Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Brazil Transport & Digital Development Global Practice IBRD/IDA Investment Project Financing FY 2010 Seq No: 16 ARCHIVED on 01-Jun-2018 ISR31660 Implementing Agencies: State of São Paulo, Secretaria dos Transportes Metropolitanos (STM) Public Disclosure Authorized Key Dates Key Project Dates Bank Approval Date:20-Apr-2010 Planned Mid Term Review Date:03-Oct-2013 Original Closing Date:30-Jun-2014 Project Development Objectives Effectiveness Date:12-Nov-2010 Actual Mid-Term Review Date:12-Feb-2014 Revised Closing Date:30-Dec-2018 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The objective is to improve mobility for public transport users in the Capão Redondo-Largo Treze-Chácara Klabin corridor in a cost-efficient and environmentally friendly way. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured)phrpdodel The project development objectives are: (a) to improve the mobility of public transport users in the Capao Redondo-Largo Treze-Chacara Klabin (Line 5) and Vila Sonia-Luz (Line 4) Corridors in a cost-efficient and environmentally-friendly manner; and (b) to facilitate the integration between metro and bus at the metro stations. Components Public Disclosure Authorized Name Infrastructure and Equipment:(Cost $614.20 M) Institutional and Policy Development:(Cost $34.60 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate 6/1/2018 Page 1 of 11
Implementation Status and Key Decisions The Line 5 implementation progress is at a good pace despite accumulated delays, due mainly to initial delays related to civil works. The project continues to be moderately satisfactory and the PDO continues to be fully achievable. The civil works are expected to be concluded by March 2018, except for Campo Belo Station, which is expected for December 2018. The train contract is progressing as per the schedule with all 26 trains delivered. The implementation of the systems contract is progressing, despite delays. The restructuring of the Line 5 project was accomplished by the first addition, signed on June 29, 2017, which changes the contract, including in its objectives Civil Works of four stations of Line 4, a new station (Vila Sônia), its tunnels of access with about 1,5 Km of extension, bus terminal in the yard Vila Sônia, acquisition and installation of escalators, platform doors and systems of signaling and telecommunications of the referred stations. As Line 4 closes on February 28th 2018, Line 5 will include supervision of remaining works. 6/1/2018 Page 2 of 11
6/1/2018 Page 3 of 11
6/1/2018 Page 4 of 11
Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Low Low Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Moderate Moderate Fiduciary -- Low Low Environment and Social -- Moderate Substantial Stakeholders -- Low Low Other -- Moderate Moderate Overall -- Moderate Moderate Results Project Development Objective Indicators Travel time plus average waiting time between selected stations of Line 5 (Minutes, Custom) Value 72.00 64.00 64.00 25.00 Date 31-Dec-2009 30-Dec-2016 31-Dec-2017 31-Dec-2018 6/1/2018 Page 5 of 11
