Bawakaraeng Urgent Sediment Control Project

Similar documents
SEDIMENT TRANSPORT ANALYSIS FOR SECURING WATER (CASE STUDY : UPPER JENEBERANG RIVER)

DEBRIS FLOW DISASTER MITIGATION THROUGH COMMUNITY-BASED INTEGRATED SEDIMENT MANAGEMENT (BEST PRACTICE IN MT. MERAPI AREA, INDONESIA)

EXPERIMENTAL STUDY OF FLOW IMPACT AT SAND POCKET

Sedimentation in the Nile River

2. PRESENT CONDITION OF THE RESERVOIR 2.1 View of Wonogiri Reservoir (1/3)

The Application of Sabo Technology for Lahars Flood Mitigation and Warning System in Volcanic Area. Agus Sumaryono Bambang Sukatja F.

3/3/2013. The hydro cycle water returns from the sea. All "toilet to tap." Introduction to Environmental Geology, 5e

Ayubowan. Management (CBDRM) Community Based Disaster Risk. Towards Disaster Resilient Community Developed by Disaster Management Centre,

The sketch map of field investigations in Wenchuan earthquake hit region, Chengdu City.

National Hydrology committee of Afghanistan (NHCA) Sedimentation in Reservoire

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

Internationales Symposion INTERPRAEVENT 2004 RIVA / TRIENT

CHALLENGES ON SEDIMENT- RELATED DISASTER MITIGATION

GENERAL. CHAPTER 1 BACKGROUND AND PURPOSE OF THE GUIDELINES Background of the Guidelines Purpose of the Guidelines...

Landslide Disaster Management in Sri Lanka and Nichola Oya as a Case study. Group 16 Gamini Jayathissa Udeni Nawagamuwa

A Roundup of Recent Debris Flow Events in Taiwan

Gigantic collapse of the Caldera wall of Mt. Bawakaraeng (2,830 m) in March 2004 had supplied the

Understanding disaster risk ~ Lessons from 2009 Typhoon Morakot, Southern Taiwan

REDWOOD VALLEY SUBAREA

Born in Unzen The World s First Unmanned Construction of Multilayer Sediment Control Dam Using Sediment Forms Unzen Restoration Project Office

Floods Lecture #21 20

8 Current Issues and Research on Sediment Movement in the River Catchments of Japan

Huong River. Serial No. : Viet Nam-8 Location: Thua Thien Hue Province, Viet Nam N 16 00' '

PRELIMINARY DRAFT FOR DISCUSSION PURPOSES

Debris Flow in the Kitamatasawa Tributary of the Namekawa River in the Kiso River System

Debris flow: categories, characteristics, hazard assessment, mitigation measures. Hariklia D. SKILODIMOU, George D. BATHRELLOS

ENGINEERING HYDROLOGY

CASE STUDY BINGA, PHILIPPINES

Controlling Processes That Change Land

Promoting Rainwater Harvesting in Caribbean Small Island Developing States Water Availability Mapping for Grenada Preliminary findings

EFFECT OF SAND MINING ACTIVITY ON THE SEDIMENT CONTROL SYSTEM (A CASE STUDY OF SOMBE-LEWARA RIVER, DONGGALA, INDONESIA)

CASE STUDY BINGA, PHILIPPINES

RESERVOIR SEDIMENTATION MANAGEMENT WITH BYPASS TUNNELS IN JAPAN. Keywords: Reservoir sedimentation, Sediment bypass, Diversion tunnel, Abrasion damage

WHEN IS IT EVER GOING TO RAIN? Table of Average Annual Rainfall and Rainfall For Selected Arizona Cities

Strategies for managing sediment in dams. Iwona Conlan Consultant to IKMP, MRCS

CHANGES OF RUNOFF MECHANISM OF THE BRANTAS RIVER OVER THE PAST 30 YEARS

GUIDELINES FOR CONSTRUCTION TECHNOLOGY TRANSFER DEVELOPMENT OF WARNING AND EVACUATION SYSTEM AGAINST SEDIMENT DISASTERS IN DEVELOPING COUNTRIES

EFFECT OF TWO SUCCESIVE CHECK DAMS ON DEBRIS FLOW DEPOSITION

APPENDIX-VI Sabo/ Flood Control Structural Measures

Tarbela Dam in Pakistan. Case study of reservoir sedimentation

Term Knowledge Using and applying Grade Criteria Autumn 1 Assessment window October Natural hazards pose major risks to people and property.

