TOPOGRAPHIC MONITORING OF A WATER TANK IN THE WIDENING WORKS OF EIXO NORTE-SUL HIGHWAY IN LISBON

Similar documents
UNCERTAINTY IN TACHEOMETRIC MEASUREMENT OF CONVERGENCES IN TUNNELS

Notice on a Case Study on the Utilization of Wind Energy Potential on a Remote and Isolated Small Wastewater Treatment Plant

Tsukuba, Japan International Institute of Seismology and Earthquake Engineering Building Research Institute STUDY TRIP TO ITAKO CITY

Observation of Landslide Movements by Geodetic and Borehole Tilt Measurements

Landslide FE Stability Analysis

Carlos Baião Cenorgeo DESIGN AND CONSTRUCTION OF THE MACHICO-CANIÇAL CANIÇAL EXPRESSWAY TUNNELS

Complex Analysis of the Impact of Construction of an Underground Metro Line on the Urban Environment a Case Study from the Vistula Valley in Warsaw

SEISMIC REFRACTION SURVEY RIPPABILITY STUDY

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

CCR Rule Annual Inspection Report (cont.) 2

PEACE RIVER EAST HILL - HWY 2:60 (PH2) SELECT PHOTOGRAPHS August 22, 2007 File: Photo E003. Station May 2007

LANDSLIDES IN THE WHITE MOUNTAIN (GEOTECHNICAL STUDIES AND ENGINEERING TESTS)

Slope Stability Evaluation Ground Anchor Construction Area White Point Landslide San Pedro District Los Angeles, California.

Appin Colliery - Longwall 705

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

DETAILED INVESTIGATION OF PILES DAMAGED BY HYOGOKEN NAMBU EARTHQUAKE

APPALACHIAN COLLUVIAL

KANSAS GEOLOGICAL SURVEY Open File Report LAND SUBSIDENCE KIOWA COUNTY, KANSAS. May 2, 2007

WHITE POINT LANDSLIDE GEOTECHNICAL INVESTIGATION November 29, 2012 Status Report

Waterbury Dam Disturbance Mike Fitzgerald Devin Rowland

LAND SLIDE STABILIZATION FOR A WORKING PLATFORM WHICH OCCURRED DURING EXCAVATION IN CLUJ-NAPOCA

STUDIES OF DISPLACEMENTS OF GPS STATIONS ON POLISH COPPER BASIN AREA Alojzy Wasilewski 1, Zofia Rzepecka 1, Stanislaw Oszczak 2

LIDAR AND ROBOTIZED TOTAL STATIONS DATA INTEGRATED FOR A 3-D 3 REPRESENTATION: THE MONTAGUTO EARTHFLOW STUDY

December 13, Kirk Shields Green Mountain Power 163 Acorn Lane Colchester, VT 05446

Design of Safety Monitoring and Early Warning System for Buried Pipeline Crossing Fault

Linear Functions, Equations, and Inequalities

WATERCOURSE HARNESSING BANK EROSION AND CONSOLIDATION

Geotechnical & Mining Engineering Services

The Accuracy of Electronic Distance Meters over Short Distances

CASE STUDY: BIM AND GEOTECHNICAL PROJECT IN URBAN AREA INFINITY TOWER, LISBON, PORTUGAL

Leveling. 3.1 Definitions

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

Challenge to the tunnel construction that supports national resilience

The effect of installation angle of rock bolts on the stability of rock slopes

Landslide Remediation Work and Treatment in Taiwan Miau-Bin Su 1, S.M. Chang 2, Y.S.Yen 3

DETECTION OF GROUND MOTION IN THE LISBON REGION WITH PERSISTENT SCATTERER INTERFEROMETRY (PSI)

ENGINEER S CERTIFICATION OF FAULT AREA DEMONSTRATION (40 CFR )

TEN YEARS OF DEFORMATION STUDY AND PROPOSED RESEARCH PROGRAM FOR THE AREA OF POLISH COPPER BASIN

Big Rivers Electric Corporation Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment Liner Assessment Report

Landslide Granice in Zagreb (Croatia)

Pushover Seismic Analysis of Bridge Structures

This report was prepared by Klohn Crippen Consultants Ltd. for Alberta Transportation Central Region under Contract No. CE053/2000.

