Mr. Michael Malone CPS Energy 145 Navarro Street San Antonio, Texas Project No

Similar documents
CCR Rule Annual Inspection Report (cont.) 2

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

STRUCTURAL STABILITY ASSESSMENT

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR )

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GADSDEN ASH POND 40 CFR (c)(1)(i)-(xii)

Stone Outlet Sediment Trap

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

Geosynthetics Applications and Performance Reviews Select Case Histories

Location Restriction Demonstration

Materials. Use materials meeting the following.

Rock & Aggregate Drop Inlet Protection

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Suitable Applications Sediment traps should be considered for use:

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

1. PROJECT BACKGROUND. July 18, Alberta Infrastructure & Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils

Limited Visual Dam Safety Inspections OA Oahu Reservoir No Oahu, Hawaii

TPDES: Soil, Erosion and Sedimentation Methods

APPENDIX B WORKSHEETS & EXHIBITS

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT

Coal Combustion Residuals Unit Inflow Design Flood Control System Plan

CCR Surface Impoundment Location Restrictions Demonstration. MidAmerican Energy Company, Louisa Generating Station

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

January 17, 2008 File:

December 11, 2006 File:

U-Shaped Sediment Traps

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction.

GEOSYNTEC CONSULTANTS

DAM SAFETY PROGRAM DAM INSPECTION REPORT FORM FOR REGULATORY INSPECTION

BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT

Continuing Education Associated with Maintaining CPESC and CESSWI Certification

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

The results of KCB s site inspection observations and our recommendations for further work are presented herein.

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

NORTHUMBERLAND COUNTY, PA

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

Husky Oil Operations Limited

Rock Sizing for Small Dam Spillways

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

Culvert and Pipe Phasing

SAN JACINTO RIVER / BAUTISTA CREEK LEVEE SYSTEM RIVERSIDE COUNTY, CALIFORNIA NLD ID #

J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report

3.0 ROBERTS BANK TIDAL FLAT MORPHOLOGY

RESERVOIR DRAWDOWN RATES/RESERVOIR DRAWDOWN TEST Iron Gate, Copco (I & II), and JC Boyle Dams

Large-Scale Sediment Retention Device Testing (ASTM D 7351) SedCatch Sediment Basket Inlet Filter Exposed to 1.5% Sediment Load

Advanced Geologic Exploration, Inc.

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

Coarse Sediment Traps

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

October 26, Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402

DUST CONTROL PLAN. Rawhide Energy Station 2700 East County Road 82 Wellington, Colorado 80549

ENTERGY WHITE BLUFF PLANT RECYCLE POND A AND RECYCLE POND B DEMONSTRATION OF COMPLIANCE WITH EPA CCR RULE SITING CRITERIA 257.

RE: AFIN: ADEQ Reference #: WG-LA Well Site: Suarez-Gartner 8-12 No. 1-30H

Large-Scale Sediment Retention Device Testing (ASTM D 7351) SedCatch Sediment Basket Inlet Filter Exposed to 6% Sediment Load

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Highland Lake Bathymetric Survey

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

MIDDLESEX COUNTY Department of Planning and Community Development P.O. Box 427, Saluda, VA Phone: Fax:

STORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect

Table 5-1 Sampling Program Summary for Milltown Ford Avenue Redevelopment Area, NJ.

WATER MANAGEMENT REPORT FOR PAGE ESTATES

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

3.12 Geology and Topography Affected Environment

patersongroup Consulting Engineers April 20, 2010 File: PG1887-LET.01R Novatech Engineering Consultants Suite 200, 240 Michael Cowpland Drive

AN ARCHAEOLOGICAL SURVEY FOR THE EASTHAM STATE PRISON FARM UNIT PROJECT IN HOUSTON COUNTY TEXAS

LIQUEFACTION OF EARTH EMBANKMENT DAMS TWO CASE HISTORIES: (1) LIQUEFACTION OF THE EMBANKMENT SOILS, AND (2) LIQUEFACTION OF THE FOUNDATIONS SOILS

ENTERGY INDEPENDENCE PLANT EAST AND WEST RECYCLE PONDS DEMONSTRATION OF COMPLIANCE WITH EPA CCR RULE SITING CRITERIA , FAULT AREAS.

