Probabilistic production cost simulation. EG2200 Lectures 12 14, autumn 2015 Mikael Amelin

Size: px
Start display at page:

Download "Probabilistic production cost simulation. EG2200 Lectures 12 14, autumn 2015 Mikael Amelin"

Transcription

1 Probabilistic production cost simulation EG2200 Lectures 12 14, autumn 2015 Mikael Amelin 1

2 Course objectives Apply probabilistic production cost simulation to calculate the expected operation cost and risk of power deficit in an electricity market, and to use the results of a simulation to judge the consequences of various actions in the electricity market. 2

3 Probabilistic production cost simulation (PPC) Development started in the late 1960s. Analytical method. Limited possibilities to consider the electricity market in detail. 3

4 Electricity market model Assume Perfect competition Perfect information Load is not price sensitive Neglect grid losses and limitations Neglect start-up costs and ramp rate limitations All inputs are independent (Some of these assumptions can be avoided with clever modelling.) 4

5 Calculation of system indices Basic concept Assume all power plants have 100% availability. System indices can then be calculated directly from the load duration curve (LDC). Example Known load duration curve. Two power plants, 300 MW each, always available, variable operation costs 1 and 2 respectively,

6 Calculation of system indices Basic concept LOLP = LDC(600) = 876 h/year = 10%. h/year 8760 LDC LOLP x MW 6

7 Calculation of system indices Basic concept EENS = 600 LDCxdx. h/year 8760 LDC EENS x MW 7

8 Calculation of system indices Basic concept ETOC = 1 EG EG 2 Perfect competion Unit 1 is used first as 1 2 h/year LDC 8760 EG 1 EG x MW 8

9 Load model We only consider the total load of the system. The load is assumed to be price insensitive. - The load is modelled by one input, D. - The probability distribution of the load is represented by a duration curve. 9

10 Load model How is the load duration curve determined? The probability distribution of the load cannot be computed but must be estimated from historical data and forecasts for the future. Alternative 1. Use a standard probability distribution (for example the normal distribution) with the same statistical properties as historical data. Alternative 2. Create a duration curve directly from historical data (or forecasts). 10

11 Load model Duration curve from historical data Definition The load curve states the load at a certain time, i.e., D(k) = load hour k [MWh/h]. Definition The real load duration curve states the load level that is exceeded for a certain time, i.e., LDC R (k) = load level that is exceeded during k hours [MWh/h]. 11

12 Load model Duration curve from historical data Exempel 6.9: MWh/h D(k) E[D] = MWh/day h The expectation value of the load is equal to the area below the load curve. k 12

13 Load model Duration curve from historical data Exempel 6.9: MWh/h D(k), LDC R (k) E[D] = MWh/day h The area below the real duration curve is as large as the area below the load curve. k 13

14 Load model Duration curve from historical data Definition The inverted load duration curve states how long time a certain load level is exceeded, i.e., LDC(x) = number of hours when the load is exceeding x [h]. Dividing LDC(x) by the length of the studied time period, T, gives the normalised load duration curve. The normalised duration curve states the probability that a certain load level is exceeded (cf. definition C.3). 14

15 Load model Duration curve from historical data Exempel 6.10: h LDC(x) E[D] = MWh/day MWh/h We have only switched the y and x axes; hence, the area below the curve has not changed. x 15

16 Load model Duration curve from historical data Exempel 6.10: % F D MWh/h Now, the y-axis has been scaled by 1/T; the expected load is therefore the area below the curve multiplied by T. x 16

17 Load model Discrete approximation The load is in reality a continuous random variable. To compute expected energy etc. we need to integrate the load duration curve, which in general will be done using numerical methods. It might therefore be necessary to use a discrete approximation of the probability distribution of the load. 17

18 Load model Discrete approximation % F D x MWh/h 18

19 Model of thermal power plants The following properties are included in the model of thermal power plants: Installed capacity, Ĝ g. - Ramp rates are neglected. Generation cost, C Gg (G g ) = + G g. - The variable cost is independent of generation level, i.e., constant efficiency. - Start-up costs are neglected. Availability, p g. Moreover, it is assumed that failures are independent of the load and the state of other power plants. 19

20 Model of thermal power plants A thermal power plant is modelled by one input, G g (available generation capacity) and a constant variable operation cost, Gg. It is assumed that the available generation capacity has a two-point distribution. F Gg p g q g x 0 Ĝ g MW 20

21 Model of thermal power plants How are the parameters of the two point distribution determined? The probability distribution of the available generation capacity cannot be computed but must be estimated from historical data and forecasts for the future. 21

22 Model of thermal power plants Availability from historical data Definition The Mean Time To Failure is calculated by MTTF = K t K u k, k = 1 where K are the number of periods when the power plant is available and t u (k) is the duration of each of these periods. 22

23 Model of thermal power plants Availability from historical data Definition The Mean Time To Repair is calculated by MTTR = K t K d k, k = 1 where K are the number of periods when the power plant is unavailable and t d (k) is the duration of each of these periods. 23

24 Model of thermal power plants Availability from historical data Definition The failure rate is the probability that an available unit will fail and can be estimated by = MTTF Definition The repair rate is the probability that an unavailable unit will be repaired and can be estimated by = MTTR 24

25 Model of thermal power plants Availability from historical data Definition The availability is the probability that a power plant will be available and can be estimated as the share of a longer time period during which the unit is available: MTTF p = = = MTTF + MTTR Definition The unavailability is the probability that a power plant will be unavailable and can be estimated by q = 1 p = MTTR = MTTF + MTTR

26 Model of thermal power plants Availability and utilisation Availability. Probability that a power plant can be used. Capacity factor. The average available capacity divided by the installed capacity. 1 capacity factor = TĜ T t = 1 G t. Utilisation factor. The average real generation divided by the installed capacity. 1 utilisation factor = capacity factor. TĜ T t = 1 G t Full load hours. The number of hours a unit would be able generate its full capacity without exceeding the real annual generation. full load hours = 1 Ĝ --- T t = 1 G t = T utilisation factor. 26

27 Equivalent load We have seen that it is straightforward to compute the system indices in a power system where all power plants have 100% availability. What do we do if this is not the case? Brilliant idea: Consider outages in power plants as load increase instead of lower available generation capacity. 27

28 Equivalent load Definition The equivalent load is given by E g = D + O k, where g k = 1 E g = equivlanet load seen by power plant g +1, D = real load, O k = outage in power plant k. 28

29 Equivalent load Example MWh/h D(k) MWh/h E 2 (k) k k h h D E 2 G 1 G 1 + G 2 29

30 Calculation of system indices The system indices LOLP, EENS and ETOC can be computed from the equivalent load duration curve, Introduce the symbols F g x. g g g Gtot g = G k, Ĝtot = Ĝ and Otot = O. g k g k k = 1 k = 1 k = 1 30

