Options looking forward for sediment management in the Alameda Creek Flood Control Channel

Similar documents
May 7, Roger Leventhal, P.E. Marin County Public Works Laurel Collins Watershed Sciences

!"#$%&&'()*+#$%(,-./0*)%(!

Technical Memorandum No Sediment Model

Modeling Post-Development Runoff and Channel Impacts from Hydromodification: Practical Tools for Hydromodification Assessment

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,

Why Geomorphology for Fish Passage

Island Design. UMRS EMP Regional Workshop. Presentation for the

Stream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation)

Lower South Fork McKenzie River Floodplain Enhancement Project

Fluvial Driven Alluvial Fans

Restoring the Napa River:

Case Study 2: Twenty-mile Creek Rock Fords

Solutions to Flooding on Pescadero Creek Road

Coarse Sediment Augmentation on Regulated Rivers. Scott McBain McBain & Trush, Inc.

ADDRESSING GEOMORPHIC AND HYDRAULIC CONTROLS IN OFF-CHANNEL HABITAT DESIGN

The last three sections of the main body of this report consist of:

Technical Memorandum No

Four Mile Run Levee Corridor Stream Restoration

EAGLES NEST AND PIASA ISLANDS

Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah

Diagnostic Geomorphic Methods for Understanding Future Behavior of Lake Superior Streams What Have We Learned in Two Decades?

Technical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth

State Water Survey Division SURFACE WATER SECTION

Sessom Creek Sand Bar Removal HCP Task 5.4.6

Why Stabilizing the Stream As-Is is Not Enough

Fish Passage at Road Crossings

GEOMORPHIC CHANGES IN LOWER CACHE CREEK 2012

River Restoration and Rehabilitation. Pierre Y. Julien

Griswold Creek August 22, 2013

Degradation Concerns related to Bridge Structures in Alberta

Strategies for managing sediment in dams. Iwona Conlan Consultant to IKMP, MRCS

Geomorphic Importance of Winter Peak Flows and Annual Snowmelt Hydrographs in a Sierra Nevada Boulder-Bedrock River

Bank Erosion and Morphology of the Kaskaskia River

SELBY CREEK STREAM HABITAT RESTORATION AND RIPARIAN REVEGETATION PROJECT: GEOMORPHIC ANALYSIS AND REVIEW

Restoration Goals TFG Meeting. Agenda

Birch Creek Geomorphic Assessment and Action Plan

Dam Removal Analysis Guidelines for Sediment

Assessment. Assessment

DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6.

Hydraulic and Sediment Transport Modeling Strategy

Historical channel change on the Upper Gila River, Arizona and New Mexico in response to anthropogenic modifications and extreme floods

San Joaquin River Tributary Sediment Transport and Geomorphology Study

Tom Ballestero University of New Hampshire. 1 May 2013

Chapter 3 Erosion in the Las Vegas Wash

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

NORTHUMBERLAND COUNTY, PA

CR AAO Bridge. Dead River Flood & Natural Channel Design. Mitch Koetje Water Resources Division UP District

Mapping of Future Coastal Hazards. for Southern California. January 7th, David Revell, Ph.D. E.

Sediment Transport Model of the San Benito River Between Hollister and the Pajaro River Confluence

Vermont Stream Geomorphic Assessment. Appendix E. River Corridor Delineation Process. VT Agency of Natural Resources. April, E0 - April, 2004

Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018

1 INTRODUCTION AND MAJOR FINDINGS... 1

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

Evaluation of Geomorphic Effects of Removal of Marmot and Little Sandy Dams and Potential Impacts on Anadromous Salmonids

MIDDLE PILCHUCK RIVER ASSESSMENT

Swift Creek Sediment Management Action Plan (SCSMAP)

Subcommittee on Sedimentation Draft Sediment Analysis Guidelines for Dam Removal

Design of Levee Breaches in Sheltered Water for Flood Risk Reduction & Marsh Restoration ASFMP; June 5, 2014 Presented By:

Aquifer an underground zone or layer of sand, gravel, or porous rock that is saturated with water.