Preliminary Geotechnical Evaluation Gooseberry Point Pedestrian Improvements Whatcom County, Washington SITE AND PROJECT DESCRIPTION

UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO

TSEGI WASH 50% DESIGN REPORT

Submitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226

APPENDIX A M&T/Llano Seco Long-Term Water Reliability Study These photos are examples of rock spurs in use throughout the United States

UPPER COSUMNES RIVER FLOOD MAPPING

3.0 SUMMARY OF FINDINGS

When Creek Meets Valley Wall: Prioritizing Erosion Mitigation alongside the Oshawa Landfill

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY

R.M.HARW & ASSOCIATES LTD. GEOTECHNICAL INVESTIGATION PROPOSED BRIDGE SITE. HELAVA CREEKl MILE MACKENZIE HIGHWAY E-2510 OCTOBER 16, 1973

HISTORY OF CONSTRUCTION W.H. Sammis Coal Plant North and South Ponds Stratton, Ohio

Why Geomorphology for Fish Passage

APPENDIX B HYDROLOGY

MAINTENANCE DREDGE BENTHIC ASSESSMENT SUNSET POINT FARM LLC LONG POINT KEY MONROE COUNTY, FLORIDA. Prepared by:

Crows Landing Naval Base Easement

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P.

Appendix E Guidance for Shallow Flooding Analyses and Mapping

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP

Rock Sizing for Waterway & Gully Chutes

January 16, Re: Soo Line Dump Site 2018 Annual Soil Cover Inspection. Dear Mr. Nichols:

Emergency Action Plan (EAP) Tata Pond Dam

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3

Waterbury Dam Disturbance Mike Fitzgerald Devin Rowland

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

NRCS - THUNDER ROAD #2, TRIBUTARY TO QUILEUTE RIVER CULVERT REMOVAL AND REPLACEMENT PLAN CLALLAM COUNTY, WA., WRIA: 20, SITE:

Transcription:

January 17, 2018 Mr. Michael Malone 145 Navarro Street San Antonio, Texas 78205 Project No. 0337367 Environmental Resources Management CityCentre Four 840 West Sam Houston Pkwy N. Suite 600 Houston, Texas 77024 (281) 600-1000 (281) 600-1001 (Fax) Subject: CCR Units 2017 Annual Inspection and Fugitive Dust Control Report San Antonio, Texas Dear Mr. Malone: Environmental Resources Management (ERM) conducted an inspection of coal combustion residual (CCR) units for two power plants located at the CPS Energy in Bexar County, Texas. The CCR units are shared by the J.K. Spruce and J.T. Deely Power Plants, which are co-located at 12940 U.S. Highway 181 South in San Antonio, Texas. The CCR units utilized by the power plants are described in Table 1. Table 1. CCR Unit Descriptions Unit Name Unit ID Purpose of Unit Fly Ash Landfill (a.k.a. 5- Year Landfill) 010 Receives fly ash, bottom ash, economizer ash, scrubber sludge from flue gas desulphurization ponds, and flue gas desulphurization gypsum (temporary storage). Evaporation Pond 021 Receives boiler chemical cleaning waste and other authorized liquid wastes. North Bottom Ash Pond 005 Receives sluiced bottom ash. (North BAP) South Bottom Ash Pond (South BAP) 006 Receives sluiced bottom ash. Sludge Recycle Holding (SRH) Ponds (North and South) 026 Receives flue gas desulphurization scrubber sludge. The annual inspection was conducted by Mr. Chris Cunningham, P.E., on December 19, 2017. Photographs taken during the inspection are provided in Attachment 1. No issues were observed that indicated potential stability or operational issues at the CCR units. Details of the observations made by Mr. Cunningham are provided below. Texas Registered Engineering Firm F-2393 Texas Board of Professional Geoscientist Firm 50036 Copyright 2018 by ERM Worldwide Group Ltd and/or its affiliates ( ERM ). All Rights Reserved. No part of this work may be reproduced or transmitted in any form, or by any means, without the prior written permission of ERM