GIS Application in Landslide Hazard Analysis An Example from the Shihmen Reservoir Catchment Area in Northern Taiwan

Debris flow hazard mapping with a random walk model in Korea

Analysis of Sedimentation in Wonogiri Reservoir

The Effects of Hydraulic Structures on Streams Prone to Bank Erosion in an Intense Flood Event: A Case Study from Eastern Hokkaido

A Numerical Method for Determine the Dredging Requirements for Channel Restoration Using Alishan Creek in Central Taiwan as an Example

Session: For more information:

Figure 1. Which part of the river is labelled in Figure 1? a) Mouth b) Source c) Lower course d) channel

Proposal to limit Namakan Lake to 1970 Upper Rule Curve for remainder of summer

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

The SedAlp Project: WP6: INTERACTION WITH STRUCTURES

VULNERABILITY OF WATER SUPPLY TO NATURAL HAZARDS IN JAMAICA

The effectiveness of check dams in controlling upstream channel stability in northeastern Taiwan

CASE STUDY NATHPA JHAKRI, INDIA

APPLICATION TO PAST DISASTERS OF A METHOD OF SETTING THE RANGE OF DEBRIS FLOW DAMAGE TO HOUSES

Subcommittee on Sedimentation Draft Sediment Analysis Guidelines for Dam Removal

SPECIFIC DEGRADATION AND RESERVOIR SEDIMENTATION. By Renee Vandermause & Chun-Yao Yang

EIT-Japan Symposium 2011 on Human Security Engineering

Unconventional Wisdom and the Effects of Dams on Downstream Coarse Sediment Supply. Byron Amerson, Jay Stallman, John Wooster, and Derek Booth

FINAL REPORT VOLUME-VII PHOTO BOOK

Upgrading Feasibility Study on the Upper Seti Storage Hydroelectric Project in Nepal

4.17 Spain. Catalonia

GEOMORPHIC CHANGES OF A LANDSLIDE DAM BY OVERTOPPING EROSION

3.0 TECHNICAL FEASIBILITY

Which map shows the stream drainage pattern that most likely formed on the surface of this volcano? A) B)

Lecture 14: Floods. Key Questions

The Huong River the nature, climate, hydro-meteorological issues and the AWCI demonstration project

Hazard Resilience Index (HRI) Earthquakes, Tsunamis, and Volcanoes

Role of Hydro-Met Services in Disaster Risk Management

In Issue of International Sabo News Letter

(Specification B) 40352H (JUN H01) General Certificate of Secondary Education Higher Tier June 2011 TOTAL. Time allowed 1 hour

Geostatistical Analysis of Rainfall Temperature and Evaporation Data of Owerri for Ten Years

Attachment B to Technical Memorandum No.2. Operations Plan of Ross Valley Detention Basins

TWO LARGE-SCALE LANDSLIDE DAMS AND OUTBURST DISASTER IN THE SHINANO RIVER, CENTRAL JAPAN

Theme 4. Disaster Mitigation and Risk Management

The World Bank BiH Floods Emergency Recovery Project (P151157)

Chiang Rai Province CC Threat overview AAS1109 Mekong ARCC

Level 1/Level 2 Certificate Specimen Paper

Fenhe (Fen He) Map of River. Table of Basic Data. China 10

Hydro-engineers.ch HEC-RAS ANALAYSIS. River: L Aïre Mesfin Tewolde. Hydro-engineers.ch 23 oct. 2017

ISO Lead Auditor Lean Six Sigma PMP Business Process Improvement Enterprise Risk Management IT Sales Training

COUNTRY PRESENTATION ON MR JAYNAL ABEDIN JOINT SECRETARY ( WORKS & DEVELOPMENT ) MINISTRY OF DEFENCE

Changing Hydrology under a Changing Climate for a Coastal Plain Watershed

Local Flood Hazards. Click here for Real-time River Information

Final Presentation on Disaster Risk Management in Japan. Through ADRC V. R Programme. Main Findings and Action Plan:

