Case study comparing from Q-system and Terzaghi s Rock Load Classification. *Han Fook Kwang and Cho Man-Sup 1)

Similar documents
Underground Excavation Design Classification

COMPARING THE RMR, Q, AND RMi CLASSIFICATION SYSTEMS

NNN99. Rock Engineering for the Next Very Large Underground Detector. D. Lee Petersen CNA Consulting Engineers

An introduction to the Rock Mass index (RMi) and its applications

Session 3: Geology and Rock Mechanics Fundamentals

Final design of Belesar III and Los Peares III Hydropower Projects. (Galicia, Spain).

EXAMINATION PAPER MEMORANDUM

Observational Methods and

Instructional Objectives. Why use mass classification? What is rock mass classification? 3 Pillars of empirical design and rock mass classification

Seismic analysis of horseshoe tunnels under dynamic loads due to earthquakes

ON THE FACE STABILITY OF TUNNELS IN WEAK ROCKS

MEMORANDUM SUBJECT: CERTIFICATE IN ROCK MECHANICS PAPER 1 : THEORY SUBJECT CODE: COMRMC MODERATOR: H YILMAZ EXAMINATION DATE: OCTOBER 2017 TIME:

Building on Past Experiences Worker Safety

Weak Rock - Controlling Ground Deformations

In-situ Experiments on Excavation Disturbance in JNC s Geoscientific Research Programme

1 of 46 Erik Eberhardt UBC Geological Engineering ISRM Edition

Geotechnical Monitoring for Safe Excavation of Large Rock Cavern: A Case Study

DESIGN AND CONSTRUCTION OF LARGE

ENGINEERING GEOLOGY AND ROCK ENGINEERING

Entrance exam Master Course

Introduction and Background

Geotechnical & Mining Engineering Services

Numerical modelling for estimation of first weighting distance in longwall coal mining - A case study

Correlation of Revised BQ System in China and the International Rock Mass Classification Systems

Rock-Quality Study at Tunnel Site in the Kameng Hydro-Electric Project, Bichom, Arunachal Pradesh, India

H.Öztürk & E.Ünal Department of Mining Engineering, Middle East Technical University, Ankara, Turkey

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE. METALLIFEROUS MINING OPTION Updated November 1998

Numerical Approach to Predict the Strength of St. Peter Sandstone Pillars acted upon by Vertical Loads A case study at Clayton, IA, USA.

Ground support modelling involving large ground deformation: Simulation of field observations Part 1

Influence of foliation on excavation stability at Rampura Agucha underground mine

Numerical analysis of K0 to tunnels in rock masses exhibiting strain-softening behaviour (Case study in Sardasht dam tunnel, NW Iran)

Calculation of periodic roof weighting interval in longwall mining using finite element method

7. Foundation and Slope Stability

ROCK MASS PROPERTIES FOR TUNNELLING

Rock slope rock wedge stability

A PROBABILISTIC APPROACH FOR CHARACTERIZING THE COMPLEX GEOLOGIC ENVIRONMENT FOR DESIGN OF THE NEW METRO DO PORTO

10. GEOTECHNICAL EXPLORATION PROGRAM

Successful Construction of a Complex 3D Excavation Using 2D and 3D Modelling

SERVICEABILITY LIMIT STATE DESIGN

Moglicë HPP - Albania. Jorge Terron

Two Case Studies on Soil Nailed Slope Failures

Ground Support in Mining and Underground Construction

Appraisal of Soil Nailing Design

The effect of installation angle of rock bolts on the stability of rock slopes

Stability Assessment of a Heavily Jointed Rock Slope using Limit Equilibrium and Finite Element Methods

Borehole Camera And Extensometers To Study Hanging Wall Stability Case Study Using Voussoir beam - Cuiabá Mine

Estimates of rock mass strength and deformation modulus

Flin Flon Mining Belt

Boreholes. Implementation. Boring. Boreholes may be excavated by one of these methods: 1. Auger Boring 2. Wash Boring 3.