January 17, 2018 0337367\A9018 Page 2 Environmental Resources Management Unit Descriptions All units are built with above-grade earthen embankments reportedly composed of sandy clay and clayey sand fill. Some units have CCR ash used in the surface roadways of the features (e.g., Fly Ash Landfill and Bottom Ash Ponds). Figure 1 shows the locations of each CCR unit. Dimensions of the CCR units were not measured during the annual inspection. Measurements used herein are based on an assessment conducted in June 2014 by CDM Smith, and checked using computer satellite mapping software. Based on a comparison of recent and historical aerial photographs dating back to 1995, no significant changes in the dimensions or geometry of the units were observed. Table 2 provides a summary of the unit dimensions. TABLE 2: CCR Unit Dimensions Dimension Fly Ash Landfill Evaporation Pond North BAP South BAP SRH Ponds Length (feet) 1,000 500 530 680 440 Width (feet) 950 400 460 400 330 Depth (feet) 32.5 22 12 12 8 Avg. Crest Width 20 20 15 15 15 (feet) Perimeter (feet) 4,000 1,800 2,100 2,200 1,550 Interior Slopes, H:V 3:1 2:1 2:1 2:1 3:1 Exterior Slopes, H:V 3:1 3:1 3:1 3:1 3:1 Total Area (acres) 21.8 4.5 6.0 7.0 3.5 The Evaporation Pond is reportedly lined with 30-mil high-density polyethylene (HDPE) liner. There are no inlet or outlet structures to the pond. Liquid from boiler chemical cleanouts and other authorized liquid wastes are trucked to the pond, and are allowed to evaporate. Periodically, dried material is removed from the Pond and placed in the Fly Ash Landfill. The North and South BAPs are reportedly lined with clay, but the thickness and hydraulic conductivity of the clay are unknown. Both ponds have two discharge points. One 24-inch steel pipe in each pond allows water to be returned to the plant for reuse. Both ponds also have outlet structures consisting of a horizontal 12-inch steel discharge pipe at an approximate elevation of 489 feet MSL (bottom drain used to empty the pond), and a vertical 12-inch steel overflow pipe at an approximate of elevation 499 feet MSL (normal operation level pool drain). The outfall structure is in one corner of each pond (northeast for North BAP and southeast for South BAP) and is partially surrounded by steel sheet piling. The sheet piling and pond berms create an opening for water to reach the discharge pipes. This opening is typically protected by floating sorbent booms. Water from these outlets discharges to Calaveras Lake through a TPDES permitted outfall.

January 17, 2018 0337367\A9018 Page 3 Environmental Resources Management The interior slopes of the two SRH Ponds are reportedly covered with 30-mil HDPE liner and a six-inch thick concrete slab. The ponds are delineated by a concrete divider wall with a sluice gate that allows the two sides to be isolated from each other. Water is pumped from the ponds to clarifiers via two 18-inch steel pipes. Both ponds have eight-foot-wide concrete overflow chutes that discharge to the South BAP. These overflow chutes are at an approximate elevation of 499.5 feet MSL. The Fly Ash Landfill is reportedly lined with a 30-mil HDPE liner covered with a 10-ounce geotextile and 12 inches of sand. The bottom of the landfill slopes from west-to-east, from approximately 514 feet MSL to 503 feet MSL. The top berm is at an approximate elevation of 535.5 feet MSL, for a total landfill depth of approximately 32.5 feet at the deepest point. Storm water collects in the southeast corner of the landfill and is allowed to settle. A water quality sample is collected and analyzed prior to discharge through a TPDES permitted outfall. No instrumentation is associated with the CCR units. All units are located within the Upper San Antonio River watershed, though water in the immediate vicinity drains to Calaveras Lake. Unit History The Evaporation Pond was originally constructed as a fly ash landfill. In 1990, a pond liner was installed. Then in 1996, the unit was converted from a landfill to an impoundment. Fly ash was placed in the landfill prior to it being used as an impoundment. The top of the Evaporation Pond is at an approximate elevation of 522 feet MSL and the bottom is at an approximate elevation of 500 feet MSL. The North and South BAPs were constructed in 1977, and the SRH Ponds in 1992. Embankments are reported to have been constructed of on-site material, though the actual location of the borrow pit is unknown. The top of the SRH Ponds embankments is at an approximate elevation of 500 feet MSL, and the bottom at an approximate elevation of 492 feet MSL. Up to a foot of ash and other material have been added to the roads on the top of the BAP embankments, making the top elevation approximately 501 feet MSL. The bottom of the BAPs is at an approximate elevation of 489 feet MSL. The Fly Ash Landfill was constructed in 1992 with a HDPE liner. Liner on the side slopes was originally not covered with a protective layer, and began to show signs of deterioration. Portions of the liner on the north and west side embankments were repaired in 2010 and all side slopes are currently covered with a protective layer No changes to unit operations or dimensions were reported to have occurred during the life of the facility.