Do you think sediment transport is a concern?

Geomorphology Geology 450/750 Spring Fluvial Processes Project Analysis of Redwood Creek Field Data Due Wednesday, May 26

Step 5: Channel Bed and Planform Changes

Ways To Identify Background Verses Accelerated Erosion

Development of Riparian Maps for Sonoma County Long Term Riparian Corridor Conservation. Mark Tukman & Dylan Loudon Tukman Geospatial

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT

Swift Creek Sediment Management Action Plan (SCSMAP)

Estimated Sediment Volume: Bridge Street Dam Impoundment, Royal River, Yarmouth, Maine

Highland Lake Bathymetric Survey

60 PERCENT DESIGN REPORT HABITAT RESTORATION OF THE CHELAN RIVER REACH 4 AND TAILRACE

SCOPE OF PRESENTATION STREAM DYNAMICS, CHANNEL RESTORATION PLANS, & SEDIMENT TRANSPORT ANALYSES IN RELATION TO RESTORATION PLANS

GENERAL SUMMARY BIG WOOD RIVER GEOMORPHIC ASSESSMENT BLAINE COUNTY, IDAHO

PolyMet NorthMet Project

Implementing a Project with 319 Funds: The Spring Brook Meander Project. Leslie A. Berns

Two-Dimensional Simulation of Truckee River Hydrodynamics

Seagrass Transplantation & Environmental & Marine Consulting Services, Inc. Drew Campbell, Vice President & Lead Scientst.

Dolores River Watershed Study

Minimizing Flood Risks and Habitat Impacts Due to Post-Flood Recovery Efforts

Section 4: Model Development and Application

Appendix K.2: Sediment Management Excerpt from South Orange County Hydromodification Management Plan

Development of a Fluvial Erosion Hazard Mitigation Program for Indiana

MATHEMATICAL MODELING OF FLUVIAL SEDIMENT DELIVERY, NEKA RIVER, IRAN. S.E. Kermani H. Golmaee M.Z. Ahmadi

Sediment Transport Analysis for Stream Restoration Design: The Good, the Bad, and the Ugly.

Remaining Capacity in Great Lakes Reservoirs

SECTION G SEDIMENT BUDGET

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON

May Creek Canyon LWD Stream Restoration Project. Helicopter Placement of LWD in an Urban Stream. By Kathryn Neal, P.E.

Swirling in Sediment and Slowing Fisheries Recovery

APPENDIX B Hydraulic Considerations for Pipeline Crossings of Stream Channels

MEMORANDUM. Situation. David Ford Consulting Engineers, Inc J Street, Suite 200 Sacramento, CA Ph Fx

Fluvial Geomorphology Assessment of Northern Connecticut River Tributaries

Rosgen Classification Unnamed Creek South of Dunka Road


Stop 1: Marmot Dam Stop 1: Marmot Dam

CASE STUDIES. Introduction

DAM REMOVAL ENGINEERING ISSUES & OPTIONS

Restoring Entrenched Rivers: lessons learned from the

Project Proposal. Lyme Brook. Newcastle-under-Lyme. 3 rd July 2015

Upper Truckee River Restoration Lake Tahoe, California Presented by Brendan Belby Sacramento, California

NEWS RELEASE UNDER SECTION 404 OF THE CLEAN WATER ACT (33 USC 1344) ACTION NUMBER SPA ABQ

Diego Burgos. Geology 394. Advisors: Dr. Prestegaard. Phillip Goodling

Transcription:

Options looking forward for sediment management in the Alameda Creek Flood Control Channel Lester McKee Alameda Watershed Council Annual Conference 1

Alameda Creek Flood Channel Large alluvial fan and floodplain complex Aerial photo of the urbanized alluvial fan and flood control channel from Niles Canyon to the Bay 2

Alameda Creek Flood Channel 12 mile long Flood Control Project Looking upstream in the lower fluvial reaches of the flood control channel 3

