LHC status & 2009/2010 operations. Mike Lamont

Similar documents
LHC Commissioning in 2008

Plans for 2016 and Run 2

LHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1

LHC Commissioning and First Operation

The LHC Collider. STOA lecture, Brussels, 27 th November 2012 Steve Myers Director of Accelerators and Technology, CERN

Large Hadron Collider at CERN

LHC Beam Operations: Past, Present and Future

Main aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5)

Status of the LHC Machine

STATUS OF LHC COMMISSIONING

LHC. Construction Understanding first the commissioning. Prospects for

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

LHC: Past, Present and Future

Status and Outlook of the LHC

Status of the LHC Beam Cleaning Study Group

Status of splices in 6 ka circuits

LHC operation in 2015 and prospects for the future

The LHC accelerator: Technology and First Commissioning

LHC Status and CERN s future plans. Lyn Evans

MINIMUM REQUIREMENTS FOR THE 13 KA SPLICES FOR 7 TEV OPERATION

Commissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department

BUSBAR AND JOINTS STABILITY AND PROTECTION

LHC Luminosity and Energy Upgrade

Beam. RF antenna. RF cable

Beam Loss Monitors, Specification

LHC Performance Workshop Chamonix, January, 2010

LHC Collimation and Loss Locations

The Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy

Practical Lattice Design

Tools of Particle Physics I Accelerators

LHC Commissioning The good, the bad the ugly

The LHC: the energy, cooling, and operation. Susmita Jyotishmati

LHC RunII Commissioning and HL-LHC Status

Retraining of the 1232 Main Dipole Magnets in the LHC

Turn-around improvements

Run II Status and Prospects

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

Daniel Wollmann, CERN

CUIT ) SHOULD BE COMMIS

BETATRON SQUEEZE: STATUS, STRATEGY AND ISSUES

Overview of LHC Accelerator

Beam losses versus BLM locations at the LHC

Luminosity for the 100 TeV collider

LHC upgrade based on a high intensity high energy injector chain

LHC Upgrade Plan and Ideas - scenarios & constraints from the machine side

Interface with Experimental Detector in the High Luminosity Run

SPIRAL 2 Commissioning Status

FY04 Luminosity Plan. SAG Meeting September 22, 2003 Dave McGinnis

THE ALIGNMENT OF THE LHC DURING THE SHUT-DOWN D. Missiaen, CERN, Geneva, Switzerland. Fiducialisation

Early Physics with the CMS detector at LHC

PoS(EPS-HEP 2013)149. LHC, HL-LHC and beyond. M. Lamont.

A Luminosity Leveling Method for LHC Luminosity Upgrade using an Early Separation Scheme

LHC ORBIT SYSTEM, PERFORMANCE AND STABILITY

Machine Protection Basics of Accelerator Science and Technology at CERN

Preliminary design of the new HL-LHC beam screen for the low-β triplets

LHC Run 2: Results and Challenges. Roderik Bruce on behalf of the CERN teams

The Large Hadron Collider Lyndon Evans CERN

TRANSVERSE DAMPER. W. Höfle, CERN, Geneva, Switzerland. Abstract INTRODUCTION AND HIGHLIGHTS IN Controlled Transverse Blow-up

MACHINE PROTECTION ISSUES AND STRATEGIES FOR THE LHC

Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group

Stability Analysis of the Interconnection of the LHC Main Superconducting Bus Bars

Plans for the LHC Luminosity Upgrade Summary of the CARE-HHHAPD-LUMI-05 workshop

Much of this material comes from lectures given by Philippe Lebrun (head of CERN's Accelerator Technology Department), at SUSSP, Aug

Wolfgang Pauli, CERN, and the LHC. Rüdiger Voss Physics Department, CERN

Machine Protection Systems

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Milestone Report. Cryogenic Scenarios for the Cold Powering System

Chamonix XII: LHC Performance Workshop. Requirements from the experiments in Year 1*

The LHC. Part 1. Corsi di Dottorato Corso di Fisica delle Alte Energie Maggio 2014 Per Grafstrom CERN and University of Bologna

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

The TESLA Dogbone Damping Ring

LHC Upgrade (accelerator)

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

FLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR

HL-LHC OPERATIONAL SCENARIOS

Emittance blow-up and loss maps in LHC using the transverse damper as exciter

Higgs Factory Magnet Protection and Machine-Detector Interface

Are we ready for the 2009 beam operation?

