Preliminary Economic Assessment Delivers Strong Business Case for the Woodlawn Zinc-Copper Project

Size: px
Start display at page:

Download "Preliminary Economic Assessment Delivers Strong Business Case for the Woodlawn Zinc-Copper Project"

Transcription

1 ASX/TSX Release 22 April 2015 Level 1, 37 Ord Street, West Perth WA / ABN: Preliminary Economic Assessment Delivers Strong Business Case for the Woodlawn Zinc-Copper Project Heron Resources Limited (Heron or the Company) is pleased to report the completion of the Preliminary Economic Assessment 1 (PEA) on the Company s 100%-owned and fully permitted Woodlawn Zinc-Copper Project located in New South Wales, Australia. Highlights include: Strong base case NPV / IRR results: ASX:HRR / TSX:HER Issued Shares 361M Share Price $0.125 Market Cap $45.1M Cash (31 Mar 15) $25.6M Investments $ 2.8M Total C+I $28.4M Combined Underground plus Tailings UG Starter Case Post-tax NPV 8.3* Post-tax IRR 46% Initial Capital Payback Period Net Cash Flow After Tax A$300 million A$140 million 2.0 years from commissioning A$594 million *Results reported using an 8.3% post tax real discount rate (approx. 10% post-tax nominal), with AUD/USD FX trending from 0.80 to 0.73 by 2021, and with flat real commodity prices of US$1.09/lb Zn, US$0.95/lb Pb, US$3.00/lb Cu, US$18.5/oz Ag and US$1,200/oz Au. Other assumptions are detailed later in this release. Attractive project characteristics: o o o o Initial 11 year mine life based on underground and tailings resources, and including 1.0Mt Indicated and 2.8Mt Inferred Mineral Resource contribution from underground Total life-of-mine (LOM) Production Target of 353Kt of zinc, 77Kt of copper, 112Kt of lead, 8.9Moz of silver and 59Koz of gold Processing rate of 1.5Mtpa through standard sequential flotation, with steady state ( ) annual Production Target of 51Kt of zinc, 10Kt of copper, 16Kt of lead, 1.1Moz of silver and 8.7Koz of gold contained within zinc, lead, and copper concentrates Utilises existing infrastructure to achieve significant reductions in development costs, with a revised portal location on the west side of the pit enabling first production from the second quarter after underground works commence Quality resource and mine plan: o UG Starter Case focused on the shallower areas of the deposit reflecting the success of the recent drilling programme high level of confidence for extensions to the mineralisation at depth and along strike 1 IMPORTANT NOTE: A Preliminary Economic Assessment (PEA) is a formal study in standard form prescribed by Canadian National Instrument Standards of Disclosure for Mineral Projects ( NI ) which includes an economic analysis of the potential viability of Mineral Resources, but which is not a pre-feasibility study or feasibility study. In accordance with Canadian requirements in relation to preliminary economic assessments, the Company advises that the preliminary economic assessment is preliminary in nature, that it includes some Inferred Mineral Resources considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorised as Mineral Reserves, and that there is no certainty that the economics set out in the preliminary economic assessment will be realised. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. ASX/TSX Release Heron Resources Limited 1 of 33

2 o o o o Heron Resources Limited Based upon 36% Measured, 35% Indicated and 29% Inferred Mineral Resources, comprising: Woodlawn Underground Project (WUP): 32% Indicated and 68% Inferred Woodlawn Tailings Retreatment Project (WRP): 47% Measured, 37% Indicated and 16% Inferred Conservative approach taken to re-modelling of the underground Mineral Resource, with exclusion of all moderate to higher risk areas to be reconsidered post mine access and re-assessment from underground Highly successful Phase I exploration drilling programme over the last 8 months of the total underground plant feed of 1.0Mt Indicated and 2.8Mt Inferred Mineral Resources, recent exploration has contributed approximately 2.8 million new Inferred tonnes Low-risk underground resource base: 80% of underground tonnes in the production schedule are from areas away from previous mining Robust economics: o o o C1 costs of US$(0.01)/lb zinc and C3 of US$0.44/lb expected to place the Project firmly in the lower half of the cost curve (refer to page 10 for definitions) Economics remain robust using current commodity prices (forward curve adjusted), achieving a post-tax NPV 8.3 of A$192 million and IRR of 34% Significant leverage to zinc, which comprises approximately 47% of total payable metal value Excellent exploration potential: o o Significant exploration potential remains within the underground including additional shallow, near-surface targets that will be tested in the next stage of drilling with scope to materially increase the Production Target Deeper underground extensions to be targeted with underground drilling post-commissioning management anticipates that any such depth extensions discovered have the potential to add significant project value Expedited development path: o o o Heron s Board has committed to commence the Feasibility Study (FS) to progress the development of the Project with the objective of completing this study by mid-2016 New drill programme to commence comprising in-fill drilling and follow up on high priority exploration targets Early start up potential, based on a staged development of the tailings (Front-end Engineering & Design FEED completed 2012) followed by the integration of underground hard rock components The completed PEA study document will be published on Heron s web site, the ASX (ASX:HRR) and SEDAR (TSX:HER) within 45 days of this news release. Heron s Chairman, Mr. Craig Readhead, said This PEA study confirms not only the economic viability of the Woodlawn Project, which has the potential to deliver a long term supply of zinc into a supply constrained market, but also the quality of this asset with a very competitive cost of production within the current market. The project is underpinned by a revised, high quality Mineral Resource, including the discovery of 2.8 million tonnes from recent drilling and has achieved its aim of establishing a robust resource base on which to build a new operation. The PEA study demonstrates that the approach of co-treating the low risk tailings resource with the high-grade underground resource can deliver a robust outcome and a low cost, long life, mining operation. We are now committed to advancing this project rapidly through to feasibility study stage. Please refer to page 12 for important Cautionary and Forward Looking Statements that are to be read in conjunction with this release. ASX/TSX Release Heron Resources Limited 2 of 33

3 Project Overview Heron Resources Limited SUMMARY OF THE PEA Woodlawn is a high-grade, volcanogenic massive-sulphide (VMS) deposit situated in New South Wales, Australia, located approximately 50 km northeast of Canberra, and 250 km southwest of Sydney (refer Figure 1). The Woodlawn Project benefits from a mining lease (SML 20) that has recently been renewed for a further 15 years, and major project approvals (statutory approval) that allows for mining operations at the Woodlawn site until 31 December The mineral rights and production are 100%-owned by Heron. Figure 2 shows the Woodlawn site layout including location of the proposed plant site. The Woodlawn site (SML 20) is surrounded by a larger exploration license (EL 7257) which is held 100% by Heron. This exploration license, of 179 square km, includes the previous Currawang Mine located 9km to the north of Woodlawn. The Currawang Mine provided satellite feed to the previous Woodlawn operations. Figure 1: Woodlawn location map with relative population sizes ASX/TSX Release Heron Resources Limited 3 of 33

4 Figure 2: Woodlawn Site Layout Underground (WUP) Mineral Resource Heron is pleased to announce an updated Mineral Resource estimate, as detailed in Table 1 below, for the Woodlawn Underground Project compiled under JORC 2012 and NI guidelines and incorporating the results of the Phase 1 drilling programme and an extensive review of historic data. As announced on 6 March 2015, during the Phase 1 drill programme a total of 20 diamond core holes (DDH) for 7,613m and 11 reverse circulation (RC) holes for 1,201m were completed. Figure 3 provides an oblique view through the Mineral Resource block model. Drilling focused initially on the Kate Lens before drilling key positions within the near-surface portions of other lenses. The deepest hole (WNDD0006) was drilled to a depth of 940m and intersected multiple massive sulphides in the I and D lens positions. It became apparent during the course of the program that there was scope to expand the resource base within the upper 500m of the system, deferring the need to drill deeper targets. While considerable resource potential exists in deeper parts of the system, the PEA focus has been only on the shallower, up-dip lens positions, with the result that the underground Mineral Resource used in the production schedule for the PEA extends the depth of the mine only 80m below previous workings. Heron has taken a deliberately cautious approach to areas that would be considered remnant, which has reduced the underground Mineral Resource compared with the previously published estimate. There are numerous areas adjacent to historical mining which have been excluded from the new resource estimate, and there is considerable potential to reincorporate these zones into the mine plan once operations are under way and underground access facilitates closer and more detailed assessment. The Mineral Resource has been reported undiluted to a lower cut-off grade of 7% ZnEq, a value that approximates the estimated lower cut-off grade for the mining methods considered by the PEA study. For further information please refer to the item entitled Compliance with ASX Listing Rule for updated Underground Mineral Resources on page 13 for technical details associated with the Resource estimation process. ASX/TSX Release Heron Resources Limited 4 of 33

5 Figure 3: Woodlawn underground Mineral Resource. Oblique sectional view looking north-east block model coloured by ZnEq grades Table 1: Mineral Resource Estimate - Woodlawn Underground Project (WUP) Reported at a 7% ZnEq lower cut-off grade Type Resource Category Quantity (Mt) Grades ZnEq(%) Zn(%) Cu(%) Pb(%) Au(g/t) Ag(g/t) Polymetallic Indicated Polymetallic Inferred Copper Indicated Copper Inferred Notes to accompany Mineral Resource Table: 1) Please refer to the page 33 of this release for Qualified Persons statements; 2) ZnEq% refers to a calculated Zn equivalent grade the formula for which is stated in Appendix 1; Polymetallic Type refers to polymetallic massive sulphide mineralisation with high-grade Zn and Pb; Copper Type refers to Cu dominated massive and stringer sulphide mineralisation; Values are rounded to two significant numbers and some rounding related discrepancies may occur in the totals; the Mineral Resource is reported in accordance with the guidelines set out in the JORC (2012) and NI Codes; further details of the Mineral Resources estimation can be found in Appendix 1 and in the JORC Code (2012) Table 1 Appendix 2. ASX/TSX Release Heron Resources Limited 5 of 33