31 Calculation of system indices Risk of power deficit Power deficit occurs when the load is higher than the available generation capacity, i.e., LOLP g = PD = PD Ĝtot g Otot g = G g tot PD + Otot g Ĝ = PE g Ĝ = F gĝtot g. g tot g tot 31

32 Calculation of system indices Unserved energy Everything to the right of in the equivalent load duration curve corresponds to load that cannot be served due to power deficit. Ĝ g tot EENS g = T Ĝ g tot F gxdx. Remember to scale by the time period considered see page 16! 32

33 Calculation of system indices Expected generation Remember that in the equivalent load we are assuming that all power plants are always available and add load instead. The expected generation can therefore not be computed directly from the equivalent load duration curve. However, it can be computed indirectly by comparing the unserved energy with and without a power plant: EG g = EENS g 1 EENS g. 33

34 Calculation of system indices Expected generation For two-state generating units, the expected generation of power plant g can be computed directly from : F g 1 x EG g = Ĝ g tot T p g F g 1xdx. tot Ĝ g 1 34

35 Calculation of system indices Expected total operation cost The expected total operation cost is computed from the expected generation in each power plant: ETOC g = g k = 1 k EG k. If there is a cost for load that is disconnected then that can be included as well: ETOC g = g k = 1 k EG k + U EENS g. 35

36 Calculation of system indices Example Run-of-the river hydro (500 kw, 0 /kwh, 100% availability). Diesel generator set (200 kw, 1 /kwh, 90% availability). Load (N(400,80)-distributed, not price sensitive). 36

37 Calculation of system indices Example F 0 F 1 A = 100 A = 99,84 A = 96,11 A = 72,12 A = 27,87 A = 3,89 A = 0, kw A = 0 x EENS 1 = 1 F 1xdx 500 = = 4.05 kwh/h. 37

38 Calculation of system indices Example F 2 A = 100 A = 99,86 A = 96,50 A = 74,90 A = 34,69 A = 10,71 A = 2,93 A = 0,39 A = 0,02 A = 0 x kw EENS 2 = 1 F 2xdx 700 = = 0.41 kwh/h. 38

39 Calculation of system indices Example 1 F A = 100 A = 99,86 A = 96,50 A = 74,90 A = 34,69 A = 10,71 A = 2,93 A = 0,39 A = 0,02 A = 0 x kw LOLP = F %. EG 2 = EENS 1 EENS 2 = = 3.64 kwh/h. ETOC = 1 EG 2 = 3.64 /h. 39

40 Equivalent load duration curve Derivation F gx = P(E g > x) = P(D + O O g 1 + O g > x). The probability distribution of a sum of independent random variables can be computed using convolution. The formula for computing equivalent load duration curves can also be understood as follows: - Assume that the equivalent load duration curve without power plant g, F g 1x, is known. - What is the probability that the equivalent load exceeds x if power plant g is available? - What is the probability that the equivalent load exceeds x if power plant g is unavailable? - Combine the results. 40

41 Equivalent load duration curve Derivation Power plant g is available E g = D + O O g 1 + O g. O g = 0 E g = D + O O g 1 = E g 1. Hence, PE g x G g = Ĝ g = P(E g 1 > x) = F g 1x. 41

42 Equivalent load duration curve Derivation Power plant g is unavailable E g = D + O O g 1 + O g. O g = Ĝ g E g = D + O O g 1 + Ĝ g = E g 1 + Ĝ g. Hence, PE g x G g = 0 Ĝ g = P(E g 1 + > x) = = P(E g 1 > x Ĝ g ) = F g 1x Ĝ g. 42

43 Equivalent load duration curve Derivation The probability that the equivalent load exceeds x is then P(E g > x) = p g PE g x + q g PE g x = G g = Ĝ g G g = 0 = F gx = p g F g 1x + q g F g 1x Ĝ g. The formula above is an example of a convolution formula. Starting from the load duration curve, F 0x (which is an input to the simulation), the equivalent load duration curves can be computed by adding one power plant at a time. Power plants should be added according to merit order, i.e., according to increasing variable costs (as we assume perfect competition). 43

44 Probabilistic production cost simulation Example I Problem description Load kwh/h Mon Fri 5 19, Sat Sun kwh/h all other times Power plants - Diesel generator set 150 kwh/h, 90% availability, 10 /kwh. - Diesel generator set 100 kwh/h, 80% availability, 12 /kwh. Compute ETOC and LOLP. 44

45 Probabilistic production cost simulation Example I Solution The frequency function of the load can be computed from the given data: = 0.5 x = 100, f 0 (x) = P(D = x) = = 0.5 x = 200, 0 all other x. From theorem C.4 we then have F 0x = f 0 t = t x = 1 x 100, x 200, x. 45

46 Probabilistic production cost simulation Example I % EENS 0 = f 0 x F 0 x kwh/h 1 F 0xdx 0 = = 150 kwh/h. x 46

47 Probabilistic production cost simulation Example I The larger diesel generator set is first in the merit order: F 1x = 0. F 0x + 0. F 0x 150 = = = = = = x 100, 100 x 200, 200 x 250, 250 x 350, 350 x. 47

48 Probabilistic production cost simulation Example I % F 0x F 1x x kwh/h EENS 1 = 1 F 1xdx = = 150 = 37.5 kwh/h. 48

49 Probabilistic production cost simulation Example I Next, we add the smaller diesel generator set: F 2x = 0.8 F 1x + 0. F 1x 100 = = 1 x 100, = x 200, = x 250, = = x 300, = x 350, = x 450, x. 49

50 Probabilistic production cost simulation Example I % F 0x F 1x F 2x x kwh/h EENS 2 = 1 F 2xdx = = 250 = 11.5 kwh/h. 50

51 Probabilistic production cost simulation Example I EG 1 = EENS 0 EENS 1 = kwh/h EG 2 = EENS 1 EENS 2 = 26.0 kwh/h ETOC = 10EG EG 2 = /h LOLP = F 2250 = 15% 51

52 Model of wind power The following properties are included in the model of wind power plants: Installed capacity, Ŵ n. Generation cost, C Wn (W n ) = + W n. - The variable cost is generally negligible. Availability, p. Wind speed distribution, F v. Moreover, it is assumed that failures and wind speed are independent of each other as well as of the load and the state of other power plants. 52

53 Model of wind power A wind power plant or a wind farm (i.e., a group of wind power plants) can be represented by a single input, W n (available generation capacity) and a constant variable operation cost, Wn (which can generally be assumed as zero). The density function for W n can be computed by combining the probability distribution of the wind speed by the power curve (the wind power generation as a function of wind speed), i.e., W n v. - See the course compendium for details. 53