DYNAMIC APERTURE STUDIES FOR HL-LHC V1.0 *

LHC State of the Art and News

2008 JINST 3 S Main machine layout and performance. Chapter Performance goals

R&D ON FUTURE CIRCULAR COLLIDERS

Reliability of Beam Loss Monitors System for the Large Hadron Collider

Signaling the Arrival of the LHC Era December Current Status of the LHC. Albert De Roeck CERN Switzerland

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report SIMULATION MODELS FOR ENERGY DEPOSITION

Thanks to all Contributors

Reliability of Beam Loss Monitors System for the Large Hadron Collider

Optimization of the SIS100 Lattice and a Dedicated Collimation System for Ionisation Losses

LHC RUN 2: RESULTS AND CHALLENGES

arxiv: v1 [physics.acc-ph] 10 Aug 2016

Accelerators. Lecture V. Oliver Brüning. school/lecture5

OPERATIONAL BEAMS FOR THE LHC

Parameters for the Linear Collider Update November 20, 2006

The Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory

AFP - TCL collimator studies

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics. LHC Accelerator R&D and Upgrade Scenarios. Francesco Ruggiero

Linac4: From Initial Design to Final Commissioning

(a) (b) Fig. 1 - The LEP/LHC tunnel map and (b) the CERN accelerator system.

OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE

UPGRADE ISSUES FOR THE CERN ACCELERATOR COMPLEX

Collimators and Cleaning, Could this Limit the LHC Performance?

Transcription:

LHC status & 2009/2010 operations Mike Lamont

Contents 7-9-09 LHC status - CMS week 2 Consolidation brief recall Splices Operational energies Potential performance Present status Plans for 2009-2010

Consolidation 1/2 Besides the major effort required to repair sector 34 Major upgrade of the quench protection system Protection of all main quadrupole and dipole joints (0.3 mv threshold). High statistics measurement accuracy to < 1 nω. Installation of > 200 km of cables, production of thousands of electronic boards. >> protection against similar issues in the future. Massive measurement campaign to identify bad splices Calorimetric methods (~ 40 nω) to identify possible bad cells High precision voltage meas. (~ 1 nω) to identify problematic splices 07-09-09 LHC status - CMS week 3

Consolidation 2/2 Mitigation of collateral effects in case of problems: Additional release valves ( DN200 ) Improvement of the pressure relief system to eventually cope with maximum He flow of 40 kg/s in the arcs (maximum conceivable flow) Installation completed in 4 sectors (1-2, 3-4, 5-6, 6-7) Also done for Inner triplets, Standalone Magnets and DFBs: Reinforcement of the quadrupole supports Arc quadrupoles (total 104 with vacuum barrier) Semi-stand alone magnets Inner triplet and DFBAs Energy extraction times lowered Faster discharge of the energy from circuits Possible because of lower energy running 7-9-09 LHC status - CMS week 4

Additional splice problem The enhanced quality assurance introduced during sector 3-4 repair has revealed new facts concerning the copper bus bar in which the superconductor is embedded. The process of soldering the superconductor in the interconnecting high-current splices can cause discontinuity of the copper part of the bus-bars and voids which prevent contact between the super-conducting cable and the copper Danger occurs only in case of a quench The challenge: to find a safe limit for the measured joint resistance as a function of the current in magnet circuits (max energy in the machine) LHC status - CMS week

Additional splice problem The enhanced quality assurance introduced during sector 3-4 repair has revealed new facts concerning the copper bus bar in which the superconductor is embedded. The process of soldering the superconductor in the interconnecting high-current splices can cause discontinuity of the copper part of the bus-bars and voids which prevent contact between the super-conducting cable and the copper. Danger occurs only in case of a quench 07-09-09 LHC status - CMS week 6