6 Tailings (WRP) Mineral Resource A Mineral Reserve was previously stated for the Woodlawn Tailings Retreatment Project (WRP) as part of the Bankable Feasibility Study which was completed in This PEA does not replace the WRP Feasibility Study, and the previously published tailings Mineral Reserves remain unchanged. For the purposes of the PEA, the plant design is based primarily on the 2012 FEED study design for the WRP, and adopts the processing of this tailings material in combination with underground material. The tailings are reported here as a Mineral Resource as part of this PEA study with Table 2, below, detailing the previously disclosed estimate. This Mineral Resource contributes some 11.2Mt (9.4Mt of Measured and Indicated and 1.8Mt of Inferred) to the total PEA plant feed as detailed in the following sections. Table 2: Mineral Resource Estimate - Woodlawn Retreatment Project (WRP) Resource Category Quantity (Mt) ZnEq (%) Zn (%) Cu (%) Grades Pb (%) Au (g/t) Ag (g/t) Measured + Indicated Mineral Resources North Dam Measured Indicated Sub-Total South Dam Measured Indicated Sub-Total West Dam Measured Indicated Sub-Total All Dams Measured Indicated Total Measured + Indicated Inferred Mineral Resources North Dam South Dam West Dam Total Inferred Notes to accompany Mineral Resource Table: 1) Please refer to the page 33 of this release for Qualified Persons statements; 2) ZnEq% refers to a calculated Zn equivalent grade the formula for which is stated in Appendix 1 and these are different to the originally reported (May 2009) ZnEq grades which were based on a different formula; 3) Values are rounded to two significant numbers and some rounded related discrepancies may occur in the totals; 4) The Mineral Resource is reported in a manner compliant with the JORC 2004 and NI Codes. This information was prepared and first disclosed under the JORC Code (2004) in May It has not been updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last reported. 5) TriAusMin acquired more drill hole data in 2008, subsequent to the Mineral Resource estimation. That data however does not materially alter the Mineral Resource estimate and due to data collection problems it is not viable for use in a re-estimate. Nevertheless, statistics of the later assays confirm the reported estimated grades. ASX/TSX Release Heron Resources Limited 6 of 33

7 PEA Scope & Plant Feed The PEA was prepared by SRK Consulting (Australasia) Pty Ltd (SRK) with contributions from GR Engineering Services Limited (GRES), other consultants and Company employees. The Project will be developed as a combined underground project together with a tailings retreatment project, with feed processed through a single plant designed for co-treatment. The base case Plant Feed Estimate, detailed in Table 3 below, of 15Mt ( UG Starter Case ) assumes the following parameters: Underground tonnages above a variable 4.7 to 6.6% ZnEq cut-off grade depending on stoping method; Underground mining recoveries ranging from 85 to 98% depending on the stoping method and stope width; Underground dilution of mineralisation includes a minimum mining width of 3m and in addition dilution ranging from 9 to 20% at zero grade depending on lens location and stope width; Tailings tonnages above the 0% ZnEq cut-off grade; Tailings mining recovery based on an average expected loss of 20cm of tailings material in contact with other material; and Tailings dilution equivalent to 10cm average vertical gain at no grade to account for potential contamination from the original ground surface. Table 3 Woodlawn PEA Plant Feed Estimate Type Category Quantity ZnEq(%) Zn(%) Cu(%) Pb(%) Au(g/t) Ag(g/t) (Mt) Underground Polymetallic Indicated Inferred Copper Indicated Inferred Tailings Tailings Measured & Indicated Inferred Notes to accompany Woodlawn PEA Plant Feed Estimate Table 3: 1) Please refer to the page 33 of this release for Qualified Persons statements; 2) ZnEq% refers to a calculated Zn equivalent grade, the formula for which is stated in Appendix 1. Values are rounded to two significant numbers and some rounding related discrepancies may occur in the totals. Whilst the current Mineral Resource base forms the foundation of the PEA and will also be the starting point for the future FS, the Board is of the view that there is very strong potential for the Project to deliver significantly greater tonnages from underground based on the exploration potential of the Woodlawn mineralised system. Plant Design GR Engineering Services Limited have updated the previous Woodlawn Retreatment Project Feasibility Study / FEED Study design for the 1.5Mtpa tailings processing facility to deliver a plant that has been designed on the basis of a 50% blend of fresh underground material being co-treated with 50% reclaimed tailings over life-of-mine. The design allows initial operations to treat 100% reclaimed tailings, whilst at the same time the development of the initial mine decline will be undertaken to provide access for mining of fresh material. The contribution from underground approaches 700Ktpa during the middle years of the current preliminary mine life and the mill feed blend ratio will be reviewed further in the next stage of the project studies. For underground production, a two stage crushing circuit has been incorporated into the plant design, together with a primary grind ball mill. For tailings material, a fine grind mill is planned that reduces the particle size down to 30µm, a size which previous and current testwork confirms maximises recovery performance from the flotation circuit. For the underground material, the initial float (copper concentrate) is undertaken at a 75µm grind size, with a regrind of copper tails to 30µm being employed subsequent to that stage to maximise the recoveries from the lead and zinc flotation stages. ASX/TSX Release Heron Resources Limited 7 of 33

8 The flotation circuit comprises a talc, copper, lead and zinc differential flotation sequence. The overall plant design is consistent with the design of the original plant that was historically used to successfully treat Woodlawn ore. Talc cleaner concentrate recovered from the talc flotation cleaner cell will be discarded to final tails to remove some of the talcose gangue ahead of the differential flotation circuit. A differential flotation circuit for copper, lead and zinc will be utilised with concentrate regrind stages in the copper, lead and zinc circuits to produce marketable copper, lead and zinc concentrates. The copper circuit will also utilise a rougher and scavenger tailings regrind circuit prior to the lead flotation stage. Tailings from the flotation plant will be thickened for recovery of process water and underground paste fill, with slime tailings deposited into a new tailings storage facility TSF4. As outlined in the Company s release of 11 February Successful Metallurgical Testwork, the PEA metallurgical testwork program was undertaken by Australian Mineral Metallurgical Laboratories Pty Ltd ( AMML ) in their Gosford testing facility with input from GRES and focused on the underground massive sulphides at the Woodlawn Zinc-Copper Project. This work represents the first full suite of metallurgical tests undertaken on the underground mineralisation since the 1998 mine closure, and also the first tests on a combination of the tailings and fresh zinc-copper mineralisation. The overall results from this work have demonstrated better than historical operational performance and reflect the advancements made in the field of sulphide flotation, and in-particular fine grinding technology. The testwork demonstrated the ability to produce three readily saleable concentrates. Concentrates from the copper, lead and zinc flotation circuits will be thickened and subsequently filtered for road transport. Copper and zinc concentrates will be shipped via Port Kembla in bulk carriers. Transport of the concentrate from site will be by road with concentrate loaded into half-height containers via front end loader at site. The high precious metals lead concentrates will be loaded into bulka bags via a bagging plant at the process plant. Loaded bags will then be containerised for dispatch via Port Botany or Port Kembla. Final flotation tailings will be de-slimed and used in the paste fill plant which will generate a cemented paste that will be reticulated underground and used to backfill completed stopes. Outotec has completed an initial set of testwork on the paste fill, including rheology and strength testing, using tailings samples from the recent metallurgical testing. Whilst this is sufficient for the PEA, further work will be undertaken during the FS including leachability tests, additional trial mix tests to optimise binder type and mix to deliver adequate strength to mine fill, and longer term strength and stability tests. Underground Mining Beck Engineering (Beck), an east coast Australia-based specialist consultancy, was engaged to assist with the rock mechanics input to the proposed underground operation. As a component of their work, the extensive historical mine records have been reviewed to better understand the ground conditions previously encountered at Woodlawn and previous ground control practices. In addition to this historical knowledge base, inspection and geotechnical logging of Kate Lens diamond drill core has led Beck to note that the hanging wall appears competent for this new lens. This competency, together with the use of competent backfill, are important input parameters for the selection of an appropriate mining method that provides for maximum recovery and high productivity. A number of changes to historic work practices will improve the future management of the ground conditions. These include: Full time geotechnical resources on site to provide timely day-to-day support to mine operations; Whole-of-mine structural modelling to improve the predictive capacity for mine planning; Adoption of alternative extraction techniques to minimise creation of isolated sill pillars; and Implementation of cemented paste fill as a competent support medium that will enable significantly higher resource recovery whilst providing local and regional ground support to the mine excavations. The deposit will be accessed with a box cut located on the western side of the existing open-pit, which provides for early access to underground material. Stoping areas will be accessed by rehabilitating some of the existing workings and constructing additional underground declines and levels to access the new areas. The mining methods have been selected to mine both areas of unmined and remnant material around the previously mined areas of the deposit. The mining method selection takes into consideration the location of the existing open-pit above the ASX/TSX Release Heron Resources Limited 8 of 33

9 deposit which is being used as a bioreactor by Veolia Environmental Services Ltd (Veolia). The mine design has assumed that stopes will be filled with paste fill, and multi-level continuous fill method areas will be filled using rock fill. Production will be transferred from stoping areas to loading bays and a haulage fleet used to deliver plant feed to the runof-mine (ROM) pad. Appendix 1 provides details of the proposed production schedule. The production schedule for the underground benefits from the inclusion of significant material discovered from the recent drilling campaigns, with approximately 2.8 million tonnes of Inferred Mineral Resources identified from this work. Importantly, 80% of the total underground plant feed material is away from former mining areas and is amenable to low cost, low risk mining methods. Figure 4 below shows the stope designs currently planned, with stopes coloured green being material which is away from previously mined areas and hence amenable to lower cost, lower risk mining methods, with areas in orange being adjacent to previously mined areas for which more conservative mining methods have been employed. Figure 4: PEA Stope Design (SRK) Previous mining was undertaken to a depth of 620m below surface. The underground Resource within the production schedule for the PEA extends this by only 80m to 700m. Considerable potential remains to investigate further depth extensions to the mineralisation, which will best be assessed by underground drilling once underground access is secured. Capital and Operating Costs Capital costs have been estimated to a +/-25% accuracy. Tailings retreatment process plant capital costs have been updated to allow for installation of equipment sized to also accommodate the underground feed, potentially allowing a staged development of the project to be undertaken. Initial capital costs to Peak Cash Draw are estimated at A$101.4 million for the tailings components, with an incremental A$38.6 million required to complete the underground access and plant additions, for a total of A$140.0 million including contingency. Refer to Appendix 1 for full details. ASX/TSX Release Heron Resources Limited 9 of 33

