Industrial Processes I Manufacturing Economics

Size: px
Start display at page:

Download "Industrial Processes I Manufacturing Economics"

Transcription

1 Industrial Processes I Manufacturing Economics Equipment Cost Rate (Example 1) A production machine is purchased for an initial cost plus installation of $500,000. Its anticipated life = 7 yrs. The machine is planned for a two-shift operation, 8 hours per shift, 5 days per week, 50 weeks per year. The applicable overhead rate on this type of equipment = 35%. Determine the equipment cost rate. H = (50 weeks per year)*(5 days per week)*(8 hours per shift)*(2 shifts per day) C eq = equipment cost rate, $/min IC = initial cost of the equipment, $ N = anticipated number of years of service H = annual number of hours of operation, hr/yr R OH = applicable overhead rate for the equipment, % IC = $500,000 N = 7 yr H = (50 weeks per year)*(5 days per week)*(8 hours per shift)*(2 shifts per day) H = hr/yr R OH = 35% = 0.35 Solve for C eq C eq = $/min C eq = $/hr 1

2 Industrial Processes I Manufacturing Economics Cycle Time and Cost per Piece (Example 2) There is a production machine used to produce a batch of parts that each has a starting material cost of $2.35. Batch quantity = 100. The actual processing time in the operations = 3.72 min. Time to load and unload each workpiece = 1.60 min. Tool cost = $4.40, and each tool can be used for 20 pieces before it is changed, which takes 2.0 minutes. Before production can begin, the machine must be setup, which takes 2.5 hours. Hourly wage rate of the operator = $16.50/hr, and the applicable labour overhead rate = 40%. Determine (a) the cycle time for the piece, (b) average production rate when setup time is figured in, and (c) cost per piece. T c = cycle time of the unit operation, min/pc T o = actual processing time in the operation, min/pc T h = work part handling time, min/pc T t = tool handling time if that applies in the operation, min/pc T o = 3.72 min T h = 1.60 min T t = 2.00 min / 20 pc = min/pc Solve for T c T c = min/pc 2

3 Industrial Processes I Manufacturing Economics T p = average production time per piece, min/pc T su = setup time, min/batch Q = batch quantity, number of pieces (pc) T c = cycle time of the unit operation, min/pc T su = (2.5 hours/batch)*(60 min/hour) = min/batch Q = 100 pc T c = min/pc Solve for T p T p = min/pc 3

4 Industrial Processes I Manufacturing Economics R p = average hourly production rate, pc/hr T p = average production time per piece, min/pc T p = min/pc Solve for R p R p = pc/hr 4

5 Industrial Processes I Manufacturing Economics C L = labor cost rate, $/min R H = worker s hourly wage rate, $/hr R LOH = labor overhead rate, % R H = $/hr R LOH = 40 % = 0.40 Solve for C L C L = $/min C L = $/hr 5

6 Industrial Processes I Manufacturing Economics C o = cost rate of operating the work cell, $/min C L = cost rate of labor, $/min C eq = cost rate of equipment in the work cell, $/min C L = $/min C eq = $/min Solve for C o C o = $/min C pc = cost per piece, $/pc C m = starting material cost, $/pc C o = cost rate of operating the work cell, $/min T p = average production time per piece, min/pc C t = cost of tooling used in the unit operation, $/pc If applicable in the particular manufacturing process, the cost of tooling C t must be determined by dividing the actual cost of the tooling by the number of pieces between tool changes. C m = 2.35 $/pc C o = $/min T p = min/pc C t = $4.40 per 20 pc = $/pc Solve for C pc C pc = $/pc 6

7 Industrial Processes I Manufacturing Economics Scrap Rate (Example 3) A customer has ordered a batch of 1000 parts to be produced by a machine shop. Historical data indicate that the scrap rate on this type of part = 4%. How many parts should the machine shop plan to make in order to account for this scrap rate? q = the scrap rate In batch production more than the specified batch quantity is often produced to compensate for the losses due to scrap. Q = the required quantity of parts to be delivered Q o = the starting quantity q = 4% = 0.04 Q = 1000 parts Solve for Q o Q o = starting parts (round answer up) 7

8 Industrial Processes I Manufacturing Economics Cycle Time and Cost per Piece (Example 4) A high-production operation manufactures a part for the automotive industry. Starting material cost = $1.75, and cycle time = 2.20 min. Equipment cost rate = $42.00/hr, and labour cost rate = $24.00/hr, including overhead costs in both cases. Availability of the production machine in this job = 97%, and the scrap rate of parts produced = 5%. Because this is a long-running job, setup time is ignored, and there is no tooling cost to be considered. (a) Determine the production rate and finished part cost in this operation. (b) If availability could be increased to 100% and scrap rate could be reduced to zero, what would be the production rate and finished part cost. a) R p = average hourly production rate, pc/hr T p = average production time per piece, min/pc T p = 2.20 min/pc Solve for R p and multiply the result by the availability of the production machine R p = pc/hr (based on the production machine being 97% available) 8

9 Industrial Processes I Manufacturing Economics C o = cost rate of operating the work cell, $/min C L = cost rate of labor, $/min C eq = cost rate of equipment in the work cell, $/min C L = ($24.00/hr)(1 hr per 60 minutes)/availability = $/min C eq = ($42.00/hr)(1 hr per 60 minutes)/availability = $/min Solve for C o C o = $/min C pc = cost per piece, $/pc C m = starting material cost, $/pc C o = cost rate of operating the work cell, $/min T p = average production time per piece, min/pc C t = cost of tooling used in the unit operation, $/pc C m = (1.75 $/pc)/(1-q) = $/pc C o = $/min T p = (2.20 min/pc)/(1-q) = min/pc C t = 0.00 $/pc Solve for C pc C pc = $/pc 9

10 Industrial Processes I Manufacturing Economics (b) Assume 100% availability and q=0 C o = cost rate of operating the work cell, $/min C L = cost rate of labor, $/min C eq = cost rate of equipment in the work cell, $/min C L = ($24.00/hr)(1 hr per 60 minutes) = $/min C eq = ($42.00/hr)(1 hr per 60 minutes) = $/min Solve for C o C o = $/min C pc = cost per piece, $/pc C m = starting material cost, $/pc C o = cost rate of operating the work cell, $/min T p = average production time per piece, min/pc C t = cost of tooling used in the unit operation, $/pc C m = 1.75 $/pc C o = $/min T p = 2.20 min/pc C t = 0.00 $/pc Solve for C pc C pc = $/pc 10