Stablizer problem Bad electrical contact between wedge and U-profile Bad contact at joint with the U- with the bus on at least 1 side of the joint profile and the wedge 7-9-09 LHC status - CMS week 7

Splices - summary Bad splices Resolution: calorimetry 40 nω; electric 1 nω Two bad cases found in 6 sectors: 50 nω (1-2) and 100 nω (6-7); repaired. Two sectors still to be measured cold (4-5, 3-4) Copper stabilizer problem Measurements done in 6 sectors, missing 7-8 and 8-1 10 dipole (> 35 µω) and 10 quadrupole (> 80 µω) joints repaired Lot of effort has gone into modeling the problem 07-09-09 LHC status - CMS week 8

25/8/2009 LHC status - CMS week 9

25/8/2009 LHC status - CMS week 10

Initial operating energy of the LHC Operating at 3.5 TeV with a dipole energy extraction time of 50 s. Simulations show that resistances of 120 micro-ohm are safe from thermal runaway under conservative assumed conditions of worst case conditions for the copper quality (RRR) and no cooling to the copper stabilizer from the gaseous helium Decision: Operation initially at 3.5 TeV (energy extraction time of 50 s) with a safety factor or more than 2 for the worst stabilizers. Then operate at 4 5 TeV 7-09-09 LHC status - CMS week 11

Higher than 3.5 TeV? Operating at 5 TeV com with a dipole energy extraction time of 68s Simulations show that resistances of 67 µω are safe from thermal runaway under conservative assumed conditions of worst case conditions for the copper quality (RRR), and with estimated cooling to the stabilizer from the gaseous helium We have 2 sectors which have not been measured warm. The essential question is what is the maximum resistance we can reasonably expect in the unmeasured sectors? Warm local measurements of the joint resistances in sector 45 (socalled local R16 measurement) revealed record surplus joint resistance of about 60 µω, caused by double joint fault on both sides of the SC splice Conservative estimates based on statistical analysis and the worse joints estimate a conservative maximum of ~ 90 µω 7-09-09 LHC status - CMS week 12

Higher than 3.5 TeV? FRESCA Validation of splice model in the lab Testing fully instrumented bad splice in 1.9 K Helium Full re-analysis of previous measurements Analysis of warm non-invasive dipole measurements Statistical analysis of invasive warm R16 measurements Analysis of failure modes and of worse joints found in the six sectors measured Monitor carefully all quenches to gain additional information. Behaviour (nqps) propagation times, current levels Likelihood with beam, confirmation of simulations Experiments interest in increasing the energy is noted. The jury is definitely out on this one - but we have some time. 7-9-09 LHC status - CMS week 13

3.5 TeV running - recall Emittance goes down with increasing : ε =βγε N And so beam size: * σ * = εβ And thus luminosity increases with increasing IF we can hold other parameters constant: L γ However, because beam size goes as: 1 γ Lower energy: increased beam size less aperture higher * separation of beams in interaction regions drops long range beam-beam 7-09-09 LHC status - CMS week 14

3.5 TeV limits Ralph Assmann Werner Herr Parameter Limit Reason(s) Beam Intensity ~6 e13 collimation cleaning efficiency * - crossing angle off 1 m aperture * - with crossing angle 2 3 m aperture, long range beam-beam Crossing angle [50 ns] ~300 µrad *, aperture, long range beam-beam Peak luminosity ~1 e32 6 e13 7-09-09 LHC status - CMS week 15

Operation - assumptions Given these constraints what can we do? Fill length: 8 hours Turnaround time: 5 hours 20 hours luminosity lifetime 30 day months. 40% machine availability Nominal crossing angle assumed for 50 ns. Nominal transverse emittance Total intensity limited to around 12% of nominal No squeeze beyond 2 m. with 156 bunches, crossing angle off - conservative 7-09-09 LHC status - CMS week 16

