Monitoring Considerations and Costs

Similar documents
Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610)

WATER MANAGEMENT REPORT FOR PAGE ESTATES

Continuing Education Course #101 Drainage Design with WinTR-55

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

Section 4: Model Development and Application

City of Columbia BMP Manual. Detailed Unified Sizing Criteria Example Wet Pond Design

BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY

Submitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3

Continuing Education Associated with Maintaining CPESC and CESSWI Certification

PONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details

Las Colonias Subdivision September 2010 Flood Study

Hydrology and Hydraulics Design Report. Background Summary

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS

Section 3.0 Existing Systems Hydrology and Hydraulics

WQ Outlet Design Single Orifice Orifice diameter = 24. Perforated riser/orifice Plate Outlet area per perforation row = 4

Rucker Pond. Background

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

Stage Discharge Tabulation for Only Orifice Flow

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

Estimating Sewage System Flows

******************* Project Description ******************* File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF

Application of Real-Time Rainfall Information System to CSO control. 2 October 2011 Naruhito Funatsu METAWATER Co., Ltd.

January 22, Coronado National Forest 300 West Congress Street Tucson, AZ Jim Upchurch, Forest Supervisor. Dear Mr.

STORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect

Drainage Analysis. Appendix F

EROSION CONTROL NARRATIVE

Sediment Capture in Pervious Concrete Pavement tsystems: Effects on Hydrological Performance and Suspended Solids

REPORT FOR: ISLAND LAKE ESTATES 4275 Placida Road Englewood, FL 34224

Appendix O. Sediment Transport Modelling Technical Memorandum

Attachment B to Technical Memorandum No.2. Operations Plan of Ross Valley Detention Basins

International Journal of Agriculture and Environmental Research

Study 16.5 Probable Maximum Flood (PMF)

STREAM RESTORATION AWRA Summer Specialty Conference, GIS and Water Resources IX

Lake Tahoe Watershed Model. Lessons Learned through the Model Development Process

Clark Regional Wastewater District

STORMWATER MANAGEMENT REPORT

Notes: We all know that Toulmins Spring Branch is a sub-watershed of Three Mile Creek watershed. Some part of it is in Mobile area and rest of it is

The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention basin design

Precipitation Rabi H. Mohtar

Statement of Impact and Objectives. Watershed Impacts. Watershed. Floodplain. Tumblin Creek Floodplain:

DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO

Inflow and Infiltration. John Sorrell, P.E. City of Raleigh Public Utilities Department

2012 Rainfall, Runoff, Water Level & Temperature Beebe Lake Wright County, MN (# )

APPENDIX B DRAINAGE REPORT

ATTACHMENT A. STORMWATER MANAGEMENT REPORT Tamiami Trail East Ochopee, FL 34141

Chapter 5 CALIBRATION AND VERIFICATION

WELCOME Lake Wabukayne OPEN HOUSE

Study 16.5 Probable Maximum Flood (PMF)

Illinois State Water Survey Division

9/12/2014 O V E RV I E W

Hydrologic budget of the ORW mitigation wetland, 2002

PH YSIC A L PROPERT IE S TERC.UCDAVIS.EDU

Lessons Learned and Shared

Caledon Villas Corporation

Vermont Soil Climate Analysis Network (SCAN) sites at Lye Brook and Mount Mansfield

City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229

Stormwater Drainage Design Report. Reeve & Associates, Inc. Maverik, Inc. 88th Avenue and Pecos Street. Thornton, CO

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS

MS4 Flow and Precipitation Monitoring Project Progress Report

CIVIL CONSULTING ENGINEERS

Interconnected Channel and Pond Routing Model (ICPR) 2002 Streamline Technologies, Inc. Page 1 of 5

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase.

Hillcrest Residential Development Hollywood, Florida

September 6, City of Thornton 9500 Civic Center Drive Thornton, CO (303) RE: Maverik Thornton, CO - Drainage Report

Large-Scale Sediment Retention Device Testing (ASTM D 7351) SedCatch Sediment Basket Inlet Filter Exposed to 6% Sediment Load

Large-Scale Sediment Retention Device Testing (ASTM D 7351) SedCatch Sediment Basket Inlet Filter Exposed to 1.5% Sediment Load

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY

Great Lakes Update. Volume 199: 2017 Annual Summary. Background

Lower Tuolumne River Accretion (La Grange to Modesto) Estimated daily flows ( ) for the Operations Model Don Pedro Project Relicensing

2016 Fall Conditions Report

Local Flood Hazards. Click here for Real-time River Information

HYDROLOGY REPORT Tentative Tract No. 5978

Implementing a Thermal Urban Runoff Model (TURM)

Flow Monitoring in the Collection System September 11, 2014

Memo. I. Executive Summary. II. ALERT Data Source. III. General System-Wide Reporting Summary. Date: January 26, 2009 To: From: Subject:

Rainfall Estimation at S-44 Site

Basic Hydraulics June 2007

Bushkill Creek 3 rd Street Dam Removal Analysis

Wal-mart Store # Ft. Walton Beach, FL NE Corner of Eglin Parkway/S.R. 85 and South Street STORMWATER REPORT. February 2017

RELIABILITY OF DESIGN STORMS IN MODELLING

DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING Urban Drainage: Hydraulics. Solutions to problem sheet 2: Flows in open channels

University of the Virgin Islands Conceptual Stormwater Management Plan Coral Bay Watershed Final Letter Report (May 2005)

Technical Memorandum. City of Salem, Stormwater Management Design Standards. Project No:

COLLIER COUNTY RESOURCE RECOVERY BUSINESS PARK ENGINEERING REPORT AND CALCULATIONS

EROSION CONTROL NARRATIVE

Range Cattle Research and Education Center January CLIMATOLOGICAL REPORT 2016 Range Cattle Research and Education Center.

Climate Adaptation Challenges for Boston s Water and Sewer Systems


Table (6): Annual precipitation amounts as recorded by stations X and Y. No. X Y

This site will utilize an infiltration berm to manage the two-year/24-hour volume increase.

Optimal Artificial Neural Network Modeling of Sedimentation yield and Runoff in high flow season of Indus River at Besham Qila for Terbela Dam

CLIMATOLOGICAL REPORT 2002

1 in = ft (round answer to nearest integer)

9. PROBABLE MAXIMUM PRECIPITATION AND PROBABLE MAXIMUM FLOOD

DAVID NOEL KELLY CIVIL. David Noel Kelly :24:14-04'00'

Rainfall Observations in the Loxahatchee River Watershed

Transcription:

Monitoring Considerations and Costs Stormwater BMP Selection, Design, and Monitoring Florida Stormwater Association September 9, 2016 Harvey H. Harper, Ph.D., P.E. Environmental Research & Design, Inc.

Objectives of BMP Monitoring Internal Objectives Just to satisfy contract requirements or to learn about BMP Evaluate the load reduction effectiveness of the BMP as constructed How much mass went in and how much left Most BMPs include both hydrologic/hydraulic and water quality components Evaluate hydrologic/hydraulic performance Wet ponds/wetlands Conduct complete hydrologic budget to include precipitation, inflows, evaporation, GW inputs/losses Evaluate water quality changes Monitor inflow/outflow quality Calculate BMP efficiency Calculate and compare pre vs. post loadings

Quality Assurance Project Plans Quality Assurance Project Plans (QAPP) QAPP provides details of proposed field and lab activities and QA procedures Sampling and analyses must conform to Requirements outlined in Chapter 62-160 F.A.C. Provides basic requirements for approved field methods, record keeping, lab certification, lab methods, holding times, sample preservation, audits Requirements for Field and Analytical Work performed for the Department of Environmental Protection under Contract (DEP-QA- 002/02), February 2002 Describes quality objectives, field and lab activities, documentation, record keeping, and QC requirements Methodologies for field monitoring are outlined in the FDEP document titled Standard Operating Procedures for Field Activities (DEP-SOP-001/01) dated March 1, 2014

FDEP Monitoring Requirements No. of Events Standard FDEP monitoring protocol specifies pre/post monitoring for a minimum of 7 10 events Only appropriate for BMPs where the performance is not impacted by previous runoff Inappropriate for wet ponds, wetlands, rain gardens, gross pollutant separators May be appropriate for infiltration devices and alum treatment Lab Analyses All labs doing analyses for DEP funded grant monitoring must be NELAC certified Not all labs are created equal Be sure to specify detection limits Do not use wastewater labs

Flow Monitoring The most common challenge in conducting stormwater monitoring is flow measurement at low flow conditions Flow meters with area/velocity (AV) autosamplers generally have a low end velocity measurement of 0.2 fps Data below this range are generally unreliable A velocity of 0.2 fps in a full 48 pipe is 2.5 cfs Some sites have a continuous baseflow that substantially exceeds the runoff volume on an annual basis This baseflow must be captured when conducting efficiency studies, especially for pond systems The flow monitoring challenge can be overcome by: Changing the flow measurement to a more accurate primary device such as a weir Pressure transducer probes on a primary device are much more accurate than AV probes Conduct periodic field measurements of discharge using an accurate device such as a SonTek Accoustic Doppler flowmeter Develop flow patterns for baseflow

Sample and Data Collection Discrete or Composite Discrete Individual samples collected during runoff hydrograph and then combined together Composite multiple samples collected at timed or flowweighted basis Number of Samples Collect flow-weighted samples over a wide range of rainfall conditions Commonly conduct hydrologic and water quality sampling for an annual period Sampling needs to include baseflow, if present Hydrologic Data Include flow meters, rain gauges, water level recorders, evaporimeter, staff gauges, monitoring wells

