NEW DEVELOPMENT IN HIGH POWER RFQ ACCELERATORS*

Similar documents
OVERVIEW OF RECENT RFQ PROJECTS *

Recent High Power RFQ Development

Preliminary design studies of a 100 MeV H /H + LINAC as injector for SNS synchrotron/ads LINAC

RADIO-FREQUENCY QUADRUPOLE LINACS

RFQ BEAM DYNAMICS DESIGN FOR LARGE SCIENCE FACILITIES AND ACCELERATOR-DRIVEN SYSTEMS

Developmental Studies of High Current Proton Linac for ADS Program

Review of ISOL-type Radioactive Beam Facilities

Overview. Scientific Case

A high intensity p-linac and the FAIR Project

China high-intensity accelerator technology developments for Neutron Sources & ADS

Accelerator Option for Neutron Sources & the

Chopping High-Intensity Ion Beams at FRANZ

Proton LINAC for the Frankfurt Neutron Source FRANZ

BEAM DYNAMICS IN A HIGH FREQUENCY RFQ

Comparative Assessment of HIPPI Normal Conducting Structures

TEST MEASUREMENTS WITH THE REX-ISOLDE LINAC STRUCTURES*

Linac JUAS lecture summary

Introduction Frankfurt Neutron Source at Stern-Gerlach-Zentrum FRANZ Development of new accelerator concepts for intense proton and ion beams. High in

Development and application of the RFQs for FAIR and GSI Projects

Proton LINAC for the Frankfurt Neutron Source FRANZ

PIP-II Injector Test s Low Energy Beam Transport: Commissioning and Selected Measurements

A Low Energy Beam Transport Design with high SCC for TAC Proton Accelerator

HIGH CURRENT PROTON BEAM INVESTIGATIONS AT THE SILHI-LEBT AT CEA/SACLAY

WG2 on ERL light sources CHESS & LEPP

Beam Dynamics and Electromagnetic Design Studies of 3 MeV RFQ for SNS Programme

IFMIF High energy beam line design and beam expansion using non-linear multipole lenses and "step-like" magnet

The Impact of Nuclear Science on Life Science. Accelerators for ADS M. Napolitano University Federico II and INFN, Naples, Italy

BEAM DYNAMICS IN A HIGH FREQUENCY RFQ

1.5-GeV FFAG Accelerator as Injector to the BNL-AGS

The SARAF 40 MeV Proton/Deuteron Accelerator

Compact Linac for Deuterons (Based on IH Structures with PMQ Focusing)

Microwave Discharge Ion Sources. Luigi Celona. Istituto Nazionale di Fisica Nucleare Laboratori Nazionali del Sud Via S. Sofia Catania Italy

FUTURE HIGH-INTENSITY PROTON ACCELERATORS

HALO SIMULATION IN A REALISTIC PROTON LINAC DESIGN

BEAM DYNAMICS ISSUES IN THE SNS LINAC

Proposal to convert TLS Booster for hadron accelerator

Space Charge Studies on the ISIS Ring

SPES Conceptual Design Report

Commissioning of the SNS Beam Instrumentation

IFMIF mini-workshop on Beam Instrumentation. Ciemat, Madrid (Spain) 2-3 July 2007

Development of the UNILAC towards a Megawatt Beam Injector

Physics design of a CW high-power proton Linac for accelerator-driven system

Short Introduction to CLIC and CTF3, Technologies for Future Linear Colliders

Accelerators for the Advanced Exotic Beam Facility

DESIGN AND CONSTRUCTION OF LOW ENERGY ELECTRON ACCELERATORS AT SINP MSU

A Project to convert TLS Booster to hadron accelerator 1. Basic design. 2. The injection systems:

HIGH POWER PROTON ACCELERATOR IN KOREA*

Direct-Current Accelerator

Design Status of the PEFP RCS

Design of a 10 MeV normal conducting CW proton linac based on equidistant multi-gap CH cavities *

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

Review of proposals of ERL injector cryomodules. S. Belomestnykh

Superconducting RF Accelerators: Why all the interest?

