WFIRST Project Response to post-wietr direction. Jeffrey Kruk WFIRST Project Scientist

Similar documents
Team X Study Summary for ASMCS Theia. Jet Propulsion Laboratory, California Institute of Technology. with contributions from the Theia Team

FY15 President s Budget Request for NASA Astrophysics

The WFIRST Coronagraphic Instrument (CGI)

Science with a Wide-Field Telescope in Space. NASA HQ Perspective. Richard Griffiths. Astrophysics Division Science Mission Directorate

WFIRST STATUS NAC meeting, March 10, Project Scientist Project Manager

Scientific Capability of the James Webb Space Telescope and the Mid-InfraRed Instrument

Hubble Space Telescope Users Committee (STUC)

Evaluation of the Implementation of WFIRST/AFTA in the Context of New Worlds, New Horizons in Astronomy and Astrophysics

Status of the JWST Science Instrument Payload

March 4, 2013 Eric P. Smith JWST Program Office

Princeton Astrophysics Community Meeting

SDT Interim Reports. Paul Hertz. Director, Astrophysics Division Science Mission Directorate. March 26, 2014

NICMOS Status and Plans

Stefanie Milam Deputy Project Scientist for Planetary Science NASA GSFC January 12, 2017


Presentation to the Committee for an Assessment of the Astrophysics Focused Telescope Assets (AFTA) Mission Concept

The next-generation Infrared astronomy mission SPICA Space Infrared Telescope for Cosmology & Astrophysics

CASE/ARIEL & FINESSE Briefing

Exoplanet High Contrast Imaging: Space

New Worlds, New Horizons in Astronomy and Astrophysics

WFIRST Project Activities. Neil Gehrels WFIRST Project Scientist NASA-GSFC

ESA activities towards the Gravitation Waves Space Observatory

The James Webb Space Telescope

November 3, 2014 Eric P. Smith JWST Program Office

WFIRST Science Definition Team and Project Interim Report Presentation to the Astrophysics Sub-Committee

The JWST mission: status and overview

Status of the James Webb Space Telescope (JWST) Observatory

Tuesday Nov 18, 2014 Rapporteurs: Aki Roberge (NASA GSFC) & Matthew Penny (Ohio State)

Coronagraphic Imaging of Exoplanets with NIRCam

WFIRST Exoplanet Imaging: Datacubes, Community Challenges, and the Starshade Study W F I R S T

life detection capabilities of LUVOIR and HabEx and WFIRST

The next-generation Infrared astronomy mission SPICA (1)Oxford presentation (2)Status and Schedule (3)Operation and Observation Program

Planning for the 2020 Decadal Survey An Astrophysics Division White Paper

Microlensing 22 Update on WFIRST and the Microlensing Science Investigation Team Activities

Decadal Survey: Summary of the ExoPAG s Response to Paul Hertz s Charge Regarding Large Missions"

Proximity Glare Suppression for Astronomical Coronagraphy (S2.01) and Precision Deployable Optical Structures and Metrology (S2.

Astrophysics Advisory Committee

The SPICA infrared space observatory project status

CL# Copyright 2018 California Institute of Technology Government sponsorship acknowledged1

Sun Shield. Solar Paddle

Cosmic Shear Weak Lensing with the Wide Field Infrared Survey Telescope (WFIRST)

SOFIA Stratospheric Observatory For Infrared Astronomy

Subaru GLAO: Comparisons with Space Missions. I. Iwata (Subaru Telescope) 2011/08/ /05/28 small revisions 2013/06/04 include JWST/NIRISS

Opportunities with the James Webb Space Telescope

CRaTER Project Monthly Technical Progress and Schedule Status Report (NNG05EB92C DRD 20 & 21) April 2005

The Large UV Optical IR survey telescope. Debra Fischer

What is Systems Engineering? & What Does a Systems Engineer Do??? Guest Lecture for Senior Design class Howard University Jeffrey Volosin NASA

WISE Science Data System Single Frame Position Reconstruction Peer Review: Introduction and Overview

An Astrophysics Mission of Opportunity on the International Space Station

James Webb Space Telescope Cycle 1 Call for Proposals and Update on WFIRST

Tibor Kremic, Glenn Research Center

NASA Plan for Development of Optical Communication for Space Applications

DRAFT. Robotic Lunar Exploration Program Lunar Reconnaissance Orbiter 431-ICD Date: September 15, 2005

The James Webb Space Telescope Overview

GEMINI 8-M Telescopes Project

Goals of the meeting. Catch up with JWST news and developments: ERS and GO call for proposals are coming!!

