Snead Pond Restoration

Similar documents
Materials. Use materials meeting the following.

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

Geotube Technology for Residuals and Biosolids Management

Culvert and Pipe Phasing

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

Instream Sediment Control Systems

Continuing Education Associated with Maintaining CPESC and CESSWI Certification

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources

Why Stabilizing the Stream As-Is is Not Enough

Sediment Weirs (Instream)

Rock & Aggregate Drop Inlet Protection

**Temporary Erosion Control**

Agenda. INDOT Office of Environmental Services. Describe Results of FHWA QAR. Landscape and Waterway Permitting Unit. Interviews Site Inspections

APPENDIX B WORKSHEETS & EXHIBITS

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

Why Geomorphology for Fish Passage

Tom Blackman Project Lead. Mékell Mikell Communications Representative

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University

Specifications Whitcomb Elementary School Demolition January 15, 2016

Considerations for Mechanical Dredging, Hydraulic Dredging and Mechanical Dewatering of Sediments

TPDES: Soil, Erosion and Sedimentation Methods

WELCOME Lake Wabukayne OPEN HOUSE

WATER OBSTACLE COURSE

IN SITU SPECIFIC GRAVITY VS GRAIN SIZE: A BETTER METHOD TO ESTIMATE NEW WORK DREDGING PRODUCTION

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

3. MARINE HABITAT RESTORATION

Stormwater Outlet Sediment Traps

Sediment and Erosion Control Techniques on Stream Restoration Projects

Stream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation)

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

GOING WITH THE FLOW (1 Hour)

Coarse Sediment Traps

Sedimentation. Several factors affect the separation of settleable solids from water. Some of the more common types of factors to consider are:

20217 CLEAR STONE TON $14.20 $5, $ $ $ %

East Branch Grand Calumet River Great Lakes Legacy Act Sediment Remediation and Restoration Project

ADDENDA #1 CONTRACT # C May 3, 2013 Page 1 of 1

U-Shaped Sediment Traps

20217 CLEAR STONE TON $14.20 $5, $ $ $ %

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION

Highland Lake Bathymetric Survey

Learning Objectives: I can identify and interpret river flows and directions.

Photographic Log. Photo No. 1. Date: 10/27/15. Direction Photo Taken: Southwest. Photo Taken By: JBH1

December 11, 2006 File:

Black Gore Creek Sediment Source Monitoring and TMDL Sediment Budget

MISSISSIPPI COASTAL IMPROVEMENTS

Design and Construction

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

KEYWORDS: erosion shoreline change nourishment community issues

CCR Rule Annual Inspection Report (cont.) 2

Port of Kalama, 2013 TEMCO Berth Maintenance Dredging and In-water Flow-Lane Placement Project

Early Exploration Permit Activity Information

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

Suitable Applications Sediment traps should be considered for use:

FROST HEAVE. GROUND FREEZING and FROST HEAVE

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Rock Sizing for Drainage Channels

Stream Simulation: A Simple Example

APPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013

Steven Noble MDEQ - WRD Enbridge Response Unit

Large-Scale Sediment Retention Device Testing (ASTM D 7351) SedCatch Sediment Basket Inlet Filter Exposed to 1.5% Sediment Load

October 26, Ms. Aimee Zack Canadian Pacific 120 S. Sixth Street Suite 900 Minneapolis, Minnesota 55402

Large-Scale Sediment Retention Device Testing (ASTM D 7351) SedCatch Sediment Basket Inlet Filter Exposed to 6% Sediment Load

Sediment Distribution and Characteristics

Erosion and Sediment Control Measures 2.7 Silt Fences

Instream Erosion Control General

Best Management Practices for Coldwater Fisheries Enhancement and Restoration

Orica Australia Pty Ltd Ammonium Nitrate Facility Upgrade

In-channel coarse sediment trap Best Management Practice

Erosion and Deposition

Session: For more information:

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

Sediment Management for Dam Removals

Estimated Sediment Volume: Bridge Street Dam Impoundment, Royal River, Yarmouth, Maine

Chutes Part 5: Rock linings

Muck. Kevin Henderson, P.E. Evergreen Engineering, Inc. Presentation to Rivers Coalition 9/29/16

Advanced Geologic Exploration, Inc.

