Public Disclosure Copy. Implementation Status & Results Report Cambodia Global Partnership for Education Second Education Support Project (P144715)

Similar documents
Public Disclosure Copy. Implementation Status & Results Report Cambodia Global Partnership for Education Second Education Support Project (P144715)

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

Public Disclosure Copy. Implementation Status & Results Report REVITALIZING EDUCATION DEVELOPMENT IN SIERRA LEONE (P133070)

The World Bank Pakistan: Third Punjab Education Sector Project (P154524)

PAMSIMAS Support Trust Fund (P116236)

The World Bank Local and Regional Competitiveness Project (P154263)

The World Bank Regional Infrastructure Development Fund (P154947)

Public Disclosure Copy

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

Public Disclosure Copy. Implementation Status & Results Report Girls Education and Womens Empowerment and Livelihood Project (P151451)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Cusco Regional Development (P117318)

The World Bank Indonesia: Geothermal Energy Upstream Development Project (P155047)

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report KH - Livelihood Enhancement and Association of the Poor Project (LEAP) (P153591)

The World Bank BiH Floods Emergency Recovery Project (P151157)

The World Bank Earthquake Housing Reconstruction Project (P155969)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Education Infrastructure for Resilience (EU Facility for SuTP) (P162004)

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

The World Bank Local and Regional Competitiveness Project (P154263)

Urban Water Supply Project (P156739)

Public Disclosure Copy

Public Disclosure Copy

The World Bank GUINEA - Pooled-Fund for Basic Education (P148127)

The World Bank. Kenya: Off-grid Solar Access Project for Underserved Counties (P160009) Key Dates. Project Development Objectives.

The World Bank Strengthening Social Safety Net Project (P145699)

The World Bank Earthquake Housing Reconstruction Project (P155969)

Public Disclosure Copy. Implementation Status & Results Report UGANDA North Eastern Road-corridor Asset Management Project (NERAMP) (P125590)

SUSTAINABLE CITIES (P128605)

Public Disclosure Copy

The World Bank Ho Chi Minh City Green Transport Development (P126507)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Uganda Energy for Rural Transformation III (P133312)

Key Dates. Project Development Objectives. Components. Overall Ratings

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank Can Tho Urban Development and Resilience (P152851)

Public Disclosure Copy. Implementation Status & Results Report Pacific Islands Regional Oceanscape Program - Solomon Islands (P151777)

Public Disclosure Copy

The World Bank Zambia Water Resources Development Project (P114949)

Public Disclosure Copy

Key Dates. Project Development Objectives. Components. Overall Ratings

Access to Quality Education Project (P145323)

Malawi Education Sector Improvement Project (MESIP) (P154185)

Key Dates. Project Development Objectives. Components. Overall Ratings

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Georgia National Innovation Ecosystem (GENIE) Project (P152441)

Public Disclosure Copy

Public Disclosure Copy. AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power

The World Bank Mali Reconstruction and Economic Recovery (P144442)

The World Bank Health System Strengthening and Support Project (P152799)

Public Disclosure Copy

Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund (P126180)

The World Bank Greater Maputo Water Supply Expansion Project (P125120)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Mali Reconstruction and Economic Recovery (P144442)

The World Bank Zambia Water Resources Development Project (P114949)

The World Bank Indonesia National Slum Upgrading Project (P154782)

Public Disclosure Copy

The World Bank Guilin Integrated Environment Management (P133017)

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report Small Town Water Supply and Urban Septage Management Project (P156738)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

Sindh Enhancing Response to Reduce Stunting (P161624)

SUSTAINABLE CITIES (P128605)

The World Bank Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819)

The World Bank MA- Noor Ouarzazate Concentrated Solar Power Project (P131256)

The World Bank Integrated Forest Ecosystem Management (P151102)

The World Bank Ethiopia: National Quality Infrastructure Development Project (P160279)

Public Disclosure Copy

The World Bank Nigeria - State Education Program Investment Project (P122124)

West Bank and Gaza: Finance for Jobs (P151089)