Exoplanets Direct imaging. Direct method of exoplanet detection. Direct imaging: observational challenges

1 Introduction to POPPY and WebbPSF

WISE Science Data System Frame Co-addition Peer Review: Introduction and Overview

Lessons Learned! from Past & Current ESA-NASA Collaborations

Vibration Analysis of the Advanced Stirling Radioisotope Generators. Tom Sutliff (for June Zakrajsek) Applied Physics Laboratory

Hubble Science Briefing

Mars Sample Return Mission

TMT and Space-Based Survey Missions

A Large Monolithic-Aperture Optical/UV Serviceable Space Telescope Deployed to L2 by an Ares-V Cargo Launch Vehicle

Newsletter of the INTEGRAL Science Operations Centre

JWST Science and best practices! Massimo Stiavelli, Jason Kalirai, Klaus Pontoppidan! ROE, July 5 th, 2016! Space Telescope Science Institute!

Plato, Euclid and the New Hard X-Ray mission

Astrophysics. Paul Hertz Director, Astrophysics Division Science Mission

Application of Precision Deformable Mirrors to Space Astronomy

Stellar Observations Network Group

Appendix: B. Mission Requirements Summary NEW WORLDS OBSERVER (NWO) MISSION 4/23/2009

Designing the Future of Exoplanet Exploration: Mission Studies for the 2020 Decadal Survey

JAMES WEBB SPACE TELESCOPE (JWST) - FINE GUIDENCE SENSOR AND TUNABLE FILTER IMAGER OPTICAL DESIGN OVERVIEW AND STATUS

Exoplanets Direct imaging. Direct method of exoplanet detection. Direct imaging: observational challenges

Announcement of Opportunity AKARI (ASTRO-F)

The JWST mission. P. Ferruit (ESA project scientist) MIRI. NIRSpec FGS/NIRISS. NIRCam. Slide #1

Deep Space Climate Observatory (DSCOVR) Mission Briefing

The Transneptunian Automated Occultation Survey (TAOS II) Matthew Lehner ASIAA

James Webb Space Telescope (JWST)

Lunar Reconnaissance Orbiter Project. Cosmic Ray Telescope for the Effects of Radiation to Spacecraft Mechanical Interface Control Document

Lunar Discovery and Exploration program

NASA's Plankton, Aerosol, Cloud, ocean Ecosystem (PACE) mission update

How Do We Look For Life Beyond Earth?

Astrophysics. Paul Hertz Director, Astrophysics Division Science Mission

Report to the GSMT Committee

Issues for SDT Consideration Arising from Conference. Neil Gehrels, WFIRST Project Scientist

The SPICA Coronagraph

CIRiS: Compact Infrared Radiometer in Space LCPM, August 16, 2017 David Osterman PI, CIRiS Mission

Key Technology Challenges for the Study of Exoplanets and the Search for Habitable Worlds

Hertz & the 2020 Decadal Survey: a PAG Panel Discussion!

Cosmic Ray Telescope for the Effects of Radiation to Spacecraft Thermal Interface Control Document

Infrastructure for a Permanent LUVOIR Observatory in Space

DARE Mission and Spacecraft Overview

The Swift GRB MIDEX. Neil Gehrels May 20, 2002

Exoplanet Microlensing Surveys with WFIRST and Euclid. David Bennett University of Notre Dame

The Quantum Sensor Challenge Designing a System for a Space Mission. Astrid Heske European Space Agency The Netherlands

SPOCCIE. Sagan Polar Orbiting Coronagraph Camera for Imaging Exoplanets. Daniel Angerhausen Kerri Cahoy Ian Crossfield James Davidson Christoph Keller

The Kepler Exoplanet Survey: Instrumentation, Performance and Results

Using the International Space Station as an Engineering Technology Research Laboratory for Space Based Telescopes

Transcription:

WFIRST Project Response to post-wietr direction Jeffrey Kruk WFIRST Project Scientist