Dust Storms in Arizona: The Challenge to Ensure Motorist Safety Jennifer Toth, P.E. Deputy Director for Transportation

Dam Monitoring With Tiltmeters

Project of a scissor lift platform and concept of an extendable cabin

DAMS REGIONAL SAFETY WARNING USING TIME-SERIES INSAR TECHNIQUES

ENVIRONMENTAL EFFECTS OF EARLY AGE AND LONG TERM RESPONSE OF PCC PAVEMENT

Yoshinori KAWAMURA, Oriental Consultants Global Co., Ltd.

Underground Excavation Design Classification

Mass Wasting. Revisit: Erosion, Transportation, and Deposition

STRUCTURAL OPTIMIZATION OF A MATERIAL EXHIBITING NEGATIVE STIFFNESS

Ground Penetrating Radar Survey Report:

16 January 2018 Job Number: RICHARD NEWMAN C\- CLARK FORTUNE MCDONALD AND ASSOCIATES PO BOX 553 QUEENSTOWN

Programmatic Approaches to Assessing and Mitigating Risk to Pipelines from Natural Forces

GIBE II TUNNEL PROJECT - ETHIOPIA - 40 BARS OF MUD ACTING ON THE TBM

The effects of the accidental torsional eccentricity on the seismic behaviour of building structures

Converse Consultants Geotechnical Engineering, Environmental & Groundwater Science, Inspection & Testing Services

State Of Wisconsin. Department of Military Affairs. Division of Emergency Management

The results of KCB s site inspection observations and our recommendations for further work are presented herein.

VERIFICATION OF MATERIAL PARAMETERS OF EARTHEN DAMS AT DIAMOND VALLEY LAKE USING GEODETIC MEASUREMENTS

A COMPREHENSIVE ANALYSIS OF THE CAPABILITES AND LIMITATIONS OF PSI

STUDIES ON SEVARAL COUNTERMEASURES AGAINST LIQUEFACTION-INDUCED FLOW AND AN APPLIVATION OF A MEASURE TO EXISTING BRIDGES IN TOKYO

Land Navigation Table of Contents

Date: April 2, 2014 Project No.: Prepared For: Mr. Adam Kates CLASSIC COMMUNITIES 1068 E. Meadow Circle Palo Alto, California 94303

Geoscientific Instrumentation in River Valley Projects

Monthly Magnetic Bulletin

Seepage Analysis for Shurijeh Reservoir Dam Using Finite Element Method. S. Soleymani 1, A. Akhtarpur 2

Monthly Magnetic Bulletin

Monthly Magnetic Bulletin

TEGAM s Connection to the EarthScope Project

25th International Conference on Ground Control in Mining

Prepared By: John Blair Sean Donahue Celeste Hoffman Kimberly Klinkers Megan Slater

MAINTENANCE OF THE GEOMETRY OF LEP IMPROVEMENT & OPTIMIZATION OF THE VERTICAL AND RADIAL SMOOTHING

Appraisal of Soil Nailing Design

Experimental Research on Ground Deformation of Double Close-spaced Tunnel Construction

RESIDUAL DEFORMATION OF CAISSON, SHEET PILE AND GROUND BY SIMPLIFIED ANALYSIS

February 18, 2003 File: NORTH CENTRAL REGION LANDSLIDE ASSESSMENT HWY 43:16 WHITECOURT EAST HILL (NC1) 2002 ANNUAL INSPECTION REPORT

AGRAS H.E.P-MINIMIZING EMBANKMENT SETTLEMENTS TO PREVENT OVERTOPPING. Abstract

PROJECT FOR THE PRODUCTION OF 1/1000 SCALE BASE MAPS FROM COLOUR IMAGES USING DIGITAL CAMERAS IN BURSA METROPOLITAN AREA (BMA) IN TURKEY