January 17, 2018 0337367\A9018 Page 4 Environmental Resources Management Structural Integrity There is no reported historic evidence of structural instability in the CCR units. Geotechnical properties of the foundation and abutment materials, on which the ponds were constructed, are provided in the document entitled Geotechnical Engineering Study for Ash Pond Berms Spruce/Deely Generation Units, San Antonio, Texas, dated May 7, 2014 by Raba Kistner Consultants, Inc., and are summarized in the reports entitled Assessment of Dam Safety of Coal Combustion Surface Impoundments Final Report for the Deely and Spruce power plants, June 2014 revision, by CDM Smith. As summarized in the CDM Smith report, embankment material is light clay (ASTM CL ) with a clay fraction of approximately 45%, and an assumed liquid limit between 35 and 47. Foundation material for the BAPs and SRH Ponds consists of sandy clay (ASTM CL ) with a clay fraction between 50% and 60%, and a liquid limit of approximately 51; or clayey sand (ASTM ML ) with a clay fraction of approximately 35%, and a liquid limit of approximately 33. Evaporation Pond material is similar, except the liquid limits for the foundation materials are approximately 55. No information on the embankment and foundation materials were available for the Fly Ash Landfill, but foundation materials are anticipated to be similar to those of the Evaporation Pond based on the proximity of the units. Annual Inspection Summary Signage was present at each CCR unit and no issues were observed at the CCR units which threatened structural integrity. Fly Ash Landfill The Fly Ash Landfill (a.k.a. 5-Year Landfill) was at approximately 36.5% capacity based on calculations provided by. Approximately six acres of the landfill interior were covered with discrete piles of ash, the largest piles appearing to be less than 20 feet in height. Minor surface erosion was observed in the interior of the northeast corner, and minor rutting from vehicle traffic at the exterior toe of the north embankment. Two animal burrows were observed on the exterior of the north embankment, near the center of the landfill. The observed burrows were approximately two to three inches in diameter. Grass on the exterior of the landfill was less than six inches in height, with no woody plants observed. The erosion and animal burrows do not appear to immediately impact unit stability. Inspection records from January 4, 2017 through December 13, 2017 reported no problems observed at the Fly Ash Landfill. Since the 2016 annual inspection, there have been no noticeable changes in the geometry of the landfill, or any other changes that appear likely to have affected the stability or operation of the landfill.