11 Production Scheduling with Machine-Machine Diagrams Problem MM1: The cell represented in the following figure is formed by three machines. The setup time between operations can be considered null. The company works 5 days a week, 8 hours per shift, with two shifts per day. 1. Calculate the cycle time. 2. Determine the maximum weekly production. 3. Show the machine-machine diagram, assuming a stable state. First, all the cycles must be calculated. The cycles can be obtained from the represented production process. Cycles: M1 = 5 min + 2 min + 1 min = min M2 = 10 min The larger cycle time fixes the cycle = min 11

12 Production Scheduling with Machine-Machine Diagrams Problem MM1 Continued: Maximum weekly production can be easily obtained by calculating the amount of minutes included in a week under problem working conditions: 5 day 2 shift 8 hr 60 min 1part P weekly = = parts/week week day shift hr cycle time min In order to draw the diagram, it is important to start with the machine that fixes the working cycle (in a stable situation). Next, the other machines operations must be included trying to minimize the product lead time. Finally, it is important to draw one product cycle. 12

13 13 MM1 Machine-Machine Diagram M1 OP M Cycle time min

14 Production Scheduling with Machine-Machine Diagrams Problem MM2: The cell represented in the following figure is formed by two machines. The setup time between operations can be considered null. The company works 7 days a week, 8 hours a day. 1. Determine the maximum weekly production. 2. Calculate the cycle time. 3. Show the machine-machine diagram, assuming a stable state. First, all the cycles must be calculated. The cycles can be obtained from the represented production process. Cycles: M1 = min + min = min M2 = min + min = min The larger cycle time fixes the cycle = min 14

15 Production Scheduling with Machine-Machine Diagrams Problem MM2 Continued: Maximum weekly production can be easily obtained by calculating the amount of minutes included in a week under problem working conditions: 7 day 8 hr 60 min 1part P weekly = = parts/week week day 1hr cycle time min In order to draw the diagram, it is important to start with the machine that fixes the working cycle (in a stable situation). Next, the other machines operations must be included trying to minimize the product lead time. Finally, it is important to draw one product cycle. 15

16 MM2 Machine-Machine Diagram OP1 0 M2 M Cycle time min 16

17 Production Scheduling with Machine-Machine Diagrams Problem MM4: The cell represented in the following figure is formed by two machines. The setup time between operations can be considered null. The company works 5 days a week, 8 hours a day. 1. Calculate the cycle time and the lead time. 2. Determine the maximum weekly production. 3. Show the machine-machine diagram, assuming a stable state. First, all the cycles must be calculated. The cycles can be obtained from the represented production process taking into account that one final product needs two components C2. Cycles: M1 = min + min = min M2 = min + min = min The larger cycle time fixes the cycle = min 17

18 Production Scheduling with Machine-Machine Diagrams Problem MM4 Continued: Maximum weekly production can be easily obtained by calculating the amount of minutes included in a week under problem working conditions: 5 day 8 hr 60 min 1part P weekly = = parts/week week day 1hr cycle time min In order to draw the diagram, it is important to start with the machine that fixes the working cycle (in a stable situation). Next, the other machines operations must be included trying to minimize the product lead time. Finally, it is important to draw one product cycle. The lead time has to be obtained looking at the diagram because it depends on the operation order. Lead time = min (lead time can be minimized, but this is not the goal of the problem) 18

19 MM4 Machine-Machine Diagram Cycle Time min OP2 OP2 0 M2 M LT Lead time min 19

20 Production Scheduling with Machine-Machine Diagrams Problem MM5: The cell represented in the following figure is formed by two machines. The company works 5 days a week, 8 hours a day. The company uses the one-piece flow concept to manufacture the product. As a result, the batch size is one part. Besides, the part must be in the machine to start the setup process. The setup time in M2 is 1 minute, and the setup time in M1 (which depends on the operation sequence) is shown in the following table: 1. Calculate the cycle time. 2. Determine the maximum weekly production. 3. Show the machine-machine diagram, assuming a stable state. 20

21 Production Scheduling with Machine-Machine Diagrams Problem MM5 Continued: First, all the cycles must be calculated. The cycles can be obtained from the represented production process. Cycles: M2 (including setup times) = 1 min + min + 1 min + min = min M1 cycles depend on the selected sequence. Processing times are fixed (2 min + 2 min + 1 min + 3 min = 8 min) Many sequences are possible. It important not to choose a sequence which makes M1 being the machine that fixes the working cycle. M1 OP1-OP3-OP4-OP6-OP1 = 8 min + 2 min + 1 min + 1 min + 2 min = 14 min The larger cycle time fixes the cycle = min Maximum weekly production can be easily obtained by calculating the amount of minutes included in a week under problem working conditions: 5 day 8 hr 60 min 1part P weekly = = parts/week week day hr cycle time min In order to draw the diagram, it is important to start with the machine that fixes the working cycle (in a stable situation). Next, the other machine operations must be included trying to minimize the product lead time. Finally, it is important to draw one product cycle. 21

22 22 MM5 Machine-Machine Diagram M1 S OP1 OP1 S M2 7 S S S S Cycle time min S S S S 27 S S S S S 40 S

23 Additive Manufacturing Build Cycle Time in Stereolithography (Example 1) The square cup-shaped part shown below is to be fabricated using stereolithography. The base of the cup is 40 mm on each side and 5 mm thick. The walls are 4 mm thick, and the total height of the cup = 52 mm. The SL machine used for the job uses a spot diameter = 0.25 mm, and the beam is moved at a speed = 950 mm/s. Layer thickness = 0.10 mm. Repositioning and recoating time for each layer = 21 s. Compute an estimate of the cycle time to build the part if the setup time = 20 min. The geometry of the part can be divided into two sections: (1) base and (2) walls The cross-sectional area of the base A 1 = mm 2 The thickness of the base = mm The cross-sectional area of the walls A 2 = mm 2 The height of the walls = mm Building the base with a layer thickness = mm / = layers to build the base Building the walls with a layer thickness = mm / = layers to fabricate the walls Total number of layers = + = layers 23

24 Additive Manufacturing T i = time to complete layer i, s (sec) where the subscript i is used to identify the layer A i = area of layer i, mm 2 (in 2 ) v = speed of the moving spot on the surface, mm/s (in/sec) D = diameter of the spot (assumed circular), mm (in) T r = repositioning and recoating time between layers, s (sec) Time per layer for the base Time per layer for the walls A i = mm 2 A i = mm 2 v = mm/s D = mm T r = s v = mm/s D = mm T r = s Solve for T i for the base T i = s for the base Solve for T i for the walls T i = s for the walls 24

