INTENSITY AND ENERGY LIMITATIONS OF THE CERN PS COMPLEX

Similar documents
TUNE SPREAD STUDIES AT INJECTION ENERGIES FOR THE CERN PROTON SYNCHROTRON BOOSTER

Raising intensity of the LHC beam in the SPS - longitudinal plane

THE PS IN THE LHC INJECTOR CHAIN

Measurement and Compensation of Betatron Resonances at the CERN PS Booster Synchrotron

OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE

+ EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN PS DIVISION. The CERN Antiproton Decelerator (AD) Operation, Progress and Plans for the Future

Accelerator Physics. Accelerator Development

Plans for ions in the injector complex D.Manglunki with the help of I-LHC and LIU-PT teams

The Booster has three magnet systems for extraction: Kicker Ke, comprising two identical magnets and power supplies Septum Se

NOVEL METHOD FOR MULTI-TURN EXTRACTION: TRAPPING CHARGED PARTICLES IN ISLANDS OF PHASE SPACE

PBL SCENARIO ON ACCELERATORS: SUMMARY

Challenges and Plans for the Proton Injectors *

MISMATCH BETWEEN THE PSB AND CPS DUE TO THE PRESENT VERTICAL RECOMBINATION SCHEME

Physics 610. Adv Particle Physics. April 7, 2014

ULTIMATE LHC BEAM. G. Arduini, CERN, Geneva, Switzerland

PBL (Problem-Based Learning) scenario for Accelerator Physics Mats Lindroos and E. Métral (CERN, Switzerland) Lund University, Sweden, March 19-23,

Beam Diagnostics Lecture 3. Measuring Complex Accelerator Parameters Uli Raich CERN AB-BI

ELECTRON COOLING OF PB54+ IONS IN LEIR

1.5-GeV FFAG Accelerator as Injector to the BNL-AGS

Low energy electron storage ring with tunable compaction factor

Longitudinal Dynamics

Statusreport. Status of the GSI accelerators for FRS operation. Jens Stadlmann (FAIR Synchrotrons)

Linac4: From Initial Design to Final Commissioning

The TESLA Dogbone Damping Ring

LIS section meeting. PS2 design status. Y. Papaphilippou. April 30 th, 2007

LHC Luminosity and Energy Upgrade

Betatron Matching and Dispersion Matching

Engines of Discovery

Studies of trapped modes in the new extraction septum of the CERN Proton Synchrotron

First propositions of a lattice for the future upgrade of SOLEIL. A. Nadji On behalf of the Accelerators and Engineering Division

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

MULTITURN EXTRACTION BASED ON TRAPPING IN STABLE ISLANDS AT CERN PS: RECENT MEASUREMENT ADVANCES

Conceptual design of an accumulator ring for the Diamond II upgrade

INJECTION PAINTING AND ASSOCIATED HW FOR 160 MeV PSB H

Introductory slides: Ferrite. Ferrite

LHC Status and CERN s future plans. Lyn Evans

LCLS Accelerator Parameters and Tolerances for Low Charge Operations

Lattice Design and Performance for PEP-X Light Source

ACHIEVABLE SPACE-CHARGE TUNE SHIFT WITH LONG LIFETIME IN THE CERN PS & SPS

Compressor Lattice Design for SPL Beam

Operational performance of the CERN injector complex with transversely split beams

Status of the LIU project and progress on space charge studies

Particle physics experiments

FY04 Luminosity Plan. SAG Meeting September 22, 2003 Dave McGinnis

Beam Diagnostics. Measuring Complex Accelerator Parameters Uli Raich CERN BE-BI

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

Beam. RF antenna. RF cable

Accelerator Physics. Tip World Scientific NEW JERSEY LONDON SINGAPORE BEIJING SHANGHAI HONG KONG TAIPEI BANGALORE. Second Edition. S. Y.