10 Operating costs have been estimated by GRES for the plant component and by SRK for the mining component, with additional costs estimated by Heron. The detailed cost breakdown is provided in Appendix 1. The resulting cost profile for the operation based on the Production Target provides C1 2 costs of US$(0.01)/lb or US$(30)/tonne) of zinc in concentrate produced over the initial 11 year mine life. On a C3 3 cost basis, the operation averages costs of US$0.44/lb of zinc in concentrate. Summary Economics The Woodlawn project economics have been assessed using the discounted cash flow method, based on a quarterly schedule of tonnes mined and processed from both the WUP and the WRP. Capital and operating costs are applied to mining, processing and overheads. The processed material has recovery factors applied, together with flotation splits to the three concentrates which make up the project production. Shipping and logistics, product payability, treatment and refining costs, state royalties and taxes are adjusted for to derive a Net Present Value (NPV) for the project. The Project s post-tax NPV at an 8.3% post-tax real discount rate (approximately equivalent to a 10% post-tax nominal discount rate) is A$300 million and the IRR is 46%. Payback of start-up capital is achieved approximately 2 years from commissioning. UG Starter Case 1: Net increase in cash after tax and after paying back capital. Forecast Commodity Price Deck Post-tax NPV 8.3 A$300 million A$192 million Post-tax IRR 46% 34% Forward Curve Price Deck Initial Capital A$140M / US$112M A$141M / US$113M Payback Period 2 years from commissioning 2.5 years from commissioning Mine life 11 years 11 years Post-tax Cash Flow 1 A$594M A$408M C1 Cash Cost US$(0.01)/lb Zn US$0.12/lb Zn C3 Total Cost US$0.44/lb Zn US$0.56/lb Zn Results are based on AUD/USD FX trending from 0.80 to 0.73 by 2021 (forward curve as at 31 March 2015). The Forecast Commodity Price Deck is based on the average of a number of forecasts for each commodity resulting in prices of US$1.09/lb Zn, US$0.95/lb Pb, US$3.00/lb Cu, US$18.5/oz Ag and US$1,200/oz Au. Other economic assumptions are detailed in Appendix 1. For comparison, the economics are also shown using commodity forward curves which were sourced and applied as at 27 March The results demonstrate that the project economics remain robust at lower prices. Refer to Appendix 1 for more detailed sensitivity analysis. The project is highly leveraged to commodity prices. In particular, zinc makes up around 47% of expected total payable metal value for the project. Hence the project provides excellent exposure to what is anticipated to be a market where demand will exceed supply, with positive potential implications for the future price of zinc. Whilst the UG Starter Case presents a strongly positive economic outcome for the project and will form the basis for the future FS in order to minimise development time and costs, there is potential for the project to deliver significantly greater tonnages from underground based on both expansion of the current resource and on the broader exploration potential of the Woodlawn mineralised system. 2 C1 costs calculated as total direct cash operating costs including all mining and processing costs, mine site overheads and realisation costs (including transport costs, treatment and refining costs and smelter recovery deductions) net of revenue credits from sale of by products (Pb, Cu, Ag and Au), divided by the amount of payable zinc produced. 3 C3 is calculated using the same methodology as C1 but incorporates a capital charge and royalties. ASX/TSX Release Heron Resources Limited 10 of 33

11 With plant, underground access and development costs included for mining to a depth of 700 m below surface under the UG Starter Case, the incremental net present value associated with new discoveries and/or conversion of additional resource tonnes into the future mine plan has the potential to be very positive. Exploration Very significant exploration potential exists for the Project, with the majority of the recent drilling focused on shallow extensional targets within the underground to develop the production schedule for the PEA. Future exploration will focus on: Following up on additional shallow, up-dip targets which have the potential to be added in to the resource base for the underground; Regional targets including the Montrose, Cowley Hills and the Currawang prospects; and Deeper targets at the Woodlawn mine. Project Funding Strategy The funding strategy for the Woodlawn Project is to finance the project through a combination of debt and equity. An early stage development concept is being evaluated which would allow construction of the plant to commence whilst the FS for the underground mine is completed. Under this staged scenario the plant would be commissioned and run on tailings only with underground feed to be introduced as soon as practicable. Whilst the staged development option is under consideration, the Company continues to be fully funded for the forthcoming FS on the combined Project and is continuing with this work. Forward Programme Heron s Board is delighted with the outcomes of the PEA and has determined that it will continue with the further study of the Woodlawn project through undertaking a FS on the combined underground and tailings project. Whilst detailed planning is under way, the Company considers that the FS could be completed within approximately 12 months. An initial step in the FS is a further drilling program that will cover the required resource in-fill drilling as well as the testing of high priority exploration targets. The in-fill drilling is designed to lift the resource classification to permit the calculation of a Mineral Reserve as part of the FS. The high priority exploration targets include locations previously generated from downhole EM surveys, unexplained high-grade intercepts and interpreted structural positions, all of which have the potential to discover new massive sulphide lenses. The program consists of approximately 18,000 to 19,000 metres and has been approved by the Heron Board. About Heron Resources Limited: Heron is engaged in the exploration and development of base and precious metal deposits in Australia. Heron s projects include the high-grade Woodlawn Zinc-Copper Project located 250km southwest of Sydney, New South Wales, and the Kalgoorlie Nickel Project located north of Kalgoorlie, Western Australia. In addition the Company holds a number of other high quality exploration properties located in the Lachlan Fold Belt, New South Wales. For further information, please visit or contact: Australia: Mr Wayne Taylor, Managing Director and Chief Executive Officer: Tel: or heron@heronresources.com.au Canada: Tel: (Toronto) ASX/TSX Release Heron Resources Limited 11 of 33

12 Cautionary Statements: Heron Resources Limited In accordance with Canadian requirements in relation to preliminary economic assessments, the Company advises that the Preliminary Economic Assessment is preliminary in nature, that it includes some Inferred Mineral Resources considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorised as mineral reserves, and that there is no certainty that the economics set out in the Preliminary Economic Assessment will be realised. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. In accordance with the ASX listing rules, the Company advises the PEA referred to in this announcement is based on lower-level technical and preliminary economic assessments, and (other than in relation to the Woodlawn Tailings Retreatment Project) is insufficient to support estimation of Ore Reserves or to provide assurance of an economic development case at this stage, or to provide certainty that the conclusions of the PEA will be realised. The Production Target referred to in this announcement is partly based on Indicated Mineral Resources and on Inferred Mineral Resources detailed herein. There is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the Production Target or Preliminary Economic Assessment will be realised. Forecast financial information provided in this announcement is based on the Production Target disclosed herein. The Company has concluded that it has a reasonable basis for providing the forward-looking statements included in this announcement. The detailed reasons for this conclusion are outlined throughout this announcement and in particular in Appendix 1 headed Disclosure of Additional Assumptions. However, the Company cautions that there is no certainty that the forecast financial information derived from the Production Targets will be realised. Forward-Looking Statements: This release contains certain forward looking statements and certain forward-looking information as defined under applicable Canadian and U.S. securities laws. Forward-looking statements and information can generally be identified by the use of forward-looking terminology such as may, will, expect, intend, estimate, anticipate, believe, continue, plans or similar terminology. Forward-looking statements and information are not historical facts, are made as of the date of this press release, and include, but are not limited to, statements regarding discussions of future plans, guidance, projections, objectives, estimates and forecasts and statements as to management's expectations. These forward looking statements involve numerous risks and uncertainties and actual results may vary. Important factors that may cause actual results to vary include without limitation, certain transactions, the successful completion of a Feasibility Study within the next 12 months, the timing and receipt of certain approvals, changes in commodity and power prices, changes in interest and currency exchange rates, risks inherent in exploration results, timing and success, inaccurate geological and metallurgical assumptions (including with respect to the size, grade and recoverability of mineral reserves and resources), changes in development or mining plans due to changes in logistical, technical or other factors, unanticipated operational difficulties (including failure of plant, equipment or processes to operate in accordance with specifications, cost escalation, unavailability of materials, equipment and third party contractors, delays in the receipt of government approvals, industrial disturbances or other job action, and unanticipated events related to health, safety and environmental matters), political risk, social unrest, and changes in general economic conditions or conditions in the financial markets. Information concerning Mineral Reserve and Mineral Resource estimates also may be considered forward-looking statements, as such information constitutes a prediction of what mineralisation might be found to be present if and when a project is actually developed. The actual results or performance by the Company could differ materially from those expressed in, or implied by, any forward-looking statements relating to those matters. Accordingly, no assurances can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what impact they will have on the results of operations or financial condition of the Company. Except as required by law, we are under no obligation, and expressly disclaim any obligation, to update, alter or otherwise revise any forward-looking statement, whether written or oral, that may be made from time to time, whether as a result of new information, future events or otherwise, except as may be required under applicable securities laws. ASX/TSX Release Heron Resources Limited 12 of 33

13 Appendix 1: Disclosure of Additional Assumptions Note: In the tables and graphics disclosed herein, years are financial years ending 30 June unless otherwise specified. Compliance with ASX Listing Rule for updated Underground Mineral Resources Capital The updated underground Mineral Resource estimate for Woodlawn comprises 33 separate domains of polymetallic (Zn-Pb dominated) or copper-dominated VMS mineralisation styles, which were individually wire framed, based primarily on geological criteria. Heron has remodelled the underground Mineral Resource, incorporating the recent and historical drilling results with newly digitised information compiled from detailed underground mapping of geology and structure, combined with careful consideration of the expected mining methods. Sample points were mostly derived from diamond drill core, half or quarter-core sampled over an average of 1m intervals, to geological contacts, using an orientated cut line. Samples were analysed by an independent commercial laboratory using industry standard analytical techniques including fire assay and AAS finish for Au and mixed acid digest and ICP finish for the multi-element suite (40 elements), including Zn, Cu, Pb, Ag and Fe. Mineral Resource grades were estimated into a conventional digital block model for Zn, Pb, Cu, Au, Ag and Fe using ordinary kriging, employing parameters derived from an independent geostatistical analysis of the sample data set. Statistical analysis indicated that high-grade sample cuts were not required for most elements estimated except for Ag, where a high-grade cut of 880ppm was applied. A ZnEq grade was calculated for each block and a ZnEq lower cut-off grade of 7% was used in the reporting of the Mineral Resource. Density was assigned to each block using a grade regression equation derived from densities measurements. In general terms the Mineral Resource was classified as Inferred where geological continuity was confirmed and the drill hole spacing better than 50m x 50m centres and as Indicated where drilling was on 20m x 20m centres or better. This closer spacing reflects much of the drill hole spacing in the underground historical drilling and is not necessarily a reflection of drill hole spacing required to achieve Indicated Mineral Resources in future drilling. A variety of conventional underground mining methods, employing paste-fill where required, were considered for the extraction of the mineralised material including, underhand stoping, and drift and halfupper stoping. Preliminary metallurgical testwork has been undertaken on the mineralised material which has demonstrated that it can be processed through a fine grinding circuit and industry standard sequential flotation to produce a Zn, Cu and Pb concentrate. Please refer to Appendix 2 for further details. A summary of the initial capital cost estimates (+/-25%) and inclusive of a 7.7% contingency is provided below: Initial Capital Item Scope Tailings Components (A$M) Underground Components (Incremental A$M) Total (A$m) Underground Development & Rehabilitation Pre-commissioning Post-commissioning Mining Equipment & Infrastructure Treatment Plant and Services Infrastructure Tailings Storage Construction & Engineering Subtotal Owners Costs Pre-Production Working Capital Total to Peak Cash Draw Peak Cash Draw is defined as initial capital working capital post commissioning until the mine achieves a break-even cash position, and excludes financing costs. Maintenance capital has been built into the operating cost estimates. No allowance has been made for financing charges or interest, GST related cash flows, or fluctuations in the exchange rate (estimates were provided on the basis of an exchange rate of 0.80 AUD:USD). The basis for the capital estimates includes: ASX/TSX Release Heron Resources Limited 13 of 33