Drought in Southeast Colorado

HYDROLOGIC AND WATER RESOURCES EVALUATIONS FOR SG. LUI WATERSHED

AN ASSESSMENT OF THE RELATIONSHIP BETWEEN RAINFALL AND LAKE VICTORIA LEVELS IN UGANDA

A distributed runoff model for flood prediction in ungauged basins

Stop 1: Marmot Dam Stop 1: Marmot Dam

A3 RIVER BASIN AND RIVER CHANNEL

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1

HYDRAULIC SIMULATION OF FLASH FLOOD AS TRIGGERED BY NATURAL DAM BREAK

Temperature and Sound Survey on Steep Tea Farm Area and Salt Pan Site

Stream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation)

Flash flood disaster in Bayangol district, Ulaanbaatar

Experimental Study on Effect of Houses on Debris-Flow Flooding and Deposition in Debris Flow Fan Areas

Kiribati Adaptation Phase III (LDCF) (P112615)

FORECAST-BASED OPERATIONS AT FOLSOM DAM AND LAKE

Use of Geospatial data for disaster managements

Transcription:

Departmen Permukiman Umum Direktorat Jenderal Sumber Daya Air Bawakaraeng Urgent Sediment Control Project (The Most Urgent Components) August 2005 1

The Collapse On March 26, 2004, Mt. Sorongan (EL.2,541m) in the caldera of Mt. Bawakaraeng Collapsed. The estimated collapsed volume: 200 300 mil. cum. Damage: 32 people death and missing, 635 cows losing, Houses and elementary school in Lengkese village and about 1,500 ha. of agricultural land buried; The damages expected: - The riverbed aggradations and loss of properties along the river such as paddy fields; - Sedimentation of Bili-Bili Dam (; and - Secondary disaster due to debris flow (Carrying away of Daraha Bridge, Existing bank erosion etc.). 2

Location 35 km 7 km 12 km 17 km 5 km Makassar City Malino Bili-Bili Irrigation System Sunggminasa Kampili Irrigation System Bili-Bili Dam S.P. S.P. 2 S.P. 4 S.D. S.P. 5 Malino River S.D. 5 Jeneberang River S.D. 8 S.D. 4 Lengkese Collapsed Caldera-wall Mt. Bawa Karaeng Caldera Rim Bissua Irrigation System Jenelata River Pamukulu Dam (Proposed) N Palu Sulawesi Island Menado Pamukulu Irrigation System Makassar City Kendari PROJECT AREA 0 5 10 Km SCALE 3

Schematic Map of Site Outer Rim of Caldera Makassar City Bili-Bili Dam Jeneberang River Malino River 2.5 km Malino Mt. Bawakaraeng Sand Pocket 5 Sabo Dam 4 Lenkese Jenelata River 35 km 7 km 25 km 4 km 1.5 km 5 km 200-500 m Lengkese Road 50-100 m Collapse Mass 4

Collapsed Mountain Before the Collapse As of July 2002 Mt. Sorongon Mt. Bawakaraeng After the Collapse As of March 2004 Collapsed Mountain Mt. Bawakaraeng 5

Collapsed Mountain (Aerial Photos) August 1993 July 2004 6

Collapsed Area (As of April 8, 2005) 2 1 a b a Photo A b Photo B Location Map Photo B Bili-Bili Reservoir 1 2 Photo A 7

After Collapse at Lengkese (March 26, 2005) Evacuation of Village People Buried Houses Buried Paddy Field (Parangkeke) 8

Development of Gully April 8, 2004 December 9, 2004 June 20, 2004 January 22, 2005 February 14, 2005 September 27, 2004 9

Damages Sand Pocket Dam No. 5 Before Collapse Debris Flow Jeneberang River Channel Paddy fields along the river were buried. The damage expands day by day. Bili-Bili Reservoir Sand Pocket Dam No. 5 The left abutment of SP No. 5 was completely buried by debris. At the downstream of SP No.5, village people start cultivating. March 26, 05 Evacuated Houses along the River (Bonto-Jai) March 26, 04 10

Damages Sedimentation of Bili-Bili Dam June 24, 04 Sedimentation at Upstream of the Bili-Bili Reservoir at present, the sediment volume is estimated at 10mil m3 while the design sediment volume is set at 29mil. m3. Aug 20, 05 Raw Water Turbidity at Somba-Op Water Purification Plant During rainy season in 04 to 05, the operation and supply water were stopped for 22days or 350hrs. in total due to the sediment content. 11