August 10, 2007 File:

[LLAZC X.L EA0000; AZ SRP ] Notice of Temporary Closures: Selected Public Lands in La Paz County, AZ

Drilled Shafts for Bridge Foundation Stability Improvement Ohio 833 Bridge over the Ohio River An Update

Hydric Rating by Map Unit Harrison County, Mississippi. Web Soil Survey National Cooperative Soil Survey

Evaluating the Integrity of a Railway Corridor Using Remote Sensing

The Potential of High Resolution Satellite Interferometry for Monitoring Enhanced Oil Recovery

PREDICTION OF THE CYCLIC BEHAVIOR OF MOMENT RESISTANT BEAM-TO-COLUMN JOINTS OF COMPOSITE STRUCTURAL ELEMENTS

4 Survey Datums. 4.1 Horizontal Datum Policy SURVEY DATUMS SEPTEMBER 2006

NEWS RELEASE. Province boosts winter highway safety measures

Comparison between predicted liquefaction induced settlement and ground damage observed from the Canterbury earthquake sequence

Chapter 11 10/30/2013. Mass Wasting. Introduction. Factors That Influence Mass Wasting. Introduction. Factors That Influence Mass Wasting

J.H. Campbell Generating Facility Pond A - Location Restriction Certification Report

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Drilled Shafts for Bridge Foundation Stability Improvement: Ohio 833 Bridge over the Ohio River. Meigs County, Ohio Mason County, West Virginia

3.12 Geology and Topography Affected Environment

THE GSI FUTURE PROJECT: AN INTERNATIONAL ACCELERATOR FACILITY FOR BEAMS OF IONS AND ANTIPROTONS

Erosion and Sediment Control Measures 2.7 Silt Fences

BAYESIAN ESTIMATION IN DAM MONITORING NETWORKS

Rock slope stability planar shear failure

THE STRUCTURAL DESIGN OF PILE FOUNDATIONS BASED ON LRFD FOR JAPANESE HIGHWAYS

INCLINOMETER COMPARISON

Transcription:

TOPOGRAPHIC MONITORING OF A WATER TANK IN THE WIDENING WORKS OF EIXO NORTE-SUL HIGHWAY IN LISBON João HENRIQUES 1 and Ana Paula FALCÃO 2 1 Geóide, Empresa de Serviços Topográficos,Leiria - Portugal 2 Departamento de Engenharia Civil e Arquitectura- IST, Lisboa- Portugal Abstract: A monitoring necessity for a water tank in Lisbon originated in the widening work of the Eixo Norte-Sul highway, which involved excavation near the tank. As the excavation could affect the tank s safety and the water supply service, the owner (EPAL Empresa Portuguesa de Águas Livres) and the employer (EP Estradas de Portugal) agreed on the installation of a topographic monitoring system. This paper describes the processes in the topographic monitoring of the water tank, and stresses the importance of the installed system. The use of the sub-system for vertical displacement determination as a warning system is also focused. Due to the complexity of the works and an unexpected behaviour of the structure, the integration of the results of the topographic monitoring with the geotechnical instruments was critical in the analysis, understanding and validation of the results. 1. INTRODUCTION The need to monitor the water tank was motivated by the widening works of North-South highway, one of the largest roads in Lisbon, which involve excavation near the water tank. By project indication, after the excavation two support walls would be constructed, in two different levels. The main function of these walls would be to stabilize the slope in the water tank. Fearing that the excavation could jeopardise the safety of the water tank and affect the normal water supply to the population, it was decided by EPAL the tank owner and EP - the promoter, to install a topographic monitoring system. Surveying company GEÓIDE, and Instituto Superior Técnico as a cooperative partner, were responsible for the definition and implementation of such system. Additionally, we also installed geotechnical instrumentation. The topographic monitoring began on April 20, 2005, with daily readings frequency, going on a twice per day stage where shifts had become more significant. After solving the problem, the frequency of campaigns was progressively reduced until the conclusion of works. The system was observed for the last time on January 8, 2007. 1

