The last three sections of the main body of this report consist of:

Similar documents
3.12 Geology and Topography Affected Environment

Appendix C. Draft Geomorphic and Hydraulic Report

1 INTRODUCTION AND MAJOR FINDINGS... 1

Why Stabilizing the Stream As-Is is Not Enough

AASHTO Extreme Weather Events Symposium Vermont s Road and Rivers - Managing for the Future

LEVEE DESIGN FOR FLOOD PROTECTION ON ALLUVIAL FANS

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

GEOL 1121 Earth Processes and Environments

Solutions to Flooding on Pescadero Creek Road

3.18 GEOLOGY AND SOILS

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

UPPER COSUMNES RIVER FLOOD MAPPING

Why Geomorphology for Fish Passage

DRAFT Design Hydraulic Study. Bridge 04C-0055, Mattole Road Bridge over Mattole River at Honeydew. Humboldt County. Prepared for:

Chapter 3 Erosion in the Las Vegas Wash

Case Study 2: Twenty-mile Creek Rock Fords

Step 5: Channel Bed and Planform Changes

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT

Design Hydraulic Study. Bridge 09C-0134, Blairsden-Graeagle Road over Middle Fork Feather River. Plumas County. Prepared for:

3.12 Geology and Topography Affected Environment

HYDROLOGIC AND HYDRAULIC REPORT FOR SR. 0522, SECTION 5BN ALONG BLACKLOG CREEK CROMWELL TOWNSHIP HUNTINGDON COUNTY. Prepared for:

ADDRESSING GEOMORPHIC AND HYDRAULIC CONTROLS IN OFF-CHANNEL HABITAT DESIGN

CASE STUDIES. Introduction

Assessment. Assessment

Dan Miller + Kelly Burnett, Kelly Christiansen, Sharon Clarke, Lee Benda. GOAL Predict Channel Characteristics in Space and Time

Four Mile Run Levee Corridor Stream Restoration

Riparian Assessment. Steps in the right direction... Drainage Basin/Watershed: Start by Thinking Big. Riparian Assessment vs.

The Effects of Hydraulic Structures on Streams Prone to Bank Erosion in an Intense Flood Event: A Case Study from Eastern Hokkaido

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013

PolyMet NorthMet Project

Vermont Stream Geomorphic Assessment. Appendix E. River Corridor Delineation Process. VT Agency of Natural Resources. April, E0 - April, 2004

APPENDIX B Hydraulic Considerations for Pipeline Crossings of Stream Channels

Do you think sediment transport is a concern?

3/3/2013. The hydro cycle water returns from the sea. All "toilet to tap." Introduction to Environmental Geology, 5e

Gateway Trail Project

Diagnostic Geomorphic Methods for Understanding Future Behavior of Lake Superior Streams What Have We Learned in Two Decades?

Case Study 14. Rocky Creek Vented Box Culvert Ford

4.17 Spain. Catalonia

LOMR SUBMITTAL LOWER NEHALEM RIVER TILLAMOOK COUNTY, OREGON

Geomorphic Importance of Winter Peak Flows and Annual Snowmelt Hydrographs in a Sierra Nevada Boulder-Bedrock River

High-Gradient Streams

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

Wetland & Floodplain Functional Assessments and Mapping To Protect and Restore Riverine Systems in Vermont. Mike Kline and Laura Lapierre Vermont DEC

Stop 1: Marmot Dam Stop 1: Marmot Dam

Grant 0299-NEP: Water Resources Project Preparatory Facility

Swift Creek Sediment Management Action Plan (SCSMAP)

GEOMORPHIC CHANGES IN LOWER CACHE CREEK 2012

The subject paper is being submitted for approval for publication in the annual volume entitled Geological Survey Research.

Eagle Creek Post Fire Erosion Hazard Analysis Using the WEPP Model. John Rogers & Lauren McKinney

SCOPE OF PRESENTATION STREAM DYNAMICS, CHANNEL RESTORATION PLANS, & SEDIMENT TRANSPORT ANALYSES IN RELATION TO RESTORATION PLANS

Natural hazards in Glenorchy Summary Report May 2010

Pat Dryer Half Moon Lake: A True Oxbow Lake? Geography 364 April 1 st, 2007

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams

!"#$%&&'()*+#$%(,-./0*)%(!

Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018

IMPACTS OF SECONDARY FLOOD EMBANKMENTS ON THE WAIMAKARIRI FLOODPLAIN, NEW ZEALAND

Stream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation)

Opportunities to Improve Ecological Functions of Floodplains and Reduce Flood Risk along Major Rivers in the Puget Sound Basin

SECTION G SEDIMENT BUDGET

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION DISTRICT 6-0 HYDROLOGIC AND HYDRAULIC REPORT. for SR 3062, SECTION 29S STRASBURG ROAD.

