STATUS REPORT ON STORAGE RING REALIGNMENT AT SLRI

Similar documents
Lattice Design for the Taiwan Photon Source (TPS) at NSRRC

Lattice Design and Performance for PEP-X Light Source

Accelerator Design and Construction Progress of TPS Project

Abstract. 1. Introduction

Boster Synchrotron COMMISSIONING RESULTS LINAC. Storage Ring. Proceedings of IPAC2011, San Sebastián, Spain

David Martin High Precision Beamline Alignment at the ESRF IWAA, Grenoble 3-7 October 2016

Preliminary design study of JUICE. Joint Universities International Circular Electronsynchrotron

THE SPEAR3 UPGRADE PROJECT AT SLAC *

First propositions of a lattice for the future upgrade of SOLEIL. A. Nadji On behalf of the Accelerators and Engineering Division

SURVEY AND ALIGNMENT FOR THE SYNCHROTRON LIGHT SOURCE ELETTRA

Phase Space Study of the Synchrotron Oscillation and Radiation Damping of the Longitudinal and Transverse Oscillations

ILC Damping Ring Alternative Lattice Design **

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

Accelerator Physics. Accelerator Development

ALIGNMENT RESULT FOR MAGNET UNITS OF THE SPRING-8 STORAGE RING

STATUS REPORT ON SURVEY AND ALIGNMENT OF J-PARC AFTER THE EARTHQUAKE

Conceptual design of an accumulator ring for the Diamond II upgrade

The Alignment of BEPCII RING

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

FIRST OPERATION OF THE SWISS LIGHT SOURCE

On-axis injection into small dynamic aperture

JSPS Asien Science Seminar Synchrotron Radiation Science

ALIGNMENT OF CAVITIES AND MAGNETS AT J-PARC LINAC

Fine Alignment of the ATF Damping Ring

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

The 10th International Workshop on Accelerator Alignment, KEK, Tsukuba, February 2008 ALIGNMENT OF S-LSR

LOW EMITTANCE MODEL FOR THE ANKA SYNCHROTRON RADIATION SOURCE

HIRFL STATUS AND HIRFL-CSR PROJECT IN LANZHOU

1 BROOKHAVEN SCIENCE ASSOCIATES

COMMISSIONING OF NSLS-II*

MAX-lab. MAX IV Lattice Design: Multibend Achromats for Ultralow Emittance. Simon C. Leemann

Canadian Light Source: Overview

Accelerator Physics. Tip World Scientific NEW JERSEY LONDON SINGAPORE BEIJING SHANGHAI HONG KONG TAIPEI BANGALORE. Second Edition. S. Y.

1.5-GeV FFAG Accelerator as Injector to the BNL-AGS

COMBINER RING LATTICE

COMMISSIONING OF THE MAX IV LIGHT SOURCE

HLS online monitoring during beam assisted girder re-alignment at the accelerator SLS (Swiss Light Source)

Accelerator. Physics of PEP-I1. Lecture #7. March 13,1998. Dr. John Seeman

The optimization for the conceptual design of a 300 MeV proton synchrotron *

RADIATION SOURCES AT SIBERIA-2 STORAGE RING

2.6 Electron transport lines

MAGNET INSTALLATION AND ALIGNMENT FOR THE FUJI TEST BEAM LINE AT KEKB

Emittance Growth and Tune Spectra at PETRA III

ThomX Machine Advisory Committee. (LAL Orsay, March ) Ring Beam Dynamics

Update on Optics Modeling for the ATF Damping Ring at KEK Studies for low vertical emittance

Diagnostics at the MAX IV 3 GeV storage ring during commissioning. PPT-mall 2. Åke Andersson On behalf of the MAX IV team

First commissioning of the HLS-II storage ring*

LIS section meeting. PS2 design status. Y. Papaphilippou. April 30 th, 2007

Insertion Devices Lecture 2 Wigglers and Undulators. Jim Clarke ASTeC Daresbury Laboratory

