MONTE CARLO SIMULATION RISK ANALYSIS AND ITS APPLICATION IN MODELLING THE INCLEMENT WEATHER FOR PROGRAMMING CIVIL ENGINEERING PROJECTS

Similar documents
WHEN IS IT EVER GOING TO RAIN? Table of Average Annual Rainfall and Rainfall For Selected Arizona Cities

2017 Settlement Calendar for ASX Cash Market Products ASX SETTLEMENT

Jackson County 2013 Weather Data

Multivariate Regression Model Results

Published by ASX Settlement Pty Limited A.B.N Settlement Calendar for ASX Cash Market Products

Jackson County 2018 Weather Data 67 Years of Weather Data Recorded at the UF/IFAS Marianna North Florida Research and Education Center

2019 Settlement Calendar for ASX Cash Market Products. ASX Settlement

Generation of an Annual Typical Meteorological Solar Radiation for Armidale NSWAustralia

Determine the trend for time series data

Chiang Rai Province CC Threat overview AAS1109 Mekong ARCC

PRELIMINARY DRAFT FOR DISCUSSION PURPOSES

DAILY QUESTIONS 28 TH JUNE 18 REASONING - CALENDAR

Jackson County 2014 Weather Data

Changing Hydrology under a Changing Climate for a Coastal Plain Watershed

peak half-hourly New South Wales

8.1 Attachment 1: Ambient Weather Conditions at Jervoise Bay, Cockburn Sound

2015 Fall Conditions Report

YACT (Yet Another Climate Tool)? The SPI Explorer

The Effect of Cloudy Days on the Annual Typical Meteorological Solar Radiation for Armidale NSW, Australia

Chapter 3. Regression-Based Models for Developing Commercial Demand Characteristics Investigation

DROUGHT INDICES BEING USED FOR THE GREATER HORN OF AFRICA (GHA)

CIMA Professional

CIMA Professional

Development of Pakistan s New Area Weighted Rainfall Using Thiessen Polygon Method

CIMA Professional 2018

CIMA Professional 2018

Validation of the Weather Generator CLIGEN with Precipitation Data from Uganda. W. J. Elliot C. D. Arnold 1

NSP Electric - Minnesota Annual Report Peak Demand and Annual Electric Consumption Forecast

SYSTEM BRIEF DAILY SUMMARY

The Climate of Bryan County

Jackson County 2019 Weather Data 68 Years of Weather Data Recorded at the UF/IFAS Marianna North Florida Research and Education Center

REPORT ON LABOUR FORECASTING FOR CONSTRUCTION

ISO Lead Auditor Lean Six Sigma PMP Business Process Improvement Enterprise Risk Management IT Sales Training

2018 Annual Review of Availability Assessment Hours

A Report on a Statistical Model to Forecast Seasonal Inflows to Cowichan Lake

OVERVIEW OF IMPROVED USE OF RS INDICATORS AT INAM. Domingos Mosquito Patricio

Mountain View Community Shuttle Monthly Operations Report

REPORT ON SOWING PERIOD AND FLOODING RISKS IN DOUALA, CAMEROON. Cameroon Meteorological Department

SYSTEM BRIEF DAILY SUMMARY

A New Probabilistic Rational Method for design flood estimation in ungauged catchments for the State of New South Wales in Australia

Meteorological Data recorded at Armagh Observatory from 1795 to 2001: Volume I - Daily, Monthly and Annual Rainfall

Alberto Troccoli, Head of Weather and Energy Research Unit, CSIRO, Australia ICCS 2013 Jamaica, 5 December 2013 (remotely, unfortunately)

Drought in Southeast Colorado

Communicating Climate Change Consequences for Land Use

The Climate of Marshall County

IMPROVING THE ACCURACY OF RUNWAY ALLOCATION IN AIRCRAFT NOISE PREDICTION

The Climate of Murray County

ISO Lead Auditor Lean Six Sigma PMP Business Process Improvement Enterprise Risk Management IT Sales Training

peak half-hourly Tasmania

Memo. I. Executive Summary. II. ALERT Data Source. III. General System-Wide Reporting Summary. Date: January 26, 2009 To: From: Subject:

COUNTRY REPORT. Jakarta. July, th National Directorate of Meteorology and Geophysics of Timor-Leste (DNMG)

STATISTICAL FORECASTING and SEASONALITY (M. E. Ippolito; )

MISSION DEBRIEFING: Teacher Guide

The Climate of Grady County

ISO Lead Auditor Lean Six Sigma PMP Business Process Improvement Enterprise Risk Management IT Sales Training

GAMINGRE 8/1/ of 7

The Climate of Pontotoc County

Typical Hydrologic Period Report (Final)

TABLE -I RAINFALL RECORDED AT PORT BLAIR (MM) FROM 1949 TO 2009

AN OVERVIEW OF ENSEMBLE STREAMFLOW PREDICTION STUDIES IN KOREA

Constructing a typical meteorological year -TMY for Voinesti fruit trees region and the effects of global warming on the orchard ecosystem

Generation of an Annual Typical Meteorological Solar Irradiance on Tilted Surfaces for Armidale NSW,Australia

The Climate of Payne County

The Climate of Kiowa County

Agricultural Science Climatology Semester 2, Anne Green / Richard Thompson

Summary of Seasonal Normal Review Investigations CWV Review

The Climate of Seminole County

2016 Meteorology Summary

Variability of Reference Evapotranspiration Across Nebraska

Country Presentation-Nepal

Folsom Dam Water Control Manual Update Joint Federal Project, Folsom Dam

Estimation of Diffuse Solar Radiation for Yola, Adamawa State, North- Eastern, Nigeria

The Climate of Texas County

Location. Datum. Survey. information. Etrometa. Step Gauge. Description. relative to Herne Bay is -2.72m. The site new level.

Location. Datum. Survey. information. Etrometa. Step Gauge. Description. relative to Herne Bay is -2.72m. The site new level.

Seasonal Climate Watch September 2018 to January 2019

Causes of high PM 10 values measured in Denmark in 2006

Folsom Dam Water Control Manual Update Joint Federal Project, Folsom Dam

Champaign-Urbana 1999 Annual Weather Summary

Significant Rainfall and Peak Sustained Wind Estimates For Downtown San Francisco

Akira Ito & Staffs of seasonal forecast sector

Interannual variation of MODIS NDVI in Lake Taihu and its relation to climate in submerged macrophyte region

Seasonal Climate Watch June to October 2018

CPD EVENT CALENDAR

Local Ctimatotogical Data Summary White Hall, Illinois

CFCAS project: Assessment of Water Resources Risk and Vulnerability to Changing Climatic Conditions. Project Report II.

Three main areas of work:

A DAILY RAINFALL GENERATING MODEL FOR WATER YIELD AND FLOOD STUDIES

Summary of wool production estimates and forecasts for Australia. 2012/13 4th forecast 78.9

The Climate of Haskell County

Climatography of the United States No

The 2010/11 drought in the Horn of Africa: Monitoring and forecasts using ECMWF products

Saudi Arabia. July present. Desert Locust Information Service FAO, Rome Red Sea coast outbreak

ACCA Interactive Timetable

At the start of the talk will be a trivia question. Be prepared to write your answer.

Scarborough Tide Gauge

Climate Change Impact Assessment on Indian Water Resources. Ashvin Gosain, Sandhya Rao, Debajit Basu Ray

Generating Synthetic Rainfall on Various Timescales - Daily, Monthly and Yearly

EVALUATION OF ALGORITHM PERFORMANCE 2012/13 GAS YEAR SCALING FACTOR AND WEATHER CORRECTION FACTOR

Stream Discharge and the Water Budget

Transcription:

