, pp. 31-39. [5] Pells, P. J. N., 1998. State of practice for design of socketed piles in rock. Proceedings of the 8th A.N.Z. Conference on Geomechanics, Hobart, pp. 307-326 [6] Randolph, M. F., 1994. RATZ load transfer analysis of axially loaded piles, program manual. [7] Slatter,.J, 2006. Recent developments in continuous flight auger (CFA) and cast-in-situ displacement screw piling in Melbourne. Australian Geomechanics J. Vol. 41, No. 3, pp. 17-24. [8] Van Impe, W.F., 1988. Considerations on auger pile design. Proc. of 1st 2nd Int. Conference on Deep Foundations on Bored and Augered Piles, Ghent, Balkema. [9] Van Impe, W. F., 1994. Influence of screw pile installati.on parameters on the overall pile behaviour. Workshop Piled Foundations: Full Scale Investigations, Analysis and Design, Naples. 765