25 Additive Manufacturing T c = build cycle time, s (sec) T su = setup time, s (sec) n l = number of layers used to approximate the part T i = time to complete layer i, s (sec) T su = s n l = number of layers to approximate the base n l = number of layers to approximate the walls T i = s for the base T i = s for the walls Solve for T c T c = s T c = min T c = hr 25

26 Additive Manufacturing Cost per Piece in Additive Manufacturing (Example 2) The cost of a stereolithography machine is approximately $100,000 installed. It operates 5 days per week, 8 hours per day, 50 weeks per year, and is expected to last 4 years. Material cost for the photopolymer = $120/liter. Assume that all of the photopolymer in the container that is not used for the part can be reused. Labor rate = $24.00/hr, but labor will be used for only 25% of the build cycle, mostly for setup. The post-processing time = 6.0 min/part. Assume that the cycle time is hr and assume that there is no overhead rate for the equipment. Determine the part cost. C eq = equipment cost rate, $/min IC = initial cost of the equipment, $ N = anticipated number of years of service H = annual number of hours of operation, hr/yr R OH = applicable overhead rate for the equipment, % IC = $ N = yr H = hr/yr R OH = % Solve for C eq = equipment C eq = $/min C eq = $/hr 26

27 Additive Manufacturing C pc = cost per piece that sums the material, labor, and machine operating costs, $/pc C m = material cost, $/pc C L = labor cost, $/hr C eq = equipment cost, $/hr T c = cycle time, hr/cycle U L = utilization rate should be applied to the labor rate during the build cycle, % T pp = post-processing time required for support removal, cleaning, and/or finishing, hr Solve for C m Assume that the volume of the part is 35,072 mm 3 C m = $/pc C L = $/hr C eq = $/hr T c = hr/cycle U L = % = converted to decimal format T pp = hr Solve for C pc = cost C pc = $/pc 27

28 Additive Manufacturing Additive Manufacturing (Problem 1) 3D Printing is used to fabricate a prototype part whose total volume = 1.17 in 3, height = 1.22 in, and base area = 1.72 in 2. The printing head is 5 in wide and sweeps across the 7-in worktable in 3 sec for each layer. Repositioning the worktable height, recoating powders, and returning the printing head for the next layer take another 13 sec. Layer thickness = in. Compute an estimate for the time required to build the part. Ignore setup time. T c = build cycle time, s (sec) T su = setup time, s (sec) n l = number of layers used to approximate the part T i = time to complete layer i, s (sec) T c = sec T c = min T c = hr 28

29 Additive Manufacturing Additive Manufacturing (Problem 2) A tube with a rectangular cross section is to be fabricated by stereolithography. Outside dimensions of the rectangle are 38 mm by 60 mm, and the corresponding inside dimensions are 30 mm by 52 mm (wall thickness = 4 mm except at corners). The height of the tube (z-direction) = 40 mm. Layer thickness = 0.10 mm, and laser spot diameter = 0.25 mm. The beam velocity across the surface of the photopolymer = 800 mm/s. Compute an estimate for the cycle time to build the part, if 20 s are lost each layer for repositioning and recoating. Ignore setup time. T i = time to complete layer i, s (sec) where the subscript i is used to identify the layer A i = area of layer i, mm 2 (in 2 ) v = speed of the moving spot on the surface, mm/s (in/sec) D = diameter of the spot (assumed circular), mm (in) T r = repositioning and recoating time between layers, s (sec) T i = s 29

30 Additive Manufacturing T c = build cycle time, s (sec) T su = setup time, s (sec) n l = number of layers used to approximate the part T i = time to complete layer i, s (sec) T c = sec T c = min T c = hr 30

SYMBIOSIS CENTRE FOR DISTANCE LEARNING (SCDL) Subject: production and operations management

SYMBIOSIS CENTRE FOR DISTANCE LEARNING (SCDL) Subject: production and operations management Sample Questions: Section I: Subjective Questions 1. What are the inputs required to plan a master production schedule? 2. What are the different operations schedule types based on time and applications?

More information

Ch01 Introduction-3e-SI 12-15, 16/06, 06/04/07

Ch01 Introduction-3e-SI 12-15, 16/06, 06/04/07 Ch01 Introduction-3e-SI 12-15, 16/06, 06/04/07 Answer: Flexible automation is an extension of programmable automation. A flexible automated system is capable of producing a variety of parts (or products)

More information

ORI 390Q Models and Analysis of Manufacturing Systems First Exam, fall 1994

ORI 390Q Models and Analysis of Manufacturing Systems First Exam, fall 1994 ORI 90Q Models and Analysis of Manufacturing Systems First Exam, fall 1994 (time, defect rate) (12,0.05) 5 6 V A (16,0.07) (15,0.07) (5,0) M 1 1 2 M1 M2 O A (10,0.1) 7 8 V B (8,0.2) M4 2 4 M5 The figure

More information

Assembly Lines. Worked out Problems:

Assembly Lines. Worked out Problems: Assembly Lines Worked out Problems: Problem1. A product whose work content time = 50 min is to be assembled on a manual production line. The required production rate is 30unit/hr. From previous experience

More information

Name Class Date. You can use the properties of equality to solve equations. Subtraction is the inverse of addition.

Name Class Date. You can use the properties of equality to solve equations. Subtraction is the inverse of addition. 2-1 Reteaching Solving One-Step Equations You can use the properties of equality to solve equations. Subtraction is the inverse of addition. What is the solution of + 5 =? In the equation, + 5 =, 5 is

More information

Study Unit 3 : Linear algebra

Study Unit 3 : Linear algebra 1 Study Unit 3 : Linear algebra Chapter 3 : Sections 3.1, 3.2.1, 3.2.5, 3.3 Study guide C.2, C.3 and C.4 Chapter 9 : Section 9.1 1. Two equations in two unknowns Algebraically Method 1: Elimination Step

More information

SEXTANT & SEXTANT PE frequently asked questions

SEXTANT & SEXTANT PE frequently asked questions SEXTANT & SEXTANT PE frequently asked questions What is SEXTANT? SEXTANT is a software application that helps Financial Executives and Estimators determine their costing and budgeting standards also known

More information

Duration of online examination will be of 1 Hour 20 minutes (80 minutes).