MONTE CARLO SIMULATION RISK ANALYSIS AND ITS APPLICATION IN MODELLING THE INCLEMENT WEATHER FOR PROGRAMMING CIVIL ENGINEERING PROJECTS Pedram Daneshmand Associate Director Blue Visions Management (bluevisions) Level 14, 99 Mount Street, North Sydney, 26, NSW pedramd@bluevisions.com.au ABSTRACT Delays due to inclement weather conditions within construction projects are generally planned for. Up until now, Deterministic Analysis has been the most common methodology used to determine the extent of the problem for construction projects. However it is the lack of risk consideration inherent in Deterministic Analysis that creates the opportunity for improving executive decision making by applying Probabilistic Analysis through quantitative risk analysis and different techniques like Monte Carlo Simulation (MCS). This caste study review outlines the application of MCS to generate a distribution of the likely of inclement weather for a road construction project in Ballina, north of NSW, Australia. The paper also examines the application of MCS methodology for project programming, the advantages and challenges, and provides practical guidance for a probabilistic analysis with the application of MCS for managing the high risk of rainfall and optimizing the float at the activity level and the project level. Introduction Ballina Bypass Alliance Project (Case Study) One of the most common climate uncertainties in civil engineering projects is inclement weather (rainfall) during the project execution phase. This weather factor directly impacts on the project schedule through the increased non-working days and consequently needs to be addressed in the project time management plan. For planning an accurate and reliable programme, the number of non-working days per year should be estimated with desired probability and risk level. In other words, the rainfall probability and its risks need to be integrated with the project programme to improve the chance of achieving the project targets. A major challenge associated with this project programme is the high risk of rain in the area and the number of non-working rainy days in the construction programme. This challenge could significantly impact upon the project objectives and deadlines. The aim of this paper is to prepare a comprehensive risk assessment through Deterministic Analysis as well as Probabilistic Analysis with the application of the Monte Carlo Simulation technique. For the purpose of this MCS analysis, the assumption of a constant rate of non working rainy days for different stages of earthworks construction was considered [1, 2]. Rainfall Database In the Ballina area, rainfall has been recorded since 1892 at two stations. Lismore station (Centre Street) operated from 1892 until 1992 before Ballina Airport AWS site commenced at 1992. The Lismore site was located approximately 2 kms from project site; therefore the database is accurate enough for our analysis without any adjustment. The Ballina Airport AWS station is located at Latitude 28.84S and longitude 153.56E.

P. Daneshmand Review of the statistical distribution of the rainfall data for Ballina shows a high probability of the number of days with rain. Average Rainfall Annual data from the Australian Government Bureau of Meteorology from 1961 to 199 (Figure 1) has indicated that average rainfall for Ballina ranges from 2 to 24 mm per year [3]. Figure 1: Average Rainfall Annual 1961 199 Bureau of Meteorology According to the recorded rainfall data for Ballina, the average number of days with rain exceeding 5mm ranges from 5 to 75 days per year (Figure 2). This is equal to from 7 to over 1 weeks per year, or approximately 13 to 21% of calendar day per year [3]. Figure 2: Average Number of Rain Day exceeding 5 mm Bureau of Meteorology On the other hand, the Consequential Factor (CF) considers the non-working time associated with different rainfalls. Depending on different factors such as ground condition, construction discipline and phase, it is known that after rain, activities are sometimes unable to proceed straight away on the following days. The concern is to evaluate how many non-working days should be allowed as consequential days. Local experiences and practical examples in the area and/or the industry will help to answer this question and establish the Consequential Factor (CF). Rainfall Data and Programming Deterministic Analysis In this case study, the rainfall database from 1892 to 26 was obtained from the Australian Government Bureau of Meteorology. Using this database, the numbers of specific rainy days for each month were identified. The mean, median and mode for this database have been tabled for each month. Using the Deterministic approach, the number of rainy days per year is predicted by adding the total median or mean or mode for each month subject to consideration of other factors and issues. 2