BEAM DYNAMICS ISSUES IN THE SNS LINAC

3. Synchrotrons. Synchrotron Basics

Multi-Purpose Accelerator-Accumulator ITEP-TWAC for Nuclear Physics and Practical Applications

Chopping High-Intensity Ion Beams at FRANZ

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

A Project to convert TLS Booster to hadron accelerator 1. Basic design. 2. The injection systems:

UPGRADE ISSUES FOR THE CERN ACCELERATOR COMPLEX

Frequency and time domain analysis of trapped modes in the CERN Proton Synchrotron

Design of an RF Photo-Gun (PHIN)

Status of linear collider designs:

Compressor Ring. Contents Where do we go? Beam physics limitations Possible Compressor ring choices Conclusions. Valeri Lebedev.

PIP-II Injector Test s Low Energy Beam Transport: Commissioning and Selected Measurements

RUN II LUMINOSITY PROGRESS*

Run2 Problem List (Bold-faced items are those the BP Department can work on) October 4, 2002

SwissFEL INJECTOR DESIGN: AN AUTOMATIC PROCEDURE

SIMULATION STUDY FOR MEIC ELECTRON COOLING*

Accelerators. There are some accelerators around the world Nearly all are for industrial (20 000) or clinical use (10 000)

Lattice Design for the Taiwan Photon Source (TPS) at NSRRC

CERN EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CTF3 DRIVE BEAM INJECTOR OPTIMISATION

LHC upgrade based on a high intensity high energy injector chain

Space Charge Studies on the ISIS Ring

Electron cloud effects for PS2, SPS(+) and LHC

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21


SRF GUN CHARACTERIZATION - PHASE SPACE AND DARK CURRENT MEASUREMENTS AT ELBE*

The Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory

Preliminary design study of JUICE. Joint Universities International Circular Electronsynchrotron

On-axis injection into small dynamic aperture

OPERATIONAL BEAMS FOR THE LHC

Accelerators for Beginners and the CERN Complex

LHC operation in 2015 and prospects for the future

COMBINER RING LATTICE

Operational Experience with HERA

The MAX IV Thermionic preinjector

Muon Front-End without Cooling

Proposal to convert TLS Booster for hadron accelerator

Bernhard Holzer, CERN-LHC

Why do we accelerate particles?

Abstract. 1. Introduction

Impedance & Instabilities

Injection: Hadron Beams

Accelerator. Physics of PEP-I1. Lecture #7. March 13,1998. Dr. John Seeman

!"#$%$!&'()$"('*+,-')'+-$#..+/+,0)&,$%.1&&/$ LONGITUDINAL BEAM DYNAMICS

Advanced Design of the FAIR Storage Ring Complex

Run II Status and Prospects

Notes on the HIE-ISOLDE HEBT

CNGS proton beam. Malika Meddahi for SL/BT group CERN

Electron Cloud Studies for KEKB and ATF KEK, May 17 May 30, 2003

Development and application of the RFQs for FAIR and GSI Projects

The CERN Accelerator School holds courses in all of the member states of CERN. 2013, Erice, Italy

Multiturn Extraction Based on Trapping in Stable Islands

The FAIR Accelerator Facility

Transcription:

INTENSITY AND ENERGY LIMITATIONS OF THE CERN PS COMPLEX M.Gourber-Pace, CERN, Geneva, Switzerland Abstract In the next few years, the PS complex (Linac2-PS Booster-PS) will accelerate again very intense proton beams (for TOF, CNGS experiments). In the present operational context, where the PS machines have been converted to become a pre-injector for the LHC, expected limitations to very high intensity acceleration are presented. 1 PRELIMINARY REMARK The limitations in energy and intensity refer to the operational so-called SFT/CT (SPS Fixed Target / Continuous Transfer) beam. This proton beam is extracted over five consecutive turns from the PS ring at 14 GeV/c and transferred through the TT2-TT10 line to fill the SPS in two pulses. The constraints requested by the LHC beam, such as high brilliance and tight transverse emittances, are not hereby taken into consideration. Since 1997, when the record intensity of 3.05 10 13 particles per pulse (ppp) (at 14 GeV/c) was achieved, no test of very high intensity has been performed on the SFT/CT beam. In addition, the project of converting the PS complex for the LHC has induced significant upgrades in the operation of the PS machines so as to meet the very demanding needs of the LHC. Consequently, regarding intensity and energy limitations, rather assumptions than quantitative results are provided in the following paragraphs. 2 LINAC2 2.1 Intensity record in 1999 In September 1999, a new intensity record has been made on the beam supplying ISOLDE (On-Line Isotope Mass Separator). The Linac2 beam current delivered to the PS Booster has increased from 170 ma (in 1997) to 175 ma and kept operational over several weeks. Furthermore, a test beam for LHC of up to 182 ma has been observed but not optimised for operational purposes. 2.2 Improvements Even if the major improvements took place in 1996-97, further optimisations have been carried out since 1997; in particular, the iterative re-optimisation of the source parameters and the 2 solenoids between the source and the RFQ (Radio Frequency Quadrupole) where neutralisation is strong due to the hydrogen flow from the source. 2.3 Identified limitations of intensity The Radio Frequency (RF) system is being operated at its limit. In order to meet the LHC requirement of 180 ma at the PSB entry and allowing for 5% beam losses in the transfer line, 190 ma have to be produced in the Linac2. Adding up copper power, beam power for this current and a margin for phase and amplitude control, tuning precision and amplifier balancing, about 2.7 MW per final RF amplifier will be needed, corresponding to 10% more than their design power. At low energy, the beam is strongly space charge dominated, leading to around 7% losses in the first tank. Except replacing the tank, no optimisation is presently foreseeable. In addition, the space charge effects lower the transmission efficiency from the last tank to the PSB where around 5% of the beam is lost passing through the bending magnets: these particles came outside the RF bucket in the first tank and got a wrong energy. Finally, the control of the beam energy spread (in 1999, V=70-80 kev, 'p/p=0.075%) is a crucial parameter: the adaptation of the PSB parameters to a new energy spread, in view of increasing the injection efficiency, is not straightforward but requires a fine optimisation. 2.4 Estimated top intensity on SFT/CT The 50 MeV Linac, whose design beam current was 150 ma, is presently approaching its fundamental limits. From simulations (in ideal conditions), the top intensity the Linac2 should be able to provide at the PSB entrance (based upon a 95% transmission) is 180 ma in stable conditions. From 2000 on, this performance could potentially be achieved for the SFT/CT beam, provided a significant effort devoted to the adjustment of the multiple parameters. 47