14 Engineering, Procurement and Construction model for non-mining infrastructure; Owner operator processing facilities and workforce; Owned fixed plant, mobile surface plant, and administration buildings; Contract mining and leased underground mining equipment and maintenance facilities; Contract concentrate road haulage, port storage and handling and ship loading; and The construction of the new tailings storage facility TSF4. Ongoing capital of A$107.7 million is required for the underground decline and lateral development, decline rehabilitation, ventilation raises, escapeways, infrastructure and sustaining capital. The profile is driven by the production schedule and is shown below starting in the second quarter post commissioning (being the quarter immediately after Peak Cash Draw, with capital prior to that period being shown in the table above): Mining Production Schedule As disclosed in the body of the announcement, total plant feed of 15.0 million tonnes has been modelled to provide an 11 year mine life at a rate of 1.5Mtpa. Timing is assumed to deliver a commissioned project in the first quarter of calendar year The overall tonnes / grade profile is illustrated below by financial year and by source: The detailed production schedule is provided in the table overleaf: ASX/TSX Release Heron Resources Limited 14 of 33

15 Financial Year LOM U/G Polymetallic Tonnes Mined kt 3, Zn Grade (Equiv.) kt 15.72% 15.72% 15.42% 17.42% 19.30% 16.34% 12.89% 10.03% 0.00% 0.00% 0.00% 0.00% Zn Grade % 7.01% 6.28% 5.51% 6.59% 9.54% 8.31% 5.96% 3.53% 0.00% 0.00% 0.00% 0.00% Pb Grade % 2.66% 3.19% 2.90% 2.70% 3.48% 2.76% 2.09% 1.34% 0.00% 0.00% 0.00% 0.00% Cu Grade % 1.38% 1.21% 1.27% 1.74% 1.47% 1.31% 1.19% 1.28% 0.00% 0.00% 0.00% 0.00% Ag Grade g/t Au Grade g/t U/G Copper Tonnes Mined kt Zn Grade (Equiv.) kt 9.44% 0.00% 0.00% 12.00% 11.34% 9.07% 10.50% 8.97% 8.57% 0.00% 0.00% 0.00% Zn Grade % 1.55% 0.00% 0.00% 4.70% 3.03% 1.57% 1.53% 1.05% 0.94% 0.00% 0.00% 0.00% Pb Grade % 0.46% 0.00% 0.00% 2.48% 1.07% 0.35% 0.41% 0.19% 0.16% 0.00% 0.00% 0.00% Cu Grade % 2.26% 0.00% 0.00% 1.08% 2.18% 2.20% 2.61% 2.38% 2.34% 0.00% 0.00% 0.00% Ag Grade g/t Au Grade g/t Tailings Tonnes Mined kt 11, , ,363 1,500 1, Zn Grade (Equiv.) kt 5.99% 5.71% 5.71% 5.71% 5.71% 5.71% 6.19% 6.26% 6.26% 6.18% 6.04% 6.04% Zn Grade % 2.22% 2.43% 2.43% 2.43% 2.43% 2.43% 1.97% 1.90% 1.90% 2.06% 2.34% 2.34% Pb Grade % 1.31% 1.15% 1.15% 1.15% 1.15% 1.15% 1.40% 1.44% 1.44% 1.42% 1.38% 1.38% Cu Grade % 0.49% 0.47% 0.47% 0.47% 0.47% 0.47% 0.57% 0.59% 0.59% 0.52% 0.40% 0.40% Ag Grade g/t Au Grade g/t Total Tonnes Mined kt 15, ,481 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1, Zn Grade (Equiv.) kt 8.14% 6.46% 7.67% 9.66% 11.43% 10.46% 9.31% 7.77% 6.72% 6.18% 6.04% 6.04% Zn Grade % 3.16% 2.71% 3.04% 3.82% 5.32% 4.89% 3.70% 2.18% 1.85% 2.06% 2.34% 2.34% Pb Grade % 1.55% 1.30% 1.50% 1.70% 2.09% 1.81% 1.66% 1.22% 1.33% 1.42% 1.38% 1.38% Cu Grade % 0.76% 0.53% 0.63% 0.89% 0.94% 0.92% 0.94% 1.09% 0.81% 0.52% 0.40% 0.40% Ag Grade g/t Au Grade g/t Zn equivalents (ZnEq) in the above table are based on the formula: Zn(%) x Pb(%) x Cu(%) x Au(gpt) x Ag(gpt). The factors in the equation, determined by SRK, take into account the plant feed grade together with relative mining recoveries, mining dilution, metallurgical recovery rates, payability and realisation costs, and are expressed as an equivalent zinc only grade (the effective grade that is delivered to the processing plant). Metal prices used in the calculation are: Zn US$2,300/t, Pb US$ 2,050/t, Cu US$6,600/t, Au US$1,250/oz and Ag US$18/oz. Metal recoveries are provided in the section on metallurgy below and it is Heron s view that all the metals within this formula are expected to be recovered and sold. As disclosed in more detail in the body of the announcement, the production schedule for the UG Starter Case contains 36% Measured, 35% Indicated and 29% Inferred Resources, broken down into WUP: 32% Indicated Resources, and 68% Inferred Mineral Resources, and WRP: 47% Measured, 37% Indicated and 16% Inferred. Approximately 80% of tonnes from underground mining relates to areas which have not previously been mined. The breakdown between remnant and new areas is illustrated below: ASX/TSX Release Heron Resources Limited 15 of 33

16 The underground Resources falls into two main types, a Polymetallic type which refers to polymetallic massive sulphide mineralisation with high-grade Zn and Pb, and a Copper type which refers to Cu dominated massive and stringer sulphide mineralisation. The mining schedule preferentially feeds the Polymetallic material, with the Copper material generally being skewed to the back end of the production profile. A one month stockpile on the ROM pad has been assumed for the underground production, consistent with the previous operations. Reclaimed tailings are fed directly into the mill after thickening. Production Based on the mining schedules above, the table below presents the detailed life-of-mine production schedule for the Woodlawn Project on an annual basis, showing concentrate production on a dry tonne basis and gross metal content by concentrate. Moisture in the shipped concentrates is expected to be around 10%. Average annual Production Target figures are as follows for the life-of-mine (LOM) and for the 4 year period where the underground is producing at target production rates: Annual Commodity Gross Production LOM Average p.a. Steady State p.a. Zinc Kt Lead Kt Copper Kt Silver Koz 805 1,099 Gold Koz Production by Product LOM Zn Concentrate dry kt Zn kt Ag koz 2, Au koz Pb Concentrate dry kt Pb kt Cu kt Ag koz 5, Au koz Cu Concentrate dry kt Cu kt Ag koz Au koz Total Production dry kt 1, Zn kt Pb kt Cu kt Ag koz 8, , , , Au koz ASX/TSX Release Heron Resources Limited 16 of 33

17 Mining Costs Underground Underground mining costs have been developed by SRK from first principles based on the mining method, vertical development, horizontal access, stoping and back fill costs, and vary according to the physical location and characteristics of the mined material within the underground. The capital cost profile is shown above. The operating costs are provided below on a A$/t mill feed basis on a contract mining (and leased equipment) basis and include maintenance costs: Tailings Tailings materials will be recovered from the three tailings dams in sequence, utilising the proven technique of high pressure water jet monitoring. The pulped material will then be pumped to the concentrator, thickened, and processed. The mining rate is tied to the mill feed ramp up rate, described below, and the resulting schedule is provided above. The cost assumption for mining the tailings material is A$2.14/t whilst blended feed is processed, reducing to A$1.67/t mill feed when the plant is running on tailings alone. Processing & Overheads The operating cost estimate has been developed on the basis of a process plant feed tonnage of 1,500,000 tonnes per annum. The operating cost estimate is A$23.42 per tonne of feed. UG Starter Case Unit Cost A$/t Crushing & Grinding 1.96 Tailings Reclamation & Grind 3.09 Flotation Concentrate Handling 0.72 Plant services 0.76 Administration 3.86 Total Plant Operating Cost The reagent component of the operating cost is subject to exchange rate fluctuation and was based on a $1.00 AU to $0.80 US exchange rate. Additional fixed costs of A$4.25 million have been estimated and applied annually and include general administration costs, insurances, and some underground fixed costs including technical services, fuel and power. Maintenance capital is included in the operating costs above. ASX/TSX Release Heron Resources Limited 17 of 33

PRESS RELEASE NEW MINERAL RESOURCE UPDATE AT PRAIRIE CREEK MINE. Measured + Indicated and Inferred Resource Tonnages Increased

PRESS RELEASE NEW MINERAL RESOURCE UPDATE AT PRAIRIE CREEK MINE. Measured + Indicated and Inferred Resource Tonnages Increased PRESS RELEASE CZN-TSX CZICF-OTCQB FOR IMMEDIATE RELEASE March 26, 2015 NEW MINERAL RESOURCE UPDATE AT PRAIRIE CREEK MINE Measured + Indicated and Inferred Resource Tonnages Increased Underground Exploration

More information

Bass Metals records further positive drill results & progress at 3 prospects.

Bass Metals records further positive drill results & progress at 3 prospects. 16 March 2011 Bass Metals records further positive drill results & progress at 3 prospects. HIGHLIGHTS: New high-grade drilling intercept confirms Switchback potential; Drilling commences at Lake Margaret

More information

New Drilling Program Commences at Mutiny s Deflector Deposit

New Drilling Program Commences at Mutiny s Deflector Deposit New Drilling Program Commences at Mutiny s Deflector Deposit Drilling Program Highlights 12,000 metre RC and diamond drilling program underway New drilling program targets strike extensions in the Northern

More information

Ausgold awarded EIS grant for Jinkas deep drilling

Ausgold awarded EIS grant for Jinkas deep drilling ASX Release 21 June 2018 Ausgold awarded EIS grant for Jinkas deep drilling Highlights: EIS grant will support drilling at the Katanning Gold Project to a value of $150,000 Grant will partly fund four

More information

Oposura Scoping Study Nearing Completion

Oposura Scoping Study Nearing Completion 20 AUGUST 2018 KEY POINTS: Oposura Scoping Study Nearing Completion Mining study with open pit optimisations and underground mine designs completed High grade massive sulphide mineralisation occurs near

More information

News Release. Infill Drilling Program

News Release. Infill Drilling Program TSX:RMX NYSE.MKT:RBY News Release January 7, 2015 Rubicon s Infill Drilling Program Confirms Continuity and Grade of the F2 Deposit and Continues to Encounter High-Grade Mineralization in Sparsely Drilled

More information

ASX announcement 16 May 2016

ASX announcement 16 May 2016 ASX announcement 16 May 2016 Adelaide Resources Limited ABN: 75 061 503 375 Corporate details: ASX Code: ADN Cash: $0.701million (at 31 Mar 2016) Issued Capital: 357,922,352 ordinary shares 37,222,104

More information

NEWS RELEASE ORCA GOLD INDICATED AND INFERRED RESOURCES AT BLOCK 14 INCREASE BY 24% AND 48% RESPECTIVELY

NEWS RELEASE ORCA GOLD INDICATED AND INFERRED RESOURCES AT BLOCK 14 INCREASE BY 24% AND 48% RESPECTIVELY Orca Gold Inc., 2000-885 West Georgia St., Vancouver, B.C., V6C 3E8, Canada Tel: +1 604 689 7842 Fax: +1 604 689 4250 NEWS RELEASE ORCA GOLD INDICATED AND INFERRED RESOURCES AT BLOCK 14 INCREASE BY 24%

