January 17, 2008 File:

Similar documents
January 12, 2006 File:

December 11, 2006 File:

September 3, 2009 File: NORTH CENTRAL REGION GEOHAZARD ASSESSMENT HWY 40:28 NORTH OF CADOMIN (NC50) 2009 ANNUAL INSPECTION REPORT

August 10, 2007 File:

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

PEACE REGION (PEACE RIVER- HIGH LEVEL AREA) GEOHAZARD ASSESSMENT CALL-OUT PH56: EMBANKMENT FAILURE ON HWY 35:08 SOUTHWEST OF MEIKLE RIVER CROSSING

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

The results of KCB s site inspection observations and our recommendations for further work are presented herein.

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

PEACE REGION GRANDE PRAIRIE GEOHAZARD RISK ASSESSMENT SITE INSPECTION FORM NAD 83 COORDINATES N 6,178,811 E 403,309

CENTRAL REGION GEOHAZARDS RISK ASSESSMENT SITE INSPECTION FORM

PEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007

ALBERTA TRANSPORTATION PEACE REGION (PEACE RIVER / HIGH LEVEL) INSTRUMENTATION MONITORING RESULTS

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

Rock & Aggregate Drop Inlet Protection

CCR Rule Annual Inspection Report (cont.) 2

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Erosion and Sediment Control Measures 2.7 Silt Fences

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

MEMORANDUM. wa.tsr..-z.n~.e.s-t.i~at.i.o.ns... Branch... Mr. Webster contends that prior to excavation of the gravel

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

January 16, Re: Soo Line Dump Site 2018 Annual Soil Cover Inspection. Dear Mr. Nichols:

October 26, Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402

Construction Exits Rock pads

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973

Geosynthetics Applications and Performance Reviews Select Case Histories

Black Gore Creek Sediment Source Monitoring and TMDL Sediment Budget

U-Shaped Sediment Traps

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION

1 INTRODUCTION 1.1 General

September 18, 2017 Project No.: 5077

Degradation Concerns related to Bridge Structures in Alberta

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Geohazards Associated with Dispersive-Soil Voids

LANDSLIDES IN THE WHITE MOUNTAIN (GEOTECHNICAL STUDIES AND ENGINEERING TESTS)

1.0 INTRODUCTION 2.0 OBSERVATIONS EBA FILE: W nd Avenue Whitehorse, YT Y1A 1C2. Attention:

3/8/17. #20 - Landslides: Mitigation and Case Histories. Questions for Thought. Questions for Thought

APPENDIX B WORKSHEETS & EXHIBITS

WHITE POINT LANDSLIDE GEOTECHNICAL INVESTIGATION November 29, 2012 Status Report

3.12 Geology and Topography Affected Environment

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive

Gotechnical Investigations and Sampling

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

Remediation of Soft Clay Utilizing the Dry Mix Method. of Batavia, New York to its discharge into the Niagara River at Tonawanda, New York.

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

Mass Wasting. Revisit: Erosion, Transportation, and Deposition

SLOPE STABILITY ASSESSMENT PROPOSED RESIDENTIAL SUBDIVISION 161 LAKESHORE ROAD EAST TOWN OF THE BLUE MOUNTAINS, ONTARIO

Husky Oil Operations Limited

(Refer Slide Time: 01:15)

DETAILED INVESTIGATION OF PILES DAMAGED BY HYOGOKEN NAMBU EARTHQUAKE

To: Rishi Adhikari and Roger Skirrow From: Leslie Cho and Ian Darrach Alberta Transportation File: Date: June 30, 2016

3.18 GEOLOGY AND SOILS

Mass Wasting. Requirements for Mass Wasting. Slope Stability. Geol 104: mass wasting

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

Crows Landing Naval Base Easement

Photographic Log. Photo No. 1. Date: 10/27/15. Direction Photo Taken: Southwest. Photo Taken By: JBH1

Assessing Slope Instabilities. Victoria Leffel & Joey Franzino

Ch. 8: Mass Movements, Wind and Glaciers

Observations on Surface Water in the Seminary Fen in Spring, Prepared 6/4/13 by Sam Wetterlin; updated 7/28/13

CHRACTERISTICS OF LANDSLIDE OCCURRED IN LOPARE, BOSNIA AND HERZEGOVINA


LONG-TERM MOVEMENTS OF HIGHWAY BRIDGE APPROACH EMBANKMENTS AND PAVMENTS

Landslide stability analysis using the sliding block method

Chapter 11 10/30/2013. Mass Wasting. Introduction. Factors That Influence Mass Wasting. Introduction. Factors That Influence Mass Wasting

APPROACH FILL DESIGN OF NORTH SASKATCHEWAN RIVER BRIDGE. A.F. Ruban, EBA Engineering Consultants Ltd., Edmonton, Alberta, Canada

Stormwater Inlet Sediment Traps

Geophysical Case studies From Texas

Nipigon River Landslide, Ontario, Canada

THE MINISTRY OF ENERGY AND ENERGY INDUSTRIES MINERALS DIVISION MINE DESIGN TEMPLATE OPERATOR NAME: OPERATOR ADDRESS: PHONE NUMBER: FACSIMILE:

STRUCTURAL STABILITY ASSESSMENT

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations.