From Largo Treze to Chacara Klabin (Minutes, Custom Breakdown) Value 72.00 64.00 64.00 25.00 Date 31-Dec-2009 31-Aug-2017 31-Aug-2017 31-Dec-2018 From Capao Redondo to Se (Minutes, Custom Breakdown) Value 99.00 70.00 70.00 49.00 Date 30-Dec-2009 31-Aug-2017 31-Dec-2017 31-Dec-2018 % of Line 5 stations integrated with buses (Percentage, Custom) Value 35.30 71.00 50.00 100.00 Date 31-Dec-2009 30-Jun-2017 31-Dec-2017 31-Dec-2018 Incremental number of users in Line 5 per day in thousands (Number, Custom) Value 150.00 120.00 123.00 280.00 Date 31-Dec-2009 30-Jun-2017 31-Dec-2017 31-Dec-2018 Number of users per day in Line 5 of households with less than 4 minimum salaries (thousands) (Number, Custom) Value 68.00 148.00 152.00 331.00 6/1/2018 Page 6 of 11
Date 31-Dec-2008 31-Aug-2017 31-Dec-2017 31-Dec-2018 Line 5 working ratio (Number, Custom) Value 1.88 0.73 0.73 0.75 Date 31-Dec-2009 30-Sep-2015 30-Sep-2015 31-Dec-2018 Travel time plus average waiting time between pairs of stations Via Sonia - Luz (Minutes, Custom) Value 55.00 55.00 40.00 40.00 Date 30-Dec-2016 30-Dec-2016 31-Dec-2017 31-Dec-2018 Total annual passenger boardings in Vila Sonia (both directions, in millions) (Number, Custom) Value 0.00 0.00 0.00 47.00 Date 30-Dec-2016 30-Dec-2016 31-Dec-2017 31-Dec-2018 Number of buses in the corridor of Line 5 (Number, Custom) 6/1/2018 Page 7 of 11
PHINDIRITBL Value 955.00 1,070.00 1,045.00 652.00 Date 31-Dec-2009 31-Aug-2017 31-Dec-2017 31-Dec-2018 Frequency of buses in the peak hour in the corridor of Line 5 (Number, Custom) Value 411.00 450.00 422.00 258.00 Date 31-Dec-2009 31-Aug-2017 31-Dec-2017 31-Dec-2018 % of Line 4 stations integrated with buses (Percentage, Custom) Value 0.00 -- 91.00 91.00 Date 30-Dec-2016 30-Dec-2016 31-Jan-2018 31-Dec-2018 Overall Comments Intermediate Results Indicators Cumulative % of completion of new trains for Line 5 (Percentage, Custom) Value 0.00 93.74 98.80 100.00 Date 31-Dec-2009 31-Jul-2017 31-Jan-2018 31-Dec-2018 6/1/2018 Page 8 of 11
PHINDIRITBL PHINDIRITBL PHINDIRITBL PHINDIRITBL % of completion per year of the Line 5 CBTC systems (Percentage, Custom) Value 0.00 44.40 56.20 100.00 Date 31-Dec-2009 31-Aug-2017 31-Jan-2018 31-Dec-2018 % of completion per year of metro climate change action plan - Line 5 (Percentage, Custom) Value 0.00 0.00 0.00 100.00 Date 31-Dec-2009 31-Jul-2017 31-Jan-2018 31-Dec-2018 Line 4 Cumulative % of completion of Vila Sonia Tunnel (Percentage, Custom) Value 0.00 2.70 31.00 77.00 Date 21-Dec-2009 31-Jul-2017 09-Feb-2018 31-Dec-2018 Line 4 Cumulative % of completion of Vila Sonia Station (Percentage, Custom) Value 0.00 18.70 24.00 76.00 Date 21-Dec-2009 31-Jul-2017 09-Feb-2018 31-Dec-2018 6/1/2018 Page 9 of 11
PHINDIRITBL PHINDIRITBL Line 4 Cumulative % of completion of Vila Sonia yard (Percentage, Custom) Value 0.00 66.90 76.00 100.00 Date 21-Dec-2009 31-Jul-2017 09-Feb-2018 31-Dec-2018 Line 4 Cumulative % of completion of existing stations (Percentage, Custom) Value 0.00 38.40 78.00 100.00 Date 21-Dec-2009 31-Jul-2017 09-Feb-2018 31-Dec-2018 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P116170 IBRD-78550 Effective USD 650.40 650.40 0.00 425.49 224.91 65% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P116170 IBRD-78550 Effective 20-Apr-2010 27-Sep-2010 12-Nov-2010 30-Jun-2014 30-Dec-2018 Cumulative Disbursements 6/1/2018 Page 10 of 11
Restructuring History Level 2 Approved on 11-Jun-2014,Level 2 Approved on 21-Dec-2016,Level 1 Approved on 15-Jun-2017 Related Project(s) There are no related projects. 6/1/2018 Page 11 of 11