More information

King of the Hills Gold Project, Leonora, to commence production in Q2 2011

King of the Hills Gold Project, Leonora, to commence production in Q2 2011 King of the Hills Gold Project, Leonora, to commence production in Q2 2011 St Barbara is pleased to announce the King of the Hills gold project near Leonora (formerly referred to as the Tarmoola higher

More information

NEWS RELEASE. FORAN INTERSECTS 9.4% ZINC OVER 6.1 METRES Feasibility Drilling Continues

NEWS RELEASE. FORAN INTERSECTS 9.4% ZINC OVER 6.1 METRES Feasibility Drilling Continues NEWS RELEASE FORAN INTERSECTS 9.4% ZINC OVER 6.1 METRES Feasibility Drilling Continues Vancouver, BC (September 11, 2018) - Foran Mining Corporation (TSX.V: FOM) ( Foran or the Company ) is pleased to

More information

FINANCIERS MANDATED FOR THE DALGARANGA GOLD PROJECT

FINANCIERS MANDATED FOR THE DALGARANGA GOLD PROJECT September 18 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 FINANCIERS MANDATED FOR THE DALGARANGA GOLD PROJECT Two tier one Australian banks mandated to arrange

More information

NEWS RELEASE. Foran Mining Intersects High Grade Zinc at McIlvenna Bay. Results expand area of known mineralization

NEWS RELEASE. Foran Mining Intersects High Grade Zinc at McIlvenna Bay. Results expand area of known mineralization NEWS RELEASE Foran Mining Intersects High Grade Zinc at McIlvenna Bay Results expand area of known mineralization Vancouver, BC (February 20, 2018) - Foran Mining Corporation (TSX.V: FOM) ( Foran or the

More information

HERON ENTERS OPTION TO PURCHASE A1 GOLD MINE, EASTERN VICTORIA

HERON ENTERS OPTION TO PURCHASE A1 GOLD MINE, EASTERN VICTORIA ASX Release 13 AUGUST 2009 HERON ENTERS OPTION TO PURCHASE A1 GOLD MINE, EASTERN VICTORIA Heron Resources Limited (ASX:HRR, Heron) is pleased to announce it has purchased an Option (Option) to acquire

More information

QUEEN SHEBA - RESOURCE TABLE: AUGUST 2011 RESOURCE CATEGORY. Tonnes Au Ag Cu (000) g/t g/t % GLOBAL RESOURCE TABLE: CONTAINED METAL

QUEEN SHEBA - RESOURCE TABLE: AUGUST 2011 RESOURCE CATEGORY. Tonnes Au Ag Cu (000) g/t g/t % GLOBAL RESOURCE TABLE: CONTAINED METAL ASX ANNOUNCEMENT 16 SEPTEMBER 2011 Phillips River Mining NL ABN 61 004 287 790 Unit 46/328 Albany Highway VICTORIA PARK WA 6100 T: 08 6250 4600 F: 08 6250 4699 info@phillipsriver.com.au CONTACT Jason Stirbinskis

More information

60% upgrade of Flying Doctor Resource to 104,600 tonnes of contained zinc and lead.

60% upgrade of Flying Doctor Resource to 104,600 tonnes of contained zinc and lead. 30 April 2008 60% upgrade of Flying Doctor Resource to 104,600 tonnes of contained zinc and lead. Perilya Limited (ASX: PEM) is pleased to announce a 60% increase in the mineral resource estimate for the

More information

FOR IMMEDIATE RELEASE August 9 th, 2018 (VTT2018 NR #7)

FOR IMMEDIATE RELEASE August 9 th, 2018 (VTT2018 NR #7) FOR IMMEDIATE RELEASE August 9 th, 2018 (VTT2018 NR #7) Vendetta Increases Pegmont Lead-Zinc Mineral Resource to 5.8 Million Tonnes and 8.3 Million Tonnes of. Open Pit Constrained Mineral Resource now

More information

TriAusMin Limited LEWIS PONDS PROJECT

TriAusMin Limited LEWIS PONDS PROJECT TriAusMin Limited LEWIS PONDS PROJECT TSX: TOR November 2010 ASX: TRO Disclaimer The Information contained in this presentation has been prepared using the information available to TriAusMin at the time

More information

Vendetta Reports Initial Results from 2017 Pegmont Program with High Grade Zone 3 Step Out Drilling

Vendetta Reports Initial Results from 2017 Pegmont Program with High Grade Zone 3 Step Out Drilling FOR IMMEDIATE RELEASE July 25 th, 2017 (VTT2017 NR # 7) Vendetta Reports Initial Results from 2017 Pegmont Program with High Grade Zone 3 Step Out Drilling Vancouver, BC July 25 th, 2017 - Vendetta Mining

More information

For personal use only

For personal use only 18 April 2018 ASX Announcement DRILLING UNDERWAY AT SLATE DAM GOLD PROJECT HIGHLIGHTS 2nd Phase Drilling Program underway at Slate Dam - 9 RC holes for ~1,000m completed to date Program designed to expand

More information

For personal use only

For personal use only ASX Announcement 15 March 2017 HIGHLIGHTS Drill contractors have been engaged with drilling to commence April 2017 pending access approvals Two mineralised lodes within the oxide volcanogenic massive sulphide

More information

$2.5 Million Resource Drilling Program Commences at Siberia Mining Centre

$2.5 Million Resource Drilling Program Commences at Siberia Mining Centre ASX ANNOUNCEMENT 14 June 2016 $2.5 Million Resource Drilling Program Commences at Siberia Mining Centre Eastern Goldfields Limited (ASX: EGS) (Eastern Goldfields or the Company) is pleased to announce

More information

High-grade Copper and Gold Discovered at Productora

High-grade Copper and Gold Discovered at Productora ASX ANNOUNCEMENT Tuesday 25th September 2012 High-grade Copper and Gold Discovered at Productora Potential for High-grade Copper-Gold Shoots to Add New Dimension to Productora High-grade copper-gold discovered

More information

Vendetta Reports Additional High Grade Drilling Results from Zones 2 and 3 at Pegmont Lead-Zinc Project

Vendetta Reports Additional High Grade Drilling Results from Zones 2 and 3 at Pegmont Lead-Zinc Project FOR IMMEDIATE RELEASE August 24 th, 2017 (VTT2017 NR # 9) Vendetta Reports Additional High Grade Drilling Results from Zones 2 and 3 at Pegmont Lead-Zinc Project Vancouver, BC August 24 th, 2017 Vendetta

More information

Assay Results Highlights (as of November 16, 2017) representing approximately 4,500 metres ( m ) of drilling:

Assay Results Highlights (as of November 16, 2017) representing approximately 4,500 metres ( m ) of drilling: TSX: RMX OTCQX: RBYCF Rubicon Minerals Provides Additional Drill Results and Observations from its 2017 Exploration Program and Commences Exploratory Underground Development TORONTO, Ontario, November

More information

ASX ANNOUNCEMENT 21 MARCH 2011

ASX ANNOUNCEMENT 21 MARCH 2011 ASX ANNOUNCEMENT 21 MARCH 2011 Sihayo Pungkut Gold Project New JORC Compliant Estimate Sihayo Resource increases 43% to 1.30 Million ounces, total project resources grow to 1.4 million ounces Highlights

More information

For personal use only

For personal use only 17 February 2011 ASX ANNOUNCEMENT SCOPING STUDY IDENTIFIES PLATFORM FOR OPEN PIT AND UNDERGROUND DEVELOPMENT OF THE SANDIEGO DEPOSIT Anglo Australian Resources NL ( AAR ) is pleased to report The Scoping

More information

Option agreement with Randgold set to commercialise Massigui Gold Project

Option agreement with Randgold set to commercialise Massigui Gold Project ASX Announcement 4 November 2016 Option agreement with Randgold set to commercialise Massigui Gold Project Option agreement with the Morila mine-operator provides potential low risk and low cost processing

More information

North American Palladium Announces Positive Exploration Results from Lac des Iles Mine

North American Palladium Announces Positive Exploration Results from Lac des Iles Mine North American Palladium Announces Positive Exploration Results from Lac des Iles Mine Toronto, Ontario, October 24, 2017 North American Palladium Ltd. ( NAP or the Company ) (TSX: PDL) (OTC PINK: PALDF)

More information

P ROJ EC T UPDATE PANDA HILL NIOBIUM PROJ ECT

P ROJ EC T UPDATE PANDA HILL NIOBIUM PROJ ECT 2 September 2013 ASX Release ASX Code: CXX P ROJ EC T UPDATE PANDA HILL NIOBIUM PROJ ECT Highlights Project is on schedule, with completion of the preliminary economic assessment study on target for Quarter

More information

Blox, Inc. Announces New Drilling Target Defined at Mansounia Gold Project.

Blox, Inc. Announces New Drilling Target Defined at Mansounia Gold Project. Blox, Inc. Announces New Drilling Target Defined at Mansounia Gold Project. Vancouver, British Columbia, July 6, 2018 Blox, Inc. (OTCQB: BLXX), ( Blox or the Company ) is pleased to announce that a new

More information

Monument Announces NOA 7/8 Drilling Program Results at Burnakura Gold Project

Monument Announces NOA 7/8 Drilling Program Results at Burnakura Gold Project September 24, 2018 News Release Release #15 2018 Monument Announces NOA 7/8 Drilling Program Results at Burnakura Gold Project Vancouver, B.C. Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument"

More information

News Release DRILLING STEPPED UP AT FORRESTANIA NICKEL PROJECT AND UPDATE ON DIGGERS SOUTH PRE - FEASIBILITY STUDY

News Release DRILLING STEPPED UP AT FORRESTANIA NICKEL PROJECT AND UPDATE ON DIGGERS SOUTH PRE - FEASIBILITY STUDY June 29, 2007 ASX & TSX: WSA News Release DRILLING STEPPED UP AT FORRESTANIA NICKEL PROJECT AND UPDATE ON DIGGERS SOUTH PRE - FEASIBILITY STUDY The Board of Western Areas is pleased to announce that the

More information

OSISKO METALS INTERSECTS 10.49% ZINC+LEAD OVER METRES AND 12.15% ZINC+LEAD OVER METRES AT PINE POINT

OSISKO METALS INTERSECTS 10.49% ZINC+LEAD OVER METRES AND 12.15% ZINC+LEAD OVER METRES AT PINE POINT OSISKO METALS INTERSECTS 10.49% ZINC+LEAD OVER 22.84 METRES AND 12.15% ZINC+LEAD OVER 17.00 METRES AT PINE POINT (Montreal November 19, 2018) Osisko Metals Incorporated (the Company or Osisko Metals )

More information

CROCODILE GOLD FILES TECHNICAL REPORTS FOR FOSTERVILLE AND COSMO GOLD MINES AND PROVIDES ANNUAL GENERAL MEETING INFORMATION

