Determination of the transition point from open pit to underground mining

Similar documents
OPTIMIZATION OF PRODUCTION PLANNING IN UNDERGROUND MINING

For personal use only

Using Integer Programming for Strategic Underground and Open Pit-to-Underground Scheduling

Oposura Scoping Study Nearing Completion

Australia s Response To The Chile Technological Roadmap In Mining : The University of Queensland Experience

Practical long-term planning in narrow vein mines a case study

MAD345 - Mining II INTRODUCTION. 10 October Hacettepe University. Introduction Prospecting Mining Dilution Resource and Reserve Estimation

Trouser Legs Mine Strong Drilling Results - including g/t Au Potential for Further Mine Development

Mining method optimisation of Bayi gold mine based on the value engineering principle

King of the Hills Gold Project, Leonora, to commence production in Q2 2011

University of Saskatchewan

New High Grade Lode Discovered at Wagtail South

FUTORES II Augmenting Prospectivity Analysis with Mining Criteria: A Test for Viability

INTERNATIONAL JOURNAL OF SCIENTIFIC & TECHNOLOGY RESEARCH VOLUME 7, ISSUE 3, MARCH 2018 ISSN

For personal use only

Introduction to Geology and Geometallurgy

MINERAL RESOURCE AND ORE RESERVE UPDATE PAMPALO GOLD MINE

Analyzing the effect of ore grade uncertainty in open pit mine planning; a case study of the Rezvan iron mine, Iran

Diversification into the exciting South Africa Platinum Industry

SITE WORKS COMMENCE AT A1 GOLD MINE, EASTERN VICTORIA

1. Rock Mechanics and mining engineering

More High Grade Gold Intercepts from the Netiana Lodes at Balogo, Burkina Faso

The Evolution of Block Caving Technology Tony Weston MAusIMM(CP) MassMin 2016

An improved formulation of the underground mine scheduling optimization problem when considering selective mining

Haulage Drift Stability Analysis- A Sensitivity Approach

AMUR MINERALS CORPORATION (AIM: AMC) April 2018 Mining Potential Update

Case study: How Leapfrog Geo helped improve geological understanding at Edna May Gold Mine, Western Australia

HERON ENTERS OPTION TO PURCHASE A1 GOLD MINE, EASTERN VICTORIA

Optimisation of Cut-Off Grade at Mount Isa Mines Limited s Enterprise Mine

Dilution and ore loss A short practical guide

For personal use only

Accurate costing in mixed integer utilisation mining models

Evolution of seismicity at Kiruna Mine

For personal use only

IMPROVING THE MINING EFFICIENCIES BY MEANS OF A NEW SUPPORT DESIGN AT UNISEL MINE. AMMSA Annual General Meeting 1 December 2017

Further Research into Methods of Analysing the October 2000 Stability of Deep Open Pit Mines EXECUTIVE SUMMARY

Ulysses Gold Project, WA

News Release DRILLING STEPPED UP AT FORRESTANIA NICKEL PROJECT AND UPDATE ON DIGGERS SOUTH PRE - FEASIBILITY STUDY

For personal use only

Drill testing of gold zones at Albury Heath intersect impressive quartz lodes

NEW DISCOVERIES AT THE RED OCTOBER MINE

Dugald River trial stoping, overall hanging wall behaviour

Dennis L Buchanan Imperial College London, UK

Aureus Mining New Liberty Project Geology

Gold Grades and Gold Costs Exploding the High-Grade Myth

AGM Presentation 12 November 2013

ASX Announcement 24 December Drilling results confirm depth potential of Lamboo Project

Some practical aspects of the use of lognormal models for confidence limits and block distributions in South African gold mines

FINANCIERS MANDATED FOR THE DALGARANGA GOLD PROJECT

NEW PHASE OF RESOURCE EXTENSION AND UPGRADE DRILLING COMMENCES AT BARDOC GOLD PROJECT, WA

76,000 Ounce Gold Resource at Akoko North

Pershing Gold Extends High-Grade Mineralization through Step-Out Drilling in Phase 1 and Initiates Phase 2 Drilling Program

Strengths and weaknesses of using elastic numerical modelling in mine design at the Callie underground mine