Identifying, Understanding and Addressing Flood-Related Hazards

Rosgen Classification Unnamed Creek South of Dunka Road

ERDC/LAB TR-0X-X 100. Figure 7-3 Maximum velocity magnitudes for existing conditions for 100-year flood event

Section 4: Model Development and Application

Laboratory Exercise #3 The Hydrologic Cycle and Running Water Processes

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

Working with Natural Stream Systems

Assessing Climate Change Vulnerability of Cultural Resources

Surface Water and Stream Development

Chapter 7 Mudflow Analysis

RISK ASSESSMENT COMMUNITY PROFILE NATURAL HAZARDS COMMUNITY RISK PROFILES. Page 13 of 524

Historical channel change on the Upper Gila River, Arizona and New Mexico in response to anthropogenic modifications and extreme floods

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,

Summary. Streams and Drainage Systems

Landscape Development

OBJECTIVES. Fluvial Geomorphology? STREAM CLASSIFICATION & RIVER ASSESSMENT

Interpretive Map Series 24

FUTURE MEANDER BEND MIGRATION AND FLOODPLAIN DEVELOPMENT PATTERNS NEAR RIVER MILES 200 TO 191 OF THE SACRAMENTO RIVER PHASE III REPORT

Countermeasure Calculations and Design

Monitoring Scour Critical Bridges During Floods For Local Bridge Owners. Presented by

APPROACH TO THE SPANISH WATER ORGANISATION IMPROVING FLOOD HAZARD MAPPING, LAWS AND AUTHORITIES COORDINATION

Earth Science Chapter 6 Section 2 Review

Sixteen Mile Creek Tributaries Meander Belt Width Assessment November 2009

EFFECTS OF RIPARIAN RETENTION (IN WATERSHEDS) ON ALLUVIAL FANS

Avoiding Geohazards in the Mid-Atlantic Highlands by Using Natural Stream Principles

SELBY CREEK STREAM HABITAT RESTORATION AND RIPARIAN REVEGETATION PROJECT: GEOMORPHIC ANALYSIS AND REVIEW

Technical Memorandum No

Hydrologic hazards can be considered in three categories; An indication of flooding potential for areas located

Best Management Practices for Coldwater Fisheries Enhancement and Restoration

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON

Environmental Geology Chapter 9 Rivers and Flooding

Chapter 7 Mudflow Analysis

Conceptual Model of Stream Flow Processes for the Russian River Watershed. Chris Farrar

Massachusetts Rivers & Roads Training

Upper Drac River restoration project

Stream Simulation: A Simple Example

CHAPTER GEOLOGICALLY HAZARDOUS AREAS Applicability Regulations.

FUTURE MEANDER BEND MIGRATION AND FLOODPLAIN DEVELOPMENT PATTERNS NEAR RIVER MILES 241 TO 235, SACRAMENTO RIVER

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

1 City of Edmonton Quesnell Bridge, Roads and Associated Structures Assessment

Transcription:

Threatened and Endangered Species Geological Hazards Floodplains Cultural Resources Hazardous Materials A Cost Analysis section that provides comparative conceptual-level costs follows the Environmental Resources section. The alternatives analysis and cost estimating was conducted at a level of detail sufficient to compare broadly the alternatives with one another. It is a greater level of analysis detail than typically used in comprehensive land use and transportation planning, but is a substantially less detailed analysis than expected in analyzing the specific impacts of a proposed project design where more exact right-of-way lines, construction limits, and facility geometry and design features are known. A summary Evaluation Matrix section completes the analysis portion of this report. The last three sections of the main body of this report consist of: Public Involvement Summary Narrative on Future Project Development that identifies potential next steps, including studies needed to support selection of a preferred alternative References used to develop this report Finally, Appendices A through F provide additional background and supporting technical documentation that was used to inform the development of this report. GEOMORPHIC AND HYDROLOGIC ASSESSMENT This section presents a summary of the geomorphic and hydrologic conditions in the study area, and focuses on the two bridge crossing areas: the existing Sandy River Bridge crossing on Lolo Pass Road, and a new bridge crossing upstream of the existing crossing (See Figure 2). A memorandum summarizing the geomorphic and hydrologic assessment is attached in Appendix C. The Sandy River and its tributaries originate high on the western slopes of Mount Hood from the Sandy, Palmer, Reid and Zigzag glaciers. The Sandy River transports large amounts of sediment during the spring and summer months, and during large floods. The sediment supplied by the glaciers and the surrounding steep, erodible slopes can migrate downstream in waves, resulting in localized rise and then fall of the channel bed elevations. As the river evolves, channel erosion and hillside erosion also contribute to the development of debris torrents and localized deposition along segments of the river. High flood waters, combined P a g e 18