River Restoration and Rehabilitation. Pierre Y. Julien

Lake Waynoka Protection and Enhancement: Study Results and Recommendations

Birecik Dam & HEPP Downstream River Arrangement R. Naderer, G. Scharler Verbundplan GmbH, 5021 Salzburg, Austria

A PRIMER ON DAM REMOVALS IN MICHIGAN. Joe Rathbun Michigan Dept. Environmental Quality

Template for Sediment and Erosion Control Plan General Instructions. Section Instructions

Fluids, Hole Cleaning and Tripping Optimization

STRUCTURAL STABILITY ASSESSMENT

Crows Landing Naval Base Easement

Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018

A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA

The River Restoration Centre therrc.co.uk. Understanding Fluvial Processes: supporting River Restoration. Dr Jenny Mant

Morphological Changes of Reach Two of the Nile River

Page 1. Name:

M. Sloat, AAg., CPESC R.J. Redden, R.P.Bio., A.Sc.T., CPESC. EDI Environmental Dynamics Inc Continental Way Prince George, B.C.

City of Camrose Winter Road Maintenance Policy

ADVENTURES IN WATER DEVELOPED BY LOUISVILLE WATER COMPANY

THIN-LAYER PLACEMENT OF DREDGE MATERIAL FOR MARSH NOURISHMENT, RESOTRATION, AND RESPONSE TO SEA LEVEL RISE

Rock Sizing for Small Dam Spillways

MIDDLESEX COUNTY Department of Planning and Community Development P.O. Box 427, Saluda, VA Phone: Fax:

Weathering, Erosion, and Deposition

Material Workshop. Galveston District 2012 Beneficial Use of Dredged. Material Workshop. Custodians of the Coast

Potential Upland Sand Sources to Support Southwest Florida Beach Projects

Transcription:

Snead Pond Restoration Project overview Location: Crewe, VA Date of Project: Summer 2016 Scope of work: Construction of check dam & hydraulic dredging of 530 cubic yards of in situ sediment utilizing geotubes for material dewatering.

Snead Pond Restoration Page 2 of 8 Introduction and overview: Pajic Construction was contacted initially to construct a check dam for a farm pond in Crewe, VA. The owner was working with Aquatic Biological Monitoring Services, LLC to restore the pond. The plan included building a check dam at the pond inlet to control and isolate the incoming sediment, and adding an aeration system to help maintain depth and water quality. While consulting with the owners they raised the question of also removing the sediment deposits on the upper end of the pond. Pajic Construction was ultimately contracted to construct a check dam at the pond inlet and hydraulically remove 530 cubic yards in situ sediment from the upper end of the pond. Site Study & Planning: The project began with a site study to better understand where dredging would be most beneficial and at what rate the in-situ sediment would dewater. This study consisted of three parts, a site sounding, a sediment dewatering study, and a polymer lab report. This information allowed us to determine the size needed for the laydown area and the capacity of the Geotubes that would be required for the dredged material. The site sounding consisted of manual soundings at 38 locations. From this data the water depth, hardpan depth, and sediment depth were determined and plotted. Sediment core samples were taken for us to complete the dewatering study and polymer lab report. The dewatering study uses a representative sediment sample in a small Geotubes to determine the rate at which the sediment dewaters and the volume of material remaining once dried to a haul away consistency. This information is what determines the specifications required for the full size Geotubes given our removal goal of in-situ sediment. A portion of the core samples are also sent to a laboratory for testing to determine the appropriate organic polymer to use for the project. The polymer is an environmentally friendly solution that is injected into the dredge slurry passing in the pipe line to flocculate the smaller solid particles. This flocculation makes the solid particles large enough that they will not pass through the filtering material of the Geotubes rendering a clean water filtrate from the bags. Once the results of these studies were processed we had the information necessary to determine the required volume of polymer & capacity of the Geotubes.