Duration of online examination will be of 1 Hour 20 minutes (80 minutes). Program Name: SC Subject: Production and Operations Management Assessment Name: POM - Exam Weightage: 70 Total Marks: 70 Duration: 80 mins Online Examination: Online examination is a Computer based examination.

More information

Mechanical Engineering 101

Mechanical Engineering 101 Mechanical Engineering 101 University of alifornia, Berkeley Lecture #16 1 Today s lecture MRP scheduling LFL EOQ/EMQ POQ apacity planning 2 Formulae I it max{ 0, I i t 1 SR GR, it it } NR it max 0, GR

More information

Systems Optimization and Analysis Optimization Project. Labor Planning for a Manufacturing Line

Systems Optimization and Analysis Optimization Project. Labor Planning for a Manufacturing Line 15.066 Systems Optimization and Analysis Optimization Project Labor Planning for a Manufacturing Line Team 1 The Tek Team Lane Ballard Christine Cheung Justin Ging Omur Kaya David Jackson Alyson Naughton

More information

Modeling and Optimization (Word Problems ALL DAY) Let the first number and = the second number. The boundaries of this problem are [0, 30].

Modeling and Optimization (Word Problems ALL DAY) Let the first number and = the second number. The boundaries of this problem are [0, 30]. New Calculus 5.4 Modeling and Optimization (Word Problems ALL DAY) The sum of two non-negative numbers is 30. a) Find the numbers if the sum of their squares is as large as possible. b) Find the numbers

More information

HYBRID FLOW-SHOP WITH ADJUSTMENT

HYBRID FLOW-SHOP WITH ADJUSTMENT K Y BERNETIKA VOLUM E 47 ( 2011), NUMBER 1, P AGES 50 59 HYBRID FLOW-SHOP WITH ADJUSTMENT Jan Pelikán The subject of this paper is a flow-shop based on a case study aimed at the optimisation of ordering

More information

b. Rewrite the formula isolating the variable P. In other words, write a formula for determining the value of P. P

b. Rewrite the formula isolating the variable P. In other words, write a formula for determining the value of P. P Math Applications The applications that follow are like the ones you will encounter in many workplaces. Use the mathematics you have learned in this chapter to solve the problems. Wherever possible, use

More information

Materials for assessing adult numeracy

Materials for assessing adult numeracy Materials for assessing adult numeracy Number Task The population of Wales is approximately Write this in numbers in the box. million. What is the value of the 7 in this number? Write your answer in words.

More information

ANALYSIS OF AUTOMATED FLOW LINE & LINE BALANCING

ANALYSIS OF AUTOMATED FLOW LINE & LINE BALANCING UNIT 3: ANALYSIS OF AUTOMATED FLOW LINE & LINE BALANCING General Terminology & Analysis: There are two problem areas in analysis of automated flow lines which must be addressed: 1. Process Technology 2.

More information

M A C H I N E L I S T - P R O D U C T I O N P R O C E S S E S

M A C H I N E L I S T - P R O D U C T I O N P R O C E S S E S S P E C T R U M O F S E R V I C E S G R A P H I C S All commonly available programmes C O N S T R U C T I O N CAD, 3D construction, static loading, structural analysis interfaces to industrial construction

More information

Program Name: PGDBA Production and Operations Management Assessment Name: POM - Exam Weightage: 70 Total Marks: 70

Program Name: PGDBA Production and Operations Management Assessment Name: POM - Exam Weightage: 70 Total Marks: 70 Program Name: PGDBA Subject: Production and Operations Management Assessment Name: POM - Exam Weightage: 70 Total Marks: 70 Duration: 60 mins Instructions (Start of Assessment): Marks: 70 Time: 60 Minutes

More information

Dimensional Issues in Stereolithography

Dimensional Issues in Stereolithography Dimensional Issues in Stereolithography Abstract David L. Winmill, Daniel M. Hoopes and Suresh S. Jayanthi DuPont Somos, Two Penn's Way, New Castle, DE 19720-2407 New stereolithography photopolymers have

More information

trunniontable.com

trunniontable.com I would recommend Martin Trunnion Tables to anyone that s looking for a long lasting solution that will out perform anything else out there. - Jordan Meier, Haas Applications Engineer trunniontable.com

More information

Bryco Machine Welcomes SME and AME. October 1, 2008

Bryco Machine Welcomes SME and AME. October 1, 2008 Bryco Machine Welcomes SME and AME October 1, 2008 2008 Type of Shop Leading precision machining contract manufacturer Manufacturer of complex parts that require state-of-the-art equipment and high level

More information

2015 MPS Qualify Exam

2015 MPS Qualify Exam 2015 MPS Qualify Exam The examination will be four hours long. There will be eight questions in all. Students must select 7 out of 8 questions to answer. The exam is open book and open notes. The students

More information

CST/CAHSEE: Algebra I 15.0 Review: Grade 7 MG 1.3

CST/CAHSEE: Algebra I 15.0 Review: Grade 7 MG 1.3 Warm-Up y CST/CAHSEE: Algebra I.0 Review: Grade 7 MG. One pipe can fill a tank in 20 minutes, while another takes 0 minutes to fill the same tank. How long would it take the two pipes together to fill

More information

Industrial Engineering and Ergonomics

Industrial Engineering and Ergonomics Industrial Engineering and Ergonomics Exercise Unit 4 Analysis of the time structure of working processes Fall Winter 2015/2016 Univ.-Prof. Dr.-Ing. Dipl.-Wirt.-Ing. Christopher M. Schlick Chair and Institute

More information

trunniontable.com Trunnion Tables for Haas Verticals

trunniontable.com Trunnion Tables for Haas Verticals Trunnion Tables for Haas Verticals I would recommend Martin Trunnion Tables to anyone that s looking for a long lasting solution that will out perform anything else out there. trunniontable.com 859-727-9900

More information

Bus 216: Business Statistics II Introduction Business statistics II is purely inferential or applied statistics.

Bus 216: Business Statistics II Introduction Business statistics II is purely inferential or applied statistics. Bus 216: Business Statistics II Introduction Business statistics II is purely inferential or applied statistics. Study Session 1 1. Random Variable A random variable is a variable that assumes numerical

More information

2015 Costs and Returns Estimate Eastern Idaho: Alfalfa Hay Establishment in Grain Stubble Paul E. Patterson Background and Assumptions

2015 Costs and Returns Estimate Eastern Idaho: Alfalfa Hay Establishment in Grain Stubble Paul E. Patterson Background and Assumptions 2015 Costs and Returns Estimate Eastern Idaho: Alfalfa Hay Establishment in Grain Stubble Paul E. Patterson Background and Assumptions Eastern Idaho The University of Idaho s costs and returns estimates

More information

MATH 1710 College Algebra Final Exam Review

MATH 1710 College Algebra Final Exam Review MATH 1710 College Algebra Final Exam Review MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. Solve the problem. 1) There were 480 people at a play.