The main concern in utilizing the Deterministic Analysis is the lack of attached probabilities to the output. The technique does not identify the probabilities and risks associated with the outcome. For areas like Ballina, with a high level of uncertainty of rainfall and the potentially dramatic impact on the construction programme, the analysis is complex to be addressed by strict and traditional Deterministic Analysis. Probabilistic Analysis There are many techniques to quantify and link the statistical distribution of databases and probabilities of uncertain events within an integrated system. The Monte Carlo Simulation technique is one of those methods for analyzing uncertainty propagation and address the associated probability to the environment. It is a combination of logical probability and experimental probability. The MCS technique determines logical probability of events and simulates them in trial situations. It is a method for iteratively evaluating a deterministic model using sets of random numbers as inputs. This method is often used when the model is complex, non linear, or involves more than a few of uncertain parameters. By using random inputs, it essentially turns the deterministic model to become a stochastic model. Monte Carlo Simulation (MCS) Process Risk analysis using the Monte Carlo Simulation technique involves three main steps described below: 1. Step 1 - Deterministic Analysis: using the rainfall database to calculate the statistical information such as Average (arithmetic mean), mode, median and standard deviation (STD) for the number of rain days each month. The historical database will help managers to have a better understanding of the statistical distribution of the data. 2. Step 2 - Estimate the uncertainty in the number of rainy days and try to determine which probability distribution for the inputs most closely matches the database. The target of this step is to identify that distribution for the number of rainy days per month. 3. Step 3 - Perform the Monte Carlo Simulation method with computer-based software and analyse the result for a better decision. MCS simulation uses the statistical information and probability distribution to create a combination of outcomes integrated with their probabilities [5, 6]. The next step is the determination of parameters and appropriate probability distribution considering the event s characteristics. Using the historical database and statistical distribution of rainfall data, the monthly distribution of rainy days are calculated. Goodness of Fit (GoF) Kolmorogrov-Smirnov Analysis is preferred to validate the assumption of the monthly probability distribution chosen. After the appropriate probability distribution is identified for the database, the final step for MCS analysis is to perform the simulation scenarios with computer based software. MCS will use its statistical parameters to simulate the situation with the chosen probability distribution. For instance for an event with the Triangle Distribution, the model usually uses three point estimates that represent the uncertainty associated with each task with Triangle Distribution probability. In this case, the three point estimates are the minimum, maximum and most likely number of rain day for each month. Once the three point estimates are determined, a probability distribution for each month is adopted. Then a uniform random number (between. and 1.) is generated by the computer for each monthly distribution and simulated to forecast the number of rainy days. This step is performed a number of times with the computer to provide statistical information of the outcome at the end of the process. The statistical information assists decision-makers to determine the risk to be incorporated into programme. Results and Discussion Deterministic Analysis Considering the Ballina Bypass Alliance project characteristics, ground conditions and local experiences, the numbers of rainy days each month from 1892 to 26 periods are identified within four categories: 3

Number of rainy days with rain exceeding 5mm Number of rainy days with rain exceeding 7.5mm Number of rainy days with rain exceeding 1mm Number of rainy days with rain exceeding 3mm. For each category, monthly statistical information such as minimum, maximum, mean, median, and standard deviation are calculated from this rainfall database. Figure 3 presents the monthly average number of rainy days and Average Daily Rainfall (mm) for each category. Figure 3: Monthly Average Number of Rainy Days in Ballina - 1892 to 26 Considering the civil and earthworks parameters in the Ballina Bypass project, after several consultations with local engineers and authorities in the area, a threshold of 7.5 mm seemed appropriate. Previous experience and research from local expertise and the engineers have indicated that rainfall less than 7.5 mm will not significantly affect construction progress on-site, therefore the main concern will focus the analysis on the rain exceeding 7.5 mm. The descriptive statistical information for the rainfall exceeding 7.5 mm from Ballina AWS site is shown in Table 1. Table 1: Descriptive Statistical information for Rainfall exceeding 7.5 mm at Ballina No. of (Rain Days > 7.5mm) per month Month Standard Min Median Maximum Mean Mode Deviation January 5 16 5 5 2.9835 February 6 18 6 6 2.996 March 6 17 6 3 3.79 April 6 14 6 6 3.334 May 6 15 6 4 3.5285 June 5 16 5 5 3.1926 July 3 14 4 3 3.2254 August 3 1 3 3 2.3574 September 2 8 2 2 1.9662 October 3 1 3 4 2.2257 November 3 23 4 3 3.376 December 4 15 4 3 2.7542 Annual 52 176 56 47 Monte Carlo Simulation (MCS) Using the Ballina rainfall database (from 1892-26), the distribution of the number of rain days on a monthly basis is shown on Table 2. 4

