Probabilistic approach for the fatigue design of tower cranes

Similar documents
Classification of Cranes and Components

NTNU Faculty of Engineering Science and Technology Department of Marine Technology TMR 4195 DESIGN OF OFFSHORE STRUCTURES

ASSESSMENT OF THE PROBABILITY OF FAILURE OF REACTOR VESSELS AFTER WARM PRE-STRESSING USING MONTE CARLO SIMILATIONS

However, reliability analysis is not limited to calculation of the probability of failure.

A new Method to determine Stress Cycle Histograms of Structures under Gusty Wind Load

Simulation model input analysis

Institute for Statics und Dynamics of Structures Fuzzy probabilistic safety assessment

t, s T, C 2. Temperature fluctuations.

DEM modeling of penetration test in static and dynamic conditions

Safety Envelope for Load Tolerance and Its Application to Fatigue Reliability Design

TOWER CRNE MAST ANCHORAGE TIE DESIGN

MODIFIED MONTE CARLO WITH LATIN HYPERCUBE METHOD

MD 485 B M20. Data Sheet. - Fleet FEM A3 ASCE Values have been rounded FEM ASCE. 3.4 USt. 6.0 USt. 8.8 USt. Power Control.

Bridge System Performance Assessment from Structural Health Monitoring: A Case Study

A Probabilistic Design Approach for Riser Collision based on Time- Domain Response Analysis

MARKOV CHAIN APPLICATION IN FATIGUE RELIABILITY ANALYSIS FOR DURABILITY ASSESSMENT OF A VEHICLE CRANKSHAFT

Structural Reliability

A techno-economic probabilistic approach to superheater lifetime determination

GOAL-BASED NEW SHIP CONSTRUCTION STANDARDS General principles for structural standards MSC 80/6/6

Cyclic fatigue demands on structures subjected to the Canterbury Earthquake Sequence

TESTS ON REINFORCED CONCRETE LOW-RISE SHEAR WALLS UNDER STATIC CYCLIC LOADING

Advanced Marine Structures Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology Madras

Structural Reliability Analysis using Uncertainty Theory

Fissuration en milieux isotrope et orthotrope via les intégrales invariantes: prise en compte des effets environnementaux

Dynamic Loads CE 543. Examples. Harmonic Loads

Time-varying failure rate for system reliability analysis in large-scale railway risk assessment simulation

Fatigue Reliability and Effective Turbulence Models in Wind Farms

Nonlinear free transverse vibration of n*p-dof

Stress Concentrations, Fatigue, Fracture


Numerical analysis for an interpretation of the pressuremeter test in cohesive soil

PLATE GIRDERS II. Load. Web plate Welds A Longitudinal elevation. Fig. 1 A typical Plate Girder

Resistance vs. Load Reliability Analysis

RELIABILITY MODELING OF IMPACTED COMPOSITE MATERIALS FOR RAILWAYS

2D - STRIP ANCHOR LIFTING SYSTEM

Bayesian model updating and boundary element method applied to concrete fracture testing.

Use of Simulation in Structural Reliability

Prediction of Reliability Index and Probability of Failure for Reinforced Concrete Beam Subjected To Flexure

RELIABILITY ASSESSMENT OF EXISTING STRUCTURES

PROCIM. Developed by. Amirali Shojaeian Paolo Bocchini, Ph.D. Clay Naito, Ph.D., P.E. Liyang Ma Aman Karamlou John Fox, Ph.D.