with these changes to the channel, have caused damage to Lolo Pass Road on a number of occasions. Erosion of channel banks and channel bottoms, deposition of large amounts of material in the channel, and channel migration or avulsion pose a special problem within the Sandy River. Roads, bridges, homes and other infrastructure can be lost due to these catastrophic changes. Traditional Federal Emergency Management Agency (FEMA) floodplain mapping does not address this type of condition. The erosion and channel migration within the Sandy River can quickly alter or create new adjacent flood-prone areas and hazards beyond the limits of the FEMA-mapped floodplain. To better prepare for and anticipate hazards within the Sandy River Basin, flood hazard mapping needs to be modified to more clearly represent areas that are vulnerable to future floods and changes in the river. The Oregon Department of Geology & Mineral Industries (DOGAMI) has been contracted to remap the Sandy River Basin to provide a better understanding of the river movements and associated hazards. Preliminary channel migration hazard maps prepared by DOGAMI extend through only the southern half of the study area, just north of the Sandy River (Lolo Pass Road) Bridge. EXISTING BRIDGE LOCATION The bridge crossing the Sandy River at Lolo Pass Road was reconstructed in 1965 following damages resulting from the December 1964 flood. The bridge has a span length of 80 feet supported by vertical concrete abutments with wing walls (see Figure 7). However, accounting for the bridge skew angle of 30 degrees, the width of the bridge opening across the river flow is only 70 feet. The low chord of the bridge (the low point on the beams underneath the bridge) is at an elevation of 1,459.6 feet and approximately 14.5 feet above the channel at the crosssection upstream of the bridge (See Figure 8). P a g e 19

Figure 7. Photo looking upstream at the Lolo Pass Road bridge crossing the Sandy River near RM 43.7 At the bridge, the river flows through a single-stem channel that is deeply incised between two terraces. The north terrace is composed of fill materials brought in to repair the bridge following the 1964 storm. The south terrace is composed of fill underlain by native soils. The channel/terrace/bridge embankment topography forms a narrow flow constriction, or pinch point, through which the velocities of most high stage flows accelerate. Both the existing height and the topographic pinch point cause an upstream backwater condition that induces bed load (material carried by the stream) in transport to deposit on the channel floor upstream of the crossing. The depositional zone is prone to channel widening caused by aggradation (deposition of sediment) and by northward channel migration. The northward channel migration and debris flows caused substantial damage to Lolo Pass Road above the existing Sandy River Bridge (from River Mile (RM) 43.75 to RM 44.2) during the 1964, 1996, and 2011 storm events. As shown in Figure 8, an avulsion channel (area where the river is likely to relocate in a future flooding event) is situated on the north side of the bridge between East Lolo Pass Road and Clear Creek. This avulsion channel poses a substantial risk to the existing bridge and road alignment. Before the 1964 storm, the avulsion channel was cut off from the main stem by East Lolo Pass Road. This channel is known to have received main stem flow during the 1964 storm; it received overbank storm flow during the period when the East Lolo Pass Road and embankment were breached. Conditions in 2015 are essentially the same as they were in 1964. The avulsion channel could receive main stem flow from any number of sites along East Lolo Pass Road (from RM 43.75 to RM 44.4) that are susceptible to damage from channel migration. P a g e 20

Figure 8. Relative Elevation Map of the Existing Sandy River Bridge Crossing at Lolo Pass Road near RM 43.7. The results of the geomorphic/hydraulic analyses indicate the safest bridge/road alignment is one that routes the road along the high ground situated between the avulsion channel and Clear Creek (see Figure 9). The design alternative to widen the existing crossing with two, 200- foot bridges would certainly yield an improvement of flood conveyance through the crossing compared to existing conditions. Improvements to the bridge, however, are not enough to maintain safe access along this alignment given the number of erosion hazards affecting the road for nearly a mile upstream. At present the channel impinges on the road corridor upstream of the crossing near RM 43.8 and RM 44.1. Additional avulsion hazards are present throughout the reach where rapid shifts in the channel alignment could result in road damage from a single storm event. Any alternative in consideration that retains a road alignment in the valley bottom between the Sandy River and Clear Creek must acknowledge the ongoing maintenance costs to address erosion and damages to the roadway as occurred in 1964 and 2011. P a g e 21