Longitudinal Top-up Injection for Small Aperture Storage Rings

ALBA Synchrotron Light Source Commissioning

Iranian Light Source Facility (ILSF) Project

The Alignment Concept For The Fermilab Recycler Ring Using Permanent Magnets

Low energy electron storage ring with tunable compaction factor

Alignment of S-LSR. H. Souda, M. Tanabe, T. Ishikawa, M. Ikegami, T. Takeuchi*, H. Tongu, T. Shirai, A. Noda

NSRRC Current Status and the TPS Project

3. Synchrotrons. Synchrotron Basics

THE SPEAR3 UPGRADE PROJECT AT SLAC * Abstract

RF systems for the MAX IV rings

THE GSI FUTURE PROJECT: AN INTERNATIONAL ACCELERATOR FACILITY FOR BEAMS OF IONS AND ANTIPROTONS

Turn-by-Turn Beam Position Measurements at ANKA with LIBERA ELECTRON

Commissioning of PETRA III. Klaus Balewski on behalf of the PETRA III Team IPAC 2010, 25 May, 2010

Beam Optics for Parity Experiments

Putting it all together

3.2 The MAX IV 3 GeV Storage Ring

Simulation of Optics Correction for ERLs. V. Sajaev, ANL

Lattice Cell/Girder Assembly

Experience on Coupling Correction in the ESRF electron storage ring

Operational Experience with HERA

USPAS Accelerator Physics 2017 University of California, Davis

6 Bunch Compressor and Transfer to Main Linac

Bernhard Holzer, CERN-LHC

ILC Damping Ring Alternative Lattice Design (Modified FODO)

Lattices for Light Sources

Effect of Insertion Devices. Effect of IDs on beam dynamics

Design Status of the PEFP RCS

Tools of Particle Physics I Accelerators

MAX IV, NSLS II, PLS II, LCLS, SACLA, European XFEL,

Linear Collider Collaboration Tech Notes. A New Structure for the NLC Positron Predamping Ring Lattice

COMMISSIONING AND STATUS OF THE DIAMOND STORAGE RING

LCLS Accelerator Parameters and Tolerances for Low Charge Operations

X-band RF driven hard X-ray FELs. Yipeng Sun ICFA Workshop on Future Light Sources March 5-9, 2012

Part V Undulators for Free Electron Lasers

BEPC AND THE FUTURE PROGRAM AT IHEP

Survey and Alignment of the Fermilab Electron Cooling System

TitleOutline of the Compact Electron Sto.

S2E (Start-to-End) Simulations for PAL-FEL. Eun-San Kim

A Project to convert TLS Booster to hadron accelerator 1. Basic design. 2. The injection systems:

Summary Report: Working Group 2 Storage Ring Sources Future Light Source Workshop SLAC, March 1-5, S. Krinsky and R. Hettel

ELECTRON COOLING EXPERIMENTS IN CSR*

e + e Factories M. Sullivan Presented at the Particle Accelerator Conference June 25-29, 2007 in Albuquerque, New Mexico e+e- Factories

A PRELIMINARY ALIGNMENT PLAN FOR RIA AT MSU

Low Emittance Storage Ring for Light Source. Sukho Kongtawong PHY 554 Fall 2016

Lattice Design of 2-loop Compact ERL. High Energy Accelerator Research Organization, KEK Miho Shimada and Yukinori Kobayashi

Polarised e ± at HERA

and Applications in the Middle East S E S A M E Applications in the Middle East Upgrading of SESAME to 2.5GeV The Yellow Book November 2003

Collider Rings and IR Design for MEIC

Beam Dynamics Activities at the Thomas Jefferson National Accelerator Facility (Jefferson Lab)

Status Report on the Survey and Alignment efforts at DESY

3.2.2 Magnets. The properties of the quadrupoles, sextupoles and correctors are listed in tables t322_b,_c and _d.

Transcription:

STATUS REPORT ON STORAGE RING REALIGNMENT AT SLRI S. Srichan #, A. Kwankasem, S. Boonsuya, B. Boonwanna, V. Sooksrimuang, P. Klysubun Synchrotron Light Research Institute, 111 University Ave, Muang District, Nakhon Ratchasima 30000, Thailand Abstract Siam Photon Source (SPS), a synchrotron light source operated by Synchrotron Light Research Institute (SLRI) in Thailand, was installed and commissioned in the year 2001. During the past eleven years since the commissioning, the 1.2 GeV electron storage ring had been realigned in total three times. The first realignment was carried out and the result was reported in 2002. Optical survey has been regularly carried out on an annual basis afterwards, with the survey data providing assessment whether realignment is necessary. In this report, we describe the realignment procedures at the SPS, together with the results from the second realignment performed in 2006 and the most recent storage ring realignment in June 2012. INTRODUCTION SLRI is a synchrotron radiation research facility located in Nakhon Ratchasima, Thailand. The SPS accelerator complex consists of two 20 MeV injector linacs, a 1.0 GeV booster synchrotron (SYN) and a 1.2 GeV electron storage ring (STR). The storage ring has a double bend achromat (DBA) lattice with four super periods. In total there are 8 bending magnets, 28 quadrupoles in four families, 16 sextupoles, and 28 correctors. The ring circumference is 81.3 meters. [1] Machine specifications of SPS can be summarized as listed in Table 1. The layout of the SPS accelerator is as shown in Figure 1. In this report we focus mainly on the survey data and realignment of the SPS storage ring. We will describe the survey instruments involved, the realignment procedures for all the components, and finally the results of the latest realignment in June 2012. Table 1: Summary of SPS machine specifications. [2] Electron beam energy 1.2 Beam current [ma] 150 Lattice DBA Superperiod 4 Horizontal emittance [nm. rad] 41 Emittance ratio [%] 3.5 Circumference [m] 81.3 Number of straight sections 4 (7 m) Betatron tunes ν x, ν y 4.76, 2.83 Synchrotron tune ν s 0.0026 Natural chromaticities ξ x, ξ y -9.21, -6.56 Momentum compaction factor α c 0.0169 Radio frequency [MHz] 118.0 Harmonic number 32 RF voltage [kv] 120 RF power [kw] 30 Energy loss per turn [kev] 66.0 Injection beam energy [GeV] 1.0 Number of RF cavity 1 Number of insertion device 1 (U60 undulator) Number of bending magnet 8 Number of quadruple magnet 28 Number of sextupole magnet 16 Number of steering magnet 28 #supawan@slri.or.th

SURVEY AND REALIGNMENT ACTIVITY After the installation of SPS accelerator complex was completed in December 2000, the booster synchrotron had undergone realignment in June 2001, and the first machine commissioning was succeeded in October 2001. One year after the commissioning, the maximum difference of STR dipole magnet levels was found to be 4.2 mm. The first STR realignment was carried out in June 2002, resulting in increased beam lifetime. [3] Table 2 shows an overview of the SPS survey and alignment activities, together with the equipments used, approximate time required, and frequency of each activity. Horizontal and vertical adjustments for STR and SYN magnets are made using hand tools. The machine realignment is performed during machine shutdown period, and the responsibility falls with an engineer team in Accelerator Technology Division. Table 2: Overview of survey and realignment activities of SPS accelerator. Activity Instrument Time requirement Frequency of occurrence Storage Ring STR level 1 day Once per year survey STR horizontal and vertical realignment SYN level survey SYN horizontal and vertical realignment Laser tracker, Figure 1: Layout of the SPS accelerator complex. 4-6 weeks 3 times up till now: I-June 2002 II-November 2006 III-June 2012 Booster Synchrotron 1 day At least every 2 years Laser 4 weeks Once up till tracker, now: June 2001 Figure 2 shows the elevation survey data after the first STR realignment (labeled 'May 2003') and two survey data taken before the latter two STR realignments (labeled 'March 2006' and 'May 2012'). The data shown uses the level of horizontal bending magnet 2 (BH2), the final magnet of the high energy beam transport (HBT), as reference (zero). The vertical displacement in May 2003, about one year after the first realignment, was in range of ±1.00 mm. The displacement then grew to about 2.5 mm in March 2006. During the second machine shutdown of 2006 at the end of the year, the SPS storage ring was realigned. The position of all the components was brought to within ±0.2 mm with respect to design values. [1, 4] In the latest optical survey in May 2012, almost 6 years after the second realignment, the maximum vertical displacement grew to almost 3.0 mm. It was decided that STR realignment would be carried out during the machine shutdown in June 2012. What is interesting in the survey data is that, as seen in Fig. 2, the variations in the STR magnet heights from the three separate occasions follow roughly the same pattern. For example, the vertical deviation of the BM05 and BM06 dipoles magnets are much more than that of the others. It is very likely that the misalignment was primarily due to the effect of floor settlement. This finding suggests the displacement of pile foundation under the storage ring, together with the distortion of the floor, should be investigated and analyzed.