54 Model of wind power The probability distribution of the wind speed must be estimated from historical data or forecasts (similar to the probability distribution of the load). A standard probability distributions that is commonly used for wind speeds is the Rayleigh distribution. f v F v low v v = mean wind speed high v x low v high v x m/s m/s 54

55 Model of wind power The power curve depends on the type of wind power plant. Pitch control Stall control kw W(v) kw W(v) v m/s v m/s 55

56 Model of wind power Discrete approximation The available wind power generation capacity is a continuous random variable. To apply the convolution formula it is preferable to have a discrete probability distribution. It is therefore preferable to use a discrete approximation of the probability distribution of the available wind power generation capacity. 56

57 Model of wind power Discrete approximation f W x x Ŵ kw 57

58 Equivalent load duration curve General formula The convolution formula for the equivalent load duration curve can be generalised as follows: F gx = N g p gi F g 1 i = 1 x x g i, where N g = number of states for power plant g, p g, i = f G G = = probability of state i, g g f G Ĝ g x g g i x g, i = outage (compared to installed capacity) in state i. 58

59 Equivalent load duration curve General formula Verification for thermal power plants: N g = 2 p g, 1 = p g, x g, 1 = 0 p g, 2 = q g, x g, 2 = Ĝ g Using these values in the general formula for the equivalent load duration curve yields F gx = N g p gi F g 1 i = 1 x x g i = p g F g 1x+ q g F g 1x Ĝ g, i.e., the same expression as we used earlier. = 59

60 Probabilistic production cost simulation Example II Problem description Load kwh/h Mon Fri 5 19, Sat Sun kwh/h all other times Power plants - Diesel generator set 150 kwh/h, 90% availability, 10 /kwh. - Diesel generator set 100 kwh/h, 80% availability, 12 /kwh. - Wind power plant 100 kwh/h (20%), 50 kwh/h (30%), 0 kwh/h (50%), negligible variable costs. Compute ETOC and LOLP. 60

61 Probabilistic production cost simulation Example II Solution The load duration curve, F 0x, is the same as in example I. The first power plant in the merit order is now the wind power plant. Model of the wind power plant: - N 1 = 3 - p 1, 1 = 0.2, x 1, 1 = 0 - p 1, 2 = 0.3, x 1, 2 = 50 - p 1, 3 = 0.5, x 1, 3 =

62 Probabilistic production cost simulation Example II F 1x = 0.2 F 0x + 0. F 0x F 0x 100 = = = = = = = x 100, 100 x 150, 150 x 200, 200 x 250, 250 x 300, 300 x. 62

63 Probabilistic production cost simulation Example II % F 0x F 1x kwh/h G EENS 1 = 1 F 1xdx = = 100 = 115 kwh/h. x 63

64 Probabilistic production cost simulation Example II F 2x = 0. F 1x + 0. F 1x 150 = = = 1 x 100, = x 150, = x 200, = x 250, = x 300, = x 350, = x 400, = x 450, x. 64

65 Probabilistic production cost simulation Example II % F 0x F 1x F 2x kwh/h EENS 2 = 1 F 2xdx = 250 = = kwh/h. x G 65

66 Probabilistic production cost simulation Example II F 3x = 0.8 F 2x + 0. F 2x 100 = = = 1 x 100, = x 150, = x 200, = x 250, = x 300, 66

67 Probabilistic production cost simulation Example II = = = = = = x 350, 350 x 400, 400 x 450, 450 x 500, 500 x 550, 550 x. 67

68 Probabilistic production cost simulation Example II % F 0x F 1x F 2x F 3x kwh/h EENS 3 = 1 F 3xdx = 350 = = 7.15 kwh/h. x G 68

69 Probabilistic production cost simulation Example II EG 2 = EENS 1 EENS 2 = kwh/h EG 3 = EENS 2 EENS 3 = 15.6 kwh/h ETOC = 10EG EG 3 = /h LOLP = F 3350 = 9.5% 69

70 Wind power Correlation between wind power generation and load Available wind power generation, W, and demand, D, are both depending on weather conditions and might thus be correlated. Annual variations. Some seasons are more windy and colder than others. - Cold weather low load in warm countries. - Warm weather high load in cold countries. Daily variations. More windy and lower load during night time. Special variations. Windy and cold increased load in buildings with electric heating. 70

71 Example: Daily variations Problem Day time 7:00-21:00, night time 21:00-7:00. Load - Day time: 250 kw (10%), 200 kw (30%), 150 kw (30%), 100 kw (30%) - Night time: 150 kw (20%), 100 kw, (40%), 50 kw (40%) Diesel generator set 200 kw, 95% availability Wind power - Day time: 200 kw (30%), 100 kw (40%), 0 kw (30%) - Night time: 200 kw (40%), 100 kw (50%), 0 kw (10%) 71

72 Example: Daily variations Solution % F 0 day F night 0 x kwh/h G 72

73 Example: Daily variations Solution Compute LOLP for day time: LOLP day = F 2400 = 0. F F = 0.(0. F F F ) (0.3 F F F ) = 0.95( ) ( ) = = 5.9%. 73

74 Example: Daily variations Solution Compute LOLP for night time: LOLP night = = 2.%. To compute the system LOLP regardless of time, the results above are weighted according to the duration of the corresponding time period: 14 day 10 LOLP = -----LOLP LOLP night = 4.5%

RTO Winter Resource Adequacy Assessment Status Report

RTO Winter Resource Adequacy Assessment Status Report RTO Winter Resource Adequacy Assessment Status Report RAAS 03/31/2017 Background Analysis performed in response to Winter Season Resource Adequacy and Capacity Requirements problem statement. Per CP rules,

More information

APPENDIX 7.4 Capacity Value of Wind Resources

APPENDIX 7.4 Capacity Value of Wind Resources APPENDIX 7.4 Capacity Value of Wind Resources This page is intentionally left blank. Capacity Value of Wind Resources In analyzing wind resources, it is important to distinguish the difference between

More information

Monte Carlo Simulation in Engineering

Monte Carlo Simulation in Engineering Monte Carlo Simulation in Engineering Mikael Amelin Draft version KTH Royal Institute of Technology Electric Power Systems Stockholm 203 PREFACE This compium describes how Monte Carlo methods can be applied

More information

A PROBABILISTIC MODEL FOR POWER GENERATION ADEQUACY EVALUATION

A PROBABILISTIC MODEL FOR POWER GENERATION ADEQUACY EVALUATION A PROBABILISTIC MODEL FOR POWER GENERATION ADEQUACY EVALUATION CIPRIAN NEMEŞ, FLORIN MUNTEANU Key words: Power generating system, Interference model, Monte Carlo simulation. The basic function of a modern

More information

Bringing Renewables to the Grid. John Dumas Director Wholesale Market Operations ERCOT

Bringing Renewables to the Grid. John Dumas Director Wholesale Market Operations ERCOT Bringing Renewables to the Grid John Dumas Director Wholesale Market Operations ERCOT 2011 Summer Seminar August 2, 2011 Quick Overview of ERCOT The ERCOT Market covers ~85% of Texas overall power usage