214'-7" Hook Height L1 114'-10" 22,025# Version "A" (With TSK 212 Section) HOOK HEIGHT ft/m TOWER TYPE TS TSK 212

Structural reliability analysis of deep excavations

C C JTS 16:00 17:30. Lebet

CRANE LOADING EVALUATION ON THE BASIS OF A PRIORI INFO~TION. Michael Rubin. Rakenteiden Mekan.::i. ikka, Vol. 23 No ABSTRACT

Reliability-based Design of New Expansion Joints for the Little Belt Suspension Bridge

DESIGN OF CONCRETE COLUMNS BASED ON EC2 TABULATED DATA - A CRITICAL REVIEW

Comparative study between the push-over analysis and the method proposed by the RPA for the evaluation of seismic reduction coefficient

Haulage Drift Stability Analysis- A Sensitivity Approach

Load Resistance Factor Design (LRFD) and Allowable Stress Design

Sparse polynomial chaos expansions based on an adaptive Least Angle Regression algorithm

Introduction. Yuan et al. 647

NUMERICAL MODELLING OF STORAGE RACKS SUBJECTED TO EARTHQUAKE

Mathematical Modeling of Nonlinear Dynamic. System of the Truck Crane

Excerpt from the Proceedings of the COMSOL Conference 2010 Boston

Fatigue of stay cables inside end fittings high frequencies of wind induced vibrations

RELIABILITY ANALYSIS OF A STEEL BEAM USING THE MONTE CARLO METHOD

TEST METHOD FOR DETERMINING BREAKAWAY FORCE OF A MAGNET

Project of a scissor lift platform and concept of an extendable cabin

A Simplified Method for the Design of Steel Beam-to-column Connections

2D - STRIP ANCHOR LIFTING SYSTEM

Uncertainty in wind climate parameters and the consequence for fatigue load assessment

Volume 2 Fatigue Theory Reference Manual

Risk Assessment of Highway Bridges: A Reliability-based Approach

S.C. Rulmenti S.A. Barlad Romania Republicii Street No

Performance based Engineering

A Thesis presented to the Faculty of the Graduate School at the University of Missouri-Columbia

Effects of Error, Variability, Testing and Safety Factors on Aircraft Safety

National Exams May 2015

Reliability assessment of tower crane structural members

3.1 CONDITIONS FOR RIGID-BODY EQUILIBRIUM

A Structural Reliability Analysis Method Based on Radial Basis Function

Selection on selected records

BEST ESTIMATE PLUS UNCERTAINTY SAFETY STUDIES AT THE CONCEPTUAL DESIGN PHASE OF THE ASTRID DEMONSTRATOR

Introduction to Engineering Reliability

SDNV114 Simulation of benchmark SAFE - T5 veil

A Simple Weak-Field Coupling Benchmark Test of the Electromagnetic-Thermal-Structural Solution Capabilities of LS-DYNA Using Parallel Current Wires

Modelling Under Risk and Uncertainty

Uncertain Structural Reliability Analysis

MATERIALS FOR CIVIL AND CONSTRUCTION ENGINEERS

A probabilistic method to predict fatigue crack initiation

Hydraulic Design Of Polyethylene Pipes

ER2 Short-head Electric Chain Hoist

Simplified Method for Mechanical Analysis of Safety Class 1 Piping

RELIABILITY OF COMPOSITE STRUCTURES - IMPACT LOADING -

Estimating Risk of Failure of Engineering Structures using Predictive Likelihood

CALCULATION OF A SHEET PILE WALL RELIABILITY INDEX IN ULTIMATE AND SERVICEABILITY LIMIT STATES

Rapid Earthquake Loss Assessment: Stochastic Modelling and an Example of Cyclic Fatigue Damage from Christchurch, New Zealand

Drop towers and fitness flooring assemblies

Optimising slew torque on a mining dragline via a four degree of freedom dynamic model

Uncertainty modelling using software FReET

Lecture 2: Introduction to Uncertainty

Uncertainty and Risk in Foundation Design

Reliability-Based Design Guidelines for Fatigue of Ship Structures

Maximum Likelihood Estimation of the Flow Size Distribution Tail Index from Sampled Packet Data