CROCODILE GOLD FILES TECHNICAL REPORTS FOR FOSTERVILLE AND COSMO GOLD MINES AND PROVIDES ANNUAL GENERAL MEETING INFORMATION 65 Queen Street West Suite 825, P.O. Box 75 Toronto, Ontario M5H 2M5 Canada CROCODILE GOLD FILES TECHNICAL REPORTS FOR FOSTERVILLE AND COSMO GOLD MINES AND PROVIDES ANNUAL GENERAL MEETING INFORMATION May

More information

ASX/Media Announcement

ASX/Media Announcement ASX/Media Announcement 25 March 2013 MAIDEN HIGH-GRADE JUDY LODE RESOURCE INDICATES POTENTIAL TO INCREASE ANDY WELL MINE LIFE 106,000 ounce high-grade resource (Indicated & Inferred) Judy South (137,000t

More information

GOLDEN MINERALS DISCOVERS ADDITIONAL HIGH GRADE VEINS AT SANTA MARIA RESULTS UP TO 1.88 g/t Au and 648 g/t Ag

GOLDEN MINERALS DISCOVERS ADDITIONAL HIGH GRADE VEINS AT SANTA MARIA RESULTS UP TO 1.88 g/t Au and 648 g/t Ag GOLDEN MINERALS DISCOVERS ADDITIONAL HIGH GRADE VEINS AT SANTA MARIA RESULTS UP TO 1.88 g/t Au and 648 g/t Ag Golden, Colorado /Globe Newswire/ July 12, 2018 Golden Minerals Company (NYSE American and

More information

For personal use only

For personal use only ASX RELEASE 2 August 2011 Significant Gold intersections at Chameleon Prospect Maiden 15 hole RC drilling programme (3,170 metres) completed by Scotia Gold Rights JV partner, Aphrodite Gold at the Chameleon

More information

SALAZAR ANNOUNCES AN UPDATED RESOURCE REPORT OF 5.53 MT INDICATED AND 1.46 MT INFERRED AT ITS HIGH GRADE VMS EL DOMO DEPOSIT

SALAZAR ANNOUNCES AN UPDATED RESOURCE REPORT OF 5.53 MT INDICATED AND 1.46 MT INFERRED AT ITS HIGH GRADE VMS EL DOMO DEPOSIT SALAZAR ANNOUNCES AN UPDATED 43-101 RESOURCE REPORT OF 5.53 MT INDICATED AND 1.46 MT INFERRED AT ITS HIGH GRADE VMS EL DOMO DEPOSIT VANCOUVER, BRITISH COLUMBIA, January 12, 2012 - Salazar Resources Ltd.

More information

HIGHLIGHTS INCLUDE: ^ Includes 466g/t Au Includes 153g/t Au + Includes 45.3g/t Au

HIGHLIGHTS INCLUDE: ^ Includes 466g/t Au Includes 153g/t Au + Includes 45.3g/t Au Atlantic Gold Announces Additional Drill Results From Resource Extension Drilling At The Cochrane Hill Gold Deposit HIGHLIGHTS INCLUDE: COCHRANE HILL GOLD DEPOSIT 11m @ 43.65 g/t Au from 227m^ 7m @ 23.69

More information

MAJOR EXPLORATION SUCCESS AT JACK HILLS IRON ORE PROJECT EXPLORATION TARGET OF ADDITIONAL MILLION TONNES

MAJOR EXPLORATION SUCCESS AT JACK HILLS IRON ORE PROJECT EXPLORATION TARGET OF ADDITIONAL MILLION TONNES ASX ANNOUNCEMENT ASX CODE: MMX 3 September 2009 MAJOR EXPLORATION SUCCESS AT JACK HILLS IRON ORE PROJECT EXPLORATION TARGET OF ADDITIONAL 400-1000 MILLION TONNES Murchison Metals Limited (Murchison) is

More information

STEP-OUT DRILLING EXTENDS HIGH GRADE COPPER ZONE AT SYNDICATED S 100% BARBARA SOUTH LODE

STEP-OUT DRILLING EXTENDS HIGH GRADE COPPER ZONE AT SYNDICATED S 100% BARBARA SOUTH LODE November 5th 2009 Manager Announcements Companies Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000 STEP-OUT DRILLING EXTENDS HIGH GRADE COPPER ZONE

More information

ATLANTIC GOLD REPORTS ADDITIONAL RESULTS FROM THE PHASE 3 RESOURCE EXPANSION DRILL PROGRAM AT FIFTEEN MILE STREAM

ATLANTIC GOLD REPORTS ADDITIONAL RESULTS FROM THE PHASE 3 RESOURCE EXPANSION DRILL PROGRAM AT FIFTEEN MILE STREAM ATLANTIC GOLD REPORTS ADDITIONAL RESULTS FROM THE PHASE 3 RESOURCE EXPANSION DRILL PROGRAM AT FIFTEEN MILE STREAM HIGHLIGHTS INCLUDE: Egerton Maclean: 11m @ 2.22g/t from 24m, 23m @ 1.04g/t from 7m and

More information

Malachite Resources Limited ABN

Malachite Resources Limited ABN Malachite Resources Limited ABN 86 075 63 268 ASX Announcement ASX Code: MAR 27 October 20 NEW DRILLING RESULTS AT LORENA SUPPORT COMMENCEMENT OF MINING FEASIBILITY STUDY Malachite Resources Limited (

More information

NEWS RELEASE. Foran Intersects Over 28 Metres of Copper Mineralization

NEWS RELEASE. Foran Intersects Over 28 Metres of Copper Mineralization NEWS RELEASE Foran Intersects Over 28 Metres of Copper Mineralization Vancouver, BC (May 7, 2018) - Foran Mining Corporation (TSX.V: FOM) ( Foran or the Company ) announces results of two additional drill

More information

High-grade Gold in First Drilling Undertaken at Productora South

High-grade Gold in First Drilling Undertaken at Productora South ASX ANNOUNCEMENT Wednesday 10th October 2012 High-grade Gold in First Drilling Undertaken at Productora South Shallow, high-grade, narrow-vein gold area adds further up-side to Productora Sierra Zapallo

More information

MARCH 2010 QUARTERLY REPORT

MARCH 2010 QUARTERLY REPORT MARCH 2010 QUARTERLY REPORT ASX Release HIGHLIGHTS Friday 30 April 2010 SIGNATURE METALS LIMITED Level 1 / 33 Richardson Street WEST PERTH Australia Tel: +61 8 9481 0101 Fax: +61 8 9200 4469 Contact: Bill

More information

A B C PAD A HIGHLIGHTS

A B C PAD A HIGHLIGHTS Murchison Minerals Intercepts 12.30% Zinc, 0.70% Copper, 0.18% Lead and 42.03 g/t Silver 14.97% ZnEq over 6.37 Metres and Extends Known Limits of Brabant McKenzie VMS Deposit June 25, 2018 (Toronto, Ontario):

More information

Intensive Field Based Exploration Program Commences at Dobsina Cobalt-Nickel-Copper Sulphide Project

Intensive Field Based Exploration Program Commences at Dobsina Cobalt-Nickel-Copper Sulphide Project 5 th July 2017 Intensive Field Based Exploration Program Commences at Dobsina Cobalt-Nickel-Copper Sulphide Project Intensive site based exploration has commenced at Dobsina Co-Ni Project. Activities include:

More information

NEWS RELEASE FORAN INTERSECTS 27 METRES OF CONTINUOUS MINERALIZATION

NEWS RELEASE FORAN INTERSECTS 27 METRES OF CONTINUOUS MINERALIZATION NEWS RELEASE FORAN INTERSECTS 27 METRES OF CONTINUOUS MINERALIZATION Including 8.2m of massive sulphide grading 11.3% Zn Vancouver, BC (September 27, 2018) - Foran Mining Corporation (TSX.V: FOM) ( Foran

More information

Replacement: Material Increase to Tuzon Resource

Replacement: Material Increase to Tuzon Resource Replacement: Material Increase to Tuzon Resource RNS Number : 1067C Hummingbird Resources PLC 12 March 2014 Hummingbird Resources plc ("Hummingbird Resources" or the "Company") (AIM: HUM) THE FOLLOWING

More information

Probe Metals Continues to Expand Gold Zones At Val-d Or East

Probe Metals Continues to Expand Gold Zones At Val-d Or East NEWS RELEASE 02/2018 Symbol: TSX-V: PRB Shares Issued: 93,914,742 Highlights: Probe Metals Continues to Expand Gold Zones At Val-d Or East New Beliveau Deposit resource expansion drilling to the West returned

More information

Probe Metals Intersects 3.2 g/t Gold Over 45.5 Metres At Val-d Or East

Probe Metals Intersects 3.2 g/t Gold Over 45.5 Metres At Val-d Or East NEWS RELEASE 11/2018 Symbol: TSX-V: PRB Shares Issued: 110,584,945 Highlights: Probe Metals Intersects 3.2 g/t Gold Over 45.5 Metres At Val-d Or East Near-surface intercept grading 3.2 g/t Au over 45.5

More information

HIGH-GRADE GOLD MINERALISATION CONTINUES ALONG STRIKE AT THE BODDINGTON SOUTH GOLD PROJECT

HIGH-GRADE GOLD MINERALISATION CONTINUES ALONG STRIKE AT THE BODDINGTON SOUTH GOLD PROJECT The Manager ASX Company Announcements PO Box H224, Australia Square Sydney NSW 2001 22 December 2010 HIGH-GRADE GOLD MINERALISATION CONTINUES ALONG STRIKE AT THE BODDINGTON SOUTH GOLD PROJECT New true-width

More information

24 October Dear Shareholders, 2014 ANNUAL REPORT

24 October Dear Shareholders, 2014 ANNUAL REPORT Azumah Resources Limited ABN 72 112 320 251 Suite 2, 11 Ventnor Avenue West Perth WA 6005 PO Box 1073 West Perth WA 6872 P +618 9486 7911 F +618 9481 4417 W www.azumahresources.com.au E info@azumahresources.com.au

More information

New High Grade Gold-Copper Extensions At Mutiny s Deflector Deposit Highlight Project s Significant Growth Potential

New High Grade Gold-Copper Extensions At Mutiny s Deflector Deposit Highlight Project s Significant Growth Potential ASX/Media Release P. (08) 9368 2722 F. (08) 9367 9043 E. mgl@mutinygold.com.au 18 March 2011 New High Grade Gold-Copper Extensions At Mutiny s Deflector Deposit Highlight Project s Significant Growth Potential

More information

For personal use only OZ MINERALS CARRAPATEENA COPPER GOLD PROJECT SOUTH AUSTRALIA 27 MARCH 2012

For personal use only OZ MINERALS CARRAPATEENA COPPER GOLD PROJECT SOUTH AUSTRALIA 27 MARCH 2012 OZ MINERALS CARRAPATEENA COPPER GOLD PROJECT SOUTH AUSTRALIA 27 MARCH 2012 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written

More information

Northern Dynasty Minerals Ltd.