The Flood Control Channel Flood control channel completed 1975 Straightening, widening, regrading, and partially rip-rapping 12 miles Maintenance manual provides guidelines to maintain the 100-year flood capacity 52,000 cfs at the junction with Dry Creek, FEMA 1975 Sediment is periodically removed at great cost so that nowhere shall the mean elevation in a reach exceeds 2 feet above design grade. Fremont area during the 1955 flood, prior to construction of the flood control channel (source: Young 1962). 4

Dredging History of Alameda Creek * Provisional Peak Flow at Niles (cfs) 20000 15000 10000 5000 0 * Maintenance (yd3) 200,000 150,000 100,000 50,000 0 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010? Year 5

The Permitting Problem Revised guidelines Take into account threatened and endangered species and habitats within creeks Maintenance procedures must achieve both flood control and environmental criteria Sediment removal Impact on the creek itself Proper disposal A resource for future use Permits will no longer be issued without further investigations and improved practices 6

Two Conceptual Management Options Reduce and manage water and sediment supply from upstream (nonpoint source solutions) Multi-agency and private landowner effort Facilitated by watershed goals Change the way sediment is managed in the channel (reach specific solutions) **Ultimately both solutions may have benefit 7

The Santa Cruz - Example 1955 flood destroys part of the town 8

Corps project Straightening Levees Below grade Channel substrate Flat Shallow Sandy stream bed 9

Early 1970s Annual floods deposited sediment during the 60s and early 70s reducing capacity from 100 y to 30 y Corps argued that sediment removal was best ongoing solution City argued cost prohibitive and permits would be too challenging to obtain Meanwhile FEMA remapped floodplain 10

1982: Flood Channel bed scour Soquel Ave bridge central pier lowered 18 feet Earlier estimates assumed a fixed bed Subsequent studies revealed backwater effects and aprons stopping scour 11

Late 1980s Corps HEC-6 study found that scour providing for 100 y but without the required 3 ft freeboard Conceded that annual sediment removal was not most cost effective 12

1990s City and Corps developed a floodwall and levee raising plan Project completed in 2001 Channel constrictions causing sedimentation removed 13

River Enhancement plans (1990, 2003) City, resource agencies and Corps agree on vegetation and habitat management plan City monitors and removes vegetation for roughness design specs Channel capacity is tested using HECRAS as part of adaptive management Ripping operations to prevent root armoring of the channel bed Vegetation is kept in an early succession state with limited to vegetation width and stem diameter by maintenance (scrub willow alder cover) The bankfull channel is maintained as part of the river vegetation management 14

Outcome Multi-stage channel More confined deeper channel Gravel cobble substrate Greater hydraulic complexity Biological habitat value Most of the channel has Over-story cover Deep pools Salmonid rearing Occasional instances of spawning in lower river 15

Outstanding issues Corps claims that some sediment removal is still necessary City disagrees. No finalization of O & M plan Post-Katrina Corps vegetation management is calling for removal of vegetation planted on backside of the levee that was part of the Corps levee raising project City is undertaking studies 16

But there are other examples San Lorenzo provides an example of what is possible when multiple agencies objectives are met, however: Smaller in area Steeper gradient Wetter system Flows to ocean Not managed for water supply 17

Wildcat, Richmond, Contra Costa 18

Guadalupe River, San Jose, Santa Clara 19

Other examples Russian River, Sonoma County Trinity River, Northern California 20

Previous and ongoing Scientific and Engineering Studies in Alameda Sediment source analysis in the upper watershed Reconnaissance (Watershed Sciences) Sediment budget for the middle reaches (SFEI) Review of sediment gaging (SFEI) Modeling sediment transport processes in the Flood Control Channel (DHI ongoing) Studies of sediment grain size in the Flood Control Channel (SFEI ongoing) 21

Previous and ongoing Scientific and Engineering Studies in Alameda Modeling and engineering design of the lower three miles in relation to saltpond restoration and levee breach (PWA ongoing) Studies of fine and coarse sediment load from small tributaries on the Alameda Fan (SFEI/ Pearce et al ongoing) Historical Ecology of Alameda Creek (SFEI / Grossinger et al ongoing) Spartina monitoring plan to support saltpond restoration (SFEI / Grenier ongoing) 22