A. Vorontsov, V. Volokhovsky (Intron Plus Ltd., Moscow, Russia) J. Halonen, J. Sunio (Konecranes Plc, Hyvinkaa, Finland)

Virtual tests based on model reduction strategies for fatigue analysis

BAYESIAN UPDATING OF PROBABILISTIC TIME-DEPENDENT FATIGUE

The Comparison of Seismic Effects of Near-field and Far-field Earthquakes on Relative Displacement of Seven-storey Concrete Building with Shear Wall

Characterization and reliability of A36 steel under alternating dynamic and static loading

ICDS12 International Conference DURABLE STRUCTURES: from construction to rehabilitation LNEC Lisbon Portugal 31 May - 1 June 2012

Transcription:

Probabilistic approach for the fatigue design of tower cranes S. Bucas a,b,c, P. Rumelhart c, N. Gayton a,b, A. Chateauneuf a,b a. Clermont Université, Université Blaise Pascal, IFMA, Institut Pascal, BP 1448, F-63 Clermont Ferrand, France b. CNRS, UMR 662, Institut Pascal, F-63171 Aubière, France c. Manitowoc Crane Group, 18 chemin de Charbonnières, F-6913 Ecully, France Résumé : Les acteurs du bâtiment veulent maximiser l efficacité de leurs équipes et matériels dans le but de minimiser la durée des chantiers. Cela conduit à une utilisation intensive des grues dont la charpente est principalement composée d éléments mécano-soudés. De ce fait, les Ingénieurs Structure doivent considérer la résistance à la fatigue durant le dimensionnement. L objectif de ce travail est de démontrer l utilité d une méthode fiabiliste pour une meilleure optimisation du dimensionnement à la fatigue d éléments de flèche de grues à tour. Abstract : Crane owners want to maximize the efficiency of their equipment and teams in order to minimize the amount of time needed to complete a construction site. This leads to very intensive crane use and stress on crane structures made primarily of welded steel elements (plates and beams). Therefore, Structural Engineers have to consider fatigue resistance during the design process. The aim of the paper is to demonstrate the utility of a probabilistic approach for a better optimization of the fatigue design of tower cranes elements (e.g. jib elements). Mots clefs : reliability; fatigue; tower cranes 1 Introduction Tower crane structures are made of steel plates or beams connected by welding and, due to intensive workload, fatigue resistance is an important aspect to consider for Structural Engineers. Classical design methods can lead to non-optimized structures with non-uniform safety margins, and consequently to a non-optimized distribution of safety factors related to fatigue. The proposed work takes place further to two projects called DEFFI [1] and APPRoFi [2] in which reliability approaches for fatigue assessment of industrial applications were experimented and developed. Based on these previous works, the aim here is to quantify and optimize the safety margins with respect to fatigue of tower crane steel structures, by means of probabilistic approaches. This study focuses on jib elements of a top slewing tower crane. The jib s function is to support the trolley that moves the load from one radius to another (see R 1 and R 2 in figure 1). This jib structure is submitted to load variation depending on the radius and the live hoisted load. All structures made by metal plates or beams connected by welding are subjected to fatigue phenomenon after many years of intensive cyclic use. This phenomenon is showing large variation for several reasons. First, there is the randomness of the loading on the structure, due to the variability of crane use by the owners. Second, the non-even fabrication process (manual welding) leads to material and geometry differences in the structure. Third, the great variety of geometries makes it impossible for 1