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Southcentral Idaho: Magic Valley Alfalfa Hay Establishment with Oats Ben Eborn Magic Valley Background and Assumptions The University of Idaho s costs and returns estimates

More information

Planning and Scheduling of batch processes. Prof. Cesar de Prada ISA-UVA

Planning and Scheduling of batch processes. Prof. Cesar de Prada ISA-UVA Planning and Scheduling of batch processes Prof. Cesar de Prada ISA-UVA prada@autom.uva.es Outline Batch processes and batch plants Basic concepts of scheduling How to formulate scheduling problems Solution

More information

C.6 Normal Distributions

C.6 Normal Distributions C.6 Normal Distributions APPENDIX C.6 Normal Distributions A43 Find probabilities for continuous random variables. Find probabilities using the normal distribution. Find probabilities using the standard

More information

3 2 (C) 1 (D) 2 (E) 2. Math 112 Fall 2017 Midterm 2 Review Problems Page 1. Let. . Use these functions to answer the next two questions.

3 2 (C) 1 (D) 2 (E) 2. Math 112 Fall 2017 Midterm 2 Review Problems Page 1. Let. . Use these functions to answer the next two questions. Math Fall 07 Midterm Review Problems Page Let f and g. Evaluate and simplify f g. Use these functions to answer the net two questions.. (B) (E) None of these f g. Evaluate and simplify. (B) (E). Consider

More information

Mitrol MFG Work Centre Control

Mitrol MFG Work Centre Control Mitrol MFG Work Centre Control Copyright Information The information in this document is subject to change without notice and should not be construed as a commitment by Mitrol. Mitrol assumes no responsibility

More information

Math 112 Spring 2018 Midterm 2 Review Problems Page 1

Math 112 Spring 2018 Midterm 2 Review Problems Page 1 Math Spring 08 Midterm Review Problems Page Note: Certain eam questions have been more challenging for students. Questions marked (***) are similar to those challenging eam questions. Let f and g. (***)

More information

Making Measurements. On a piece of scrap paper, write down an appropriate reading for the length of the blue rectangle shown below: (then continue )

Making Measurements. On a piece of scrap paper, write down an appropriate reading for the length of the blue rectangle shown below: (then continue ) On a piece of scrap paper, write down an appropriate reading for the length of the blue rectangle shown below: (then continue ) 0 1 2 3 4 5 cm If the measurement you made was 3.7 cm (or 3.6 cm or 3.8 cm),

More information

MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. C) 5 2 C) C) 9 8 C) 25 2 C) 2 1 3

MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. C) 5 2 C) C) 9 8 C) 25 2 C) 2 1 3 MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. Write each mixed number as an improper fraction. ) 6 2 8 ) 8 C) 2 2 2) 2 2 2) 2 2 C) 28 ) ) 0 2 C)

More information

Chapter 8. Chapter 8 Opener. Section 8.1. Big Ideas Math Red Accelerated Worked-Out Solutions 4 7 = = 4 49 = = 39 = = 3 81 = 243

Chapter 8. Chapter 8 Opener. Section 8.1. Big Ideas Math Red Accelerated Worked-Out Solutions 4 7 = = 4 49 = = 39 = = 3 81 = 243 Chapter 8 Opener Try It Yourself (p. 35). trapezoids. circles Large Perimeter Diameter Small Perimeter Diameter Average of Ratios 3. trapezoid, triangle. triangles 5. rectangle, triangle 6. rectangle,

More information

Background and Assumptions

Background and Assumptions 2013 Costs and Returns Estimate Southwest Idaho: Treasure valley Commercial Dry Beans Kathleen Painter Background and Assumptions Southwestern Idaho The University of Idaho s costs and returns estimates

More information

The Assignment Problem

The Assignment Problem CHAPTER 12 The Assignment Problem Basic Concepts Assignment Algorithm The Assignment Problem is another special case of LPP. It occurs when m jobs are to be assigned to n facilities on a one-to-one basis

More information

T H E O T H E R A U D I T W H AT T O D O W H E N T H E A G E N C Y C O M E S K N O C K I N G

T H E O T H E R A U D I T W H AT T O D O W H E N T H E A G E N C Y C O M E S K N O C K I N G T H E O T H E R A U D I T W H AT T O D O W H E N T H E A G E N C Y C O M E S K N O C K I N G AUDIT: THE 5-LETTER CURSE WORD Once upon a midnight dreary, while I pondered, weak and weary, Over many a quaint

More information

What have we learned from the LCLS injector?*

What have we learned from the LCLS injector?* SLAC-PUB-14644 LCLS-TN-11-4 October 19, 2011 What have we learned from the LCLS injector?* Feng Zhou and Axel Brachmann for the LCLS injector team The LCLS injector reliably delivered a high quality electron

More information

lim4 4. By the definition of a limit, there is a positive real number such that if 0 x 2. The largest valid value of is

lim4 4. By the definition of a limit, there is a positive real number such that if 0 x 2. The largest valid value of is ACTM Regional Calculus Competition 017 Begin by removing the three tie breaker sheets at the end of the exam and writing your name on all three pages. Work the multiple-choice questions first, choosing

More information

= cm = 30.5 cm. in. = 39 in. = 380,000. = 150, 000, 000 km. 1 mi. = 1, 800 arcsec

= cm = 30.5 cm. in. = 39 in. = 380,000. = 150, 000, 000 km. 1 mi. = 1, 800 arcsec Chapter 1 Exercise Solutions 1. a) 1 in 2.54 cm or 2.54 cm 1 in b) 1.6 km 1 mi or 1 mi 1.6 km c) 60 arcmin 3600 arcsec or 3600 arcsec 60 arcmin 2. a) 12 in. 2.54 cm 12 2.54 cm 30.5 cm 1 in. b) 100 cm 1

More information

Introduction. Table of contents

Introduction. Table of contents Introduction The advanced manufacturing sector is changing. New innovative and digital technologies are constantly being developed. Today s and tomorrow s employees need the right kind of mathematical

More information

Introduction to LP. Types of Linear Programming. There are five common types of decisions in which LP may play a role