Geotechnical Investigation and Monitoring Results of a Landslide Failure at Southern Peninsular Malaysia (Part 1: Investigating Causes of Failure)

Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No


depression above scarp scarp

ROCK EXCAVATION (GRADING) OPSS 206 INDEX

A new design approach for highway rock slope cuts based on ecological environment protection

Internal C Unit Dilatanc y

February 22, 2016 AG File No

Background. Valley fills Sites in the Area. Construction over Mine Spoil Fills

Canadian Consulting Engineering Awards 2017 Southern Alberta Rock Slope Stabilization & Other Work Amec Foster Wheeler

ISSUED FOR CONSTRUCTION

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE

POTENTIAL EFFECTS OF EARTHQUAKE SHAKING ON THE PROPOSED CRRRC LANDFILL

POLICY MANUAL. Hamlets/Residential named hamlets within the County of Grande Prairie whose roads are hard surfaced.

Geotechnical Completion Report Knights Stream Park Stage3A Development (Lots 107 to 148)

TABLE OF CONTENTS LIST OF TABLES. Page

CHAPTER 7 GEOLOGY AND SOILS

When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill

Geotechnical Investigation Bow Ridge Subdivision Phase 3 Cochrane, Alberta

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013

Location Restriction Demonstration

Challenge Statement: Earthwork Monitoring From Above. 5-Oct-16 / 1

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

3.12 Geology and Topography Affected Environment

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Transcription:

January 17, 2008 File: 15-85-73 Alberta Infrastructure and Transportation Room 301, Provincial Building 9621-96 Avenue Peace River, Alberta T8S 1T4 Attention: Mr. Ed Szmata PEACE REGION (SWAN HILLS AREA) GEOHAZARD ASSESSMENT HWY 750:04 EMBANKMENT SLUMP (SH 14), SALT CREEK 2007 ANNUAL INSPECTION REPORT Dear Sir: This letter documents the 2007 annual site inspection of an area of slope instability located along Hwy 750:04 about 4 km north of the junction of Hwy 679, northeast of High Prairie, Alberta. Thurber Engineering Ltd. (Thurber) undertook this inspection in partial fulfillment of our Geotechnical Services for Geohazard Assessment, Instrumentation Monitoring and Related Work contract (CE047/2004) with Alberta Infrastructure and Transportation (INFTRA). Mr. Barry Meays, P.Eng. and Mr. Gurpreet Bala, M.Sc. of Thurber undertook the inspection on June 15, 2007 in the presence of Mr. Ed Szmata, Mr. Rocky Wang and Mr. Rodney Johnston of INFTRA. 1. BACKGROUND The available background for this site was summarized in June 2004 in the Geotechnical File Review in Section A of the binder. The site has a history of instability going back to 1988 when a slide occurred in the west side of the highway. At that time, the slide was about 80 m wide with a 25 m crack at the highway centreline and 0.3 m of differential settlement. Following the slide event, a 9 m wide by 3 m high toe berm was constructed and two 150 mm diameter subdrain pipes were installed. Repairs in the last few years have consisted mainly of maintenance to the highway surface to preserve a smooth surface.

2. SITE OBSERVATIONS The changes in condition since last year are shown on the attached site sketch plan and discussed below. Selected photographs taken during the visit are also attached. The current instability consists of a 40 m-long slump in the west sideslope. The asphalt surface contains arc-shaped cracks. A drop of about 30 mm was measured at the crack in the highway. A dip was observed to the south of the crack within the highway pavement. Mr. Johnston informed that the drivers of the snowploughs felt the dip during winter snow clearing activities. An additional 5 m long crack was also noted in the sideslope of the highway at about 4 m from the edge of highway embankment. The toe roll of the slide has pushed out the barbed-wire fence about 0.8 m at the contact between the upper slope and the toe berm. Two Telus cables have been routed overland along the fence line over the slide area. Erosion and shallow instability have also been observed northwest of the slide area. Both of the north and south drain pipes near the toe of the slump were dry at the time of our visit. Additional slumping was noted in the creek banks west of the highway. A beaver dam was being constructed west of the culvert inlet. Mr. Johnston noted that the culvert was running full for a week during the spring snow melt this year. The shallow slump scarps that were observed last year on the backslope east of the highway have resulted in a slump around 50 m wide and about 12 m in length from the back scarp to the toe. The back scarp of the slump was 0.9 m high and the toe roll was about 0.3 m high and was extending up to the highway ditch. Two intermittent cracks extending along the entire length of the scarp were observed. At about 150 m to the south of the main slide zone, a 40 m wide and about 10 m long backslope slump was observed. The height of the backslope from the bottom of the drainage ditch to the crest was about 3.5 m. The backscarp was 1 m in height with a 0.3 m to 0.4 m high toe roll. A portion of the slump to the north was within a treed area. The right of way (ROW) limits of the highway appeared to be along the crest of the slope and the slump extended slightly into the farmer s field. A survey marker was present within the treed area. An erosion gully was present at the south corner of the slump. File: 15-85-73 Page 2 of 5