Northern Dynasty Minerals Ltd. Northern Dynasty Minerals Ltd. 1020 800 W Pender St. Vancouver BC Canada V6C 2V6 Tel 604 684-6365 Fax 604 684-8092 Toll Free 1 800 667-2114 http://www.northerndynasty.com RESOURCE ESTIMATE FOR PEBBLE EAST

More information

NEWS RELEASE ORCA GOLD REPORTS CONTINUED SUCCESS AT GSS

NEWS RELEASE ORCA GOLD REPORTS CONTINUED SUCCESS AT GSS NEWS RELEASE OA GOLD REPORTS CONTINUED SUCCESS AT GSS May 26, 2014 Orca Gold Inc. (TSX.V:ORG) ( Orca or the Company ) is pleased to provide an update on exploration at its Galat Sufar South ( GSS ) prospect

More information

Caravel commences major new drilling program at Calingiri copper-molybdenum project 8,500-9,000m of RC drilling planned across multiple targets

Caravel commences major new drilling program at Calingiri copper-molybdenum project 8,500-9,000m of RC drilling planned across multiple targets FOR IMMEDIATE RELEASE: 14 JANUARY, 2015 CVV ASX Shares Outstanding: 727m Caravel commences major new drilling program at Calingiri copper-molybdenum project 8,500-9,000m of RC drilling planned across multiple

More information

Vendetta Mining Intersects Meters of 11.91% Pb+Zn from Zone 5 at the Pegmont Lead-Zinc Deposit

Vendetta Mining Intersects Meters of 11.91% Pb+Zn from Zone 5 at the Pegmont Lead-Zinc Deposit FOR IMMEDIATE RELEASE November 30 th, 2016 (VTT2016 NR # 9) Vendetta Mining Intersects 14.77 Meters of 11.91 Pb+Zn from Zone 5 at the Pegmont Lead-Zinc Deposit Vancouver, BC November 30 th, 2016 Vendetta

More information

LUNDIN MINING ANNOUNCES EAGLE EAST MINERAL RESOURCE, PEA RESULTS AND PROJECT COMMENCMENT

LUNDIN MINING ANNOUNCES EAGLE EAST MINERAL RESOURCE, PEA RESULTS AND PROJECT COMMENCMENT NEWS RELEASE Corporate Office 150 King Street West, Suite 1500 P.O. Box 38 Toronto, ONM5H 1J9 Phone: +1 416 342 5560 Fax: +1 416 348 0303 UK Office Ground Floor Hayworthe House, 2 Market Place, Haywards

More information

Highlights. 9 November 2018 DRILLING UPDATE - SORBY HILLS Pb-Ag-Zn PROJECT CORPORATE DIRECTORY

Highlights. 9 November 2018 DRILLING UPDATE - SORBY HILLS Pb-Ag-Zn PROJECT CORPORATE DIRECTORY 9 November 2018 DRILLING UPDATE - SORBY HILLS Pb-Ag-Zn PROJECT CORPORATE DIRECTORY Managing Director Simon Noon Directors Richard Monti (Chairman) Peter Harold (Non-exec.) Andrew Parker (Non-exec.) Company

More information

Highlights from the four holes announced in this news release include:

Highlights from the four holes announced in this news release include: November 20, 2017 OTCQB: SVBL, TSX: SVB SILVER BULL INTERSECTS 9 METERS OF SULPHIDE MINERALIZATION GRADING 20.7% ZINC, 1% LEAD AND 98G/T SILVER, INCLUDING 3.65 METERS OF MASSIVE SULPHIDE MINERALIZATION

More information

Kalana Main Diluted Mineral Resource Estimate Above a 0.9 g/t Au Cut-off Grade 1,2

Kalana Main Diluted Mineral Resource Estimate Above a 0.9 g/t Au Cut-off Grade 1,2 Avnel Reports that Measured plus Indicated Resource Increases to 2.81 Million Ounces of Gold at a Diluted Grade of 2.85 g/t at Kalana Main Deposit at $1,100/oz ST. PETER PORT, GUERNSEY, OCTOBER 5, 2015

More information

ASANKO GOLD ANNOUNCES ENCOURAGING INITIAL DRILL RESULTS FROM NEW EXPLORATION TARGET

ASANKO GOLD ANNOUNCES ENCOURAGING INITIAL DRILL RESULTS FROM NEW EXPLORATION TARGET PRESS RELEASE ASANKO GOLD ANNOUNCES ENCOURAGING INITIAL DRILL RESULTS FROM NEW EXPLORATION TARGET Highlights: Highly encouraging results from new near-mine exploration target, Akwasiso 10,000 metres of

More information

Exploration Program planned at White Rock s Red Mountain zinc project in Alaska

Exploration Program planned at White Rock s Red Mountain zinc project in Alaska ASX and Media Release: 18 December 2017 ASX Code: WRM Exploration Program planned at White Rock s Red Mountain zinc project in Alaska ASX Code: WRM Issued Securities Shares: 907.7 million Options: 206.9

More information

PRESS RELEASE. Banro Announces a Mineral Reserve Estimate at its Namoya Gold Mine, Democratic Republic of the Congo

PRESS RELEASE. Banro Announces a Mineral Reserve Estimate at its Namoya Gold Mine, Democratic Republic of the Congo PRESS RELEASE Banro Announces a Mineral Reserve Estimate at its Namoya Gold Mine, Democratic Republic of the Congo - Banro s total Proven & Probable Mineral Reserves now 2.36 Moz Au - Banro s total Measured

More information

For personal use only

For personal use only 18 April 2013 ASX CODE: KAS OUR PRIME COMMODITY IS TIN HIGHLIGHTS Drilling Confirms Continuity & Grade at Achmmach Drilling on sections 3130mE, 3170mE and 3290mE has successfully confirmed position, continuity

More information

CROCODILE GOLD INTERSECTS 7.1 G/T AU OVER 4.5 METERS INCLUDING 11.2 G/T AU OVER 2.6 METERS AT THE UNION REEFS PROJECT, PROSPECT DEPOSIT

CROCODILE GOLD INTERSECTS 7.1 G/T AU OVER 4.5 METERS INCLUDING 11.2 G/T AU OVER 2.6 METERS AT THE UNION REEFS PROJECT, PROSPECT DEPOSIT 65 Queen Street West Suite 825, P.O. Box 75 Toronto, Ontario M5H 2M5 Canada CROCODILE GOLD INTERSECTS 7.1 G/T AU OVER 4.5 METERS INCLUDING 11.2 G/T AU OVER 2.6 METERS AT THE UNION REEFS PROJECT, PROSPECT

More information

76,000 Ounce Gold Resource at Akoko North

76,000 Ounce Gold Resource at Akoko North 31 st March 2009 76,000 Ounce Gold Resource at Akoko North 76,000 ounce Indicated and Inferred Mineral Resource estimated for Akoko North gold deposit Scoping study (assuming toll milling) estimates $A24M

More information

Minsud to recommence resource outline diamond drilling at the Chita Valley Cu- Au-Ag-Mo Project, San Juan, Argentina

Minsud to recommence resource outline diamond drilling at the Chita Valley Cu- Au-Ag-Mo Project, San Juan, Argentina TSX-V: MSR August 17, 2016 Minsud to recommence resource outline diamond drilling at the Chita Valley Cu- Au-Ag-Mo Project, San Juan, Argentina Program features preliminary test of Epithermal Au-Ag Vein

More information

The Manager Companies ASX Limited 20 Bridge Street

The Manager Companies ASX Limited 20 Bridge Street ABN 79 106 879 690 10 July 2012 The Manager Companies ASX Limited 20 Bridge Street SYDNEY NSW 2000 (5 pages by email) Dear Madam, 1.54 Moz Gold Equivalent Maiden Gold/Copper Resource at Wonogiri The Directors

More information

Probe Metals Continues to Intersect Significant Gold Mineralization in Expansion Drilling at Val-d Or East, including 4.1 g/t Gold Over 15.

Probe Metals Continues to Intersect Significant Gold Mineralization in Expansion Drilling at Val-d Or East, including 4.1 g/t Gold Over 15. NEWS RELEASE 10/2018 Symbol: TSX-V: PRB Shares Issued: 110,584,945 Probe Metals Continues to Intersect Significant Gold Mineralization in Expansion Drilling at Val-d Or East, including 4.1 g/t Gold Over

More information

MANDALAY RESOURCES CORPORATION INCREASES MINERAL RESOURCES AND RESERVES AT ITS BJÖRKDAL GOLD MINE

MANDALAY RESOURCES CORPORATION INCREASES MINERAL RESOURCES AND RESERVES AT ITS BJÖRKDAL GOLD MINE MANDALAY RESOURCES CORPORATION INCREASES MINERAL RESOURCES AND RESERVES AT ITS BJÖRKDAL GOLD MINE TORONTO, ON, December 15, 2016 -- Mandalay Resources Corporation ("Mandalay" or the "Company") (TSX: MND)

More information

CORPORATE UPDATE. Feasibility Study being finalised for completion towards the end of April.

CORPORATE UPDATE. Feasibility Study being finalised for completion towards the end of April. 16 March 2018 Company Announcement Officer ASX Limited 20 Bridge Street SYDNEY NSW 2000 Highlights CORPORATE UPDATE Inaugural Bowdens Reserve Statement due early April. Feasibility Study being finalised

More information

ASX Release 29 November 2017

ASX Release 29 November 2017 Middle Island Resources Ltd ACN 142 361 608 ASX code: MDI www.middleisland.com.au ASX Release 29 November 2017 Substantial Exploration Target announced for key deposit at Sandstone gold project, WA Capital

More information

For personal use only

For personal use only Company Announcements Office, ASX Securities Limited, 20, Bridge Street, Sydney, N.S.W. 2000 COMMENCEMENT OF DRILLING, PILOT MOUNTAIN - NEVADA The Board of Thor Mining Plc ( Thor or the Company ) (AIM,

More information

INFILL DRILLING EXPANDS MINERALIZATION IN HIGH-GRADE GOLD-COPPER CORE AT SOUTHWEST DISCOVERY ZONE TURQUOISE HILL PROJECT, MONGOLIA

INFILL DRILLING EXPANDS MINERALIZATION IN HIGH-GRADE GOLD-COPPER CORE AT SOUTHWEST DISCOVERY ZONE TURQUOISE HILL PROJECT, MONGOLIA For Immediate Release November 18, 2002 INFILL DRILLING EXPANDS MINERALIZATION IN HIGH-GRADE GOLD-COPPER CORE AT SOUTHWEST DISCOVERY ZONE TURQUOISE HILL PROJECT, MONGOLIA 110 METRES GRADING 4.08 G/T GOLD