Plugging in the numbers 3.5 TeV 7-09-09 LHC status - CMS week 17 Month OP scenario Max number bunch Protons per bunch Min beta* Peak Lumi Integrated % nominal events/x 1 Beam commissioning 2 Pilot physics combined with commissioning 43 3 x 10 10 4 8.6 x 10 29 ~200 nb -1 3 43 5 x 10 10 4 2.4 x 10 30 ~1 pb -1 4 156 5 x 10 10 2 1.7 x 10 31 ~9 pb -1 2.5 5a No crossing angle 156 7 x 10 10 2 3.4 x 10 31 ~18 pb -1 3.4 5b 6 No crossing angle pushing 156 1 x 10 bunch intensity 11 2 6.9 x 10 31 ~36 pb -1 4.8 1.6 partial 50 ns nominal crossing angle 144 7 x 10 10 2-3 3.1 x 10 31 ~16 pb -1 3.1 0.8 7 288 7 x 10 10 2-3 8.6 x 10 31 ~32 pb -1 6.2 8 432 7 x 10 10 2-3 9.2 x 10 31 ~48 pb -1 9.4 9 432 9 x 10 10 2-3 1.5 x 10 32 ~80 pb -1 12 10 432 9 x 10 10 2-3 1.5 x 10 32 ~80 pb -1 12 11 432 9 x 10 10 2-3 1.5 x 10 32 ~80 pb -1 12

Possible evolution Physics at 3.5 TeV beta* = 2 m no crossing angle, 156 bunches Step up in energy Ramp, squeeze, ramp to 4-5 TeV beta* = 2 m no crossing angle, 156 bunches Ramp, squeeze at 4-5 TeV beta* = 2 m crossing angle, 50 ns 7-09-09 LHC status - CMS week 18

Step up in energy 7-09-09 LHC status - CMS week 19 Task Comment Time Hardware commissioning of main circuits Qualification of machine protection without beam Operation dry runs of requalified sectors Modification and testing of dump resistors Installation of snubbing circuits Calorimetry and QPS measurements FMCMs, PIC, Collimators, TCDQ, BLMs, BPM interlocks, SMPs, RF, LBDS ~ 2 weeks In parallel with HWC After hand over from HWC Re-commissioning of ramp and associated machine protection Re-commissioning of squeeze Optics and operations checks at high energy Collimator re-optimization Safe beam: LBDS, BLMs, RF Could possibly ramp-squeeze-ramp (avoiding the need to re-com the 3.5 TeV squeeze) ~ 1 week ~ 2 days ~4 days Estimate: 4 weeks to re-establish physics

Plugging in the numbers with a step in energy Month OP scenario Max number bunch Protons per bunch Min beta* Peak Lumi Integrated % nominal 1 Beam commissioning 2 27-08-09 Pilot physics combined with commissioning 43 3 x 10 10 4 8.6 x 10 29 ~200 nb -1 3 43 5 x 10 10 4 2.4 x 10 30 ~1 pb -1 4 156 5 x 10 10 2 1.7 x 10 31 ~9 pb -1 2.5 5a No crossing angle 156 7 x 10 10 2 3.4 x 10 31 ~18 pb -1 3.4 5b 6 7 No crossing angle pushing bunch intensity 156 1 x 10 11 2 6.9 x 10 31 ~36 pb -1 4.8 Shift to higher energy: approx 4 weeks Would aim for physics without crossing angle in the first instance with a gentle ramp back up in intensity 4 5 TeV (5 TeV luminosity numbers quoted) 156 7 x 10 10 2 4.9 x 10 31 ~26 pb -1 3.4 8 50 ns nominal Xing angle 144 7 x 10 10 2 4.4 x 10 31 ~23 pb -1 3.1 9 50 ns 288 7 x 10 10 2 8.8 x 10 31 ~46 pb -1 6.2 10 50 ns 432 7 x 10 10 2 1.3 x 10 32 ~69 pb -1 9.4 11 50 ns 432 9 x 10 10 2 2.1 x 10 32 ~110 pb -1 12 20 LHC status - CMS week