Introduction to LP. Types of Linear Programming. There are five common types of decisions in which LP may play a role Linear Programming RK Jana Lecture Outline Introduction to Linear Programming (LP) Historical Perspective Model Formulation Graphical Solution Method Simplex Method Introduction to LP Continued Today many

More information

IE 316 Exam 1 Fall 2011

IE 316 Exam 1 Fall 2011 IE 316 Exam 1 Fall 2011 I have neither given nor received unauthorized assistance on this exam. Name Signed Date Name Printed 1 1. Suppose the actual diameters x in a batch of steel cylinders are normally

More information

Full file at

Full file at MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. Write each mixed number as an improper fraction. ) 6 2 8 ) 8 C) 2 2 2) 2 2 2) 2 2 C) 28 ) ) 0 2 C)

More information

1. What would be the dose rate of two curies of 60Co with combined energies of 2500 kev given off 100% of the time?

1. What would be the dose rate of two curies of 60Co with combined energies of 2500 kev given off 100% of the time? 1.11 WORKSHEET #1 1. What would be the dose rate of two curies of 60Co with combined energies of 500 kev given off 100% of the time?. What would be the dose rate of 450 mci of 137Cs (gamma yield is 90%)?

More information

Graph the linear inequality. 1) x + 2y 6

Graph the linear inequality. 1) x + 2y 6 Assignment 7.1-7.3 Name MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. Graph the linear inequality. 1) x + 2y 6 1) 1 2) x + y < -3 2) 2 Graph the

More information

M A N U F A C T U R I N G P R O C E S S E S ME A S S I G N M E N T

M A N U F A C T U R I N G P R O C E S S E S ME A S S I G N M E N T H.- J. Steinmetz, Jan. 004 M A N U F A C T U R I N G P R O C E S S E S ME 38.3 A S S I G N M E N T 0 0 4 A machine shop has 15 workers and one shop foreman. The shop has to manufacture a quantity of 800

More information

RATES AND UNIT RATES

RATES AND UNIT RATES RATES AND UNIT RATES 7.. 7.. Rate of change is a ratio that describes how one quantity is changing with respect to another. Unit rate is a rate that compares the change in one quantity to a one-unit change

More information

Section 3.4 Writing the Equation of a Line

Section 3.4 Writing the Equation of a Line Chapter Linear Equations and Functions Section.4 Writing the Equation of a Line Writing Equations of Lines Critical to a thorough understanding of linear equations and functions is the ability to write

More information

INDUSTRIAL INSULATION for Systems Operating Above Ambient Temperature

INDUSTRIAL INSULATION for Systems Operating Above Ambient Temperature INDUSTRIAL INSULATION for Systems Operating Above Ambient Temperature U.S. Department of Energy Energy Efficiency and Renewable Energy Office of Industrial Technologies Washington, D.C. 20585 From September,

More information

Algebra 1 Chapter 1 Test Review

Algebra 1 Chapter 1 Test Review Algebra 1 Chapter 1 Test Review Multiple Choice Identify the choice that best completes the statement or answers the question. 1. Which expression shows 3 less than x? A. B. 3x C. D. 6. Which is a correct

More information

c. (4abc 2 ) 0 6. Solve the following equations, and name the properties used for each step.

c. (4abc 2 ) 0 6. Solve the following equations, and name the properties used for each step. Name: CC Algebra 9H Midterm Review Date:. Simplify the following: (3x + x 3) (x 5x + 7) (9 t t ) (8t + t ). Simplify the following (x + )(3x 8x + ) (x 3) c. (x + ) 3 3. Simplify the following using the

More information

Chapter 7 Forecasting Demand

Chapter 7 Forecasting Demand Chapter 7 Forecasting Demand Aims of the Chapter After reading this chapter you should be able to do the following: discuss the role of forecasting in inventory management; review different approaches

More information

Acquisition of Multi-Function Equipment at DIA: Conditions, Factors, Considerations & Integration. Presented by Mike Carlson September 20, 2012

Acquisition of Multi-Function Equipment at DIA: Conditions, Factors, Considerations & Integration. Presented by Mike Carlson September 20, 2012 Acquisition of Multi-Function Equipment at DIA: Conditions, Factors, Considerations & Integration Presented by Mike Carlson September 20, 2012 1 Denver International Airport 5 Runways 12,000 /. (3,658m)

More information

Algebra 1 STAAR Review Name: Date:

Algebra 1 STAAR Review Name: Date: Algebra 1 STAAR Review Name: Date: 1. Which graph does not represent y as a function of x? I. II. III. A) I only B) II only C) III only D) I and III E) I and II 2. Which expression is equivalent to? 3.

More information

Chapter 13. Manufacturing Models

Chapter 13. Manufacturing Models Chapter 13. anufacturing odels 13.1. anufacturing odels Introduction 13.. anufacturing perations Design Unit Process Concept A unit process is an elemental modification of material or process status done

More information

Multicriteria Decision Making

Multicriteria Decision Making Multicriteria Decision Making Goal Programming Multicriteria Decision Problems Goal Programming Goal Programming: Formulation and Graphical Solution 1 Goal Programming Goal programming may be used to solve

More information

Looking Ahead to Chapter 4

Looking Ahead to Chapter 4 Looking Ahead to Chapter Focus In Chapter, you will learn about functions and function notation, and you will find the domain and range of a function. You will also learn about real numbers and their properties,

More information

Antti Salonen PPU Le 2: Forecasting 1

Antti Salonen PPU Le 2: Forecasting 1 - 2017 1 Forecasting Forecasts are critical inputs to business plans, annual plans, and budgets Finance, human resources, marketing, operations, and supply chain managers need forecasts to plan: output

More information

5/15/18. Operations Research: An Introduction Hamdy A. Taha. Copyright 2011, 2007 by Pearson Education, Inc. All rights reserved.