January 17, 2018 0337367\A9018 Page 5 Environmental Resources Management Evaporation Pond The Evaporation Pond had approximately six feet of freeboard available at the time of the inspection. This corresponds to an available capacity of approximately 38 acre-feet, with approximately 84 acre-feet of water and CCR contained. A small amount of water from recent rains was ponding on the top of the northern berm. Grass along the external slope of the embankment was observed to be less than six inches high. One area approximately four feet in diameter on the southern berm was observed to be bare of vegetation, but did not appear to be eroding. Nothing was observed that is likely to immediately impact unit stability. Inspection records from January 4, 2017 through December 13, 2017 reported no problems observed at the Evaporation Pond. Since the 2016 annual inspection, there have been no noticeable changes in the geometry of the impoundment, or any other changes that appear likely to have affected the stability or operation of the impoundment. Based on information provided by, the maximum depth of the water and CCR in the impoundment during 2017 was 20 feet, which corresponds to a volume of 109.1 acre-ft. The minimum depth was approximately 18 feet, which corresponds to a volume of 96.6 acre-ft. North Bottom Ash Pond The North BAP was offline and completely drained of liquid during the inspection. Most of the accumulated CCR had been removed from the pond and transported offsite for beneficial use. No obstruction of or damage to outfall structures was observed. Grass along the external slope of the embankment was observed to be less than six inches high. Inspection records from January 4, 2017 through December 13, 2017 reported minor damage to the surface of the berm from animals digging in the northeast corner on March 13, 2017. A work order was filed for repairs. The work order resolution was not available for review by ERM, but the facility reports the damage was repaired during routine grounds maintenance. The damage was not reported in subsequent inspections. Since the 2016 annual inspection, there have been no noticeable changes in the geometry of the impoundment, or any other changes that appear likely to have affected the stability or operation of the impoundment. Based on information provided by, the maximum depth of the water and CCR in the impoundment during 2017 was 10 feet, which corresponds to a volume of 60.6 acre-ft. The minimum depth is zero feet, as observed during the inspection. South Bottom Ash Pond The South BAP was in use during the inspection, with an estimated freeboard of approximately 2.0 feet. This is the maximum operating capacity, corresponding to approximately 14.7 acre-feet

January 17, 2018 0337367\A9018 Page 6 Environmental Resources Management of available capacity (including freeboard), with approximately 67.5 acre-feet of water and CCR contained. Some shallow (i.e., less than one foot deep) erosion channels were observed on interior of the north embankment of the South BAP. The eroded material appears to be mostly ash, with no evidence of damage to underlying clay. This erosion does not appear to impact unit stability. No obstruction of or damage to outfall structures were observed. High grass (i.e. one to two feet) was observed growing on the interior portion of the south berm. Grass along the external slope of the embankment was observed to be less than six inches high. Inspection records from January 4, 2017 through December 13, 2017 reported erosion on the south bank during each inspection in January, though no work order for repairs was documented. The erosion was not reported after the January 24, 2017 inspection, implying it was repaired. High grass was reported in the pond on February 27, 2017, and damage to the berm surface in the southeast corner due to animals digging was reported on March 6, 2017. Work orders were prepared for both issues. The work order resolutions were not available for review by ERM, but the facility reports the damage was repaired and grass addressed during routine grounds maintenance. The damage was not reported in subsequent inspections. Since the 2016 annual inspection, there have been no noticeable changes in the geometry of the impoundment, or any other changes that appear likely to have affected the stability or operation of the impoundment. Based on information provided by, the maximum depth of the water and CCR in the impoundment during 2017 was 10 feet, which corresponds to a volume of 67.5 acre-ft. The minimum depth since the last inspection was approximately zero feet. Sludge Recycle Holding (SRH) Ponds At the time of the inspection, the gate on the divider wall between the SRH Ponds was closed, with water having been drained from the North SRH Pond, and approximately six feet of water in the South SRH Pond. The North SRH Pond appeared to be approximately 75% full of CCR and had been taken offline. This corresponds to an approximate available capacity (including freeboard) of 11.0 acre-feet, with approximately 19.2 acre-feet of water and CCR contained. No obstruction of or damage to outfall structures was observed. Grass along the external slope of the embankment was observed to be less than six inches high. Inspection records from January 4, 2017 through December 13, 2017 reported less than two feet of freeboard in the North SRH Pond on November 14, 2017. The North SRH Pond has been taken offline for cleaning, as noted above. Since the 2016 annual inspection, there have been no noticeable changes in the geometry of the impoundment, or any other changes that appear likely to have affected the stability or operation of the impoundment. Based on information provided by, the maximum depth of the water and CCR in the impoundment during 2017 was 8 feet in both ponds, which corresponds to a volume of 30.1 acre-ft. The minimum depth since the last inspection was one pond empty, which corresponds to a volume of 15.0 acre-ft.