BH2 BM01-C QF31U QF41U QF32U BM02-U BM02-D QF12C QD23C BM03-C QF33U QD42U QF34U BM04-U BM04-D QF14C QD25C BM05-C QF35U QD43U QF36U BM06-U BM06-D QF16C QD27C BM07-C QF37U QD44U QF38U BM08-U BM08-D QF18C QD21C BM01-C Displacement (mm) Figure 2: Surveying data of SPS storage ring magnets. STORAGE RING ALIGNMENT PROCEDURE During the installation of the SPS, survey network was established and reference marks were installed. [5] Table 3 shows the alignment tolerance allowed for each of the STR component, and Table 4 lists the survey instrumentation involved. The alignment process can be summarized as shown in the flow chart in Figure 3. The alignment process is as followed. First, the individual storage ring component is adjusted to the reference height, and its tilt reset to zero, simultaneously. After that, fine adjustment of the position in 3-D space is carried out with the help of a laser tracker. This whole process is iterated until the position in 3-D space of all the components converges to the design values. Table 3: Alignment tolerance. [5] Components Reference components or marks Required precision (mm) Dipoles 1.50 1.00 0.50 0.00-0.50-1.00-1.50-2.00-2.50-3.00 Multipoles Steering magnets Beam Position Monitor Survey data of STR magnet May 2003 March 2006 May 2012 Dipole reference marks / Level marks Dipole reference marks / Level marks X and Y Beam stream Tilt (mm/m) +0.2 +0.2 +0.2 +0.2 +0.2 +0.2 Quadrupoles +0.5 +0.5 +0.5 Quadrupoles +0.5 +0.5 +0.5 Table 4: Alignment instrumentation. Measurement Instrument Accuracy Coordinates Laser tracker Angular resolution FARO-CAM2 0.02 arc seconds Angular repeatability 3 µm + 1 µm/m Angular accuracy 18 µm + 3 µm/m Interferometer max working range 35 m Centering Elevation Inclination QM alignment Optical plummet LEICA-NL Precision level LEICA-NAK2 Parallel plate micrometer LEICA-GMP3 Electronic tilt meter WYLER- NT41H Alignment START BM alignment Survey check Does the component align to the ideal position with targeted accuracy? END Standard deviation when plumbing with two observations at 180 o = 1:200,000 Standard deviation per 1 km Double-run leveling ±0.3 mm Sensitivity : 0.001 mm/m Base dimension : 45x150 mm Figure 3: Storage ring alignment procedure. [6] Adjusting elevation Alignment of other machine components (SXF, SXD, STH, STV, BPM, etc.) YES Realign the component whose position lies outside the tolerance limit As stated earlier, all the storage ring components are adjusted using the height of the horizontal bending magnet BH2 as a reference. The tools for the adjustment process are a LEICA-NAK2, an invar staff, and a survey target. NO