More information

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas Renewables and the Smart Grid Trip Doggett President & CEO Electric Reliability Council of Texas North American Interconnected Grids The ERCOT Region is one of 3 North American grid interconnections. The

More information

The Spatial Analysis of Wind Power on Nodal Prices in New Zealand

The Spatial Analysis of Wind Power on Nodal Prices in New Zealand The Spatial Analysis of Wind Power on Nodal Prices in New Zealand Le Wen Research Fellow Energy Centre The University of Auckland l.wen@auckland.ac.nz 1974 1975 1976 1977 1978 1979 1980 1981 1982 1983

More information

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology Chapter 2 Planning Criteria By Turaj Amraee Fall 2012 K.N.Toosi University of Technology Outline 1- Introduction 2- System Adequacy and Security 3- Planning Purposes 4- Planning Standards 5- Reliability

More information

Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, Wind Power Forecasting tools and methodologies

Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, Wind Power Forecasting tools and methodologies Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, 2011 Wind Power Forecasting tools and methodologies Amanda Kelly Principal Engineer Power System Operational Planning Operations

More information

UPDATE ELECTRICITY STATEMENT OF OPPORTUNITIES FOR THE NATIONAL ELECTRICITY MARKET

UPDATE ELECTRICITY STATEMENT OF OPPORTUNITIES FOR THE NATIONAL ELECTRICITY MARKET UPDATE ELECTRICITY STATEMENT OF OPPORTUNITIES FOR THE NATIONAL ELECTRICITY MARKET Published: 26 October 2015 ELECTRICITY STATEMENT OF OPPORTUNITIES IMPORTANT NOTICE Purpose AEMO publishes the Electricity

More information

Total Market Demand Wed Jan 02 Thu Jan 03 Fri Jan 04 Sat Jan 05 Sun Jan 06 Mon Jan 07 Tue Jan 08

Total Market Demand Wed Jan 02 Thu Jan 03 Fri Jan 04 Sat Jan 05 Sun Jan 06 Mon Jan 07 Tue Jan 08 MW This report provides a summary of key market data from the IESO-administered markets. It is intended to provide a quick reference for all market stakeholders. It is composed of two sections: Section

More information

Comparing Variance Reduction Techniques for Monte Carlo Simulation of Trading and Security in a Three-Area Power System

Comparing Variance Reduction Techniques for Monte Carlo Simulation of Trading and Security in a Three-Area Power System Comparing Variance Reduction Techniques for Monte Carlo Simulation of Trading and Security in a Three-Area Power System Magnus Perninge Email: magnus.perninge@ee.kth.se Mikael Amelin Email: mikael.amelin@ee.kth.se

More information

Wind power and management of the electric system. EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015

Wind power and management of the electric system. EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015 Wind power and management of the electric system EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015 HOW WIND ENERGY IS TAKEN INTO ACCOUNT WHEN MANAGING ELECTRICITY TRANSMISSION SYSTEM IN FRANCE?

More information

Recent US Wind Integration Experience

Recent US Wind Integration Experience Wind Energy and Grid Integration Recent US Wind Integration Experience J. Charles Smith Nexgen Energy LLC Utility Wind Integration Group January 24-25, 2006 Madrid, Spain Outline of Topics Building and

More information

LECTURE 22 WIND POWER SYSTEMS. ECE 371 Sustainable Energy Systems

LECTURE 22 WIND POWER SYSTEMS. ECE 371 Sustainable Energy Systems LECTURE 22 WIND POWER SYSTEMS ECE 71 Sustainable Energy Systems 1 AVG POWER IN WIND WITH RAYLEIGH STATISTICS The average value of the cube of wind speed can be calculated with Raleigh probability density

More information

FORECAST ACCURACY REPORT 2017 FOR THE 2016 NATIONAL ELECTRICITY FORECASTING REPORT

FORECAST ACCURACY REPORT 2017 FOR THE 2016 NATIONAL ELECTRICITY FORECASTING REPORT FORECAST ACCURACY REPORT 2017 FOR THE 2016 NATIONAL ELECTRICITY FORECASTING REPORT Published: November 2017 Purpose The National Electricity Rules (Rules) require AEMO to report to the Reliability Panel

More information

Capacity Scarcity Condition Monday, September 3, 2018 Two primary factors led to the implementation of OP 4 event Significant generation outages and r

Capacity Scarcity Condition Monday, September 3, 2018 Two primary factors led to the implementation of OP 4 event Significant generation outages and r S E P T E M B E R 1 2, 2 0 1 8 September 3 OP-4 Event and Capacity Scarcity Condition Vamsi Chadalavada E X E C U T I V E V I C E P R E S I D E N T A N D C H I E F O P E R A T I N G O F F I C E R Capacity

More information

California Independent System Operator (CAISO) Challenges and Solutions

California Independent System Operator (CAISO) Challenges and Solutions California Independent System Operator (CAISO) Challenges and Solutions Presented by Brian Cummins Manager, Energy Management Systems - CAISO California ISO by the numbers 65,225 MW of power plant capacity

More information

WIND energy has become a mature technology and has

WIND energy has become a mature technology and has 1 Short-term wind power prediction based on models Mario J. Durán, Daniel Cros and Jesus Riquelme Electrical Engineering Department Universidad de Sevilla Abstract The wind power penetration increase and

More information

About Nnergix +2, More than 2,5 GW forecasted. Forecasting in 5 countries. 4 predictive technologies. More than power facilities

About Nnergix +2, More than 2,5 GW forecasted. Forecasting in 5 countries. 4 predictive technologies. More than power facilities About Nnergix +2,5 5 4 +20.000 More than 2,5 GW forecasted Forecasting in 5 countries 4 predictive technologies More than 20.000 power facilities Nnergix s Timeline 2012 First Solar Photovoltaic energy

More information

PROJECT ECONOMIC ANALYSIS

PROJECT ECONOMIC ANALYSIS Electricity Transmission Expansion and Supply Improvement Project (RRP NEP 41155) PROJECT ECONOMIC ANALYSIS A. Overview 1. The economic analysis undertaken for the Electricity Transmission and Supply Improvement

More information

EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY

EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY EVALUATION OF WIND ENERGY SOURCES INFLUENCE ON COMPOSITE GENERATION AND TRANSMISSION SYSTEMS RELIABILITY Carmen Lucia Tancredo Borges João Paulo Galvão carmen@dee.ufrj.br joaopaulo@mercados.com.br Federal

More information

Analysis and Comparison of Risk and Load Point Indices of Power System Model HLI and HLII