Monitoring Multiple Locations Basic approach is to monitor all significant inflows to a BMP that is being evaluated Characteristics of lesser inflows can be estimated using characteristics from nearby sites Runoff inflow volumes can be estimated using hydrologic modeling

Elder Rd. Monitoring Locations for the Elder Creek Site 18 RCP from Elder Rd. Not Monitored Site 3 Elder Ditch/Elder Rd. Inflow 48 RCP Staff Gauge Water Level Recorder Broad-Crested Concrete Weir 18 RCP from Elder Rd. Not Monitored Rain Gauge Evaporimeter Shallow Planted Area Site 2 Elder Ditch Inflow 34 x53 ERCP Site 4 Pond Outflow Compound Weir Narcissus Rd. Site 1 Elder Creek Inflow 58 x91 ERCP

Powering Monitoring Equipment Use 120 VAC power when available Especially useful when refrigerated samplers are being used For long term projects, a power pole and meter is set at the project site Possible hook up to public utility sites (lift stations, etc.) or private individuals Also use 12 VDC batteries to power equipment using solar panels for recharging the batteries Sites are visited at least once each week to review battery status and replace if necessary

Dry Detention and Underdrain Monitoring Sites Field Monitoring - Conducted for 12 months - 17 Isco Avlanche autosamplers - 17 Isco flowmeters - 17 insulated equipment shelters - 4 Isco Model 674 rainfall recorders - 4 Bulk precipitation collectors - 10 Global Water digital water level recorders - 4 Class A pan evaporimeters - 10 shallow monitoring wells - 1 SonTek Acoustic Doppler flow meter - 1 Hydrolab Datasonde 4a water quality monitor Orlando Underdrain Site Bonita Springs Dry Detention Site Naples Dry Detention Site Pembroke Pines Dry Detention Site

Bonita Springs Dry Detention Pond Site Dry Detention Pond Dry Detention Pond Conservation Area Dry Detention Pond Wiggins Pass Rd.

Bonita Springs Stormwater System 42 36 Parameter Units Value Pond 2 (0.45 ac.) Basin = 2.92 ac. 42 Pond 1 (0.09 ac.) Basin = 2.92 ac. Project Area acres 22.11 Impervious Area acres 16.68 DCIA % 75.4 Conservation Area Commercial Retail Store 15 Stormwater System Pervious CN Value acres 1.57 % of area 7.1-63.1 15 42 42 36 Water Quality Vol. Treatment Depth Year Constructed ac-ft 1.54 Inches over basin 0.84-2006 Pond 3 (1.11 ac.) Basin = 16.27 ac. Outfall Structure 24 54 15 15 15 15

Pembroke Pines Dry Detention Ponds Pond 1 Inflow from Parking Area Inflow from Pond 1 Inflow from Parking Area a. Inflow to Pond 1 from parking lot b. Inflows to Pond 2 Outfall Structures c. Dual outfall structures in Pond 2 d. Pond 2 under flooded conditions

Schematic of aluminum V-notch structure used to measure pond inflows Fabricated V-notch Weir

Naples Monitoring Sites 1 & 2 Fabricated V-notch Weir Fabricated V-notch Weir Site 1 Parking Lot Inflow monitoring site Site 1 Parking Lot Inflow equipment Fabricated V-notch Weir Site 2 Parking Lot Inflow Site Conduit for Tubing and Cables Site 2 Parking Lot Inflow equipment

Naples Monitoring Sites 3 & 4 Fabricated V-notch Weir Fabricated V-notch Weir Monitoring Well Site 3 Rear Store Area Inflow Site Site 3 Monitoring Equipment Site 3 Equipment Shelter Outfall Structure Conduit for Tubing and Cables Skimmer Site 4 System Outfall Site 4 Monitoring equipment at outfall structure

Pembroke Pines Monitoring Site 1 Fabricated V-notch Weir Fabricated V-notch Weir Site 1 North pond monitoring equipment Site 1 Storm event conditions

Monitoring Open Channels Ditch Inflow From S.R. 46 Inflow from Lake Gem Inflow to Club II Pond

Monitoring Open Channels con t. a. Weir structure formed and poured with concrete b. Completed weir structure used to provide constant control section for flow measurement

Monitoring Open Channels con t. Equipment Shelter Pond 1 Weir Weir a. Inflow channel with weir structure b. Inflow channel upstream of weir structure Water Level Recorder c. Horizontal weir

Monitoring Costs A typical 12-month monitoring program for a wet detention based BMP is ~ 80 100K Typical 12-month monitoring for an infiltration BMP is ~ 75K

Questions?