2. LOCATION, ENVIRONMENT AND DIMENSIONS The water tank is located at Alto Lumiar. It is a composed structure of two independent cells, built in different periods, separated by a central corridor allowing the access to both cells, and sharing the terrace. The east cell, the oldest one, was built circa 1950; the west cell was built in the 1980 s. The constructive process was quite different: the east cell has an exterior buttress system and the west cell has an interior one. The water tank size is 83 meters long, 43 meters wide and 7 meters high, with only one meter above surface level. Figure 1 illustrates the water tank, where the division line between both cells is visible. Figure 1 Water tank in Alto Lumiar (Google Earth imagery) 3. SYSTEM DEFINITION AND IMPLEMENTATION The installed topographic monitoring system is composed by two subsystems: one to evaluate horizontal displacements and a second one to assess vertical displacements. The system was complemented with geotechnical instruments, such as tiltmeters, inclinometers and fissurometers. The least square method was used in observation adjustments to determine the horizontal and vertical displacements. The network has been planned to allow high redundancy, in accordance with Cooper (1987). Among all geotechnical instruments, the main interest was in inclinometers, which provided information on depth and lateral terrain behaviour, and, in the other hand, geotechnical instruments, which operate as an independent system, and help to corroborate the values obtained by the topographic system. 3.1. Horizontal displacement subsystem The proposed system is composed by seven target points, four station points, three in pillar and one in tripod, and five reference points. Station points were designated respectively by Pillar 1, Pillar 2, Pillar 3 and POD 4. For target points we used Leica GMP104 (Figure 2a) and removable Leica mini-prisms GMP103 (Figure 2b). 2

Figure 2 a) Leica GMP 104 target; b) Leica GMP 103 target. The reference points were selected from nearby buildings, sufficiently apart from the area being monitored so that stabilization can be assumed, and implemented by Leica mini-prism GMP 104. We used five points reference, known as RH1,, RH5. Angle and distance measurements were made by a total station Leica TCA2003, with average quadratic angular error of approximately 0.5'' and 1 mm + 1 ppm in distance measurement. In the planned system, the size of a priori error ellipses varies between 1.4 mm and 4.1 mm. The geometric configuration of the network used in the determination of the horizontal displacement is illustrated in Figure 3. Figure 3 Network geometric configuration for horizontal displacements. 3.2. Vertical displacement subsystem The subsystem used to determine the vertical displacement was composed of five reference marks and 13 target marks. In practice, we use levelling (Casaca et al., 2005). All marks were welded with a two component epoxy resin in existing structures (curbs, concrete structures, etc). The equipment was a digital level Leica NA2002 and an invar code bar. Mark locations are displayed in Figure 4. 3

Figure 4 Network marks for vertical displacements. The observation system has been designed to enable cross readings between marks, increasing the redundancy and improving the specifications. The final accuracy associated with the determination of the vertical displacement is 0.3 mm. About geotechnical instrumentation were installed 4 inclinometers, 2 tiltmeters, 10 uniaxial fissurometers and 14 biaxial fissurometers. Examples are shown in Figure 5. Figure 5 Geotechnical instrumentation: inclinometers, tiltmeters, uniaxial and biaxial fissurometers. 3.2.1. Inclinometers The vertical inclinometers were installed at the top of the slope under control, up to 24 m deep (2 m below the wall foundation level), in order to monitor movements of the support wall, during and after the construction. 3.2.2. Tiltmeters Two tiltmeters here installed on both sides of the external tank, where we were expecting an higher probability of displacement. The bases were placed in perpendicular faces, at the same distance from the corner and at the same height. 3.2.3. Fissurometers Installed fissurometers were chosen by type of cracking and kind of control desired. Uniaxial fissurometers were installed in the exterior tank walls and biaxial fissurometers in the terrace and inside the water tank. Geotechnical instrumentation location is displayed in Figure 6. 4