ALIGNMENT OF THE STORAGE RING MAGNET Figure 4: Zero elevation is set at BH2 magnet. Adjusting inclination (tilt) Tilting of each storage ring component is adjusted using an electronic tilt meter resting on a survey target plate. Figure 5: Inclination of each component is adjusted using an electronic tilt meter. Adjusting horizontal position Horizontal position is adjusted with the aid of a laser tracker. The horizontal plane is defined with three or more reference marks. During the alignment process the horizontal plane needs to be redefined whenever the laser tracker is moved to a new location around the storage ring. Dipole magnets Elevation of all the dipole magnets was adjusted to be equal to the height of the datum reference. The tilt was also adjusted to be within ±0.2 mm/m. The laser tracker was used to monitor horizontal positions. The position of the laser tracker was carefully chosen such that the survey can be carried out over the whole area of the storage ring, without any obstruction from numerous equipments blocking the line of sight. The dipole magnet position was adjusted to the design coordinates. The beam trajectory is established by a set of straight lines connecting these dipoles. Quadrupole magnets As mentioned above, the dipole magnets were used to project a straight line needed for the alignment of other magnets in between. There are two sets of quadrupole magnets in the SPS storage ring. The old ones have only one target hole at the center, while the new quadrupoles have two target holes, one upstream and one downstream. The height and tilt adjustment of the new quadrupoles can be done with more precision than in the case of the old magnets. For horizontal adjustment with the laser tracker, both target holes on the new magnet are used for setting the reflector. After the realignment, all the quadrupole magnets were brought to be within ± 0.2 mm with respect to the design values. The tilt was measured to be the within ± 0.2 mm/m. Sextupole magnets, steering magnets, and beam position monitors Sextupoles magnets, steering magnets, and beam position monitors are aligned using the precision level and the laser tracker in the same manner as for dipoles and quadrupoles, with both as the reference. Septum magnet, bump magnets, RF cavity, and insertion devices In the case of septum magnet, it was impossible to use the same alignment method as was done in the machine installation because the centre of magnet was not precisely known. Therefore, we only made the survey without adjusting the magnet position. The three bump magnets are adjusted to design coordinates with the precision level and the laser tracker. For the RF cavity, the same precision level/laser tracker combo is used, and the position of the cavity is also brought to be within the ±0.2 mm tolerance limit. The same is true for the only insertion device installed in the SPS ring, the U60 permanent magnet planar undulator. Figure 6: Laser tracker is used for adjusting position in the horizontal plane.

Figure 7: Survey data of SPS dipoles and quadrupoles, before and after the June 2012 realignment. MOST RECENT RESULTS Figure 7 shows the vertical displacement of the dipoles and quadrupoles before and after the most recent realignment performed in June, 2012, all of which satisfies the tolerance requirement as listed in Table 3. [6] K. Mishima, K. Endo, T. Ishii, M. Sugawara and W. Pairsuwan, Survey and alignment for the Siam Photon Project, APAC 01, Beijing, Chaina, 2001, p.571-578. CONCLUSION Realignment of the 1.2 GeV electron storage ring of Siam Photon Source has been successfully carried out in June 2012. The alignment was based on the existing network. All the magnets were moved to the design positions. After realignment, the beam can be injected and stored in the SPS ring without the need for orbit correction by steering magnets. ACKNOWLEDGMENT The works presented in this report could not have been accomplished without the hard work of many colleagues at SLRI. The authors would like to thank all colleagues who have contributed to this work. REFERENCES [1] P.Klysubun et al., Operation and improvement of the Siam Photon Source, APAC 07, Indore, February 2007, p.607-609. [2] SLRI Annual report, 2011, p.56. [3] N.Sanguansak et al., Realignment magnets of Siam Photon Source storage ring, 7 th IWAA2002, Spring-8, 2002, p.55-58. [4] A.Kwankasem et al., Realignment storage ring, NSRC Technical Note TN-2006/13, December 2006. [5] Mitsubishi Elec., PASCO Corp., The report for the survey for the reference marks and the alignment for the storage ring component on the National Synchrotron Research Center in Thailand, May 2001.