PRESERVING BEAM QUALITY IN LONG RFQS ON THE RF SIDE: VOLTAGE STABILIZATION AND TUNING. Antonio Palmieri INFN-LNL Legnaro (PD), Italy

PULSE-TO-PULSE TRANSVERSE BEAM EMITTANCE CONTROLLING FOR MLF AND MR IN THE 3-GeV RCS OF J-PARC

The FAIR Accelerator Facility

The Turkish Accelerator Center (TAC) Project. Bora Ketenoğlu. Department of Engineering Physics Ankara University / TURKEY

Front end, linac upgrade, and commissioning of J-PARC. Y. Liu KEK/J-PARC, Japan

HIRFL STATUS AND HIRFL-CSR PROJECT IN LANZHOU

CEA Saclay Codes Review for High Intensities Linacs Computations

Novel, Hybrid RF Injector as a High-average. Dinh Nguyen. Lloyd Young

An Accelerator Driven System MYRRHA

Advanced Design of the FAIR Storage Ring Complex

FAIR AT GSI. P. Spiller, GSI, Darmstadt, Germany

De Prisco, Renato; Comunian, Michele; Grespan, Franscesco; Piscent, Andrea; Karlsson, Anders

C. Wiesner, FRANZ and Small-Scale Accelerator-Driven Neutron Sources

PROTON AND ION SOURCES FOR HIGH INTENSITY ACCELERATORS

Lectures on accelerator physics

Compressor Ring. Contents Where do we go? Beam physics limitations Possible Compressor ring choices Conclusions. Valeri Lebedev.

Design of a Fast Chopper System for High Intensity Applications

Modules 5&6. Beam dynamics overview and Linac architecture

Accelerator Physics, BAU, First Semester, (Saed Dababneh).

SPIRAL 2 Commissioning Status

Technological Challenges for High-Intensity Proton Rings

Run2 Problem List (Bold-faced items are those the BP Department can work on) October 4, 2002

Neutron Imaging at Spallation Neutron Sources

SPIRAL-2 FOR NEUTRON PRODUCTION

ILC Particle Sources -Electron and PositronMasao KURIKI (Hiroshima University)

New Electron Source for Energy Recovery Linacs

Optimization of the SIS100 Lattice and a Dedicated Collimation System for Ionisation Losses

Operational Experience in PIAVI-ALPI Complex. E. Fagotti INFN-LNL

Physics 610. Adv Particle Physics. April 7, 2014

A Multi-beamlet Injector for Heavy Ion Fusion: Experiments and Modeling

Thorium-Cycle Fission for Green Nuclear Power. Pt Peter McIntyre MIt Texas A&M University

Thorium-Cycle Fission for Green Nuclear Power. Pt Peter McIntyre MIt Texas A&M University

The TESLA Dogbone Damping Ring

XX International Linac Conference, Monterey, California

The SARAF CW 40 MeV Proton/Deuteron Accelerator

Accelerator Technology Summary talk

CHOPPING HIGH-INTENSITY ION BEAMS AT FRANZ

Low Energy RHIC electron Cooling (LEReC)

SIMULATION STUDY FOR MEIC ELECTRON COOLING*

Tools of Particle Physics I Accelerators

UPGRADE OF THE HIT INJECTOR LINAC-FRONTEND

ICFA ERL Workshop Jefferson Laboratory March 19-23, 2005 Working Group 1 summary Ilan Ben-Zvi & Ivan Bazarov

Linac4: From Initial Design to Final Commissioning

UPGRADE AND COMMISSIONING OF THE PIAVE-ALPI ECR INJECTOR AT LNL

JAPAN PROTON ACCELERATOR RESEARCH COMPLEX

Abstract. 1. Introduction

Section 4 : Accelerators

Transcription:

NEW DEVELOPMENT IN HIGH POWER RFQ ACCELERATORS* A. Schempp Institut für Angewandte Physik, J. W. Goethe-Universität, D-60054 Frankfurt am Main, Germany Abstract RFQs are the standard solution for new ion injectors for light and heavy ions. A survey on work on high duty factor high current RFQs will be given to illustrate the various solutions and the special problems in that field, which covers e.g. RFQs as spallation source injectors, neutron generators as well as idustrial applications. High power RFQs play a key role in this development, because in that the low energy section the beam from the ion source is formed and a bunched low emittance beam is generated. 1 INTRODUCTION The application of accelerators outside have nuclear and particle physics is rapidly increasing. One important application is the "production" of secondary particles, which were positrons, antiprotons and other exotic nuclear matter at the beginning and is now a wide area from neutron to radioactive beam production. The production rates can be increased by optimizing the beam energy and target arrangement and naturally by increasing the beam current to the target In case of heavy ion beams the duty factor of the machines had to be large because of the limits of sources for (multiple charged) heavy ions. For protons and deuterons the beam currents from ion sources could be pushed up to the 100 ma region, so the duty factors of the accelerators could be modest. Examples are the spallation sources LAMPF, ISIS and IPNS with beam powers of up to 200kW and the synchrotron injectors specially modified or operated as drivers for neutron production or sources of radioactive beams with beams of some kw. To reach the magnitude of Megawatts of beam power the duty factor has again to be increased up to cw operation. This requires new technologies and different optimisation but also another magnitude of technical and financial effort. There are three kinds of projects, which can be distinguished by their beam requirements: 1.: Spallation sources with H - beams and "modest" duty factors between 2% and 10%, beam powers up to 5 MW. 2.: ADS systems which need cw beams of up to 100MW. 3.: Material test accelerators, which deliver low energy beams p.e. 35-40 MeV of D + for IFMIF, 2-4 MeV D + for neutron sources. *supported by the BMBF 2 RFQ DESIGN The RFQ design is the choice of parameters for the beam dynamics the rf-structure and the mechanical (technical) realization. Sometimes RFQ design is meant to be the beam dynamics design is only. But especially for high power beams it is crucial to have a balanced design which takes into account the special rf-problems as well as the engineering to ensure tolerances, to handle the rflosses, the beam with losses, the diagnostics and also maintenance possibilities and control. Beam dynamics is defined by the choice of frequency f, electrode voltage U, beam current, input and output energy and emittances ε and the cell parameters along the RFQ: cell length Li, aperture a i, modulation m i. The result is an RFQ with certain total length L and power consumption N which adiabatically bunches and focuses the dc beam from the ion source with small emittance growth. Fig. 1 Scheme of a RFQ injector While for smaller neutron sources RFQ aspects can dominate the choice e.g. of the frequency and length and rf-power consumption to simplify alignment and tuning, for bigger projects like spallation sources, the optimization of the total linac, the availability of power sources and naturally costs will set some design input parameters and e.g. will increase the frequency to lower the charge per bunch. This reduces emittance growth and matching problems. The choice of basic RFQ parameters will scale others. So a high rf-frequency will require a higher injection energy and allow for higher final energy as well. The radial acceptance and the beam current are inversely proportional to the frequency and proportional to the applied electrode voltage. The total rf-power to reach a final energy depends not on the frequency, so the problems with tolerances and power density dominate at higher frequencies. The energy spread, the output emittance and the beam losses can be improved with a reduced accelerating gradient resp. longer RFQs, which clearly go into costs and sets new limit to the rf-tuning and stability. A major concern are beam losses in the RFQ but also losses along the following linac which can be influenced

by proper shaping and preparing the beam in the RFQ. A lot of works has been done to understand and avoid losses and halo formation in the RFQ and in the following linacs. The choice if a rather high frequency shifts the mechanical and rf-parameters to a region where tolerance and tuning problems and power density question require even new solutions and prototype developments. The 4-vane RFQ structure employed in most cases can be treated as four weakly azimutally coupled resonators in longitudinal 0-mode a system which is very sensitive against unbalance of the four quadrants. Iin addition the longitudinal field tilt sensitivity is proportional to (L/λ)². Mechanical tolerances, coupler loops, tuners, vacuum ports, changes of electrode modulation all contribute to field tilts, which have to be balanced to come close to the ideal homogeneous frequency per unit length distribution. Figure 2: Scheme of a 4-Vane RFQ structure Fig.4: Coupling and stabilizing resonators Making the coupling line or cavity resonant the ideal zero impedance will not allow a voltage drop and fix the fields up to the limits set by the group velocity. Examples for nonresonant stabilizers are VCR rings and their magnetic equivalent the PISLs. Resonant devices are resonant rings and posts connecting the quadrants. Typically there is no field in these stabilizers and no additional losses, if the structure is balanced. The RFQ should be short to reduce possible field tilts. One can break the RFQs into several individually driven structures, which creates complexity and matching problems. A unique system has been developed at LANL, where like in a CCL the structure is subdivided into e.g. four parts but the connection is via resonant cells. The electrode structure is nearly unchanged but now the tilt sensitivity is reduced and depending linear on the cavity length L/λ only. Azimutal posts (like post couplers in the Alvarez) have been incorporated into these cells as indicated in fig. 4, so that the RFQ is still difficult to tune but very stable. Fig 3: Rf representation of a 4Vane resonator A number of resonant and nonresonant stabilizing schemes for the 4 Vane RFQs have been proposed and tested. The basic idea is to strongly couple two resonators with a low impedance line (a short) or a coupling slot. For stronger coupling, the unwanted modes will be pushed away and a fixed ratio of fields will be established. Figure 5: Scheme of a RFQ coupling cell with azimutal and longitudinal resonant stabilization Another new solution for operational stability was the compensation of thermal drift by keeping different cooling water temperatures in electrodes and tank which keeps the resonant frequency constant and eases problems during conditioning and avoids large numbers of moving tuners.