Sri Lanka Strategic Cities Development Project (P130548)

The World Bank Dam Operational Improvement and Safety (P096532)

The World Bank Swaziland Health, HIV/AIDS and TB Project (P110156)

Public Disclosure Copy

The World Bank Indonesia National Slum Upgrading Project (P154782)

Public Disclosure Copy

The World Bank Ghana - Maternal, Child Health and Nutrition Project (P145792)

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized

Key Dates. Global Development Objectives. Components. Overall Ratings. Implementation Status and Key Decisions

The World Bank Livestock Sector Development Support Project (P159476)

Public Disclosure Copy

Name Previous Rating Current Rating

The World Bank China: Qinghai Xining Urban Transport Project (P127867)

Rio de Janeiro Strengthening Public Sector Management Technical Assistance Project (P127245)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

The World Bank Health System Performance Reinforcement Project (P156679)

Zambia - Mining and Environmental Remediation and Improvement Project (P154683)

Public Disclosure Copy

Transcription:

Public Disclosure Authorized EAST ASIA AND PACIFIC Cambodia Education Global Practice Recipient Executed Activities Investment Project Financing FY 2014 Seq No: 3 ARCHIVED on 30-May-2015 ISR18803 Implementing Agencies: Ministry of Education, Youth, and Sports Public Disclosure Authorized Key Dates Key Project Dates Board Approval date:04-jun-2014 Planned Mid Term Review Date:03-Oct-2016 Original Closing Date:31-Jul-2017 Project Development Objectives Effectiveness Date:16-May-2014 Actual Mid-Term Review Date:17-Nov-2014 Revised Closing Date:31-Jul-2017 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The objectives of the Project are to assist the Recipient to: (i) expand access to early childhood education (ECE) for 3-5 year olds and (ii) contribute to improved access to and quality of basic education, particularly for those from disadvantaged backgrounds. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component 1: Improving the Access and Educational Experience of Vulnerable and Disadvantaged Students:(Cost $23.80 M) Public Disclosure Authorized Component 2: Benchmarking Student Competencies:(Cost $4.30 M) Component 3: Improving Cambodia s Teaching Force:(Cost $2.50 M) Component 4: System Strengthening and Monitoring and Evaluation:(Cost $7.90 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating Low Low 5/30/2015 Page 1 of 10

Implementation Status and Key Decisions Overall implementation progress towards the achievement of project development objectives has been substantial. Since the last implementation support mission the project has made progress on all components with a solid, accelerated work plan set for 2015. Many activities related to earlychildhood development, primary/secondary scholarships, school health, national assessments, EGRA, and results based M&E, have made good progress. The project continues to show strong collaboration between the MoEYS, development partners, and the Bank as the supervising entity for the project. The MoEYS technical teams, in consultation with Bank team members, have completed several key steps to advance the project further in the implementation stage. Organizationally, relevant departments in the MoEYS have created strong and well-functioning component technical teams to lead the project implementation. 5/30/2015 Page 2 of 10

Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Low Low Macroeconomic -- Low Low Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Low Low Institutional Capacity for Implementation and Sustainability -- Low Low Fiduciary -- Moderate Moderate Environment and Social -- Low Low Stakeholders -- Low Low Other -- -- -- Overall -- Low Low Results Project Development Objective Indicators Lower Secondary enrollment rate (Percentage, Custom) Value 35.10 35.10 35.10 37.10 Lower Secondary enrollment rate (girls) (Percentage, Custom Breakdown) Value 37.40 37.40 37.40 38.10 5/30/2015 Page 3 of 10