5/15/18. Operations Research: An Introduction Hamdy A. Taha. Copyright 2011, 2007 by Pearson Education, Inc. All rights reserved. The objective of queuing analysis is to offer a reasonably satisfactory service to waiting customers. Unlike the other tools of OR, queuing theory is not an optimization technique. Rather, it determines

More information

PPU411 Antti Salonen. Forecasting. Forecasting PPU Forecasts are critical inputs to business plans, annual plans, and budgets

PPU411 Antti Salonen. Forecasting. Forecasting PPU Forecasts are critical inputs to business plans, annual plans, and budgets - 2017 1 Forecasting Forecasts are critical inputs to business plans, annual plans, and budgets Finance, human resources, marketing, operations, and supply chain managers need forecasts to plan: output

More information

Antti Salonen KPP Le 3: Forecasting KPP227

Antti Salonen KPP Le 3: Forecasting KPP227 - 2015 1 Forecasting Forecasts are critical inputs to business plans, annual plans, and budgets Finance, human resources, marketing, operations, and supply chain managers need forecasts to plan: output

More information

ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1

ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 SUB:OPERATION RESEARCH CLASS: III B.SC SUB CODE:EMT617S SUB INCHARGE:S.JOHNSON SAVARIMUTHU 2 MARKS QUESTIONS 1. Write the general model of

More information

Polar Sundial. Cut carefully on this line. Cut on this line.

Polar Sundial. Cut carefully on this line. Cut on this line. 1 The Sundial Primer - "Dialling Guides" The purpose of the "Dialling Guides" is to provide an easy method for laying out the hour lines for a number of polar sundials located at any latitude in either

More information

Rational Numbers 2-1. Lesson Objectives. Vocabulary. Additional Examples. Write rational numbers in equivalent forms. rational number (p.

Rational Numbers 2-1. Lesson Objectives. Vocabulary. Additional Examples. Write rational numbers in equivalent forms. rational number (p. LESSON 2-1 Rational Numbers Lesson Objectives Write rational numbers in equivalent forms Vocabulary rational number (p. 6) relatively prime (p. 6) Additional Examples Example 1 Simplify. A. 1 6 0 16 1

More information

5-axis. The Power of Five

5-axis. The Power of Five 5-axis The Power of Five Trunion Machines Swivel Head Machines Machine Axis configuration Standard 3 Axis Operation Setup Time Load Time Cycle Time Description 1 30 min 20 sec 3 min 58 sec Drill top holes

More information

Pre-Test. Name Date. 1. Carolee makes quilts to sell at an arts and crafts fair. She charges $75 per quilt. a. Name the quantity that is constant.

Pre-Test. Name Date. 1. Carolee makes quilts to sell at an arts and crafts fair. She charges $75 per quilt. a. Name the quantity that is constant. Pre-Test Name Date 1. Carolee makes quilts to sell at an arts and crafts fair. She charges $75 per quilt. a. Name the quantity that is constant. b. Which quantity depends on the other? c. Write an algebraic

More information

Chapter 3 Introduction to Linear Programming PART 1. Assoc. Prof. Dr. Arslan M. Örnek

Chapter 3 Introduction to Linear Programming PART 1. Assoc. Prof. Dr. Arslan M. Örnek Chapter 3 Introduction to Linear Programming PART 1 Assoc. Prof. Dr. Arslan M. Örnek http://homes.ieu.edu.tr/~aornek/ise203%20optimization%20i.htm 1 3.1 What Is a Linear Programming Problem? Linear Programming

More information

Programmers A B C D Solution:

Programmers A B C D Solution: P a g e Q: A firm has normally distributed forecast of usage with MAD=0 units. It desires a service level, which limits the stock, out to one order cycle per year. Determine Standard Deviation (SD), if

More information

Multiplying Rational Numbers. ESSENTIAL QUESTION How do you multiply rational numbers?

Multiplying Rational Numbers. ESSENTIAL QUESTION How do you multiply rational numbers? LESSON 1.5 Multiplying Rational Numbers Number and operations 7.3.A Add, subtract, multiply, and divide rational numbers fluently. Also 7.3.B? ESSENTIAL QUESTION How do you multiply rational numbers? Multiplying

More information

Density of Brass: Accuracy and Precision

Density of Brass: Accuracy and Precision Density of Brass: Accuracy and Precision Introduction Density is a measure of a substance s mass-to-volume ratio. For liquids and solids, density is usually expressed in units of g/ml or g/cm 3 ; these

More information

Re: January 27, 2015 Math 080: Final Exam Review Page 1 of 6

Re: January 27, 2015 Math 080: Final Exam Review Page 1 of 6 Re: January 7, 015 Math 080: Final Exam Review Page 1 of 6 Note: If you have difficulty with any of these problems, get help, then go back to the appropriate sections and work more problems! 1. Solve for

More information

b) Rectangular box: length L, width W, height H, volume: V = LWH, cube of side s, V = s 3

b) Rectangular box: length L, width W, height H, volume: V = LWH, cube of side s, V = s 3 Basic Math Review for PHYS 100 - Physics of Everyday Experience ----------------------------------------------------------------------------------------------------- Basic Algebra a) If x = y + z, then:

More information

Paul Patterson Background and Assumptions

Paul Patterson Background and Assumptions 2015 Costs and Returns Estimate Southcentral Idaho: Magic Valley Alfalfa Hay Production Paul Patterson Background and Assumptions Magic Valley The University of Idaho s costs and returns estimates are

More information

REVIEW: HSPA Skills 2 Final Exam June a) y = x + 4 b) y = 2x + 5 c) y = 3x +2 d) y = 2x + 3

REVIEW: HSPA Skills 2 Final Exam June a) y = x + 4 b) y = 2x + 5 c) y = 3x +2 d) y = 2x + 3 Part I- Multiple Choice: 2 points each: Select the best possible answer. 1) The nutrition label of cookies states that there are 20 servings in a box and that one serving contains 1.5 grams of fat. Kyle

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Southcentral Idaho: Magic Valley Alfalfa Hay Production Ben Eborn Magic Valley Background and Assumptions The University of Idaho s costs and returns estimates are based

More information

Winter Break Packet Honors Show ALL WORK DUE JANUARY 5, 2015 xozgimc5

Winter Break Packet Honors Show ALL WORK DUE JANUARY 5, 2015 xozgimc5 Winter Break Packet Honors Show ALL WORK DUE JANUARY 5, 2015 Name: Date: xozgimc5 1. Simplify 27 3 + 4 2 3 2 using the correct order of operations. 1. 2. Simplify: 10 3(5 2) 2. 3. In order to find 4 5

More information

Design and Fabrication of Indexing Set Up for Drill Jig

Design and Fabrication of Indexing Set Up for Drill Jig Design and Fabrication of Indexing Set Up for Drill Jig Sangamesh 1, V. V. Kulkarni 2, 1pg scholar & dept. of mechanical engg, dept. of machine design K.L.S. Gogte institute of technology belagavi 2Prof.