Analysis and Comparison of Risk and Load Point Indices of Power System Model HLI and HLII Analysis and Comparison of Risk and Load Point Indices of Power System Model HLI and HLII L.B. Rana and N.Karki Abstract Aim of this work is to evaluate risk analysis of the Electrical Power Network with

More information

-Assessment of current water conditions. - Precipitation Forecast. - Recommendations for Drought Monitor

-Assessment of current water conditions. - Precipitation Forecast. - Recommendations for Drought Monitor April 27, 2010 -Assessment of current water conditions - Precipitation Forecast - Recommendations for Drought Monitor 7 Day Precipitation 19-25 April 2010 Month-to-Date Precipitation 1-25 April 2010

More information

Average Cold Spell Methodology

Average Cold Spell Methodology Average Cold Spell Methodology Introduction This document is being written under Special Condition 4L.12 (Financial incentives on EMR) of National Grid Electricity Transmission plc s Electricity Transmission

More information

A possible notion of short-term value-based reliability

A possible notion of short-term value-based reliability Energy Laboratory MIT EL 1-13 WP Massachusetts Institute of Technology A possible notion of short-term value-based reliability August 21 A possible notion of short-term value-based reliability Yong TYoon,

More information

Energy Forecasting Customers: Analysing end users requirements Dec 3rd, 2013 Carlos Alberto Castaño, PhD Head of R&D

Energy Forecasting Customers: Analysing end users requirements Dec 3rd, 2013 Carlos Alberto Castaño, PhD Head of R&D IT Solutions for Renewables Energy Forecasting Customers: Analysing end users requirements Dec 3rd, 2013 Carlos Alberto Castaño, PhD Head of R&D carlos.castano@gnarum.com I. Who we are II. Customers Profiles

More information

LOOP frequency estimates due to external events

LOOP frequency estimates due to external events LOOP frequency estimates due to external events PSAM 14 Conference, 17.9.2018 Mikael Biese, Nuclear Safety Engineer 1 Agenda 1 2 3 4 SITE CHARACTERISTICS METHODOLOGY FREQUENCY EVALUATION SUMMARY 2 Site

More information

Mathematics - Course 121 THE BINOMIAL DISTRIBUTION AND POWER SYSTEM RELIABILITY

Mathematics - Course 121 THE BINOMIAL DISTRIBUTION AND POWER SYSTEM RELIABILITY Mathematics - Course 121 THE BINOMIAL DISTRIBUTION AND POWER SYSTEM RELIABILITY I THE BINOMIAL DISTRIBUTION Recall (from 121.00-3) that the number of different combinations of r objects which can be formed

More information

SYSTEM BRIEF DAILY SUMMARY

SYSTEM BRIEF DAILY SUMMARY SYSTEM BRIEF DAILY SUMMARY * ANNUAL MaxTemp NEL (MWH) Hr Ending Hr Ending LOAD (PEAK HOURS 7:00 AM TO 10:00 PM MON-SAT) ENERGY (MWH) INCREMENTAL COST DAY DATE Civic TOTAL MAXIMUM @Max MINIMUM @Min FACTOR

More information

Confronting Climate Change in the Great Lakes Region. Technical Appendix Climate Change Projections EXTREME EVENTS

Confronting Climate Change in the Great Lakes Region. Technical Appendix Climate Change Projections EXTREME EVENTS Confronting Climate Change in the Great Lakes Region Technical Appendix Climate Change Projections EXTREME EVENTS Human health and well-being, as well as energy requirements, building standards, agriculture

More information

It is never so good as expected and never so bad as feared.

It is never so good as expected and never so bad as feared. 2018 General: The weather conditions in the Baltics and Scandinavia have not been perfect - not enough rain and high temperatures after drilling. As Scandinavia and Baltics was the area where there was

More information

Battery Energy Storage

Battery Energy Storage Battery Energy Storage Implications for Load Shapes and Forecasting April 28, 2017 TOPICS» What is Energy Storage» Storage Market, Costs, Regulatory Background» Behind the Meter (BTM) Battery Storage Where

More information

Modelling wind power in unit commitment models

Modelling wind power in unit commitment models Modelling wind power in unit commitment models Grid integration session IEA Wind Task 25 Methodologies to estimate wind power impacts to power systems Juha Kiviluoma, Hannele Holttinen, VTT Technical Research

More information

EVALUATION OF ALGORITHM PERFORMANCE 2012/13 GAS YEAR SCALING FACTOR AND WEATHER CORRECTION FACTOR

EVALUATION OF ALGORITHM PERFORMANCE 2012/13 GAS YEAR SCALING FACTOR AND WEATHER CORRECTION FACTOR EVALUATION OF ALGORITHM PERFORMANCE /3 GAS YEAR SCALING FACTOR AND WEATHER CORRECTION FACTOR. Background The annual gas year algorithm performance evaluation normally considers three sources of information

More information

SYSTEM BRIEF DAILY SUMMARY

SYSTEM BRIEF DAILY SUMMARY SYSTEM BRIEF DAILY SUMMARY * ANNUAL MaxTemp NEL (MWH) Hr Ending Hr Ending LOAD (PEAK HOURS 7:00 AM TO 10:00 PM MON-SAT) ENERGY (MWH) INCREMENTAL COST DAY DATE Civic TOTAL MAXIMUM @Max MINIMUM @Min FACTOR

More information

Peak Load Forecasting

Peak Load Forecasting Peak Load Forecasting Eugene Feinberg Stony Brook University Advanced Energy 2009 Hauppauge, New York, November 18 Importance of Peak Load Forecasting Annual peak load forecasts are important for planning

More information

2013 WEATHER NORMALIZATION SURVEY. Industry Practices

2013 WEATHER NORMALIZATION SURVEY. Industry Practices 2013 WEATHER NORMALIZATION SURVEY Industry Practices FORECASTING SPECIALIZATION Weather Operational Forecasting Short-term Forecasting to support: System Operations and Energy Trading Hourly Load Financial/Budget

More information

Probabilistic Decision-Making and Weather Assessment

Probabilistic Decision-Making and Weather Assessment 5 Student Packet Probabilistic Decision-Making and Weather Assessment Use contents of this packet as you feel appropriate. You are free to copy and use any of the material in this lesson plan. Packet Contents

More information

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience International Workshop on Wind Energy Development Cairo, Egypt ERCOT Wind Experience March 22, 21 Joel Mickey Direcr of Grid Operations Electric Reliability Council of Texas jmickey@ercot.com ERCOT 2 2

More information

EUROPEAN EXPERIENCE: Large-scale cross-country forecasting with the help of Ensemble Forecasts

EUROPEAN EXPERIENCE: Large-scale cross-country forecasting with the help of Ensemble Forecasts WEPROG Weather & wind Energy PROGnoses EUROPEAN EXPERIENCE: Large-scale cross-country forecasting with the help of Ensemble Forecasts Session 6: Integrating forecasting into market operation, the EMS and

More information

International Studies about the Grid Integration of Wind Generation

International Studies about the Grid Integration of Wind Generation International Studies about the Grid Integration of Wind Generation Dr.-Ing. Markus Pöller/DIgSILENT GmbH Internation Studies About Grid Integration of Wind Generation Grid Integration of Wind Generationin

More information

Day Ahead Hourly Load and Price Forecast in ISO New England Market using ANN

Day Ahead Hourly Load and Price Forecast in ISO New England Market using ANN 23 Annual IEEE India Conference (INDICON) Day Ahead Hourly Load and Price Forecast in ISO New England Market using ANN Kishan Bhushan Sahay Department of Electrical Engineering Delhi Technological University

More information

ABSTRACT. WANG, SHU. Reliability Assessment of Power Systems with Wind Power Generation. (Under the direction of Dr. Mesut E Baran.