Determination of stope geometry in jointed rock mass at Pongkor Underground Gold Mine

Eurocode 7 from soil mechanics to rock mechanics. Luís Lamas, LNEC, Lisbon, Portugal Didier Virely, CEREMA, Toulouse, France

Feasibility of dynamic test methods in classification of damaged bridges

1. Rock Mechanics and mining engineering

Table of Contents Development of rock engineering 2 When is a rock engineering design acceptable 3 Rock mass classification

Estimation of support requirement for large diameter ventilation shaft at Chuquicamata underground mine in Chile

Critical Borehole Orientations Rock Mechanics Aspects

Rock mass classification systems

ROCK MASS CHARACTERISATION IN ENGINEERING PRACTICE

Rockburst mitigation experiences on underground projects in the Cheves Hydropower project in the Peruvian Andes

TBM "Boreability" in Hard Rock

R13. II B. Tech I Semester Regular Examinations, Jan MECHANICS OF SOLIDS (Com. to ME, AME, AE, MTE) PART-A

Structurally controlled instability in tunnels

Chapter (6) Geometric Design of Shallow Foundations

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE COAL MINING OPTION

Quantitative Classification of Rock Mass

Geotechnical project work flow

Structural Analysis I Chapter 4 - Torsion TORSION

Module 5: Failure Criteria of Rock and Rock masses. Contents Hydrostatic compression Deviatoric compression

Purpose of this Guide: To thoroughly prepare students for the exact types of problems that will be on Exam 3.

Engineeringmanuals. Part2

DESIGN AND DETAILING OF COUNTERFORT RETAINING WALL

Application of Core Logging Data to generate a 3D Geotechnical Block Model

Appendix 6 Geotechnical report

Determination of the coefficient of earth pressure at rest in situ in overconsolidated clay

GROUND RESPONSE AND SUPPORT MEASURES FOR PIR PANJAL TUNNEL IN THE HIMALAYAS

Some Aspects on the Design of Near Surface. Tunnels - Theory and Practice. Thomas Marcher¹, Taner Aydogmus²

The effect of dip of joints on the axial force of rock bolts

Design and implementation of a damage assessment system at Argyle Diamond s block cave project

Minimization Solutions for Vibrations Induced by Underground Train Circulation

EOSC433: Geotechnical Engineering Practice & Design

Progress with the excavation and support of the Mingtan power cavern roof

Deformability Modulus of Jointed Rocks, Limitation of Empirical Methods and Introducing a New Analytical Approach

Experimental Research on Ground Deformation of Double Close-spaced Tunnel Construction

A new design approach for highway rock slope cuts based on ecological environment protection

Module 9 : Foundation on rocks. Content

Department of National Defence B-Jetty Reconstruction

LICENTIATE THESIS. Evaluation of rock mass strength criteria. Catrin Edelbro

In situ fracturing mechanics stress measurements to improve underground quarry stability analyses

University of Sheffield The development of finite elements for 3D structural analysis in fire

K Design Graphs and Charts for Raft Foundations Spanning Local Depressions

Geotechnical data from optical and acoustic televiewer surveys

R Long term stability of rock caverns BMA and BLA of SFR, Forsmark. Diego Mas Ivars, María Veiga Ríos Itasca Consultants AB

Study of Soft Rock Roadway Support Technique

Application of a transversely isotropic brittle rock mass model in roof support design

Three-Dimensional Failure Criteria Based on the Hoek Brown Criterion

DETERMINING THE STRESS PATTERN IN THE HH RAILROAD TIES DUE TO DYNAMIC LOADS 1

THEME A. Analysis of the elastic behaviour of La Aceña arch-gravity dam

The Preliminary Study of the Impact of Liquefaction on Water Pipes

CHAPTER 4. Design of R C Beams

Rock parameters for blasting on the highway Split-Dubrovnik

Transcription:

Case study comparing from Q-system and Terzaghi s Rock Load Classification *Han Fook Kwang and Cho Man-Sup 1) 1) SK E&C, Singapore ABSTRACT This paper compares Terzaghi s Rock Load Classification System against the empirical method adopted for the Q-system based on the case study of a constructed mined tunnel. The rock load estimated from the Terzaghi s Rock Load Classification method was obtained by correlating site tunnel convergence monitoring of a mined tunnel with a back analysis of a 3-D numerical model of the mined tunnel. The rock load estimated from the Q-system empirical method was based on the Q-value and the static modulus of deformation observed from the field. Key words: Face mapping, support pressure, mined tunnel numerical model, instrumentation. 1. INTRODUCTION Over the years the Q-system had been used widely for the design of mined tunnels. The Q-system had been constantly revised to suit the various usage in particular for the design of the supporting requirements of mined tunnels through case studies from previous tunnels. Often the Q-system had also been compared against the other rock mass classification methods to identify the most appropriate supporting system. This paper attempts to compare the support pressures estimated from the Q- system and the Terzaghi s Rock Load Classification method in the lining system based on the site monitoring results obtained from a mined tunnel constructed in Singapore. In 2012 SP Power Assets Ltd commissioned the construction of two networks of deep cable tunnels; in the directions of North-South and East-West alignments. The entire length of the tunnels are 35km across Singapore. 1

Figure 1.1 Alignments of cable tunnel The North-South alignment is approximately 18.5km long from Gambas shaft (in the north) to May shaft (in the south) with a total of 7 shafts. This paper discusses the Tagore Shaft design located along the North-South Contract alignment. 1.1 Tagore Shaft The shaft consists of a 14m clear inner diameter vertical shaft constructed via controlled blasting and temporarily supported by shotcrete lining. The overall depth of the vertical shaft is approximately 65m deep. The mined tunnel layout at the bottom of the shaft consists of a 9.5m high by 11m wide adit tunnel linking to 2 nos 8.5m high by 8.5m wide enlargement tunnels via a junction [8]. 2

Figure 1.2 Overall isometric layout Figure 1.3 Shaft and tunnel cross section Based on the Contract Specifications, the mined tunnel was to be completed with an insitu permanent lining enveloped within the temporary shotcrete lining. Therefore the finished tunnel system to be adopted was a Double Shell Lining (DSL) tunnel. Waterproofing was provided via a membrane laid between the linings [8]. 2. OBJECTIVE This paper aims to compare the rock loads estimated from the Terzaghi s Rock Load Classification method via correlating the back analysis of a set of temporary lining models with the tunnel convergence monitoring obtained from the field instrumentation against the Q-system empirical method. 3. TAGORE SITE CONDITION With reference to the Geological Map of Singapore (DSTA, 2009), the Tagore Shaft is located in Bukit Timah Granite zone as shown in the map. In Singapore, Bukit Timah forms one of the major formations and it is recognized as the base rock as it underlies all other formations. 3

Figure 3.1 Geological map of Tagore Shaft Bukit Timah Granite predominately includes granite and other less common rocks such as adamellite, granodiorite, and diorite. In terms of mineralogy contents, Bukit Timah Granite composes with quartz (30%), fieldspar (60-65%), biotite and hornblende (less than 10%). In general, the texture of Bukit Timah Granite is medium to course grained, light grey colour (sometimes pinkish orthoclase), however, greenish dark grey, course grained Granite was encountered at during Tagore Shaft excavation. The rock head levels are largely undulating at Tagore Shaft location, ranging from 20m (shaft side) to 42m (adit and enlargement sides) and overlain by residual soil with small extent of peaty clay and sand layers. The mined tunnels were constructed approximately 35m below the rock head level at approximately 60m below ground level. The inclusions and intrusions within the Bukit Timah Granite in the form of dykes and fault zones were encountered during the mined tunnel work. At approximately 56m to 58m depth, a dark greenish grey, medium grained DIORITE Dyke was encountered during adit excavation and rock mapping as a dyke and highly fractured zone were encountered. Although a dyke and fault zone were encountered during adit tunnel excavation, generally the crown and face were found to be fairly stable and insignificant water ingress observed. The figure below shows the exposed rock face of the heading excavation (during the face mapping phase) which illustrates the varying quality of rock encountered during the mining activities. 4