Damages River Structures Sand Pocket No. 4 June 24, 04 Before Collapse Daraha Bridge Daraha Bridge was flushed out by debris flow on 14 April 2005. Trans 13,000 village People has been affected. May 07, 05 April 17, 05 12

The Project Bawakaraeng Urgent Sediment Control Project 13

Objectives of the Project To protect public assets such as Bili-Bili dam and the farmlands and properties along the river; To mitigate the secondary disaster due to the debris flow, To realize sustainable Sabo works and sand management, and To improve the social welfare in the affected area. 14

Counter Measures Following countermeasures will be provided to achieve the objectives in accordance with the ISDM concept: Structural Measures - Construction of Sabo Dams; - Rehabilitation of existing structures (Road, bridge and Sand Pocket Dam No. 4); - Removal of River Deposit at Sand Pocket Dams and Bili-Bili Reservoir. Nonstructural Measures -Urgent inspection for prediction of further collapse and occurrence of debris flow; -Providing forecasting and warning system against the debris flow. 15

Sediment Control plan Sediment Balance up to 2009 - Generated Sediment at Caldera 60,400,000 m 3 - Stored in Caldera by Sabo Dam 11,000,000 m 3 - Sediment Discharge from Caldera 49,400,000 m 3 - Deposit in River Channel 8,100,000 m 3 - Excavation in River 25,500,000 m 3 - Sedimentation in Bili-Bili Dam 7,900,000 m 3 - Flow down to the Downstream 7,900,000 m 3 Sedimentation in Bili-Bili Dam 7,900,000 m3 Flow down to the Downstream 7,900,000 m3 Excavation in River 25,500,000 m3 Deposit in River Channel 8,100,000 m3 Sediment Discharge from Caldera 49,400,000 m3 Generated Sediment at Caldera 60,400,000 m 3 Stored in Caldera by Sabo Dam 11,000,000 m3 Mt. Bawakaraeng 16

General Map of the Project 17

RG Collapsed Mountain Mt. Bawakaraeng RG Telemetry System for Monitoring & Warning of Debris Flow -4 Rain gauges - 1 Water Level Gauge Legend RG The Most Urgent Works Emergency Works Daraha Bridge Flashed away on April 17, 05 RG WL Sabo Dams for protection of sediment discharge from Caldera - 10 Sabo dams Construction - Total height 100 m Rain/Water Level Gauge (proposed) Sabo/Sand Pocket Dam (Proposed) Sabo/Sand Pocket Dam (Existing) SD No. 4 to be re-constructed for debris flow control Malino River Conservation of Buried Paddy Field as a regional development to relief the suffered people as well as to control sediment discharge - Groundsill & channel works - Irrigation system - Reclamation of land SP No. 5 SP No. 4 SP No. 3 Sediment Excavation at End of Reservoir & Sand Pocket Dams Excavation Volume 5 mil. m 3 /year for 5 years (1n 2006, applying NPTGA: Rp31M from 2007, JBIC Loan) SP No. 2 SP No. 1 Dredging Works to recover the effective storage of the Bili- Bili Reservoir (details are under study) Spoil Bank at Site of Quarry (beside the Spillway) Rehabilitation of Sand Pocket Dam No. 4 Bawakaraeng Urgent Sediment Control Project EL. 61 m Bili-Bili Dam 18 EL. 59 m

Sabo Dam Plan: Profile 1,150 1,100 Layout of Sabo Dams (Longitudinal Profile) SD 7-10 1,050 SD 7-9 SD 7-8 Elevation (EL. m) 1,000 950 900 SD 7-1 SD 7-2 SD 7-3 SD 7-4 SD 7-6 SD 7-5 SD 7-7 10 1 20 1 Lengkese 850 Surface of Debris (EL. m) 800 Bottom of Gully (EL. m) Design Slope (EL. m) 750-100.0 100.0 300.0 500.0 700.0 900.0 1,100.0 1,300.0 1,500.0 1,700.0 1,900.0 2,100.0 2,300.0 2,500.0 2,700.0 Distance (m) 19