ABSTRACT. WANG, SHU. Reliability Assessment of Power Systems with Wind Power Generation. (Under the direction of Dr. Mesut E Baran. ABSTRACT WANG, SHU. Reliability Assessment of Power Systems with Wind Power Generation. (Under the direction of Dr. Mesut E Baran.) Wind power generation, the most promising renewable energy, is increasingly

More information

Complementary Random Numbers Dagger Sampling. Lecture 4, autumn 2015 Mikael Amelin

Complementary Random Numbers Dagger Sampling. Lecture 4, autumn 2015 Mikael Amelin Complementary Random Numbers Dagger Sampling Lecture 4, autumn 2015 Mikael Amelin 1 Introduction All observations in simple sampling are independent of each other. Sometimes it is possible to increase

More information

Modelling trends in the ocean wave climate for dimensioning of ships

Modelling trends in the ocean wave climate for dimensioning of ships Modelling trends in the ocean wave climate for dimensioning of ships STK1100 lecture, University of Oslo Erik Vanem Motivation and background 2 Ocean waves and maritime safety Ships and other marine structures

More information

The Energy Markets. Use and interpretation of medium to extended range products. ECMWF, Reading, 14 th of November 2005

The Energy Markets. Use and interpretation of medium to extended range products. ECMWF, Reading, 14 th of November 2005 The Energy Markets Use and interpretation of medium to extended range products ECMWF, Reading, 14 th of November 2005 drs. Stefan Meulemans, MSc Sempra Energy Europe Ltd. London smeulemans@sempracommodities.com

More information

Importance Sampling Stratified Sampling. Lecture 6, autumn 2015 Mikael Amelin

Importance Sampling Stratified Sampling. Lecture 6, autumn 2015 Mikael Amelin Importance Sampling Stratified Sampling Lecture 6, autumn 2015 Mikael Amelin 1 Introduction All samples are treated equally in simple sampling. Sometimes it is possible to increase the accuracy by focusing

More information

peak half-hourly Tasmania

peak half-hourly Tasmania Forecasting long-term peak half-hourly electricity demand for Tasmania Dr Shu Fan B.S., M.S., Ph.D. Professor Rob J Hyndman B.Sc. (Hons), Ph.D., A.Stat. Business & Economic Forecasting Unit Report for

More information

Prediction of Power System Balancing Requirements and Tail Events

Prediction of Power System Balancing Requirements and Tail Events Prediction of Power System Balancing Requirements and Tail Events PNNL: Shuai Lu, Yuri Makarov, Alan Brothers, Craig McKinstry, Shuangshuang Jin BPA: John Pease INFORMS Annual Meeting 2012 Phoenix, AZ

More information

peak half-hourly New South Wales

peak half-hourly New South Wales Forecasting long-term peak half-hourly electricity demand for New South Wales Dr Shu Fan B.S., M.S., Ph.D. Professor Rob J Hyndman B.Sc. (Hons), Ph.D., A.Stat. Business & Economic Forecasting Unit Report

More information

Into Avista s Electricity Forecasts. Presented by Randy Barcus Avista Chief Economist Itron s Energy Forecaster s Group Meeting

Into Avista s Electricity Forecasts. Presented by Randy Barcus Avista Chief Economist Itron s Energy Forecaster s Group Meeting Incorporating Global Warming Into Avista s Electricity Forecasts Presented by Randy Barcus Avista Chief Economist Itron s Energy Forecaster s Group Meeting May 1, 009 Las Vegas, Nevada Presentation Outline

More information

Proper Security Criteria Determination in a Power System with High Penetration of Renewable Resources

Proper Security Criteria Determination in a Power System with High Penetration of Renewable Resources Proper Security Criteria Determination in a Power System with High Penetration of Renewable Resources Mojgan Hedayati, Kory Hedman, and Junshan Zhang School of Electrical, Computer, and Energy Engineering

More information

OFFSHORE INTEGRATION STUDY. Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018

OFFSHORE INTEGRATION STUDY. Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018 OFFSHORE INTEGRATION STUDY Analysis, benchmark and mitigation of storm and ramping risks from offshore wind power in Belgium 05/02/2018 This study has been developed in close collaboration with 1 TABLE

More information

Application and verification of ECMWF products 2012

Application and verification of ECMWF products 2012 Application and verification of ECMWF products 2012 Instituto Português do Mar e da Atmosfera, I.P. (IPMA) 1. Summary of major highlights ECMWF products are used as the main source of data for operational

More information

peak half-hourly South Australia

peak half-hourly South Australia Forecasting long-term peak half-hourly electricity demand for South Australia Dr Shu Fan B.S., M.S., Ph.D. Professor Rob J Hyndman B.Sc. (Hons), Ph.D., A.Stat. Business & Economic Forecasting Unit Report

More information

Anemos.Rulez: Extreme Event Prediction and Alarming to Support Stability of Energy Grids

Anemos.Rulez: Extreme Event Prediction and Alarming to Support Stability of Energy Grids Anemos.Rulez: Extreme Event Prediction and Alarming to Support Stability of Energy Grids Hans-Peter (Igor) Waldl, Philipp Brandt Overspeed GmbH & Co. KG, Marie-Curie-Straße 1, 26129 Oldenburg, Germany,

More information

Winter Season Resource Adequacy Analysis Status Report

Winter Season Resource Adequacy Analysis Status Report Winter Season Resource Adequacy Analysis Status Report Tom Falin Director Resource Adequacy Planning Markets & Reliability Committee October 26, 2017 Winter Risk Winter Season Resource Adequacy and Capacity

More information

Verification challenges in developing TC response procedures based on ensemble guidance

Verification challenges in developing TC response procedures based on ensemble guidance Verification challenges in developing TC response procedures based on ensemble guidance Grant Elliott Senior Metocean Meteorologist ECMWF UEF 2016 workshop Disclaimer and important notice This presentation

More information

Cost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling

Cost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling Cost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling HEPEX 10 th University Workshop June 25 th, 2014 NOAA Center for Weather and Climate Thomas D. Veselka and Les Poch Argonne