Figure 3.2 Face mapping for tunnel heading No insitu testing was carried out for the Uniaxial Compressive Strength for Rock Mass. Instead the values for GIII and GII were estimated as 0.5 MPa and 3.5 MPa respectively for mined tunnel (Drill and Blast), setting s 3 = 0, based on the GSI and intact UCS values using the Hoek-Brown equation (Hoek, Carranza-Torres and Corkum, 2002) as follows [7]; s c = s ci. s a Eq. (1) Where: s = exp [(GSI 100) / (9 3D)] Eq. (2) a = 1/2 + 1/6 x (e -GSI / 15 e -20/3 ) Eq. (3) 4. INSTALLED TEMPORARY LINING SUPPORT According to the face mapping Q-value results, various combinations of shotcrete thicknesses and rockbolts were installed in accordance to the design. Below figure shows the face mapping results carried out for the heading. 5

Figure 4.1 Face mapping results Following the face mapping results, the general thickness of shotcrete applied was 250-200mm thick with 4.5m long, 25mm thick rockbolts installed at approximately 1.5m (radially) by 1.2m (longitudinally) spacings. 5. DESIGN ANALYSIS METHODOLOGY The geometry and layouts of the numerical model was derived from Building Information Modeling (BIM). The Permanent Lining design was carried out in accordance to the Singapore Power Assets Ground Interpretation Baseline Report (GIBR) [7] and Contract Specifications Design Criteria for the design of the permanent linings. Prior to the tunnel mining works, Type 1 Temporary Lining numerical model was created (based on the similar geometry and layouts as the permanent model) for the estimation of the convergence monitoring limit, which was adopted as 10mm, for the mined tunneling works. During the actual tunnel mining works, a set of Type 2 Temporary Lining numerical models (based on the similar geometry and layouts as the permanent model) were created with a range of rock loads and springs. Displacements from these models were compared with onsite convergence monitoring at similar locations to identify the most probable rock load in accordance with the Terzaghi s Rock Load Classification method. Based on the Q-value observed onsite, the Q-system rock load was calculated in accordance with the Q-system empirical method. 6

6. NUMERICAL ANALYSIS Ground Investigations were carried out on site via boreholes and laboratory tests for the design input assumptions for the numerical modeling. Key assumptions for both Permanent and Temporary Lining models adopted were in accordance to the GIBR and utilized the Terzaghi s Rock Load Classification method. Rock assumed for the design was GIII, the density of the rock adopted was 24kN/m 3 [7]. Figure 6.1 Numerical model of shaft and tunnel Figure 6.2 Terzaghi rock load factor diagram 7

6.1 Permanent Lining Numerical Model Table 6.1 Terzaghi s Rock Load Classification Flat mesh plates were created to be approximately 1m by 1m with fixed joints and 0.3 MPa compression-only springs activiated in the Z-axis (perpendicular to the plates). Boundary conditions of the 3-D Permanent Lining model was checked with a 2-D Plaxis model. Both models were checked for similar tunnel and shaft deformation magnitudes. The plates were modelled to be reinforced concrete walls and slabs with thicknesses to the design as shown below. Element Thickness Adit Tunnel 0.5m Adit Tunnel Base Slab 1.2m Enlargement Tunnel 0.5m Enalgement Tunnel Base Slab 1.0m Junction Crown 0.5m Junction End Wall 1.5m Junction Base Slab 2.0m Table 6.1 Permanent Lining member thickness In addtion to the provision of waterproofing membrane, crack widths checks of the reinforced concrete was limited to 0.25mm for external face and 0.3mm to internal face [8]. Hydrostatic pressures were modelled to full height at ground level. Lateral loading to the tunnels and shaft was considered. Load safety factors adopted for all loads were 1.4 ULS and 1.0 SLS. 8