Introduction WFIRST highest ranked large space mission in 2010 Decadal Survey Use of 2.4m telescope enables - Hubble quality imaging over 100x more sky - Exoplanet studies with a coronagraph at 10-8 - 10-9 contrast Dark Energy Exoplanets microlensing Astrophysics coronagraph Credit: M. Rizzo, N. Zimmerman, A. Roberge (NASA GSFC), E. Douglas (MIT), L. Pueyo (STScI) HST WFIRST 2

WFIRST Observatory Concept OBA CGI IC OBA DOOR FCR AVIONICS MODULES X6 X Z Y WFI SASS Key Features Telescope: 2.4m aperture Instruments: Wide Field Imager / Spectrometer & Integral Field Unit Internal Coronagraph with Integral Field Spectrometer Data Downlink: 275 Mbps Data Volume: 11 Tb/day Orbit: Sun-Earth L2 Launch Vehicle: 4 options Mission Duration: 5 yr, 10yr goal Serviceability: Observatory designed to be robotically serviceable Starshade compatible HGAS 3

WIETR Timeline WFIRST Independent External Technical/Management/Cost Review June-July 2017: Initial activities Delivery of documents for review August 2017: Site visits October 2017: report released, new SMD direction to project December 2017: finalize revised baseline January 2018: begin delivering materials to Standing Review Board for System Requirements Review / Mission Definition Review 4

SMD direction 10/19/2017 I am directing the Goddard Space Flight Center to study modifying the current WFIRST design, the design that was reviewed by the WIETR, to reduce cost and complexity sufficient to have a cost estimate consistent with the $3.2B cost target set at the beginning of Phase A. The following constraints and changes are directed to begin this design modification study: The basic architecture of the mission, including the use of the existing 2.4m telescope, a widefield instrument, and a coronagraph instrument, shall be retained. The implementation of the mission risk classification shall be consistent with the findings of the WIETR report. Reductions shall be taken in the widefield instrument. The coronagraph instrument shall be treated as a technology demonstration instrument, consistent with the findings of the WIETR report; in addition, reductions shall be taken in the coronagraph instrument. The cost of science investigations shall be reduced. The additional use of commercial subsystems and components shall be considered for the spacecraft; however, serviceability for both the spacecraft and the payload will be retained. 5

Cost status Project baseline was revised to fit in $3.2B Savings that don t affect science return: Incorporate international contributions Improved budget profile STMD contributions towards coronagraph Optimization of design, integration & test flow Eliminated one processor by combining functions Simplifications to payload I&T saves schedule and reduces some test equipment & facility costs -> Combination of the above saves 6 months in schedule 6

Unchanged aspects of architecture Aspects of mission architecture that remain unchanged, as directed: Existing 2.4m telescope components Wide-Field Instrument Coronagraph Instrument Serviceability of spacecraft and payload 7

Risk Classification Class A will be implemented with the following tailoring: In general, a protoflight approach is used for qualification. Engineering units are used for new or modified hardware. For WFIRST-unique developments, sparing is at the subassembly level with additional kitted spares; for procured components, no spares are planned. Comply with Class A requirement for Level 1 parts except where additional screening adds little value or invalidates heritage of procured components Coronagraph is Class C with tailoring to be determined during Phase B 8

Wide-Field Instrument Modified detector requirements to specify performance at the focal plane level, rather than at the individual detector level Quality across entire focal plane is key discriminator for WFI science New requirements increase yield, i.e. decrease time required to manufacture full set of flight detectors Decreased focal plane operating temperature from 100K to 95K Reduces noise, thereby increasing detector yield Colder temperature is possible by utilizing WFI radiator thermal margin Assume the Integral Field Channel (IFC) is contributed by an international partner. Main simplification to WFI, elimination of cryocooler, was made prior to WIETR. Otherwise maintained full WFI H/W capabilities 9

Wide-Field Instrument WFIRST Field of View Diffraction-limited imaging 0.28 square degree FoV 0.11 pixels R~4 filters spanning 0.28-2.0 μm Sensitivity: 27.8 H(AB) @5σ in 1hr Slitless grism: 1.0-1.93 μm R: 435-865 10

Coronagraph Coronagraph is now treated fully as a technology demonstration instrument. Reduction in masks & filters shortens I&T flow Change to participating scientist program eliminates most associated science operation center costs Model similar to PI-class instrument Retained Class C designation with tailoring to be determined during Phase B Otherwise maintained CGI architecture & functions 11