Intensive Field Based Exploration Program Commences at Dobsina Cobalt-Nickel-Copper Sulphide Project

Excavation method in Goushfill mine

MineScape Geological modelling, mine planning and design

Brookfield Place Tel: (416) Bay Street, Suite 3630 Fax: (416) FOR IMMEDIATE RELEASE February 7, 2012

Advances in Seismic Reflection as an Exploration Tool in Hard-Rock Mining

ABSTRACT INTRODUCTION

MASSIVE AND SEMI MASSIVE SULPHIDES CONTINUE TO BE INTERSECTED AT ROCKLANDS SOUTH - SIGNIFICANT ZONE OF COPPER MINERALISATION BEING DEFINED

2016 Semester Terms and Dates Summary

AGM Presentation 6 November 2012

ROX DEFINES STRONG IP ANOMALIES AT PHA LUANG

Institutional Control Registry - Report

SECOND ADVANCED GOLD PROJECT IDENTIFIED AT THREE RIVERS PROJECT

MOUNT OXIDE MINERAL RESOURCE INCREASE AND DEVELOPMENT STUDY UPDATE

Application of the GeoSequencing Module to ensure optimised underground mine schedules with reduced geotechnical risk

Evaluation of Mineral Resource risk at a high grade underground gold mine

Geotechnical Models and Data Confidence in Mining Geotechnical Design

For personal use only

Regression revisited (again)

Northern Mining Limited 2012 Annual General Meeting Presentation

STEP-OUT DRILLING EXTENDS HIGH GRADE COPPER ZONE AT SYNDICATED S 100% BARBARA SOUTH LODE

Coal Loss and Dilution Considerations for Western Canadian Foothills Open Pit Coal Projects

ASX ANNOUNCEMENT 21 MARCH 2011

Drilling Commences at Telfer West Gold Project

This is the author s version of a work that was submitted/accepted for publication in the following source:

Rock mechanics related to mining: challenges and opportunities

October 2017 Investor Presentation. Moving to the next level: cash-flow, exploration and growth in WA s premier gold districts

Manuscript of paper for APCOM 2003.

Mining. Analysis of options of production and access ways in underground mines. Mineração. Abstract. 1. Introduction. Leandro de Vilhena Costa

WHAT IS MINERAL EXPLORATION?

For personal use only

Deep Mining Queensland (1)

CERRO PRIETO PROJECT MINERAL CONCESSIONS LOCATION AND ACCESS

A rules-based production scheduling approach allowing multiple scenarios to be generated to test the impact of advance rate variability

Disclaimer. Forward-Looking Statements. Competent Person s Statement

FOR IMMEDIATE RELEASE August 9 th, 2018 (VTT2018 NR #7)

ASX/Media Announcement

For personal use only

ACQUISITION OF THE MCCLEERY COPPER-COBALT PROJECT, CANADA

ITASCA Consulting Canada Inc.


Sipa Resources Limited

For personal use only

- 2 - TABLE 1. INDICATED AND INFERRED GOLD AND SILVER RESOURCES. All Indicated

Geotechnical approach to stope and pillar optimisation at Granny Smith Mine

Modelling Ore Bodies of High-Nugget Gold Using Conditional Probability

For personal use only

Transcription:

Determination of the transition point from open pit to underground mining Strategic Mine planning and Optimisation for Combination Mining Method J Chung, M Asad, E Topal, AK Ghosh Department of Mining Engineering and Metallurgical Engineering Western Australian School of Mines, Curtin University Western Australia The Ninth AusIMM Open Pit Operators Conference 2016 2016 Kalgoorlie, Western Australia

Presentation Outline 1. Introduction 2. Problem Definition & Objectives 3. Underground Mining System 4. Modelling the Transition Problem 5. Case Study 6. Conclusions & Recommendations 7. References Ninth Open Pit Operators Conference 2016 Page 2

Introduction Haulage cost and stripping ratio in OP mining will increase when the pit goes deeper. As the stripping cost goes over UG mining cost and OP mining becomes uneconomical, UG mining emerges as a viable option. Transition from OP to UG required. Ninth Open Pit Operators Conference 2016 Page 3

Introduction: Combination Mining In combination mining, all involved mining strategies need to be considered simultaneously in the mine planning and optimisation process to ensure global optimality achieved. 4