More information

Calibrating forecasts of heavy precipitation in river catchments

Calibrating forecasts of heavy precipitation in river catchments from Newsletter Number 152 Summer 217 METEOROLOGY Calibrating forecasts of heavy precipitation in river catchments Hurricane Patricia off the coast of Mexico on 23 October 215 ( 215 EUMETSAT) doi:1.21957/cf1598

More information

WeatherManager Weekly

WeatherManager Weekly Issue 288 July 14, 2016 WeatherManager Weekly Industries We Serve Agriculture Energy/Utilities Construction Transportation Retail Our Weather Protection Products Standard Temperature Products Lowest Daily

More information

Using Innovative Displays of Hydrologic Ensemble Traces

Using Innovative Displays of Hydrologic Ensemble Traces Upper Colorado River Basin Water Forum November 7, 2018 Communicating Uncertainty and Risk in Water Resources: Using Innovative Displays of Hydrologic Ensemble Traces Richard Koehler, Ph.D. NOAA/NWS, Boulder,

More information

Discussion of Load Forecast Uncertainty

Discussion of Load Forecast Uncertainty Discussion of Load Forecast Uncertainty August 26, 2010 Load Forecasting Task Force Draft for discussion only Arthur Maniaci System & Resource Planning New York Independent System Operator Summary of Discussion

More information

The Forecasting Challenge. The Forecasting Challenge CEEM,

The Forecasting Challenge. The Forecasting Challenge CEEM, Using NWP forecasts at multiple grid points to assist power system operators to predict large rapid changes in wind power Nicholas Cutler. n.cutler@unsw.edu.au 9 th April, 2008 CEEM, 2008 The Forecasting

More information

Spring Water Supply and Weather Outlook How about that near Miracle March?

Spring Water Supply and Weather Outlook How about that near Miracle March? Spring Water Supply and Weather Outlook How about that near Miracle March? tim.bardsley@noaa.gov NWS Reno 4.10.18 1 Out the Window March and early April have been Boom not Bust Key Points Up Front Wet

More information

1. Wind turbines are designed to operate within specified design criteria. Often the operating environment extends beyond these limits and causes

1. Wind turbines are designed to operate within specified design criteria. Often the operating environment extends beyond these limits and causes 1 2 1. Wind turbines are designed to operate within specified design criteria. Often the operating environment extends beyond these limits and causes outages. How these outages are classified can be challenging

More information

Prashant Pant 1, Achal Garg 2 1,2 Engineer, Keppel Offshore and Marine Engineering India Pvt. Ltd, Mumbai. IJRASET 2013: All Rights are Reserved 356

Prashant Pant 1, Achal Garg 2 1,2 Engineer, Keppel Offshore and Marine Engineering India Pvt. Ltd, Mumbai. IJRASET 2013: All Rights are Reserved 356 Forecasting Of Short Term Wind Power Using ARIMA Method Prashant Pant 1, Achal Garg 2 1,2 Engineer, Keppel Offshore and Marine Engineering India Pvt. Ltd, Mumbai Abstract- Wind power, i.e., electrical

More information

Skilful seasonal predictions for the European Energy Industry

Skilful seasonal predictions for the European Energy Industry Skilful seasonal predictions for the European Energy Industry Hazel Thornton, Philip Bett, Robin Clark, Adam Scaife, Brian Hoskins, David Brayshaw WGSIP, 10/10/2017 Outline Energy industry and climate

More information

2014 FORECASTING BENCHMARK AND OUTLOOK SURVEY. Mark Quan and Stuart McMenamin September 16, 2014 Forecasting Brown Bag Seminar

2014 FORECASTING BENCHMARK AND OUTLOOK SURVEY. Mark Quan and Stuart McMenamin September 16, 2014 Forecasting Brown Bag Seminar 2014 FORECASTING BENCHMARK AND OUTLOOK SURVEY Mark Quan and Stuart McMenamin September 16, 2014 Forecasting Brown Bag Seminar PLEASE REMEMBER» Phones are Muted: In order to help this session run smoothly,

More information

Optimization of the forecasting of wind energy production Focus on the day ahead forecast

Optimization of the forecasting of wind energy production Focus on the day ahead forecast Optimization of the forecasting of wind energy production Focus on the day ahead forecast Market Processes, EnBW Transportnetze AG Mirjam Eppinger, Dietmar Graeber, Andreas Semmig Quantitative Methods,

More information

The impact of climate change on wind energy resources

The impact of climate change on wind energy resources The impact of climate change on wind energy resources Prof. S.C. Pryor 1, Prof. R.J. Barthelmie 1,2, Prof. G.S. Takle 3 and T. Andersen 3 1 Atmospheric Science Program, Department of Geography, Indiana

More information

Use of Normals in Load Forecasting at National Grid

Use of Normals in Load Forecasting at National Grid Use of Normals in Load Forecasting at National Grid Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight

More information

AESO Load Forecast Application for Demand Side Participation. Eligibility Working Group September 26, 2017

AESO Load Forecast Application for Demand Side Participation. Eligibility Working Group September 26, 2017 AESO Load Forecast Application for Demand Side Participation Eligibility Working Group September 26, 2017 Load forecasting for the Capacity Market Demand Considerations Provide further information on forecasting

More information

Colorado PUC E-Filings System

Colorado PUC E-Filings System Page 1 of 10 30-Minute Flex Reserve on the Public Service Company of Colorado System Colorado PUC E-Filings System Prepared by: Xcel Energy Services, Inc. 1800 Larimer St. Denver, Colorado 80202 May 13,

More information

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory Energy and Power Engineering, 2013, 5, 625-629 doi:10.4236/epe.2013.54b121 Published Online July 2013 (http://www.scirp.org/journal/epe) The Study of Overhead Line Fault Probability Model Based on Fuzzy

More information

Demand Forecasting Reporting Period: 1 st Apr th Jun 17

Demand Forecasting Reporting Period: 1 st Apr th Jun 17 N A T I O N A L G R I D P A G E 1 O F 3 C O M M E R C I A L, E L E C T R I C I T Y C O M M E R C I A L O P E R A T I O N S Demand Forecasting Reporting Period: 1 st Apr 17 18 th Jun 17 EXECUTIVE SUMMARY

More information

Integrated Electricity Demand and Price Forecasting

Integrated Electricity Demand and Price Forecasting Integrated Electricity Demand and Price Forecasting Create and Evaluate Forecasting Models The many interrelated factors which influence demand for electricity cannot be directly modeled by closed-form

More information

Developing a Mathematical Model Based on Weather Parameters to Predict the Daily Demand for Electricity