Figure Environmental Resources Management 206 East 9 th Street, Suite 1700 Austin, Texas 78701 (512) 459-4700

FLY ASH LANDFILL EVAPORATION POND NORTH BOTTOM ASH POND SOUTH BOTTOM ASH POND SRH PONDS (2) ERM-Southwest, Inc. TX PE Firm No. 2393 Calaveras Lake 0 2000 SCALE 4000 FEET DESIGN: CC DRAWN: RLM CHKD.: CC DATE: 1/6/2016 SCALE: AS SHOWN REV.: W.O. NO.: H:\DWG\A16\0328985A01.dwg, 1/6/2016 9:48:22 AM FIGURE 1 CCR Unit Locations San Antonio, Texas

Photo Log Attachment 1 January 2018 Project No. 0337367 Environmental Resources Management 206 East 9 th Street, Suite 1700 Austin, Texas 78701 (512) 459-4700

Photograph: 1 Fly Ash Landfill standing on western berm facing north. Mobile ash conditioning machine located in northwest corner of landfill. Photo taken 12/19/17. Photograph: 2 Fly Ash Landfill - standing on western berm facing east. Photo taken 12/19/17.

Photograph: 3 Fly Ash Landfill standing on western berm facing southeast. Radial stacker located in southwest corner of landfill. Photo taken 12/19/17. Photograph: 4 Fly Ash Landfill standing on eastern berm - facing south. Photo taken 12/19/17.

Photograph: 5 Fly Ash Landfill standing on eastern berm facing southwest. Water accumulation from recent rain events. Photo taken 12/19/17. Photograph: 6 Fly Ash Landfill standing on northern berm facing west. Photo taken 12/19/17.

Photograph: 7 Fly Ash Landfill standing on northern berm. Animal burrow in exterior slope. Photo taken 12/19/17. Photograph: 8 Fly Ash Landfill standing on southern berm facing west. Photo taken 12/19/17.

Photograph: 9 Fly Ash Landfill standing on southern berm facing east. Photo taken 12/19/17. Photograph: 10 Fly Ash Landfill outside eastern perimeter at northeast corner drainage discharge. Photo taken 12/19/17.

Photograph: 11 Evaporation Pond standing on northwest corner facing east. Photo taken 12/19/17. Photograph: 12 Evaporation Pond standing on northwest corner facing south. Photo taken 12/19/17.

Photograph: 13 Evaporation Pond standing on southwest corner facing north. Photo taken 12/19/17. Photograph: 14 Evaporation Pond standing on southeast corner facing west. Photo taken 12/19/17.

Photograph: 15 North Bottom Ash Pond standing on southwestern corner facing northeast. Pond was drained to remove residuals. Photo taken 12/19/17. Photograph: 16 North Bottom Ash Pond standing on northern berm facing west. Photo taken 12/19/17.

Photograph: 17 North Bottom Ash Pond standing on northwestern berm facing southeast. Photo taken 12/19/17. Photograph: 18 North Bottom Ash Pond Outside of eastern berm. Photo taken 12/19/17.

Photograph: 19 North Bottom Ash Pond standing on northeast corner facing south. Photo taken 12/19/17. Photograph: 20 North Bottom Ash Pond standing on southern berm facing west. Photo taken 12/19/17.

Photograph: 21 North SRH Pond standing on northeast corner facing west. Photo taken 12/19/17. Photograph: 22 North SRH Pond standing on northern berm facing southeast. Photo taken 12/19/17.

Photograph: 23 North SRH Pond standing on northeast corner facing south. Photo taken 12/19/17. Photograph: 24 North SRH Pond Overflow structure to South Bottom Ash Pond. Photo taken 12/19/17.

Photograph: 25 South SRH Pond standing on southwestern corner facing east. Photo taken 12/19/17. Photograph: 26 South SRH Pond standing on western berm facing north. Photo taken 12/19/17.

Photograph: 27 South Bottom Ash Pond standing on southeastern corner facing west. Photo taken 12/19/17. Photograph: 28 South Bottom Ash Pond Outfall structure. Photo taken 12/19/17.

Photograph: 29 South Bottom Ash Pond standing on northeast corner facing southwest. Erosional features on eastern berm. Photo taken 12/19/17. Photograph: 30 South Bottom Ash Pond standing on northwest corner facing west. Photo taken 12/19/17.