Horizontal stresses applied to the model were 0.8 and 1.2 times the overburden stress. The K o values were recommended by SPPA GIBR [7]. Rock classification was estimated with boreholes carried out prior to the works and the upper levels of the shaft rock excavations. The rock was estimated to be very blocky and seamy. The overburden rock load adopted was the more onerous between Terzaghi Rock Load Classification method [8] and Unal Formula using RMR System which were calculated to be 0.25 MPa and 0.092 MPa respectively. The overburden rock load was applied to the top 120 degress of the tunnel crown The completed approved design was later reviewed during the tunnel face mapping results. Figure 6.1 Section of shaft for mapping Table 6.2 Shaft mapping results Figure 6.2 Tunnel layout for mapping Table 6.3 Tunnel mapping results 9

6.2 Type 1 Temporary Lining Numerical Model The Temporary Lining model was similar to the Permanent Lining model in terms of geomerty and layouts and with flat mesh plates were created to be approximately 1m by 1m. Spring supports were spaced uniformly around the circumfrence of the tunnels and shafts at similar spacings and tension capacity of the actual rockbolts used in the mined tunnel. Where no rockbolts are located, rock springs with 0.3 MPa compression-only springs were included to simulate the resistance from the rock mass. These rock and rock bolt springs were only activated in the direction perpendicular to the meshed plates (i.e Z-axis), the other axes were released. The moments for these springs were also released. The meshed plates were modelled to be 500mm thick concrete elements to simulate the average applied shotcrete thickness. The applied shotcrete was Fibre Reinforced Concrete however to be convservative, the model adopted plain concrete elements. No base slab, lateral loading and hydrostatic pressure were modelled. The overburden loading applied was similar to the Permanent Lining model i.e 0.25 MPa applied to the crown at approximately 120 degress. 6.3 Type 2 Temporary Lining Numerical Model The model parameters, layout and geometrical inputs were similar to the Type 1 Temporary Lining model where no base slab, lateral loading and hydrostatic pressures were not modelled. The overburden rock load adopted were based on Terzaghi s Rock Load Classification method using the similar very blocky and seamy (classification as the Permanent Lining model) providing a range 0.35 to 1.10(B+H t ) for the overburden load. Based on the range of factors (i.e 0.35 to 1.10), different vertical overburden loads were computed with an assumed rock density of 24 kn/m 3 and varying rock springs applied (i.e 0.1 MPa, 0.2 MPa, 0.3 MPa, 0.4 MPa and 0.5 MPa) to the numerical model. The nodal displacements of the model were comparied at similar locations to the measured onsite convergence monitoring results. Rock loads were applied as vertical overburden on the top 120 degress of the tunnel crown. No lateral loads was applied to the tunnel walls on the sides in the numerical model because this was considered to be more conservative. Ko = 0.8 was adopted as recommended in the SPPA GIBR [7] for the lateral loads which were applied only to the shaft walls. 10