More information

PSSA Released Items 16 Multiple Choice Questions, 1 Open-Ended Response

PSSA Released Items 16 Multiple Choice Questions, 1 Open-Ended Response Page 1 of 21 2016-2017 PSSA Released Items 16 Multiple Choice Questions, 1 Open-Ended Response Directions Do not use a calculator. You may refer to the formula sheet shown below. Show your work on this

More information

MATHEMATICS: PAPER I

MATHEMATICS: PAPER I NATIONAL SENIOR CERTIFICATE EXAMINATION NOVEMBER 017 MATHEMATICS: PAPER I Time: 3 hours 150 marks PLEASE READ THE FOLLOWING INSTRUCTIONS CAREFULLY 1. This question paper consists of 11 pages and an Information

More information

Ready To Go On? Skills Intervention 2-1 Solving Equations by Adding or Subtracting

Ready To Go On? Skills Intervention 2-1 Solving Equations by Adding or Subtracting Ready To Go On? Skills Intervention 2-1 Solving Equations by Adding or Subtracting Find these vocabulary words in Lesson 2-1 and the Multilingual Glossary. Vocabulary equation solution of an equation Solve

More information

Basic Bakery Calculations. A Primer

Basic Bakery Calculations. A Primer Basic Bakery Calcula.ons Basic Bakery Calculations A Primer Basic Bakery Calcula.ons A Primer 1: a small book for teaching children to read 2: a small introductory book on a subject 3: a short informa9ve

More information

Background and Assumptions

Background and Assumptions 2017 Costs and Returns Estimate Eastern Idaho: Lower Rainfall Dryland Feed Barley Ben Eborn and Terrell Sorensen Eastern Idaho Background and Assumptions The University of Idaho s costs and returns estimates

More information

Units and Dimensional Analysis

Units and Dimensional Analysis LESSON Units and Dimensional Analysis UNDERSTAND When solving a problem, it is important to correctly identify the units being considered or measured. This may require converting a quantity given in one

More information

Year 6 Problem Solving Part 2

Year 6 Problem Solving Part 2 Yimin Math Centre Year 6 Problem Solving Part 2 Student Name: Grade: Date: Score: Table of Contents 4 Problem Solving Part 4 1 4.1 Clock Problem...................................... 1 4.2 Book Problem.......................................

More information

Winter-Break Packet 7 th grade mathematics

Winter-Break Packet 7 th grade mathematics M.S. 181 PABLO CASALS CHRISTOPHER WARNOCK, PRINCIPAL 800 BAYCHESTER AVENUE, BRONX, NY 10475 PHONE: 718-904-5600 Conceive, it, Believe it, Achieve it! Winter-Break Packet 7 th grade mathematics Student:

More information

Exercises Stochastic Performance Modelling. Hamilton Institute, Summer 2010

Exercises Stochastic Performance Modelling. Hamilton Institute, Summer 2010 Exercises Stochastic Performance Modelling Hamilton Institute, Summer Instruction Exercise Let X be a non-negative random variable with E[X ]

More information

v ( t ) = 5t 8, 0 t 3

v ( t ) = 5t 8, 0 t 3 Use the Fundamental Theorem of Calculus to evaluate the integral. 27 d 8 2 Use the Fundamental Theorem of Calculus to evaluate the integral. 6 cos d 6 The area of the region that lies to the right of the

More information

Integer Programming Part II

Integer Programming Part II Be the first in your neighborhood to master this delightful little algorithm. Integer Programming Part II The Branch and Bound Algorithm learn about fathoming, bounding, branching, pruning, and much more!

More information

BOXED BEAM ROLL FORMING MACHINE

BOXED BEAM ROLL FORMING MACHINE BOXED BEAM ROLL FORMING MACHINE R O L L F O R M E R S U S A I W W W. R O L L F O R M E R S - U S A. C O M Page1 R O L L F O R M E R S U S A I W W W. R O L L F O R M E R S - U S A. C O M Page2 Cantilevered

More information

Section 1.3: A Simple Inventory System

Section 1.3: A Simple Inventory System Section 1.3: A Simple Inventory System Discrete-Event Simulation: A First Course c 2006 Pearson Ed., Inc. 0-13-142917-5 Discrete-Event Simulation: A First Course Section 1.3: A Simple Inventory System

More information

Mapping the Badlands. Surveying and GIS Just Got Easier. >> By Deral Paulk, LS

Mapping the Badlands. Surveying and GIS Just Got Easier. >> By Deral Paulk, LS $4.95 Mapping the Badlands Surveying and GIS Just Got Easier Surveying and mapping here in southwestern Oklahoma can be a challenge. It s a rough-hewn landscape with rugged terrain features and plenty

More information

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology Chapter 2 Planning Criteria By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Outline 1- Introduction 2- System Adequacy and Security 3- Planning Purposes 4- Planning Standards 5- Reliability

More information

Demand Forecasting Models

Demand Forecasting Models E 2017 PSE Integrated Resource Plan Demand Forecasting Models This appendix describes the econometric models used in creating the demand forecasts for PSE s 2017 IRP analysis. Contents 1. ELECTRIC BILLED

More information

STUDENT JOURNAL Week 5 Metric System Application

STUDENT JOURNAL Week 5 Metric System Application Name: Period: STUDENT JOURNAL Week 5 Metric System Application Overarching Goal for the Week: Become familiar with scientific instruments Apply knowledge of the metric system and instruments to practical

More information

Inequalities with the Variable on Both Sides 8.8.A

Inequalities with the Variable on Both Sides 8.8.A ? LESSON 11.3 ESSENTIAL QUESTION Inequalities with the Variable on Both Sides How can you use inequalities to represent real-world problems? Expressions, equations, and relationships 8.8.A Write one-variable

More information

LINEAR EQUATIONS Modeling Linear Equations Common Core Standards

LINEAR EQUATIONS Modeling Linear Equations Common Core Standards E Linear Equations, Lesson 1, Modeling Linear Functions (r. 2018) LINEAR EQUATIONS Modeling Linear Equations Common Core Standards F-BF.A.1 Write a function that describes a relationship between two quantities.

More information

Archway Learning Trust. Mathematics Department. Year 11 Mock 2 (February 2019) Foundation Tier. Paper 2. Name: Teacher:

Archway Learning Trust. Mathematics Department. Year 11 Mock 2 (February 2019) Foundation Tier. Paper 2. Name: Teacher: Name: Teacher: Archway Learning Trust Mathematics Department Year 11 Mock 2 (February 2019) Foundation Tier Paper 2 Materials: For this paper you must have: A scientific calculator Mathematical instruments

More information