Enrollment ratio of children aged 3-5 in the urban and rural districts where new 100 formal and 1,000 community based preschool facilities are provided (Percentage, Custom) Value 52.70 -- -- 55.70 Enrollment ratio of children aged 3-5 in the urban and rural districts where new 100 formal and 1,000 community based preschool facilities are provided (girls) (Percentage, Custom Breakdown) Value 49.80 49.80 -- 52.50 Percentage of primary teachers applying effective EGRA teaching methods as defined by classroom observation criteria (Percentage, Custom) Value 0.00 0.00 0.00 50.00 Percentage of students in Grades 3 reaching 45-60 words per minute on the Early Grade Reading Assessment (Percentage, Custom) Value 83.90 83.90 -- 90.00 Overall Comments The udpated data will be available from the next implmentation support mission. Intermediate Results Indicators 5/30/2015 Page 4 of 10

System for learning assessment at the primary level (Yes/No, Core) Value Y Y Y Y Date 28-Feb-2014 02-Sep-2014 31-Dec-2014 31-Jul-2017 Utility of the learning assessment system (Number, Core Supplement) Value 1.00 1.00 0.00 1.00 Date 28-Feb-2014 02-Sep-2014 31-Dec-2014 31-Jul-2017 Number of provinces implementing a unified early childhood and primary education sub-sector monitoring system (Number, Custom) Value 0.00 -- 0.00 12.00 Date 02-Dec-2013 -- 31-Dec-2014 31-Jul-2017 Direct project beneficiaries (Number, Core) Value 0.00 25234.00 25234.00 170950.00 Date 02-Dec-2013 31-Oct-2014 31-Dec-2014 31-Jul-2017 5/30/2015 Page 5 of 10

Female beneficiaries (Percentage, Core Supplement) Value 0.00 21.40 21.40 45.00 Date 02-Dec-2013 31-Oct-2014 31-Dec-2014 31-Jul-2017 Number of provinces implementing a unified early childhood and primary education sub-sector planning system Plans (Number, Custom) Value 0.00 0.00 0.00 12.00 Number of additional qualified primary teachers resulting from project interventions. (Number, Core) Value 0.00 0.00 0.00 6000.00 Roll out of Grades 3, 6, and 8 National Assessments (each assessment once during the project lifecycle) and publication of their results (Yes/No, Custom) Value N N N Y 5/30/2015 Page 6 of 10

EGMA rolled out in 5 provinces (Yes/No, Custom) Value N N N Y Percentage of ECE formal services rated as level 5 overall on the adjusted ECERS-R scale through classroom-observation evaluation (50 FPS, 100 CBPS selected) (Percentage, Custom) Value 0.00 0.00 0.00 30.00 Number of Community ECE teachers and core mothers reached by training and materials supported by the project (Number, Custom) Value 0.00 0.00 0.00 1850.00 Average age of students entering grade 1 (Number, Custom) Value 6.90 6.90 -- 6.80 5/30/2015 Page 7 of 10

Number of teachers completing training on disability screening (Number, Custom) Value 0.00 759.00 759.00 2000.00 Date 02-Dec-2013 31-Oct-2014 31-Dec-2014 31-Jul-2017 Enrollment ratio of children aged 5 in the urban and rural districts where new 100 formal and 1000 community based preschool facilities are provided (Percentage, Custom) Value 56.50 56.50 -- 71.00 Enrollment ratio of children aged 5 in the urban and rural districts where new 100 formal and 1000 community based preschool facilities are provided (girls) (Percentage, Custom Breakdown) Value 53.50 53.50 -- 67.20 Number of children aged 3-5 reached by project supported ECE services (100 FPS, 1000 CB, 500 HB) (Number, Custom) Value 0.00 0.00 0.00 32500.00 5/30/2015 Page 8 of 10

Number of District Offices of Education constructed (Number, Custom) Value 0.00 0.00 0.00 20.00 Number of principals completing leadership training (Number, Custom) Value 0.00 0.00 0.00 1600.00 Number of students receiving project financed scholarships (Number, Custom) Value 0.00 0.00 0.00 133000.00 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P144715 TF-17490 Effective USD 38.50 38.50 0.00 12.64 25.86 33% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P144715 TF-17490 Effective 16-May-2014 16-May-2014 16-May-2014 31-Jul-2017 31-Jul-2017 5/30/2015 Page 9 of 10

Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/30/2015 Page 10 of 10