Table 2: No. of Rain Days per month for Period 1892-26 at Ballina No. of rains How many times? Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 5 3 3 5 5 11 14 18 19 1 17 8 2 14 8 6 8 5 9 8 18 25 21 16 14 3 14 9 16 9 8 12 2 2 18 2 2 23 4 11 16 8 13 14 13 1 9 12 23 6 15 5 19 15 11 12 14 19 14 14 1 12 15 16 6 12 2 9 15 13 11 11 11 7 6 6 8 7 1 7 12 12 14 8 2 7 1 5 7 8 8 9 1 13 12 8 9 8 3 2 6 9 9 6 12 1 6 8 6 4 1 4 4 4 1 5 4 4 5 4 4 3 1 1 1 11 4 3 5 4 3 3 1 2 12 1 2 4 1 3 2 3 2 13 2 4 5 1 14 2 1 1 15 2 2 1 16 1 1 17 1 18 1 19 2 21 22 23 1 From the information presented in Table 2, the 12 monthly distribution graphs for the rainfall exceeding 7.5 mm were obtained. Figure 4 presents the distributions for April, May, Oct and Dec as an example. Rain days (>=7.5mm) distribution for Apr Rain days (>=7.5mm) distribution for May Hits 16 14 12 1 8 6 4 2 16 14 12 1 8 6 4 2 5 1 15 Number of rainy days 5 1 15 2-2 Number of rainy days Rain days (>=7.5mm) distribution for Oct Rain days (>=7.5mm) distribution for Dec 25 25 2 2 15 15 1 Hits 1 5 5 2 4 6 8 1 12 5 1 15 2-5 Number of rainy days -5 Number of rainy days Figure 4: No. of Rainy Days Distribution for Apr, May, Oct and Dec at Ballina 5

For the purpose of this project the Kolmogorov-Smirnov GoF test was undertaken to validate the assumptions for probability distribution in our rainfall database. The Kolmogorov-Smirnov Analysis results have confirmed that Normal Distribution is accurate and reliable enough for the number of days with rain per month in the Ballina area. Figure 5: Simulation outcome for Rainy Days >7.5 mm with Normal Distribution The CF (Consequential Factor) for earthworks activities has been calculated based on the database, local experiences and construction problems for different rainfall. For the Earthworks Programme the CF of.7 has been adapted to the plan. On the other hand, CF is equal to zero for the Structure Programme which means there is no consequential rainy days for the Structure Programme subject to site accessibility. The overlap of the number of rainy days and consequential days with the other non-working days during the year (e.g. Weekends, RDOs, P/Holidays and Christmas, etc.) have been considered. As a result for the Ballina Bypass Alliance project, the programme has a WWF (Wet Weather Factor) of.32 and.19 for Earthworks and Structures respectively with the probability of 85%. The programmes with different probabilities such as 5%, 5%, 7%, 85% and 99% considering Figure 5, CFs and other non-working days (e.g. Public Holidays, RDOs, etc.) and their overall impacts on the working days per year has been summarised in Table 3. P(X) P5 P5 P7 P85 P99 Table 3: Working Days per year without Rain vs Working Days per year with Rain Discipline Rainy Days per Yr CF Working Days per Year (Without Rain) Working Days per Year (With Rain) WWF Earthwork 43.7 23 184.2 Structure 43 23 23.12 Earthwork 58.7 23 168.27 Structure 58 23 193.16 Earthwork 63.7 23 163.29 Structure 63 23 19.17 Earthwork 68.7 23 157.32 Structure 68 23 187.19 Earthwork 91.7 23 133.42 Structure 91 23 151.34 Actual Data To be able to assess the initial outcomes and improve the quantitative risk analysis for the future projects, the construction team took the responsibility to record the actual non working days for the earthwork activities due to inclement weather. The results for the first 12 months of the construction have been presented in the Figure 6 below. 6