These solutions have been adopted by a number of other projects and allow 4Vane-RFQs with a length of up to 8 meters at frequencies of 350 MHz, which is a ratio of L/λ >9. These 4-Vane structures are used for high beam current applications especially if the frequency has to be in the range above 300 MHz. If the boundary conditions allow for lower frequencies one can also use another RFQ structure, the 4-rod RFQ, which is widely used at lower frequencies up to 200 MHz, especially for heavy ion applications Figure 6: Scheme of a 4-Rod-RFQ resonator insert It can be described as a chain of interlaced λ/2- resonators in π0-mode. The electrodes can have the typical rod shape, for cooling a cooling tube can be added radially converting it into a small vane like electrodes. with unchanged rf-properties. The radial dimensions of the 4- rod RFQ are appr. half as for a 4-Vane structure at the same frequency. Beam dynamics and experimental results for emittances and transmission are the same as for 4-Vane RFQs. While the power consumption is also roughly the same, there are some advantages because the 4-rod structure cannot show dipoles and longitudinal coupling is stronger. So only a single rf-coupler and 1-2 tuners are necessary. The rf-fields are confined in the resonant insert. A change of tank dimensions results in very little change of the frequency, so ports in the tank and e.g. the top lid along the tank do not change fields and coupling in the structure. So long RFQs can be aligned, tuned and inspected through such a top lid and tank contacts are not critical because less than 10% of the rf-power is dissipated in the tank, most of it close to the insert. The rf-power density is appr. 2-4 times higher than for 4- Vane structures which might be a problem for cw operation especially if one would try to go for the 350 MHz region. The simple way of direct cooling of the stems and rods compensates for that and operation with a temperature rising by T=50 o have shown little change of beam properties. Numerous 4-Rod RFQs with low duty factors have been built but also a number of structures with duty factors up to 25% 100% are in routine operation with heavy ions. 3 ADS RFQs High energy proton beams can be used to produce neutron via the spallation process. The energy should be around 1 GeV, the beam power between 100kW and 100MW depending on the application. For ADS application the beam power should be as high as possible to get reasonable production rates. CW operation and RFQ injectors accelerating 100mA protons from 100 kev to 5-8 MeV are typical values. The LEDA project at LANL was the first of a generation of high (average) power RFQs. This prototype RFQ was based on the work on GTA, CWDD and the Crits RFQ at CRNL, where also the new generation of ECR high current proton source was developed. The successful operation of LEDA, the full characterization of the 100 ma cw beam and all the rf-and mechanical engineering can well compete with the beam dynamics developments, which also gave new insights on losses and stability. Table 1: Parameters of the LEDA-RFQ Operating Frequency 350 MHz Proton Input Beam 75keV, 105mA, 0.2 mm* mrad, rms, normalized Proton Output Beam 6.7 MeV, 100mA, 0.22 rms,n Duty Factor 100% (cw) Peak Surface Field 1.8 Kilpatrick, 330kV/cm Structure Power Loss 1.2 MW, 85 l/s Total RF power 1.9 MW, fed by 12 WG irises Surface Heat Flux 11 W/cm 2, 65 W/cm 2 peak Configuration (OFE copper) 4 resonant segments, 8 brazed sections, each 1m long Structure Tuning static: 128 tuners, dynamic: water temperature Figure 7: The LEDA RFQ test set up Figure 8 The LEDA RFQ structure layout