Figure 9. Conceptual sketch of a widened bridge span at the existing crossing near RM 43.7 ZIGZAG MOUNTAIN ALTERNATIVES: PROPOSED NEW BRIDGE LOCATION The reconnaissance report (see Appendix A) developed for this project identifies a potential alternative that is approximately 1 mile upstream of the existing bridge; the proposed crossing is near RM 44.7. 2 Selecting the upstream bridge location was accomplished by combining onsite field work, study of hydrologic and geomorphic conditions, and review of published data. Current FEMA maps were reviewed to identify flood hazard zones within the study area. The overall channel migration zone through the study area does not appear to have any confined or narrow areas ideal for a crossing. However, there are several locations where the channel has maintained a more consistent and confined route within the last 50 years. One location, in the vicinity of the east end of Autumn Lane, appears to provide the best opportunity for a crossing location with a narrow flood hazard zone combined with a more confined recent historic channel migration zone (approximately 250 foot width). The alignment 2 The red line shows the initial proposed crossing (pushed slightly downstream based on design constraints. Current crossing location is near RM 44.6). P a g e 22

of this alternative parallels the south side of the Sandy River upstream to the end of Autumn Lane, turns northwesterly across the active channel and valley bottom, and then climbs upslope to merge with the existing road alignment on the north side of the valley (see Figure 2 and Figure 10). LIDAR mapping shows an old abandoned channel within the channel migration zone north of the potential bridge site (the avulsion zone identified in the geomorphic and hydraulic section of this report). The potential for the river to shift into this old channel during the next flood is high. The channel migrated approximately 80 to 100 feet towards the right bank at the proposed bridge location in the 2011 flood. Figure 10. Map of the Upper Sandy River showing relative ground surface elevations. The proposed bridge location is in a very dynamic section of the river that is subject to periodic episodes of accelerated channel migration and sudden avulsion. The proposed site includes the main stem channel and a potential avulsion channel located on the north alluvial terrace. In this river section, there are two directional trends of migration, downstream (west) and lateral (north). These trends indicate that as the large bend situated upstream of the proposed crossing approaches the crossing alignment it will engage the full width of the currently active channel. They also indicate that the avulsion channel will receive main stem flow during a scenario in which the channel upstream of the alignment is substantially aggraded (raised) P a g e 23

during a 100-year storm event. Geomorphic and hydraulic analyses both indicate that the bridge design should span the currently active main stem channel and the full width of the potential avulsion channel (see Figure 10 and Figure 11). Over time, the Sandy River is expected to migrate laterally and reoccupy the historic flowpath on the north of the valley. Therefore, an open flowpath to the historical channel feature should be included in the road design criteria. The upper panel of Figure 11 shows the baseline channel geometry and predicted water surface elevation for the 100-year recurrence interval peak discharge (Q100). The lower panel of Figure 11 shows the representation of a future scenario with deposition of 8-feet of sediment resulting in aggradation of the active channel and the resulting Q100 water surface. Figure 11. Cross-sectional profile through the proposed alternative bridge crossing near RM 44.7. P a g e 24

Compared to the alternative at the existing crossing, the proposed bridge location near RM 44.6 minimizes the long term risk to flood and erosion hazards. The design in this segment provides a longer span and is more resilient to lateral channel migration. ENGINEERING ISSUES Lolo Pass Road provides public access from US 26 to the west side of the MHNF. The road is the sole winter access to the MHNF and to more than 200 residences, cabins and campgrounds north of East Barlow Trail Road. ROADWAY CLASSIFICATION AND DESIGN SPEED The functional class map shows Lolo Pass Road as a minor arterial north of East Barlow Trail Road, and it is assumed to be a rural minor arterial based on the project s location outside an urban area and without urban features, such as curbs or sidewalks. The design of the existing roadway does not meet the basic rule (55 mph) in all locations, but where possible, the new or replacement roadway would be developed to meet this standard. The alternatives analysis assumed a design for the proposed roadway that meets AASHTO standards and aims for a 50 to 55 mph design speed. Design exceptions would be written as needed if this standard were not met. During a future design phase of the project, the applicable design criteria and any design exceptions would need to be finalized. Lolo Pass Road: Functional Classification: Rural Major Collector (FHWA) Rural Minor Arterial ( Transportation System Plan) Design Speed: 55 mph Surface Type: Asphalt Concrete Pavement Design Volume: 3,000 Average Daily Traffic (ADT) DESIGN ASSUMPTIONS Conceptual alignments were laid out for the three primary alternatives under consideration based on the design criteria and findings regarding hydraulics, biological resources and other sensitive resources. Profile drawings and river cross-section data are presented in Appendix D. Table 2 presents design criteria for the proposed road work for Lolo Pass Road and the new alignment alternatives. The design criteria are divided into two sections: south of East Barlow Trail Road (which currently has a speed order and is posted for 45 mph) and north of East Barlow Trail Road (which is basic rule, allowing 55 mph). The new roadway would have 11- P a g e 25