16 16 MONTHLY RAINFALL ALLOWANCE 14 MONTHLY ACTUAL RAINFALL CUMULATIVE RAINFALL ALLOWANCE 14 12 CUMULATIVE ACTUAL RAINFALL 12 1 1 Deterministic Analysis: 56 days Monthly Rainfall (Days) 8 6 8 6 Cumulative Rainfall (Days) Probabilistic Analysis: 68 days 85% Management Decision: 63 days Actual for first year: 72 days 4 4 2 2 May-9 Apr-9 Mar-9 Feb-9 Jan-9 Dec-8 Nov-8 Oct-8 Sep-8 Aug-8 Jul-8 Jun-8 Figure 6: Actual non-working days for Ballina Bypass in the first year of construction Conclusion The mean of 56, median of 52 and mode of 47 days with rain per annum are suggested for the Ballina Bypass Alliance Programme by Deterministic Analysis. The results from Probabilistic Analysis with the application of the Monte Carlo Simulation technique, presents a 4% chance for mean of 56 rainy days per annum. Considering all the results from the different probability distributions and Deterministic Analysis, the MCS Analysis is recommending 68 rainy days per annum with the 85% probability for the Ballina Bypass construction programme. To make the final decision, the 36 monthly rainfall deciles for New South Wales presented at Figure 3 was considered too. Considering the project contract type, sub-contractors responsibilities and programme deadline constraints by the client, the final decision of 63 rainy days per annum with 7% probability was made by the Construction Manager. Hence the Ballina Programme was adopted with 63 rainy days per year. Capturing the actual information during the first year of construction shows 72 non working days per year for the earthwork activities as presented in Figure 1. Considering the initial forecast of 68 days with 85% probability, shows a potential of having a good platform for inclement weather analysis in future projects. Probabilistic Analysis with the application of the Monte Carlo Simulation technique can support scheduling of the civil projects in uncertain conditions. Extra attention needs to be taken to validate the best probability distribution for the database. The distribution assumption should always be tested and proved by GoF tests such as Kolmogorov-Smirnov Analysis. REFERENCES 1. Daneshmand, P., 24, CPM, PERT and Risk Analysis in Construction, 4 th Civil Engineering Conference in Asian Region, Hong Kong. 2. Daneshmand, P., 25, Duration Sensitivity Risk Analysis in Construction Feasibility Management, The Tenth International Conference on Civil, Structural and Environmental Engineering Computing (CC25), Rome, Italy. 7

3. Australian Government Bureau of Meteorology, www.bom.gov.au 4. Meredith, J.R., Mantel, Jr., S.J., 26, Project Management: A Managerial Approach, Wiley, 6 th edition. 5. Hulett, D.T., July 1996, Scheduling Risk Analysis Simplified, PM Network, pp. 23-3. 6. McKinney, B.L., Engfer, D.R., 24, Formulating Risk into Research and Engineering Projects, Proceeding of the 24 Crystal Ball User Conference, Fusfeld Group, Inc., Plymouth, Michigan. 7. Application of the Poisson Distribution, Romeu, J.L., RAC START, Volume 9, Number 1, http://rac.alionscience.com 8. Flanagan, R., Norman, G., 1993, Risk Management and Construction, Victoria: Blackwell Science Pty Ltd, Australia. 9. Kolmogorov-Simirnov: A Goodness of Fit Test for Small Samples, Romeu, J.L., RAC START, Volume 1, Number 6, http://rac.alionscience.com BRIEF BIOGRAPHY OF PRESENTER Pedram is a certified Master Project Director (MPD) and a professional member of Engineers Australia (Civil Engineering Division) with more than 15 years experiences in construction industry. He is highly skilled and technically proficient in most aspects of construction management including Programming, Construction Methodology Development, Tender Programme, Quantitative Risk Analysis, Programme Risk Management, Schedule Risk Analysis (SRA), Cost Risk Analysis (CRA), Project Monitoring & Controls (PMC) Systems, and Earned Value Performance Measurement technique (EVPM. Following his role with the International Institute of Earthquake Engineering as the Head of Civil Engineering Department, he is currently an associate director with bluevisions Management and leading a team of professional planners and engineers in the infrastructure and civil sector. With more than ten technical papers in conferences/journals and so many national and international presentations, he is also an executive member of Centre for Engineering and Leadership (CELM), and Risk Engineering Society of Engineers Australia. 8