Caveats Big error bars on these numbers Bunch intensity/ Beam intensity quench limit, beam lifetimes, parameter tolerances & control, emittance conservation through the cycle Cleaning efficiency of collimation versus quench limits Note: we have already proved that we can quench a dipole with only ~2-3 e9 at 450 GeV Operability: reproducibility, ramp, squeeze, beam lifetime, background, critical feedback systems Machine availability: just about everything include the injectors Machine Protection has to work perfectly 7-09-09 LHC status - CMS week 21

LHC status - today Sector Status Temp 12 PO PHASE 1 1.9 K 23 COOLDOWN ~4 K 34 COOLDOWN ~175 K 45 COOLDOWN ~13 K Phase 2 powering starts this week, following installation of new QPS. 56 COOLDOWN ~2 K 1 w delay due to cryo-preparation; 67 COOLDOWN ~250 K Cool-down of 6-7 started few days earlier than foreseen 78 COOLDOWN 1.9 K 1 w delay due to cryo-preparation; 81 COOLDOWN ~75 K A lot still going on out there: ELQA, access doors, QPS 7-09-09 LHC status - CMS week 22

no shifts 2 shifts, 5 days 2 shifts, 7 days 2 shifts, 7 days 3 shifts, starting from Friday 18/9 General Schedule 24 th, August 09

Hardware commissioning - NB HWC phase 1 Limited current no powering of main circuits restricted access HWC phase 2 Individual system tests of new QPS Power main circuits to 6000 A (just over 3.5 TeV) No access during powering in sector concerned and adjacent access zones New Quench Protection System still to be installed and tested just about everywhere First 54 crates finished testing last Saturday 7-09-09 LHC status - CMS week 24

2009 - injectors Ions in the lines Injection test Sector 23 as first priority Sector 78 if part of 81 required is ready ± first LHC beam 7-09-09 LHC status - CMS week 25

Beam commissioning Global machine checkout Energy Safe Very Safe 450 1 e12 1 e11 1 TeV 2.5 e11 2.5 e10 3.5 TeV 2.4 e10 probe Essential 450 GeV commissioning Machine protection commissioning 1 450 GeV collisions Ramp commissioning to 1 TeV System/beam commissioning Machine protection commissioning 2 3.5 TeV beam & first collisions Full machine protection qualification System/beam commissioning Pilot physics 7-09-09 LHC status - CMS week One month to first collisions 26

450 GeV collisions Time limited: 3-4 shifts No squeeze Low intensity machine protection commissioning unlikely to be very advanced. ~1 week after first beam Number of bunches 1 4 12 Particles per bunch 4 4 4 Beam intensity 4 x 10 10 1.6 x 10 11 4.8 x 10 11 beta* [m] 11 11 11 Luminosity [cm -2 s -1 ] 1.7 x 10 27 6.6 x 10 27 2 x 10 28 Integrated lumi/24 hours [nb -1 ] 0.06 0.24 0.7 7-09-09 LHC status - CMS week 27

LHC 2009 All dates approximate Reasonable machine availability assumed Stop LHC with beam ~19 th December 2009, restart ~ 4 th January 2010 7-9-09 LHC status - CMS week 28

LHC 2010 very draft 27-08-09 LHC status - CMS week 29 2009: 1 month commissioning 2010: 1 month pilot & commissioning 3 month 3.5 TeV 1 month step-up 5 month 4-5 TeV 1 month ions

Conclusions Splices remain an issue Constraints of 3.5 TeV enumerated Potential performance shown 200 300 pb -1 seem reasonable Step up in energy would take ~4 weeks increase to be decided Would start with a flat machine at the higher energy before bringing on crossing angle and exploiting 50 ns. LHC well into cool-down and on schedule for mid- November start with beam With a bit of luck, first high energy collisions before Christmas 7-9-09 LHC status - CMS week 30