3 PS BOOSTER (PSB) 3.1 Intensity record in 1999 on ISOLDE beam The PSB supplied routinely ISOLDE with an intensity of 3.3 10 13 ppp summed over the four rings. Thanks to a careful adjustment of the PSB, an unprecedented intensity of more than 4 10 13 (record 4.1 10 13 ) was reached. Rings 1, 3 and 4 accelerated 950 10 10 ppp while ring 2 revealed an exceptional performance by providing up to 1250 10 10 ppp. The difference between an ISOLDE beam and a SFT/CT beam is the bunch splitting prior to extraction. 3.2 Improvements with respect to 1998 Since 1995, when the project of converting the PS complex for LHC started, the PSB machine has been in the process of being upgraded, leading to a new operation scheme for SFT/CT: acceleration on RF harmonic 1 (instead of former harmonic 5) up to the extraction energy (raised from 1 to 1.4 GeV), bunch splitting, sequential transfer of the 8 bunches (2 bunches per ring) to fill the PS in one pulse. A significant improvement has been the lowering of the longitudinal coupling impedance of the PSB, generated by resonances of the vacuum flanges [1]. During the first h=1 run in 1998, the operation suffered from a total (integrated around the ring) longitudinal coupling impedance of 1000 Ohms at 750 khz, which represents the RF frequency range at the beginning of the cycle. After having short-circuited half of the flanges during the 1998-99 shutdown, the impedance was lowered to about 200 Ohms per ring, contributing to the record intensity increase in September 1999. New RF decoupling flanges will be introduced in the 1999-2000 machine shutdown to further reduce the impedance to 30 Ohms per ring. The main advantages of the h=5 to h=1 transition are the following [3]: x Increase of the longitudinal acceptance (proportional to (V rf /h)) by a factor 1.8, allowing to eliminate a long-standing bottleneck. x Easier control of the bunching factor by the double harmonic RF system, as the RF power is not a limitation and the relative phase control has been largely improved. x Removal of the coupled bunch mode instabilities (inexistant with a single bunch) and its complex feedback system x Reduction of the longitudinal space charge effect (generating quadrupolar bunch-shape oscillations) and suppression of the Hereward damping system Finally, a promising tool, aiming at fighting harmful space charge effects, has been successfully tested during the last run. By deposition of an empty bucket (from the C16 RF cavity) on the injected beam before capture an hollow distribution in the longitudinal phase space is obtained, permitting to increase the Bunching factor (flat bunches). For the time being, this procedure needs further consolidation to become operational. 3.3 Identified limitations of intensity The space charge in PSB at low energy remains the major bottleneck for an intensity increase. The induced detuning sweeps the beam over stop-bands (mainly 3Qv =16 and 2Qv =11) and drastically limits the injection and low energy transmission efficiency (incoherent tune shift larger than 0.5 at capture). This leads to a systematic 20% of losses during the first 100 milliseconds. Another constraint deals with the reduced performance of outer rings (numbered 1 and 4), which both suffer from a discrepancy in the quality of their magnetic field inherent to the asymmetrical structure of the main magnet between inner and outer rings. This feature makes the dynamic compensation of stop-bands more tricky to achieve on the outer rings, affecting the overall PSB performance. Furthermore, the 1999 operation highlighted a restriction in the transverse acceptance of ring 3. The beam emittance at injection fills the whole acceptance of the vacuum chamber, resulting in an increase of losses. A specific effort is being devoted to investigating the origin of this unexplained behavior. 3.4 Estimated top intensity on SFT/CT The beam production for SFT/CT imposes a specific constraint with respect to the ISOLDE type operation: an equal intensity must be delivered by each of the four rings. Combining this intrinsic condition with the recent performance achieved on ISOLDE, a very approximate estimation outputs 3600 10 10 ppp as the virtual peak intensity for SFT/CT beam. Comparative parameters for ISOLDE and SFT/CT are compiled in Table 1. ISOLDE record SFT/CT estimate Ring 1 950 900 Ring 2 1250 900 Ring 3 950 900 Ring 4 950 900 Sum 4100 3600 Table 1: Individual and total intensity [10 10 ppp] Obviously, an operational margin has to be applied on the above estimation to ensure that the intensity is 48