Introduction Transition Problem is the determination of the optimal transition point with the aim of maximisation of project s value and resource utilisation. Transition Point is where the decision has to be made whether expand the pit or make the transition from OP to UG. Page 5

Problem Definition & Objectives Conservative/Simplest approach: The transition is considered near or after the exhaustion (secondary) of the available reserves inside the ultimate pit (Finch 2012). Disadvantages: 1. UG mining could have been the optimal strategy for some of the OP reserves, but were planned for OP mining 2. Evaluates OP and UG mining options separately 3. Ignores the variation in mining layout from one UG mining method to the other. 4. Defines the crown pillar (CP) is an arbitrary location. Ninth Open Pit Operators Conference 2016 Page 6

Problem Definition & Objectives Objectives of this study are: Present an implementation of an integer programming (IP) based mathematical model Evaluates possible variations in transition point from OP to UG mining for sublevel stoping and block caving methods. Demonstrates the impact of OP to UG mining strategies and different UG mining methods on the overall value of the project. Ninth Open Pit Operators Conference 2016 Page 7

UG Mining System Block Caving Mining Method High production rate and low mining cost Highly depend on cave-ability of the ore and host rock Dilution Costly if caving cannot be maintained Stoping Mining Method Minimum dilution if hanging wall is strong Stopes can be filled with waste rock, paste fill to recover pillar Early production is possible Safe working environment Ninth Open Pit Operators Conference 2016 Page 8

Mathematical Modelling for Transition Problem IP model for OP & UG stoping combined method: Objective function: Maximises the undiscounted profit from both OP mining and UG mining. Constraints: (i) OP slope or block precedence constraint (ii) UG mine design constraints (iii) Reserve restriction constraints (iv) CP design constraint that ensures the placement of CP is underneath the pit (v) The provision of required number of level needed for CP is in accordance to the geotechnical requirement. Ninth Open Pit Operators Conference 2016 Page 9

Mathematical Modelling for Transition Problem IP model for OP & UG block caving combined method: Objective function: Maximises the undiscounted profit from both OP mining and UG mining. Constraints: (i) OP slope or block precedence constraint (ii) UG mine design constraints (iii) Reserve restriction constraints (iv) CP design constraint that ensures the placement of CP is underneath the pit (v) The provision of required number of level needed for CP is in accordance to the geotechnical requirement. Ninth Open Pit Operators Conference 2016 Page 10

Mathematical Modelling for Transition Problem Issues: Size Big data handling Computer/Hardware capability What if they are solved: Accuracy Precision Effectiveness and efficiency Adapting to Change Ninth Open Pit Operators Conference 2016 Page 11

Case Study Case study profile and parameters Three-dimension (3-D) hypothetical gold deposit. 41,472 blocks with block size of 25m 25m 25m. Design stope size 2 2 2 blocks. Two levels need to be retained as crown pillar. IP problem written by Microsoft Visual Basic (VB.net) and solved by using CPLEX solver. Ninth Open Pit Operators Conference 2016 Page 12

Result Discussions Scenarios IP model results ($billion) Scenario 1: OP UG stoping method 21.657 Scenario 2: OP UG block caving method 26.020 Scenario 3: OP mining method only 18.396 Scenario 4: UG stoping method only 12.541 Scenario 5: UG block caving method only 13.123 Ninth Open Pit Operators Conference 2016 Page 13

Case Study OP-UG stoping and OP-UG block caving methods have the highest values. CP for scenario 1 is at Level 17-18 and scenarios 2 is Level 16-17. OP-UG block caving generates a higher value -- low mining cost, high production rate and economy of scale. Proved that if the deposit can be mined through a combination mining method, optimality can be achieved through strategic mine planning. Ninth Open Pit Operators Conference 2016 Page 14

Case Study If OP mining is selected for the shallow deposit without considering the potential transition to UG mining, the ultimate pit will extend deeper than the final pit generated. The IP model includes opportunity cost of all available mining strategies. Avoid the delays in production during the transition plan the development in the early stage. Maximised resource and reserve utilisation. Ninth Open Pit Operators Conference 2016 Page 15