Sabo Dam Plan: Plan Jene Berang Parangkeke Kec. Tinggimoncong Kab. Gowa Paragang Jeneberang River 20

The Most Urgent Components Selection Concepts For the early implementation of the works, the Consultant was selected under direct appointment. But the scope of works were limited to the Most Urgent Components which were selected in accordance with following concepts: The works will affect the peoples lives and their daily activities. The works related to the sediment control and must be conducted within this year to catch up the proposed schedule. 21

Scope of Works the Most Urgent Components (1) Study Components Urgent Investigations (Data Collection, Survey for Further Collapse); Preparation of hazard map and monitoring, warning and evacuation systems; Periodical survey of river and reservoir and its analysis; (2) Environmental and Regional Development Components Establishment of PAFs Participatory Process to the Project; Environmental Monitoring; (3) Structural Components Excavation of Riverbed Deposit to be conducted in 2005 and 2006; Construction of Series of Sabo Dams No. 7 to be constructed in 2005 and 2006; Establishment of Telemetry System; 22

Proposed Additional Works Works should be conducted immediately - Design of Daraha Bridge. - Rehabilitation of Sand Pocket Dam No. 4. - Sediment Flashing for Bili-Bili Dam. Works to be conducted in Stage II - Succeeding works of MUC - Construction of Daraha Bridge - Regional Development Works to be conducted in future - Reservoir Sedimentation Control Measures. - Surface Water Intake System. - Watershed Management Plan of the JRB. 23

Proposed Additional Works Proposed Additional Sediment Control Measures In the Caldera - Hillside Works - Reforestation At the Reservoir - Drainage of Natural Dams -Dredging - Sediment Trap & Bypass Tunnel - Selective Water Intake Mt. Bawakaraeng Along the Middle Section Along the Upstream Section - Riverbed Excavation at Sand Pockets -Sand Mining - Sabo Dams - Channel Works - Groundsills - Channel Works 24

Implementation Schedule E/S for MUC/Stage II 1. Riverbed Excavation Works 2. Sabo Dams Construction 3. Establishment of Telemetry System 4. Daraha Bridge Construction 5. Rehabilitation of Structures 6. Regional Development Works 7. Environmental Monitoring 8. Urgent Survey/Long Term Plan 9. Sabo Community Support 04 Under APBN 05 06 Collapse (Mar. 04) Appraisal (Oct. 04) Pledge (Jan. 05) L/A (mar. 04) MUC Urgent Survey 07 08 Stage II 09 10 Up to 2012 Long Term Plan 25

Present Activities Construction Works Construction of Sabo Dam No. 7-1 - Design Dec. 2004 -Tender May -Jul. 2005 - Construction Jul. 2005 - Oct. 2005 Telecommunication System - Design Jun. - August 2005 - Tender Sep. - Dec. 2005 -Construction Jan. -Oct. 2006 26

Present Activities Urgent Survey Starting from June 2005 Site Investigation in & around the Caldera. Data Collection - Related Reports/Topographic Maps - Rainfall Data from DCO/DINAS; - Turbidity of Raw Water from PDAM & PLN; - Debris Flow & Rainfall records from Sabo Communities. Evaluation of Collapse Mass & Sediment Movement through Map/Aerial Photo Readings. Geological Evaluation -Geological - Verification of Mechanism of the Collapse; - Evaluation of further collapse. 27

Present Activities Subcontract Works Topographic Survey - Aerial photo & Ortho-photo mapping - River Cross-sectional Survey - Reservoir echo-sounding - Topographic survey at Daraha Bridge Material & Geological Investigation - Riverbed Material Survey - CSG & ISM Trial Mix. - Geological Survey at Daraha Bridge The environmental monitoring for the construction works Assistance works of the activities of Sabo Communities in Jeneberang 28

Activities of Sabo Community Monitoring of Sediment Movement and Debris Flow. Monitoring of Rainfall at Panaikang. Public Awareness of Sediment Disaster. - Preparation of Hazard Map applying the PRA Process; - Establishment of Evacuation Center; - Indication of Hazardous Zone; - Emergency Drill of Warning & Evacuation. Support of Local Economic Activities. - Training of Production of Concrete Pavement Block; - Nourish of young trees, etc.; 29

The End 30