Developing a Mathematical Model Based on Weather Parameters to Predict the Daily Demand for Electricity - Vol. L, No. 02, pp. [49-57], 2017 The Institution of Engineers, Sri Lanka Developing a Mathematical Model Based on Weather Parameters to Predict the Daily Demand for Electricity W.D.A.S. Wijayapala,

More information

Changes in Weather and Climate Extremes and Their Causes. Xuebin Zhang (CRD/ASTD) Francis Zwiers (PCIC)

Changes in Weather and Climate Extremes and Their Causes. Xuebin Zhang (CRD/ASTD) Francis Zwiers (PCIC) www.ec.gc.ca Changes in Weather and Climate Extremes and Their Causes Xuebin Zhang (CRD/ASTD) Francis Zwiers (PCIC) Outline What do we mean by climate extremes Changes in extreme temperature and precipitation

More information

A Model for a Zonal Operating Reserve Demand Curve

A Model for a Zonal Operating Reserve Demand Curve A Model for a Zonal Operating Reserve Demand Curve Yen-Yu Lee Electrical and Computer Engineering University of Texas at Austin March 5, Outline What is operating reserves? Why do we need elastic reserves

More information

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018 Operations Report Tag B. Short, Director South Region Operations Entergy Regional State Committee (ERSC) February 14, 2018 1 Winter Operations Highlights South Region Max Gen Event Regional Dispatch Transfer

More information

Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon, Canada

Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon, Canada Abstract Failure Bunching Phenomena in Electric Power Transmission Systems Roy Billinton Gagan Singh Janak Acharya Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon,

More information

West Henrico Co. - Glen Allen Weather Center N W. - Koontz

West Henrico Co. - Glen Allen Weather Center N W. - Koontz PAGE #1 Oct 2017 West Henrico Co. - Glen Allen Weather Center 37.6554 N. 77.5692 W. - Koontz 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Oct Week TEMPERATURE F TEMPERATURE F SKY PRECIPITATION FROZ.

More information

SMART GRID FORECASTING

SMART GRID FORECASTING SMART GRID FORECASTING AND FINANCIAL ANALYTICS Itron Forecasting Brown Bag December 11, 2012 PLEASE REMEMBER» Phones are Muted: In order to help this session run smoothly, your phones are muted.» Full

More information

Chapter 6 Impact of Stochastic Renewable Energy Generation on Market Quantities 6.1 Introduction

Chapter 6 Impact of Stochastic Renewable Energy Generation on Market Quantities 6.1 Introduction Chapter 6 Impact of Stochastic Renewable Energy Generation on Market Quantities 6.1 Introduction One of the most traditional systems for the commercial exchange of electricity production from stochastic

More information

The influence of the unit commitment plan on the variance of electric power. production cost. Jinchi Li

The influence of the unit commitment plan on the variance of electric power. production cost. Jinchi Li The influence of the unit commitment plan on the variance of electric power production cost by Jinchi Li A Creative Component paper submitted to the graduate faculty in partial fulfillment of the requirements

More information

Ellen L. Mecray NOAA Regional Climate Services Director, Eastern Region Taunton, MA

Ellen L. Mecray NOAA Regional Climate Services Director, Eastern Region Taunton, MA Ellen L. Mecray NOAA Regional Climate Services Director, Eastern Region Taunton, MA Regions of the US National Climate Assessment What we Observe: Climate changes and impacts Increasing temperature Increasingly

More information

Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators. IESO Training

Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators. IESO Training Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators IESO Training May 2017 Centralized Forecasting - Registration and Communication Requirements

More information

Mid-term Adequacy Forecast 2018

Mid-term Adequacy Forecast 2018 Appendix 1: Methodology and Detailed Results 2018 edition Table of Contents 1 Methodology and assumptions... 3 1.1 Methodology advanced tools for probabilistic market modelling...4 Adequacy Indices...7

More information

THUNDERSTORMS Brett Ewing October, 2003

THUNDERSTORMS Brett Ewing October, 2003 THUNDERSTORMS Brett Ewing October, 2003 A natural hazard that occurs often on a daily basis in the lower and mid-latitudes is thunderstorms. Thunderstorms is a weather system that can produce lightning,tornadoes,

More information

The Role of Weather in Risk Management For the Market Technician s Association October 15, 2013

The Role of Weather in Risk Management For the Market Technician s Association October 15, 2013 The Role of Weather in Risk Management For the Market Technician s Association October 15, 2013 RIA PERSAD President StatWeather rpersad@statweather.com Predictive Analytics Consumer Behavior Astronomy

More information

NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast

NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast Page 1 of 5 7610.0320 - Forecast Methodology NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast OVERALL METHODOLOGICAL FRAMEWORK Xcel Energy prepared its forecast

More information

Pb1 y13 =-j10 Pb5. Pb4. y34 =-j10

Pb1 y13 =-j10 Pb5. Pb4. y34 =-j10 EE 55, Exam, Take-home. Due Monday, April, 06, 5:00pm. You may use class notes or any reference materials (e.g., books, etc.) that you like; however, you must work alone, i.e., you should not be communicating

More information

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc.

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc. Elia linemen install Ampacimon real time sensors that will communicate with the dynamic thermal ratings software to control energy import levels over this transmission line. OV RH AD TRAN MI ION D namic

More information

SHORT TERM LOAD FORECASTING

SHORT TERM LOAD FORECASTING Indian Institute of Technology Kanpur (IITK) and Indian Energy Exchange (IEX) are delighted to announce Training Program on "Power Procurement Strategy and Power Exchanges" 28-30 July, 2014 SHORT TERM

More information

Q-V droop control using fuzzy logic and reciprocal characteristic

Q-V droop control using fuzzy logic and reciprocal characteristic International Journal of Smart Grid and Clean Energy Q-V droop control using fuzzy logic and reciprocal characteristic Lu Wang a*, Yanting Hu a, Zhe Chen b a School of Engineering and Applied Physics,

More information

POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING

POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING PREPARED BY: PROCEDURE TYPE: DOCUMENT REFERENCE: FINAL APPROVER: Systems Capability System Operating Procedure SO_OP_3710 Christian Schaefer DOC. VERSION:

More information

Value of Forecasts in Unit Commitment Problems

Value of Forecasts in Unit Commitment Problems Tim Schulze, Andreas Grothery and School of Mathematics Agenda Motivation Unit Commitemnt Problem British Test System Forecasts and Scenarios Rolling Horizon Evaluation Comparisons Conclusion Our Motivation

More information

UNBILLED ESTIMATION. UNBILLED REVENUE is revenue which had been recognized but which has not been billed to the purchaser.

UNBILLED ESTIMATION. UNBILLED REVENUE is revenue which had been recognized but which has not been billed to the purchaser. UNBILLED ESTIMATION UNBILLED REVENUE is revenue which had been recognized but which has not been billed to the purchaser. Presented By: Laura Ortega Sr. Manager Demand Side Analytics, CPS Energy & Andy

More information