Some key findings from the SFEI work 23

Sediment Budget Overall Watershed Comparison for Recent Period (1994 2006) Sediment Yield Area Metric t/year % of Total ADLL at Verona Gage 104,000 63 Alameda Creek near Welch Ck Gage 3,400 2 Arroyo de La Laguna Study Reach 8,400 5 Alameda Creek Study Reach 320 0.2 Ungaged areas 47,908 29 All Areas above Niles Gage 164,000 Alameda Creek at Niles Gage 156,000 24

Dry Creek Dry Creek (10 mi 2 ) is 1.5% of the total Alameda Creek watershed area Average sediment discharge is 5,900 tonnes/yr, or 4% of the load passing Niles gage 4.0 3.5 Dry Creek Fan Perimeter 3.0 Dry Creek confluence Relative elevation (m) 2.5 2.0 1.5 1.0 Dry Creek fan 0.5 0.0-0.5 25

Sediment in the Flood Control Channel D50: mostly fine medium sand Some samples >50% cobble 86% is >62.5 micron 26

Options looking forward Further geomorphic, engineering studies, and modeling to inform flood control channel management options Further data collection in strategic locations to learn about sediment transport and supply to the channel Watershed stewardship to reduce or store water and sediment supply during large floods Facilitated by watershed goals? Wildcat Creek 27

Geomorphic and sediment related analysis for Alameda Creek (SFEI): Dr. Lester McKee, Sarah Pearce, Jen Hunt and others Restoration Design Group: Roger Leventhal, P.E. Watershed Sciences: Laurel Collins CEMAR: Gordon Becker DHI Water and Environment, Inc. 28

SFEI team study plan and progress Long term goal: Develop a sediment management plan that reduces costs and permitting, while maintaining flood capacity and maximizing habitat benefits Geomorphic assessment Support for improved maintenance practices 29

Geomorphic study questions What are the rates and locations of recent sediment deposition? What is the relationship between low-flow channel and bankfull discharge? How has the low flow channel evolved through time? What in-channel features are causing sediment deposition? Does the channel bed scour during floods? 30

Support improved maintenance practices Review Santa Clara Valley Water District s 2009 Open Channel Hydraulics and Sediment Transport Design Manual Field visit to San Lorenzo River, Santa Cruz Verify the current channel capacity in relation to the existing operations and maintenance manual 31

Support Improved maintenance practices Review 10 years of existing studies and assimilate recent SFEI team observations including HE of the channel Evaluate current level of wildlife support and likely future support in relation of planned or possible future management Evaluate sediment reuse options Final report: A qualitative analysis of interim management options Enhanced vegetation management and targeted desilting operations to reduce wildlife impacts and enhance channel configuration to a more desirable state Preliminary commentary on future conceptual design/management options including recommendations for further investigations 32

33

Stonybrook Creek Questions How much coarse sediment is contributed? What are the primary processes of sediment supply and delivery? How is sediment affecting fisheries and infrastructure? Methods Field reconnaissance utilizing GIS-based terrain mapping and aerial photograph analysis 34

35

Zone 7 SFEI studies Support improved modeling for design and compliance purposes and decisions about future operations and maintenance of its facilities AMP Flow gage 36

Study Components Determine the flow of water and sediment into and out of mainstem Arroyo Mocho Determine characteristics, rates, and causes of sedimentation Develop a sediment budget for the study reach as a tool for clearly communicating the main sources and processes affecting the function Map and characterize channel modification and mitigation opportunities based on a comparison of historic and modern channel function Communicate findings to the broader community within the Alameda Watershed Council 37

Take home messages Business as usual on the Alameda FFC may not be most cost effective or feasible There are examples of alternative management styles Studies have started to explore options It will take a coordinated agency effort with all parties committed to a future vision to reach a new management paradigm for Alameda FCC Santa Cruz experience took 30 years Alameda might be a smoother process? 38