The IPHI study has a big impact on the other studies in Europe: the ESS spallation source, the energy breeder project and the IFMIF fusion material study where the CEA group has proposed a CONCERT project which incorporates the various efforts for a combined project. Compared to these projects the TRASCO study at INFN in Legnaro aims at a "modest" average current of 30mA for a prototype for waste transmutation. The linac consists of a 80kV ECR source, a 5MeV RFQ, an independently phased low energy linac and a multi cell HE-linac, both superconducting. The RFQ is also derived from the LEDA, but aims at a less complex solution. The KOMAC project at KAERI in Korea is also looking for waste transmutation and energy breeding application of a GEV high current proton linac. Design studies and prototyping have led e.g. to the successful acceleration of a 30mA beam in an first RFQ prototype. The RFQ-group in Bejing and at CAT in Indore have also started work on an ADS type RFQs for high current linacs. also as projects on ADS to help solving the predictable future energy problem in these countries. At first both project plan for a low energy demonstrator linac, to study this high current technology. Figure 9: Exploded view and brazed of a LEDA RFQ module The IPHI-project at CEA was also aimed at a demonstration of the possibility to generate and accelerate high current proton beams for various applications. The project has generated a large number of remarkable developments in beam dynamics and structure development. Based on the experience at LANL a RFQ has been designed and prototyped which will outbeat its predecessor. A number of problems were studied in time consuming modeling and simulations, so improved solutions for optimized RFQ have been found, like for transmission and emittance growth. 4 SPALLATION SOURCE RFQs Designs for spallation sources aim at beam powers of "only" 1-10MW. This and the special pulse shape on the target require H - acceleration and a storage ring for pulse lengths compression. The 10 MW beam comes in 1sec pulses with 50 Hz as a typical value. The RFQ injector for such a system is plane d for 50mA at output energies of 2-5 MeV While projects like ESS, EHF, JHF and others have been discussed and modified for years and years the SNS project went ahead and the collaboration of six US Labs resulted in the building of SNS in Oak Ridge. LBNL was building the injector, which has been successfully operated with full specifications. The 4-Vane RFQ (2.5 MeV, 402 MHz) is stabilized with PISLs, longitudinal stabilization is not used. Fig shows the module of the brazed Cu-Glidcop structure module. Figure10: Layout of the IPHI project Figure 11: View of the first SNS-RFQ module

In Japan a common project of KEK and JAERI is going ahead with the building of a new multipurpose facility JKJ, which finally will reach 50 GeV protons. One planned operation mode corresponds to a spallation source. Specifications and technology of the RFQ injector is similar to the one from LBNL, tests of short parts have been successful Figure 12: Block diagram of the JKJ high current linac For the spallation source ISIS at RAL a new RFQ injector has been built to replace the CW-Injector. There the choice of final energy and frequency was determined by the "ancient" linac to 665keV and 202.5 MHz, which is favorable for using an short 4-Rod type RFQ-structure. The duty factor can be as high as 10%, a beam of up to 35mA has been accelerated and characterized in the first experiments. Until SNS will become operational, ISIS will still be the most powerful n-source with its 200kW beams. Another application which aims at even higher currents is done for low energy material testing n-sources.. Fig. 17 shows the 4 MeV RFQ (L=4m), designed for 50mA, 20% duty factor operation, showing a typical 4rod RFQ design with a top lid along the tank for easy access, for alignment, tuning and inspection of the structure The average beam current which is appr. 1 µa in a typical HE-machine can be as high as 1-2mA for a spallation source injector and up to 100mA in ADS applications. This illustrates the steps in development and the advances in beam physics, structure development and technology. Figure 13: Ion source - RFQ test bench at RAL Figure 14: View of the 4 MeV 4 Rod-RFQ 5 ACKNOWLEDGEMENTS I want to thank D. Schrage, A. Pisent, J. Staples for supplying information and A. Bechtold and H. Zimmermann for help