21`eme Congr`es Fran cais de M ecanique Bordeaux, 26 au 3 aoˆ ut 213 Figure 1 Crane vocabulary definitions. Figure 2 Load chart definition life prediction to reach the same predictability in every single case. Fourth, complex structural modeling requires simplification hypothesis that may result in variations depending on analysis techniques utilized. European Standards for fatigue design of tower cranes [3] consider deterministic loading cycles regardless of time in service, that lead to non-optimized safety margins. The aim of this work is to assess the fatigue damage probability of a crane structural member, namely the jib element, depending of the time in service. This kind of approach requires data collection concerning the real use of the crane. These data are used to model random variables having an influence on the fatigue damage of the structure. 2 Stochastic modeling of crane use 2.1 Definitions To understand how tower cranes work, it is necessary to introduce the concept of load chart. The example of load chart depicted in figure 2 shows the maximum load it is possible to lift according to the position of the trolley along the jib, i.e. the radius R. For a given value of radius R(i) at time t, (i) the load L(i) that can be lifted by the crane is necessarily below the load chart, i.e. below Lmax. Another important thing to consider is the motion sequence of a loading cycle which consists of four phases (see figure 2) : (1) trolley in movement without load, (2) lifting of the load, (3) trolley in movement with the load lifted, (4) drop off of the load. 2.2 Load and Radius time histories A recording has been performed during five months on a crane working on a construction site. Figures 3 and 4 present the recorded data versus the load chart respectively at the beginning and at the end of crane cycles. On the latters, horizontal tendencies can be observed at different levels of load. It corresponds to different natures of hoisted loads which can be identified separately. Three types of work were distinguished on the jobsite. The first one corresponds to the concrete pouring cycles where the concrete bucket is moved from the concrete batching plant to the wall or the floor to be fabricated. The second one corresponds to the positioning cycles. The loads lifted then are forms, walkways or prefabs. Finally, all the cycles that do not match the previous definitions are brought together in the category other cycles. 1 1 8 8 6 6 4 4 2 2 5 1 15 2 25 3 35 4 45 5 55 6 Figure 3 Data versus load chart (R1 ). 5 1 15 2 25 3 35 4 45 5 55 6 Figure 4 Data versus load chart (R2 ). 2

Figures 5a, 5b and 5c present the radii histograms respectively at the beginning and at the end of the crane cycles. Figure 5a shows that all concrete pouring cycles start at a radius of 5 meters. That corresponds to the position of the concrete batching plant on the studied construction site. All the other figures associated to the radii present quite similar profiles. The mode is more or less situated around the mean radius of the jib. (a) (b) (c) Figure 5 R 1 and R 2 histograms for (a) concrete pouring cycles, (b) positioning cycles and (c) other cycles. (a) (b) (c) Figure 6 Histogram of the maximum load lifted for (a) concrete pouring cycles, (b) positioning cycles and (c) other cycles. R 1 Estimation Choice 1 N µ.84r max U(R min,r max ) σ.4 m.5 m a R min U(1,2)R min 2 T b.93r max U(.9,1)R max c 1.16R m U(.7,1.3)R m a R min U(1,2)R min 3 T b.96r max U(.9,1)R max c.82r m U(.7,1.3)R m 1 Concrete pouring 2 Positioning 3 Other Table 1 Parameters for the fitted distributions for R 1. 1 2 3 R 2 Estimation Choice a 1.97R min U(1,2)R min T b.97r max U(.9,1)R max c 1.25R m U(.7,1.3)R m a 1.35R min U(1,2)R min T b.91r max U(.9,1)R max c 1.2R m U(.7,1.3)R m a 1.25R min U(1,2)R min T b R max U(.9,1)R max c.95r m U(.7,1.3)R m 1 Concrete pouring 2 Positioning 3 Other Table 2 Parameters for the fitted distributions for R 2. Figures 6a, 6b and 6c depict the maximum hoisted load histograms. Figure 6a depicts the histogram of the maximum load recorded during the concrete pouring cycles. The mean of the distribution is around 26 kn and corresponds to the load of the concrete bucket with the dynamic overload. 3