Conclusions & Recommendations OP, UG and CP concurrently during the strategic mine planning strategy is important global optimisation. UG mining method selection plays an important role in combination method as it will affect the mining layout and project s value directly. IP models are presented to optimise the mine planning of combination mining method Ninth Open Pit Operators Conference 2016 Page 16

Conclusions & Recommendations Technical limitations: Production rate, Equipment requirements Variation of labour skills Limitations: Timing of transition: Production scheduling Problem size reduction strategy: Nature of IP model Ninth Open Pit Operators Conference 2016 Page 17

References 1. Alford, C, 1995. Optimization in underground mine design, in Proceedings of 25th International APCOM Symposium 1995, pp 213-218 (Australasian Institute of Mining and Metallurgy,Melbourne: Brisbane, Australia). 2. Asad, M and Topal, E, 2011. Production scheduling of open pit mining operations through cutoff grade optimization. South African Institute of Mining and Metallurgy, 111(11):741-750. 3. Bakhtavar, E and Shahriar, K, 2007. Optimal ultimate pit depth considering an underground alternative, in Proceedings of Fourth AACHEN International Mining Symposium-High Performance Mine Production 2007, pp 213-221 (AIMS: Germany). 4. Bakhtavar, E, Shahriar, K and Mirhassani, A, 2012. Optimization of the transition from open-pit to underground operation in combined mining using (0-1) integer programming. J. South. Afr. Inst. Min. and Metall., 112(12):1059-1064. 5. Brazil, M, Thomas, D A, Weng, J F, Rubinstein, J H and Lee, D H, 2005. Cost optimisation for underground mining networks. Optimization and engineering, 6(2):241-256. 6. Camus, J P, 1992. Open pit optimization considering an underground alternative, in Proceedings of 23th International APCOM Symposium 1992, pp 435-441 (SME: Tucson). 7. Chung, J, Topal, E and Erten, O, 2015. Transition from open-pit to underground - using integer programming considering grade uncertainty, in The 17th annual conference of the International Association for Mathematical Geosciences 5-13 September 2015 2015, (Schaeben, H, Delgado, R T, Boogart, K G and Boogart, R), pp 268-277 (IAMG: Freiberg, Germany). 8. Chung, J, Topal, E and Ghosh, A G, in press. Where to make the transition from open-pit to underground? - using integer programming. South African Institute of Mining and Metallurgy. 9. Dagdelen, K and Traore, I, 2014. Open pit transition depth determination through global analysis of open pit and underground mine scheduling, in Orebody Modelling and Strategic Mine Planning 24-26 November 2014 2014, (Dimitrakopoulus, R), pp 195-200 (The Australasian Institute of Mining and Metallurgy: Perth, Australia). 10. Dimitrakopoulos, R, Martinez, L and Ramazan, S, 2007. A maximum upside/minimum downside approach to the traditional optimization of open pit mine design. Journal of Mining Science, 43(1):73-82. 11. IBM CPLEX Optimization Solver, 2013. Version 12.6. IBM CPLEX ILOG Corp. 12. Johnson, T B, 1968. Optimum open pit mine production scheduling. Berkeley: DTIC Document. 13. Lerchs, H and Grossman, F I, 1964. Optimum design of open-pit mines, in Operations research 1964, pp. 14. Opoku, S and Musingwini, C, 2013. Stochastic modelling of the open pit to underground transition interface for gold mines. Int. J. Min. Reclam. and Environ., 27(6):407-424. 15. Soderberg, A and Rausch, D O, 1968. Pit planning and layout, pp 142-143 (The American Institute of Mining, Metallurgical, and Petroleum Engineers, Inc: New York). 16. Topal, E and Ramazan, S, 2012. Strategic mine planning model using network flow model and real case application. International Journal of Mining, Reclamation and Environment, 26(1):29-37. Ninth Open Pit Operators Conference 2016 Page 18

Ninth Open Pit Operators Conference 2016 Page 19

Introduction Mine Planning & Optimisation Exploration stage Block model generation Determination appropriate mining method Search mineralization zone Geological block model Economic block model Shallow deposit Deep deposit Near surface orebody extend vertically to a considerable depth Open pit mining method Underground mining method Combination mining method Transition problem Transition point Ninth Open Pit Operators Conference 2016 Page 20