5 mhz 1 khz 5 mhz IFSCAM Coronagraph architecture Light From Telescope Fast Steering Mechanism SPC mask Focal plane mask Lyot mask Field stop Filter mask wheel High Order Wavefront Sensing/ Control Hybrid Lyot Coronagraph OAP1 Focus Correction Mechanism OAP2 Deformable Mirror 2 Deformable Mirror 1 OAP3 Fold Mirror OAP4 Low Order Wavefront Sensing/ Control OAP5 OAP6 OAP7 Off Axis Parabola 8 LOCAM Shaped Pupil Coronagraph IFS/Img Selector DICAM Radiation Shield Mirror Integral Field Spectrometer Basic architecture unchanged. Some modes removed and some not tested to reduce cost. 12

CGI Configuration SP HL SP HL 1% BW 3% BW 3% BW 18% BW SP Disk HL 10% BW HL Hybrid Lyot Shaped Pupil Star- Shade Comp. Engr. Pupil mask changer c Plain mirror Occulting mask changer (magnified for illustration) 1 4 4 2 3 x3 Open c Dichroics for starshade (per ICD) Pinhole Lyot mask changer Open Field stop mask changer 1 4 Open x5 Starshade filters (per ICD) ND4 filter Dark mask Filter wheel 1 4 2 3 1a, 1b, 1c 4a, 4b, 4c IFS c x3 x3 18% BW 10% BW Open Camera selector Imaging Lenses c Mirror x4 Open Pupil Lens Phase Retrieval #1,2,3, 4 IC DI Un-pol 0-pol 45-pol 90-pol 135-pol IFS 13

CGI current performance predictions 14

Commercial Subsystems The Project conducted formal make/buy trade studies for spacecraft components with the greatest potential for commercialization. Most components/subsystems procured from industry Many in-house subsystems designed in-house but fabricated by industry 15

Science investigations 10% cut across the board for future SIT funding GO modified to provide only modes required by the other surveys, and limited to three calls Still have 5 archival research calls Significant reduction to wide-field science operations center capability: Deleted PSF database & tools, simulated source injection, and ability of pipeline to process fully simulated data Consolidated science center activities at STScI. Microlensing, CGI PSP support, and GO Program remain at IPAC. 16

Science Investigations What has not changed: All observing time to be selected competitively Some close to launch, the rest periodically thereafter All data will be public immediately Scientific priorities to be updated throughout mission, based on landscape at the time Changes under consideration: Models for time allocation to large programs Models for structure of teams for large programs Have begun consultations w/fswg and will be seeking community input on both topics 17

Project Status System Requirements Review / Mission Definition Review held February 27 March 1 Do we have the right requirements? / Does the mission design meet those requirements? KDP-B scheduled for April 11, 2018 Notional schedule: PDR: late 2019 CDR: mid 2021 Launch: 3 rd quarter 2025 18

Near-Term Activities Execute the Project Plan presented at SRR/MDR Complete the element SRRs in coming months Spacecraft, telescope, instruments, ground system Complete negotiations with international partners Respond within 60 days to the language in the FY18 Consolidated Appropriations Act Flow requirements to lower levels; complete optimization of instrument design parameters 19

BACKUP 20

Key WIETR Findings The WFIRST planned science surveys program and system design offer groundbreaking and unprecedented survey capabilities to the Dark Energy, Exoplanets, and Astrophysics communities. The WFIRST team has done a considerable amount of work for a project that has yet to enter KDP-B, particularly in areas that minimize development and cost risk; key processes for execution and control are in place, and the science and mission system concepts are mature. The WFIRST Project and Subsystem Management, Science, Systems Engineering, and Business Management personnel are very experienced, including in the management of large/flagship missions, and have the necessary skills to lead a mission of the level of complexity of WFIRST. The WFIRST Project has been methodical, thorough, and inclusive in the analysis and derivation of the science and corresponding technical and data requirements, however, additional work is needed to: 1) negotiate and codify them clearly and unambiguously, 2) include Programmatic Direction that should be codified as Level 1 requirements; and 3) develop a plan to comprehensively validate them. The Wide-Field Instrument (WFI) is the primary instrument of WFIRST; a tremendous science capability that will be substantially more capable than Euclid, far better than HST or JWST, and well beyond what is possible from the ground in the conduct of faint infrared surveys that remain of high science interest. 21