routinely provided in a reliable way: 3500 10 10 ppp are assumed to be a reasonable practicable limit. 3.5 Identified limitations of energy Raising the PSB output energy from 1 to 1.4 GeV to ease space charge in the PS implied an increase of the PSB main dipole field by 26% to 0.87 T and of the quadrupole gradient to ~5 T/m [4]. Thus, an upgraded main power supply was put into service. However, during the running-in period in 1998, saturation effects were perceptible at 1.4 GeV which produced a 70 G field difference between inner and outer Rings, resulting in a 20 mm variation of the mean radial position after synchronisation with the PS machine. A trim power supply was installed across outer rings in order to equalise the bending field levels, thanks to the PSB builders who foresaw this possibility by cabling properly the different rings. In view of a future increase of the PSB extraction energy, the saturation effects of the main bending field would act as a fundamental limitation, even if an extensive analysis should be looked-up to evaluate the actual margin. h=5 h=2 4 PS 4.1 Intensity record in 1999 on ISOLDE beam Since the last intensity record in 1997 (3.115 10 13 ppp reached at transition), the PS operation scheme has experienced drastic changes but no test of very intensity has been performed. The average intensity delivered to the SPS has been kept below 1.5 10 13 ppp. Besides the change of injection energy, the acceleration is based upon new harmonics: the PS RF cavities are tuned to h=8 so as to accommodate the 8 PSB bunches, instead of 20 bunches in the former injection scheme (Fig. 1). These are then accelerated up to 3.5 GeV/c where they are split to 16 bunches, followed by acceleration on h=16 to 14 GeV/c. The beam is debunched and then recaptured on h=420 by the 200 MHz cavities right before the extraction over 5 consecutive turns. 1997 1999 h=20 h=8 Fig.1. Former and current PSB-PS injection schemes 4.2 Improvements with respect to 1997 The unprecedented brightness requested by the LHC beam results in a tune shift ('Q) which would become unmanageable at 1 GeV. Raising the PS injection energy to 1.4 GeV allows to lower 'Q from 0.3 to a more comfortable 0.2. Moreover, the application of a controlled longitudinal blow-up at PSB extraction has proven to further reduce the tune shift. During this Shutdown (1999-2000), the PSB-PS transfer line is upgraded to become Pulse to Pulse Modulated (PPM), providing each beam with a specific tuning of steering and matching, fully independent of the other circulating beams. 4.3 Identified bottlenecks for intensity For the time being, the most fundamental limitation deals with the devices involved in the five turn extraction process, known as Continuous Transfer (CT). The fast bumper dipoles (BFA) in sections 9 and 21, as well as the splitting Electrostatic septum in section 31 are both operated close to their respective limits. The BFA are used to gradually push the beam into the electrostatic septum in order to ensure that one fifth of the initial beam intensity is extracted at each turn. For technical purposes, each BFA is composed of a pair of dipoles, a "pedestal" dipole and a "staircase" dipole which combine to generate a staircase-waveform kick. Operational settings of power supplies for the BFA and the ES during the 1997 run are compiled in the following table (Table 2). Operational voltage [kv] Limit voltage [kv] Pedestal 25 30 Highest stair 38 40 E. Septum 190 Table 2: Operational settings and limits of CT equipment Both "pedestal" and "dipole" systems are based upon a 25-year old electronics (connectors, cables and thyratrons), exposed to a very high voltage. The present components could reasonably not be retained in view of a major improvement of the beam intensity, which implies a larger beam size. To cancel this limitation, the renewal of the electronics seems at first sight the most natural cure. Nevertheless, a new scheme involving the current fast kicker (KFA71-79) to enhance the BFA kick on last turns could be thoroughly analysed. The most critical element involved in the CT process is obviously the electrostatic septum (ES). Originally designed for a 10 GeV/c extraction, it was pushed, for a couple of days during the very intensity tests in 1997, to extreme operational conditions: 190 KV over a 26 mm 49