Combination Load case considered Rock Load factor 0.35 1. Selfweight 2. Adit vertical overburden (172.2 kn/m 2 ) 3. Enlargement overburden (142.8 kn/m 2 ) 4. Shaft lateral load (137.76 kn/m 2 ) Rock Load factor 1. Selfweight 0.4 2. Adit vertical overburden (196.8kN/m 2 ) 3. Enlargement overburden (163.2 kn/m 2 ) Rock Load factor 0.5 Rock Load factor 0.6 Rock Load factor 0.7 Rock Load factor 0.8 Rock Load factor 0.9 Rock Load factor 1.0 Rock Load factor 1.1 4. Shaft lateral load (157.44 kn/m 2 ) 1. Selfweight 2. Adit vertical overburden (246 kn/m 2 ) 3. Enlargement overburden (204 kn/m 2 ) 4. Shaft lateral load (196.8 kn/m 2 ) 1. Selfweight 2. Adit vertical overburden (295.2 kn/m 2 ) 3. Enlargement overburden (244.8 kn/m 2 ) 4. Shaft lateral load (236.16 kn/m 2 ) 1. Selfweight 2. Adit vertical overburden (344.4 kn/m 2 ) 3. Enlargement overburden (285.6 kn/m 2 ) 4. Shaft lateral load (275.52 kn/m 2 ) 1. Selfweight 2. Adit vertical overburden (393.6 kn/m 2 ) 3. Enlargement overburden (326.4 kn/m 2 ) 4. Shaft lateral load (314.88 kn/m 2 ) 1. Selfweight 2. Adit vertical overburden (442.8 kn/m 2 ) 3. Enlargement overburden (367.2 kn/m 2 ) 4. Shaft lateral load (354.24 kn/m 2 ) 1. Selfweight 2. Adit vertical overburden (492 kn/m 2 ) 3. Enlargement overburden (408 kn/m 2 ) 4. Shaft lateral load (393.6 kn/m 2 ) 1. Selfweight 2. Adit vertical overburden (541.2 kn/m 2 ) 3. Enlargement overburden (448.8 kn/m 2 ) 4. Shaft lateral load (432.96 kn/m 2 ) Table 6.4 Numerical Model Load Combinations 7. ONSITE CONVERGENCE MONITORING FOR ESTIMATING ROCK LOADS Convergence monitoring of the mined tunnel was carried out via a series of 3-D prisms located at specific intervals throughout the tunnels which were installed during the mining phase. The convergence array adopted for this paper as shown below was located approximately 20m from the shaft-adit tunnel. The excavation for this location was carried out on the 5 Jan 2015, the array was installed on the 17 Jan 2015 approximately 8m from the tunnel face after 4 rounds of blasting and advancements. 11

Figure 7.1 Onsite convergence monitoring points Both Terzaghi s Rock Load and the Q-system empirical methods assume the tunnel sections to be constant where the rock loads were applied in a 2-dimensional space. The mid-point of the adit tunnel convergence monitoring was adopted because it was considered that there was sufficient length of tunnel distance away from shaft and junction areas that could affect the convergence results due to the 3-dimensional geometrical effects during the mining works. The following graphs show the studies carried out for each convergence monitoring point comparing the 5 different rock springs (i.e 0.1 MPa, 0.2 MPa, 0.3 MPa, 0.4 MPa and 0.5 MPa) with the range of overburden loadings (i.e 0.35-1.1(B+H)) against the site monitored measurements. 12

13

From the above graphs, the most probable rock spring to be 0.2 MPa and the most probable applied rock load factor to be 0.4(B+H) = 196.8kN/m 2. Figure 7.2 Collated information from convergence, rock spring and rock load 8. Q-SYSTEM EMPIRICAL METHOD The Q-value observed at the adit location adopted for the numerical model approximately 20m from the shaft-adit junction location was 22.5 (see Table 6.3 Tunnel Mapping results). The depth of the tunnel at this location from the ground level to the tunnel crown is approximately 58.5m while the tunnel height and width is 9.5m and 11m respectively. The empirical equation for estimating the rock load (support pressure) [5] is P r = 0.1Q -1/3 (MPa) Eq. (4) Previous papers have found the correlation between the support pressures to be inversely proportional to the static modulus of deformation Em [4, 5]. Therefore the equation [9] is P r = 1/Em (MPa) Eq. (5) Where, Em = 25logQ (GPa) for Q > 1 From the above equations (4) and (5), the rock load was calculated to be 35kN/m 2 for equation (4) and 29.6kN/m 2 for equation (5). The range can be considered small, therefore the anticipated rock loads from both equations can be considered acceptable. 14