More information

EXPLORATION ACTIVITY TO RECOMMENCE AT KOURI GOLD PROJECT IN BURKINA FASO

EXPLORATION ACTIVITY TO RECOMMENCE AT KOURI GOLD PROJECT IN BURKINA FASO ASX/Media Announcement 26 April 2017 EXPLORATION ACTIVITY TO RECOMMENCE AT KOURI GOLD PROJECT IN BURKINA FASO Exploration program targeting the definition of a maiden JORC Mineral Resource by the end of

More information

Exploration targets identified to increase Browns Range Project s mine life

Exploration targets identified to increase Browns Range Project s mine life Exploration targets identified to increase Browns Range Project s mine life Highlights Exploration Target estimate demonstrates the potential for very significant increases in Total Mineral Resource at

More information

San Gold Drills New Mine Horizon Adjacent to Rice Lake Mine, Returns 10.4 Metres Grading 25.7 g/t Au

San Gold Drills New Mine Horizon Adjacent to Rice Lake Mine, Returns 10.4 Metres Grading 25.7 g/t Au SAN GOLD CORPORATION TSX: SGR OTCQX: SGRCF FOR IMMEDIATE RELEASE October 15, 2014 San Gold Drills New Mine Horizon Adjacent to Rice Lake Mine, Returns 10.4 Metres Grading 25.7 g/t Au WINNIPEG, MANITOBA

More information

KIRKLAND LAKE GOLD ANNOUNCES 120 METRE DOWN-PLUNGE EXTENSION OF SWAN ZONE

KIRKLAND LAKE GOLD ANNOUNCES 120 METRE DOWN-PLUNGE EXTENSION OF SWAN ZONE KIRKLAND LAKE GOLD ANNOUNCES 120 METRE DOWN-PLUNGE EXTENSION OF SWAN ZONE High-grade, visible-gold mineralization intersected 120 metres ( m ) down-plunge of Swan Zone Inferred Mineral Resource and 210

More information

MCEWEN MINING ANNOUNCES EXPLORATION UPDATE FOR EL GALLO 1, MEXICO

MCEWEN MINING ANNOUNCES EXPLORATION UPDATE FOR EL GALLO 1, MEXICO MCEWEN MINING ANNOUNCES EXPLORATION UPDATE FOR EL GALLO 1, MEXICO TORONTO, ONTARIO - (April 21, 2015) - McEwen Mining Inc. (NYSE: MUX) (TSX: MUX) is pleased to announce drill results that we expect will

More information

Resource Diamond Drilling Commences at Productora. Strong results continue from Productora central area drilling

Resource Diamond Drilling Commences at Productora. Strong results continue from Productora central area drilling Resource Diamond Drilling Commences at Productora Strong results continue from Productora central area drilling Resource diamond drilling commences at Productora 5 drill rigs to be operating shortly Productora

More information

FALCO PACIFIC COMPLETES INITIAL MODEL FOR THE HORNE 5 GOLD/SILVER/ZINC/COPPER DEPOSIT

FALCO PACIFIC COMPLETES INITIAL MODEL FOR THE HORNE 5 GOLD/SILVER/ZINC/COPPER DEPOSIT For Immediate Release NR 13-10 FALCO PACIFIC COMPLETES INITIAL MODEL FOR THE HORNE 5 GOLD/SILVER/ZINC/COPPER DEPOSIT (Vancouver, BC, September 16, 2013) Falco Pacific Resource Group Inc. ( Falco Pacific

More information

ASX Code: ORN Compelling Nickel-Copper Targets Defined at Fraser Range Project

ASX Code: ORN   Compelling Nickel-Copper Targets Defined at Fraser Range Project ASX Code: ORN www.oriongold.com.au Compelling Nickel-Copper Targets Defined at Fraser Range Project 1 Disclaimer and Forward-Looking Statements Certain statements contained in this presentation, including

More information

NEWS RELEASE CANADIAN ZINC REPORTS REMAINING DRILL RESULTS AT LEMARCHANT DEPOSIT, SOUTH TALLY POND PROJECT, NEWFOUNDLAND

NEWS RELEASE CANADIAN ZINC REPORTS REMAINING DRILL RESULTS AT LEMARCHANT DEPOSIT, SOUTH TALLY POND PROJECT, NEWFOUNDLAND NEWS RELEASE CZN-TSX CZICF-OTCQB FOR IMMEDIATE RELEASE March 5, 2018 CANADIAN ZINC REPORTS REMAINING DRILL RESULTS AT LEMARCHANT DEPOSIT, SOUTH TALLY POND PROJECT, NEWFOUNDLAND 2017 drill program successfully

More information

WHAT IS MINERAL EXPLORATION?

WHAT IS MINERAL EXPLORATION? INDABA PRESENTATION CAPE TOWN FEBRUARY 2017 AIM:SAV WHAT IS MINERAL EXPLORATION? AIM:SAV What is mineral exploration? 2 Exploration is the term used to describe a wide range of activities aimed at searching

More information

ACQUISITION OF THE MCCLEERY COPPER-COBALT PROJECT, CANADA

ACQUISITION OF THE MCCLEERY COPPER-COBALT PROJECT, CANADA ACQUISITION OF THE MCCLEERY COPPER-COBALT PROJECT, CANADA HIGHLIGHTS New claims staked covering ~9km 2 to secure a 100% interest in the McCleery Copper-Cobalt Project in the Yukon Territory, Canada ABN

More information

DRILLING AT ASCOT S PREMIER PROPERTY EXTENDS GOLD MINERALIZATION 150 METRES WEST TOWARDS UNDERGROUND PORTAL

DRILLING AT ASCOT S PREMIER PROPERTY EXTENDS GOLD MINERALIZATION 150 METRES WEST TOWARDS UNDERGROUND PORTAL Ascot Resources Ltd. Suite 1550-505 Burrard St. Vancouver, B.C., V7X 1M5 T: 778-725-1060 F: 778-725-1070 TF: 855-593-2951 www.ascotgold.com For Immediate Release NR18.17 DRILLING AT ASCOT S PREMIER PROPERTY

More information

Disclaimer. Forward-Looking Statements. Competent Person s Statement

Disclaimer. Forward-Looking Statements. Competent Person s Statement Ulysses: Genesis of a significant new underground gold mine near Leonora, WA Michael Fowler, Managing Director Resources Rising Stars, May 29-30 2018 Disclaimer Forward-Looking Statements Some statements

More information

V Sample from C.O.D vein 15 metres southwest of V

V Sample from C.O.D vein 15 metres southwest of V TSX-V: GGX Gold Drop Property Multiple Gold Bearing Rock Samples including 19.6 g/t Gold at Historic C.O.D Shaft And 14.1 g/t Gold at New Vein Showing Greenwood BC Vancouver, British Columbia June 8, 2017

More information

NEWS RELEASE TSX-V Ticker: SWA 23 April 2013 SWA.WT SARAMA RESOURCES EXTENDS HIGH-GRADE MINERALISATION AT MM PROSPECT IN BURKINA FASO

NEWS RELEASE TSX-V Ticker: SWA 23 April 2013 SWA.WT SARAMA RESOURCES EXTENDS HIGH-GRADE MINERALISATION AT MM PROSPECT IN BURKINA FASO NEWS RELEASE TSX-V Ticker: SWA 23 April 2013 SWA.WT SARAMA RESOURCES EXTENDS HIGH-GRADE MINERALISATION AT MM PROSPECT IN BURKINA FASO VANCOUVER, CANADA. Sarama Resources Limited ( Sarama or the Company

More information

NEWS RELEASE. Mountain Province Diamonds Reports Additional Kimberlite Identified in Gahcho Kué Exploration Program

NEWS RELEASE. Mountain Province Diamonds Reports Additional Kimberlite Identified in Gahcho Kué Exploration Program NEWS RELEASE September 17, 2018 TSX and NASDAQ: MPVD Mountain Province Diamonds Reports Additional Kimberlite Identified in Gahcho Kué Exploration Program Toronto and New York, September 17, 2018 Mountain

More information

For personal use only

For personal use only 1 ASX: BRW Drilling for Exploration Success Building an Australian Base Metal Company Resources Rising Stars 27 September 2011 David Hutton, Managing Director Disclaimer 2 Certain oral and written statements

More information

CROCODILE GOLD CONTINUES POSITIVE EXPLORATION RESULTS INTERSECTS HIGH GRADE GOLD AT UNION REEFS PROJECT

CROCODILE GOLD CONTINUES POSITIVE EXPLORATION RESULTS INTERSECTS HIGH GRADE GOLD AT UNION REEFS PROJECT 65 Queen Street West CROCODILE GOLD CONTINUES POSITIVE EXPLORATION RESULTS INTERSECTS HIGH GRADE GOLD AT UNION REEFS PROJECT July 6, 2011 Crocodile Gold Corp. (TSX:CRK) (OTCQX:CROCF) (Frankfurt:XGC) (

More information

CHAMPION IRON REPORTS EXPLORATION RESULTS AT POWDERHORN PROJECT, NEWFOUNDLAND

CHAMPION IRON REPORTS EXPLORATION RESULTS AT POWDERHORN PROJECT, NEWFOUNDLAND PRESS RELEASE CHAMPION IRON REPORTS EXPLORATION RESULTS AT POWDERHORN PROJECT, NEWFOUNDLAND Confirmed Continuity of High-Grade Zinc Zone and Addition of Gold to the Expanded Copper Zone Montreal, March

More information

ATLANTIC GOLD ANNOUNCES MINERAL RESOURCE ESTIMATES FOR FIFTEEN MILE STREAM AND COCHRANE HILL DEPOSITS, NOVA SCOTIA

ATLANTIC GOLD ANNOUNCES MINERAL RESOURCE ESTIMATES FOR FIFTEEN MILE STREAM AND COCHRANE HILL DEPOSITS, NOVA SCOTIA ATLANTIC GOLD ANNOUNCES MINERAL RESOURCE ESTIMATES FOR FIFTEEN MILE STREAM AND COCHRANE HILL DEPOSITS, NOVA SCOTIA NEW M&I RESOURCE ESTIMATES FOR COCHRANE HILL AND FIFTEEN MILE STREAM WITHIN PIT SHELLS

More information

Practical long-term planning in narrow vein mines a case study

Practical long-term planning in narrow vein mines a case study Underground Design Methods 2015 Y Potvin (ed.) 2015 Australian Centre for Geomechanics, Perth, ISBN 978-0-9924810-3-2 https://papers.acg.uwa.edu.au/p/1511_31_khani/ Practical long-term planning in narrow

More information

Queenston Announces 112% Increase in Indicated Resource (to 1.5 M oz. gold) and 16% Increase in Inferred Resource (to 0.7 M oz. gold) at Upper Beaver

Queenston Announces 112% Increase in Indicated Resource (to 1.5 M oz. gold) and 16% Increase in Inferred Resource (to 0.7 M oz. gold) at Upper Beaver 2012-19 Queenston Announces 112% Increase in Indicated Resource (to 1.5 M oz. gold) and 16% Increase in Inferred Resource (to 0.7 M oz. gold) at Upper Beaver September 26, 2012 Toronto, Ontario - QUEENSTON

More information