Concerning the positioning cycles, the distribution of maximum load lifted is much more widespread. It can be explained by the fact that there are a lot of possible combinations of forms, walkways and prefabs. Most of the time, there are three standardized sizes of form on a construction site (2.5 m, 1.25 m and.625 m). An equipped form of 2.5 m width weighs 17 kn, dynamic overload included. It could explain the peaks situated approximately at 34 kn, 17 kn and 8.5 kn (see figure 6b). The rest of the variability is probably due to the lifting of walkways or prefabs (balconies, stairs, etc.). Figure 6c shows the distribution of the load lifted during the other cycles where two main modes can be identified. The peak around 17 kn seems to correspond to the displacement of form ballasts. The rest of the variability of the distribution comes from the lifting of iron frameworks, junk buckets, etc. L Estimation Choice 1 N µ 26.3 kn Randomly chosen in table 4 σ.5µ.5µ 2 - - Modes : 8.5, 17 and 34 kn Randomly chosen in table 5 α.88 U(.8,.95) µ 1 8.8 kn U(6,1) 3 σ 1 9.5 kn U(6,1) µ 2 16.6 kn 16.6 kn σ 2 1.3 kn 1.3 kn fx(x) 1 Concrete pouring 2 Positioning 3 Other For R = R (i), L L (i) max (see figure 2) Radius-dependent : µ LRmax fx (x) = αn(µ 1,σ 1 )+(1 α)ln(µ 2,σ 2 ) Table 3 Parameters for the fitted distributions for L. 2.3 Load and radius random variables The assessment of jib element use for each construction site can be made through the modeling of a set of random variables. The choice of parametric radius and load distributions is derived from the studied jobsite, considered as representative. The implicit hypothesis here is to consider that the randomness of the construction sites can be modeled by varying the parameters of the distributions. Concerning the radii modeling, a normal distribution was chosen to model R 1 for concrete pouring cycles (see figure 5a). The mean of the distribution is defined by the location of the concrete batching plant and the standard deviation is fixed by expert opinion. All the other distributions associated to the radii of the cycles are modeled thanks to triangular distributions (see figures 5a, 5b and 5c). Thus, for each triangular distribution, it is necessary to define three parameters (two bounds and one mode). Concerning the modeling of the load, for the concrete pouring cycles it was chosen to define a normal variable with a mean equal to the weight of the filled concrete bucket plus a dynamic overload. The possible concrete buckets that can be randomly chosen are given in table 4. Regarding positioning cycles, figure 6b shows that it is not possible to define a simple model for the lifted load. Instead, it was considered that no more than 5 linear meters of forms can be lifted in one time. Then, knowing that for a given radius of the trolley, the load chart constrains the maximum possible lifted load (see figure 2), a configuration of forms is randomly chosen between the possible ones at each cycle. Table 5 gives the weight of all the possible form configurations and their associated probability. Note that a difference is made in term of probability between configurations 1, 2, 4, and 7 and the others. The implicit assumption is made that it is more probable to hoist these four configurations than the others. Concerning the other cycles, it was chosen to consider a linear combination of lognormal and normal distributions to model the other lifted loads(see figure 6c). The mean of the normal distribution corresponds to the load of a ballast. The mean and the standard deviation of the lognormal distribution are randomly chosen for each construction site. All the estimated parameters and the assumptions made on these parameters are summarized in tables 1, 2 and 3 where U, T, N and LN are respectively the uniform, triangular, normal and lognormal probability laws. 4