Support pressures was found to be inversely proportional to deformation modulus, a central trend for tunnel deformation is that Δ in millimeters is equal to the span in meters divided by Q [4]. Therefore, the equation gives Δ = Span / Q (mm) Eq. (6) Convergence 5 was selected for the Terzaghi Rock Load method, the span to be adopted shall be the similar length as convergence 5 which was estimated to be 11.7m. Hence equation (6) gives a Δ of 0.52mm. The recorded convergence was recorded to be 5.2mm which should be considered to be the total movement throughout the mining procedure that includes the vibrations from the blasting phase, therefore such small movements can be reasonable. 9. CONCLUSIONS The numerical model created was a wish-in place model without considerations for the staged construction sequence and the stabilization of the rock through the cumulative loosening process during the mining process. During the excavation sequences of the mined tunnel, the intact rock mass would have been disturbed and some beneficial rock loosening may have taken place. By the time of the excavation of the rock at that location, the rock mass would have stabilized thereby recording small displacements at the excavated face. Therefore the displacements obtained from the numerical model should be considered as the total displacement which can be expected to be larger than the actual displacement due to the rock load of the excavated tunnel. This explains the phenomenon where the monitored convergences obtained are generally smaller than the convergences obtained from the numerical model. However one must remember that the monitored convergences includes the vibrations effects from the blasting during the mining phase. This implies that the actual applied rock load should be lesser. Ground investigations carried out prior to the excavations suggested the rock quality to be Blocky to Seamy and Good to Fair. Throughout the mining process, the rock mass at the tunnel level was found to be Blocky and Good. This suggested that the rock mass strength should be 3.5 MPa or higher which would be more than the values adopted by all the numerical models. Therefore the displacements obtained from the numerical models will had been conservative. The Terzaghi s Rock Load Classification method for rock loads provides reasonable support pressure estimates for small tunnels but over estimates for tunnels having diameter more than 6m [2] and is generally applied to softer and/or weaker rocks condition with lower rock mass shear strength. Therefore the 196.8kN/m 2 [i.e 0.4(B+H)] rock load and 0.2 MPa rock spring discussed in this paper can still be considered to be conservative. 15

As mentioned above the quality of rock from site observations was found to be good, the Q-system empirical method discussed in this paper found to be approximately 5 times smaller at 35kN/m 2 can be considered to be reasonable since Q- system is best utilized for drill and blast tunnels [8]. This is consistent with author s opinion where the rock load obtained from Q- system empirical method should be lesser than the numerical method which would be more realistic to the actual case. Measured site convergence was also recorded to be small, i.e the largest measured was approximately 5.2mm (in total displacement). This is further evident in the small change in movement estimated to be 0.52mm. The above observations and findings further supports the author s opinion that the rock loads obtained from Q-system is considered more reasonable for good quality rock with sufficient rock cover. Understanding and adopting the suitable method based on the competency of the rock condition can help future tunnels to have an economical design whilst maintaining a safe environment during the construction process. This will also allow designers to better estimate the rock load to apply for more realistic and economical design for future deep tunnels. 10. ACKNOWLEDGMENTS The author would like to acknowledge the Singapore Power Assets Ltd and SK Engineering & Construction (Singapore) for their co-operation, review of the paper and agreement to utilize their data collected. The author would also like to thank colleagues Defence Science Technology Agency Singapore, in particular Dr Zhou Yingxin, and at WSP / Parsons Brinkerhoff for their time and efforts in their review of this paper. REFERENCES 1. Arild Palmstrom & Einar Broach (2006), Use and misuse of rock mass classification systems with particular reference to the Q-system 2. B.Singh & R.K Geol (1999), Rock mass classification: a practical approach in civil engineering: Amsterdam, Elsevier Science 3. E.Grimstad & N.Barton (1993), Updating the Q-system for NMT 4. N.R Barton (2013), Integrated empirical methods for the design of tunnels, shafts and caverns in rock, based on the Q-system 5. N.Barton (2002), Some new Q-value correlations to assist in site characterization and tunnel design 16

6. NGI 2015, Using the Q-system, Rock mass classification and support design 7. Singapore Power Asset (North-South Contract 2) Geological Baseline report 8. Singapore Power Asset (North-South Contract 2) Design Criteria and Performance Specifications, Civil and Structural Works 9. Syed Muntazir Abbas & Habil Heinz Konietzky (2016), Rock Mass Classification Systems 10. Terzaghi, K. (1946, pp15-99), Rock Defects and Loads on Tunnel Supports, In Rock tunneling with Steel Support eds R.V Proctor and T.L. White, Commercial Shearing Co., Youngstown, OHIO 17