3. ASSESSMENT The test holes drilled at the site in 2002 indicated subsurface conditions consisting of gravel and/or high plastic clay fill over high plastic clay over medium plastic clay till. The clay till has some sand layers interbedded in it. SI02-4, which was installed in the shoulder of the highway but was covered in asphalt in 2004, indicates that the slip surface of the slide was located in the clay layer about 5.2 m below ground surface. SI02-2, which was installed near the downslope crest of the berm, indicates that a slip surface also extends below the berm in the clay layer at about 4 m below ground surface at the SI location. The slide creep rate was 23.7 mm/year at the spring 2006 readings compared to 19 mm/year in 2005. None of the two slope inclinometers were operational as observed during the 2007 spring monitoring. The piezometers indicated a piezometric surface at 2.2 to 2.8 m below ground surface, and were mainly unchanged since the measurements of 2002. The standpipe piezometer SP02-4 showed a slight increase of about 0.44 m in the groundwater elevation since last year winter readings. Based on the above, the overall height and inclination of the highway embankment and toe berm fills is too steep for the existing relatively weak and wet clay foundation soils. The slide appears to be moving in two blocks, an upper block, which is spilling out onto the berm and pushing out the fence and a lower more deeply seated block that extends below the slope and the toe berm. The scarp scallops observed on the east backslope are believed to be separate, isolated slides, and likely not associated to either of the blocks on the downslope side of the highway. 4. RISK LEVEL The risk level for this site has been assessed as follows: PF(10) * CF(4) = 40 (40 in 2006) A Probability Factor of 10 is considered appropriate since the slide is active with a perceived moderate steady rate of movement. A Consequence Factor of 4 is considered appropriate since the embankment fill is fairly high and a partial closure of the road would be a direct result of an aggressive slide movement. File: 15-85-73 Page 3 of 5

5. RECOMMENDATIONS 5.1 Short Term The slide is currently affecting the highway pavement and requires ongoing asphalt patching and crack sealing maintenance. In the short term the site should be regularly inspected by the MCI to determine when further asphalt patching maintenance is required to maintain a smooth even road surface for traffic safety. The slumped soil mass at both the backslope slides on the east and west side of the highway should be cleaned from the highway ditch, in order to allow proper drainage. The slope can be regraded at the present slope with a dozer and vegetated to prevent erosion and water from entering the slumped mass of soil. 5.2 Intermediate Term An intermediate term fix for the backslopes consist of excavating the slumps to depths below the estimated slip surfaces, moisture conditioning the excavated clay and then reconstructing the slopes with well compacted horizontal lifts to establish the slope(s) to the original slope angles. The estimated cost for the repairs of the slumps can be in order of $ 50,000. 5.3 Long Term A potential long term stabilization measure for the affected highway section consists of enlarging the toe berm, digging out the lower toe roll and building a shear key that extends into the clay till, and subexcavating and replacing the failed material in the upper slope with stronger (gravel) material. In addition, consideration could be given to installing a subdrain under the upslope ditch. The road surface will also need to be repaved through the slide zone. Another long-term option consists of a pile wall to stabilize the west shoulder of the highway. The wall would need to be about 40 m long. Based on previous similar projects the cost for the construction of either of these long-term remedial measures is expected to be in the order of $500,000 to $700,000. For the two backslope slumps, the long term solution would be to flatten and regrade the slope at 4(H) to 1(V) or flatter. For this the ROW limits of INFTRA would need to be extended into the farmer s property. The cost of the long-term File: 15-85-73 Page 4 of 5

measures for the slopes is expected to be in order of $150,000, excluding the cost of extra right-of-way. 5.4 Investigation A survey of the Salt Creek slide area was carried out by EXH Engineering Services Ltd. on April 24, 2006 (refer to attached site plan). A marshland assessment (fisheries/amphibians) was completed by Spencer Environmental Management Services Ltd. and will be included with a preliminary engineering report currently being prepared by Thurber, in the near future. 5.5 Maintenance It is recommended that the site should be regularly inspected by the MCI to determine when further asphalt patching maintenance is required to maintain a smooth even road surface for traffic safety. The highway drainage ditch should be cleaned of the slumped mass to provide adequate drainage for the surface runoff. 6. CLOSURE We trust this assessment and recommendations meet with your needs at this time. Please contact the undersigned should questions arise or if the slide conditions worsen. Yours very truly, Thurber Engineering Ltd. Don Proudfoot, P.Eng. Review Principal Barry Meays, P.Eng. Gurpreet Bala, M.Sc. Project Engineer Project Coordinator /dw Attachments cc: Mr. Roger Skirrow, P. Eng. Director of Geotechnical Services, INFTRA File: 15-85-73 Page 5 of 5