Capacity (L) 8 1 125 15 2 Weight (kn) 24 25 37 43 57 Table 4 Possible concrete buckets. N 1 2 3 4 5 6 7 Weig. w/4 w/2 3w/4 w 5w/4 3w/2 2w Prob. p/4 p/4 q/3 p/4 q/3 q/3 p/4 w = 15 kn, p =.7 and q = 1 p Table 5 Possible form configurations. 2.4 Equivalent number of cycles per year Once the loading history of the jib element is established based on the previous probability laws, an equivalent number of cycle, at the reference load range F ref (see figure 7), must be determined. F ref is the reference load range used for the determination of the number of cycles of resistance N res. Figure 7 Illustration of the reference load cases. N equse is calculated based on the Miner linear damage accumulation rule N equse = i( F(i) / F ref ) c. F (i) is the load range of cycle (i) and c is the fatigue strength exponent related to structural fatigue resistance. 3 Calculation of fatigue damage probability 3.1 Monte Carlo Simulations MC simulations are perfomed in order to assess the distribution of N equse (x,t) where x is the vector of all random variables and t is the time in years. The steps are explained below : For each crane simulation (i.e. for each MC iteration) : 1. Random sampling of a number of construction sites with their duration (U(4,24) months) and with the time between two construction sites (U(.5, 2) months). 2. For each construction site : (a) Transformation of the construction site duration into a number of cycles assuming that : the median number of working days per month is equal to 22, the median number of crane cycle per hour is equal to 12, the number of working hours per day is randomly chosen in the normal distribution N(9,1.5) hours. (b) The number of cycles per type of work for the construction site is then inferred taking into account the following rates : 33% for concrete pouring cycles, 17% for positioning cycles, 5% for other cycles. (c) Random sampling of jib length for the construction site according to the possible configurations from 25 m to 65 m. (d) Random sampling of the parameters associated to R 1, R 2 and L. (e) Generation of the corresponding time-histories. (f) Cycle counting. (g) Calculation of an equivalent number of cycles after t years. 3. Registering of N equse (x,t). 5

3.2 Modeling of the equivalent number of cycles per year Time-histories of 4 years have been generated 5 times following the method presented above. The distributions of N equse (x,t) found after 1, 2, 3 and 4 years are depicted in figure 8. A lognormal model is used to fit the empirical distributions. 8. 7e-5 6e-5 5e-5 4e-5 3e-5 2e-5 1e-5 2 4 6 8 1 12 14 16 18 7.5 7. 6.5 6. 5.5 5. 5 1 15 2 25 3 35 4 Figure 8 N equse (x,t) after 1, 2, 3 and 4 years. Figure 9 Reliability index of the jib element versus the time. 3.3 Reliability index calculation To calculate the fatigue damage risk of the jib element, it is necessary to define a performance function taking into account the fatigue resistance on one hand, and the crane use on the other hand. Although the obtention of the number of cycle of resistance N res is not detailed in this paper, note that a lognormal law is chosen to model it. Due to the lognormal nature of the resistance and use distributions, the performance function and the reliability index can be expressed as follows : G(x,t) = lnn res lnn equse (x,t) β c (t) = λ N res λ Nequse (t) ξn 2 res +ξn 2 equse (t) where λ X and ξ X represent respectively the mean and the standard deviation of ln(x). Figure 9 depicts the reliability index versus the time in years. Note that the reliability index of the jib element is high regardless the number of years of work of the crane (more than 5 even after 4 years), compared to the target β values proposed by recommendations such as [4]. 4 Conclusions In this work, a probabilistic approach has been developed to model tower cranes use and the reliability of jib elements was assessed. For 4 years of lifetime, the reliability index of these elements was found to be higher than 5, which is large compared to recommendations. Two main perspectives were identified concerning crane use modeling. It is planned to include more data records coming from other jobsites, on one hand, and to develop a model allowing transformation of any jobsite drawing into crane loading time-histories, on the other hand. Relatively large statistics of crane use could be produced in limited time thanks to this technique. Références [1] A. Bignonnet, H.P. Lieurade, et al. The reliability approach in fatigue design : DEFFI project. In Fatigue Design 29, Senlis, France, November 29. [2] N. Gayton, M. Afzali, et al. APPRoFi project - probablistic methods for the reliability assessment of structures subjected to fatigue. In Fatigue Design 211, Senlis, France, November 211. [3] European Federation of Materials Handling - Heavy Lifting Appliances - Rules for the design of hoisting appliances - FEM1.1. FEM 1.1, 1998. [4] ISO2394. General principles on reliability for structures. International Standard Organization, 1998. (1) 6