gap. One should notice that the ES could not handle such settings continuously over several weeks, even if no absolute limit is formally defined. As far as the very intensity is concerned, the splitting process suffers from two drawbacks. First, the systematic losses, due to the beam-septum interaction, intrinsically limit the efficiency but also induce radiations harmful to the equipment. Moreover, the accumulation of ions (produced by interactions between the beam and the residual gas) on the ES cathode is a major concern as it provokes magnet sparkings. The more intense the proton beam is, the more ions are produced, the more likely sparkings become. It is worth saying that the septum, in its current design, is not suitable for an operational intensity flirting with 3 10 13 ppp. If such a request exists, keeping the CT principle, a study should be devoted to analysing a new septum design, as potentially a wire septum which benefits from a better protection against radiations and is equipped with a "ion trap". 4.4 Potential limitations of intensity This paragraph provides an overview of foreseeable limitations inherent to the new operation scheme. Even not observed in 1999 on the SFT/CT beam because of the rather low intensity, instabilities are likely to appear as the intensity is raised. The change of harmonic has the drawback to increase the bunch length by an amount of 20/8 with respect to 1997. During the 1999 run, transverse instabilities occurred at low energy on the LHC test beam and were cured by linear coupling. Enhanced instabilities are anticipated on the SFT/CT beam, because of its higher bunch intensity. Nevertheless, SFT/CT presents a benefit compared to the LHC beam: being injected in one single batch, it is prevented from dwelling for 1.2 sec on the PS injection flat-top and thus it should be less vulnerable to high mode instabilities (m=6, observed last year on LHC). In the longitudinal plane, due to the change of the frequency spectrum of the beam and the tuning frequency of the accelerating cavities, a new mode of coupled-bunch instability has appeared in the vicinity of the 10 th harmonic of the revolution frequency (i.e. n=2 or 6), on the LHC test beam [2]. A feedback damping system has been implemented and successfully applied. As far as the transition crossing is concerned, the present operational conditions are worse than in 1997, as bunches are more intense by a factor 20/16, given the same total intensity. In 1997, thanks to a fine optimisation, the transition process generated very few losses (around 2 %) at 3.1 10 13 ppp. One can anticipate the forthcoming difficulties if bunch intensity is largely increased, by referring to the experience gained in 1999 from the preliminary tests on the Time Of Flight (TOF) beam. Beam brake up instabilities have been observed on this single bunch beam of 7 10 12 ppp. According to the scope of the present paper (outlined in Section 1), until now the beam size has not been a criteria taken into consideration in the identification of the sources of intensity limitations. Nevertheless, the SPS injection efficiency strongly depends on the beam transverse emittance, particularly in the vertical plane, where the beam must fit into the small SPS dynamic aperture. Aiming at following the evolution of the emittances through the PSB-PS acceleration chain, a measurement campaign has been undertaken in November 1999 on the SFT/CT beam. Particular care has to be taken in the analysis of the results (Fig. 2): as two different measurement technics have been used ("Beamscope" device for PSB extraction emittance, fast wire scanner for the PS injection and extraction emittances), the absolute values of the data can not be fully significant. On the contrary, of particular relevance is the evolution of the emittance as a function of intensity. Measurement has been performed for an intensity varying from 1.2 to 2.6 10 13 ppp. Results for 3 and 3.5 10 13 ppp, extrapolated from actual data, are also provided. Normalized V emittance [um] Normalized H emittance [um] VERTICAL NORMALIZED EMITTANCES FOR VARIOUS INTENSITIES [E10] (SFT/CT fast ejection) 32 30 Estimated 3500 28 26 Estimated 3000 24 22 2600 20 18 1900 16 14 12 1200 10 PSB 1 extraction PS injection 2 PS extraction 3 80 75 70 65 60 55 50 45 40 35 30 25 HORIZONTAL NORMALIZED EMITTANCES FOR VARIOUS INTENSITIES [E10] (SFT/CT, fast ejection) Estimated 3500 Estimated 3000 2600 1900 1200 PSB extraction PS injection PS extraction 1 2 3 Figure 2: Vertical and horizontal normalised emittances The measurement results highlight that the beam emittances in both planes unavoidably increase according to the intensity. Furthermore, one could 50

expect a systematic blow-up of the emittance along its transfer: from injection to extraction in the PS machine, it is approximately estimated as 10% in the horizontal plane and as 20% in the vertical plane (taking the PS convention for naming the transverse planes, i.e. forwards the emittance exchange insertion). Ways to minimise as much as possible the amounts of missteering and mismatch are under study, as it is an issue of major importance for the small-sized LHC-type beams. 4.5 Limitations for energy From the viewpoint of the energy, the CT elements, ie. the fast bumper dipoles (BFA) and the electrostatic septum (ES), are very critical as there is roughly no operational margin for increasing their respective voltage. Thus, a CT extraction process above 14 GeV/c would imply a complete review of the current scheme. CONCLUSION The operational changes of the PS machines so as to meet the constraints of the LHC beam, probably turn out to be advantageous rather than detrimental to the quality of the SFT/CT beam. Unfortunately, no experimental results so far could confirm this assumption, in particular if much higher intensities, such as foreseen by the CNGS project, are taken into consideration. ACKNOWLEDGEMENT I would like to thank my colleagues, R.Cappi, M.Chanel, M.Thivent, M.Vretenar for devoting so much of their time to improving my knowledge on specific topics, through private communications. I am also grateful to D.Cornuet, D.Forkel, J-M.Hanon, L.Sermeus for their precious help. REFERENCES [1] PSB vacuum flanges impedance measurement, CERN/PS Note 2000-? (RF) - to be published [2] Collective effects in the CERN PS beam for LHC, CERN/PS 99-049 (CA) [3] Extract from PS for LHC design report [4] Saturation effects in the main bending magnets and required modifications, CERN/PS 98-059 (OP) 51