Snead Pond Restoration Page 3 of 8 Because the hydraulic dredge pumps at a rate of 850 to 1000 gallons per minute, and the pond inflow was much less, we needed to place the spoils site in an area where we could divert the filtrate water back into the pond. Otherwise we would pump the pond water level down, significantly reducing the amount of time the dredge could operate on any given day. A wooded area above the pond, that would allow us to direct filtrate water back into the pond while also being aesthetically pleasing was selected as the best option. During the planning stages, we were approached by the owners and asked if we could remove a small island that was left in the upper end of the pond during the original construction. The island had become overgrown and unsightly with brush and trees up to 3 in diameter. While the dredge is designed primarily to remove sediment deposits, we have found during previous projects that it can effectively remove hard pack though at a much slower rate. We agreed to excavate as much of the island as possible while staying within the project budget. Project commencement: Equipment deployed to the site included our 6 hydraulic dredge and associated pipe line, polymer injection system, backhoe, excavator, and single axle dump truck. We began the project by constructing the check dam at the pond inlet. The check dam was constructed using #2 and #3 crushed stone placed with equipment, and by hand, over a geo-cloth under-laminate. Upon completion of the check dam we began prepping the island for excavation by grubbing the vegetation and saplings. We opted to pull out as much of the growth as possible in order to remove the root balls that would slow the dredge progress. Utilizing an island to shore rigging system we pulled the larger trees and bushes, uprooting and removing as much of the root system as possible. This also helped to loosen the top layers of hard packed soil allowing as to dredge the material more efficiently. After removing as much growth and debris as possible the dredge was deployed and rigged, the pipe line was constructed, and the laydown area was prepared and leveled. Two fifty foot by forty-five foot circumference Geotubes were installed over a 6 mil plastic scour apron. The scour apron was constructed to divert the filtrate water back into the stream feeding the pond. Dredging began with a primary focus on removing the island. This was a much slower process than removing traditional silt as the island had significant areas of hard pack and debris. Excavating the island from 1.5 above the water line to a depth of approximately 3.5 took three days of operation. Once the island was excavated we focused our attention on the

Snead Pond Restoration Page 4 of 8 areas of the pond that had the highest deposits of sediment based on our sounding study. Dredging of this area continued for three additional days until the capacity of the geotubes were reached, resulting in approximately 550 cubic yards of material being removed from the pond. Once all dredging operations were concluded we completed all the necessary site restorations and repairs. This included seeding and laying straw over any areas of the shore line that had been disturbed by the heavy equipment, as well as spreading sand in a beach area the owners use for swimming. Conclusion: This project was completed within budget and schedule with minimal surprises along the way. The owners in this case had a comprehensive plan that included both restoration and upgrading the existing system to allow for easier maintenance. By constructing the check dam future sedimentation will be largely captured before it can enter the pond. The forebay area above the check dam is easily accessible by a backhoe or excavator for cleanout and maintenance, and the aeration system will help control sediment deposits and maintain depth in the pond. Removing the island eliminated the need for vegetation control on the island and shallow water surrounding it. From the owner: Dear Joe, I love it!! I have named it the Rockyford Resort and retirement center. You and Nick did everything we talked about and then some. This weekend I sat on the beach and pretended I was in the Bahamas. The beach looks incredible. Taking the Island out really improved the size and looks of the pond. Everybody doubted you but me and said it could not be done. I know it took more time and effort than you had planned but you two stuck with it and got it done. I am extending you and Nick an invitation to come swim in the pond Summer 2017. My next project is to improve the picnic area. Sincerely, Gin Snead

Snead Pond Restoration Page 5 of 8 Additional photos: Island Removal - Before Island Removal - After

Snead Pond Restoration Page 6 of 8 Geotubes

Snead Pond Restoration Page 7 of 8 Completed beach area (top), check dam (center), and seeding & erosion control (lower) Check Dam and spillway

Snead Pond Restoration Page 8 of 8 Beach and spillway (left), Seeding & Erosion control (right center, far bank) Beach and spillway (left), Seeding & Erosion control (right center, far bank)