4. RESULTS ANALYSIS Figure 6 Geotechnical instrumentation location (F-fissurometers, O-tiltmeters, I-inclinometers) All analysis, for the different kinds of instrumentation, were done in an integrated way. Noteworthy were the positive values of vertical displacements obtained by levelling for the N3 mark in L3 epoch (corresponding to April 22, 2005), as shown in Figure 7. EP REF L1- A L2 - A L3 - A L4 - M L5 - A L6 - M L7- A L8 - M L9- A 20-Apr 21-Apr 22-Apr 22-Apr 23-Apr 23-Apr 26-Apr 26-Apr 27-Apr 27-Apr 0.0 0.4 0.4 2.0 1.8 2.3 2.1 2.4 2.1 2.6 Displacements (mm) 3.0 2.5 2.0 1.5 1.0 0.5 0.0 N3 20-Apr 21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr Figure 7 Vertical displacements of N3 mark N3 mark is part of the set of marks closest to the excavation site. For the remaining instrumentation significant displacements were not observed in the same epoch. A vertical displacement (uplift) of approximately +2.0 mm was detected. It was considered by supervisors as an alert value, so works were interrupted for several weeks. When the 5

excavation of the slope was resumed, no abnormal results were detected in the first sessions. However, with the increase in excavation depth, re-emerging uplift in marks closest to the slope and subsidence in furthermost marks were noticed, suggesting the rotation of the tank around an axis perpendicular to the plane of the slope. Only in early August 2005 the horizontal displacement subsystem corroborated the values of vertical displacements, and it was no earlier than the end of that month that the geotechnical instrumentation, in particularly the inclinometers, detected these displacements (Figure 8). Figure 8 Inclinometer I3 value. The vertical and horizontal displacements determined through topographic observation system were later confirmed by geotechnical instrumentation, and classified by the team of geotechnical of EP / EPAL as the expected displacements. Notable was the fact that comparing with the geotechnical instruments the topographic methods provided, with some months in advance, the displacement detection: inclinometers I1 and I3 only identified those displacements in August 2005. Figure 9 illustrates slope behaviour. 6

PROFILE CROSS THE BUILT SLOPE Uplift subsidence Water tank original surface Figure 9 Displacement description observed by the vertical topographic subsystem. Figure 10 Photo of the site during and after final works conclusions. The analysis of displacement readings observed on the instrumentation system installed, were explained by the team, as the result of the excavation done on the natural slope and due to the presence of a silt sandy layer under saturated conditions, at 16 m depth that created a rotational landslide. When this saturated silty layer was intercepted by the excavation, the water started to flow and it washed very quickly the fine material, increasing the landslide phenomenon. The geological drilling survey done nearby the inclinometer I3, confirmed this interpretation. The solution projected by the geotechnical expert team to stop the landsliding was to shotcrete and install drain pipes on the slope of excavation, in order to stop the fine material wash. Figure 10 shows the slope excavation and the actual situation after construction conclusion. After conclusion works, all observed values stabilized in all types of instruments. As a preventive measure, the topographic monitoring system was still in operation until January 2007, although less frequently. 7

5. CONCLUSIONS The slope construction to support the water tank deserved attention of EPAL and EP. Because of the complex works and the unexpected land behaviour, the integration of values from topographic and geotechnical systems was of great importance in the analysis for understanding the slope behaviour. From all the instrumentation used, the values obtained by levelling were the most important by its sensitivity, working as a reference for warning and alert sign. Finally, we conclude that low-cost topographic methods, such as levelling, proved to be important tools in construction monitoring and related decision-making. References Casaca, J, Matos, J, Baio, M. (2005). Topografia Geral, Lidel, Lisbon. Cooper, M. A. R. (1987). Control Surveys in Civil Engineering, Collins, London. Corresponding author contacts Ana Paula FALCÃO afalcao@civil.ist.utl.pt Departamento de Engenharia Civil e Arquitectura, IST Portugal 8