Commissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department

Similar documents
LHC Collimation and Loss Locations

Simulations and measurements of collimation cleaning with 100MJ beams in the LHC

Beam losses versus BLM locations at the LHC

The LHC beam collimation

Status of the LHC Beam Cleaning Study Group

LHC APERTURE AND COMMISSIONING OF THE COLLIMATION SYSTEM

Simulations of HL halo loss and IR losses. R. Bruce, F. Cerutti, R. de Maria, A. Marsili, S. Redaelli

LHC Commissioning in 2008

Collimators and Cleaning, Could this Limit the LHC Performance?

Collimation strategy for the high-β Special Physics run at injection

LHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1

Beam Cleaning and Collimation Systems

Status and Results of the UA9 Crystal Collimation Experiment at the CERN-SPS

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report SIMULATION MODELS FOR ENERGY DEPOSITION

Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group

ASPECTS OF MACHINE INDUCED BACKGROUND IN THE LHC EXPERIMENTS

Beam Loss Monitors, Specification

The TESLA Dogbone Damping Ring

LHC status & 2009/2010 operations. Mike Lamont

INJECTION AND DUMP CONSIDERATIONS FOR A 16.5 TEV HE-LHC

Machine Protection Systems

Emittance blow-up and loss maps in LHC using the transverse damper as exciter

Case study: Energy deposition in superconducting magnets in IR7

MACHINE PROTECTION ISSUES AND STRATEGIES FOR THE LHC

BETATRON SQUEEZE: STATUS, STRATEGY AND ISSUES

TRANSVERSE IMPEDANCE OF LHC COLLIMATORS

Status and Outlook of the LHC

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report. Conceptual Design of IR Collimation

Will LHCb be running during the HL-LHC era? Burkhard Schmidt for the LHCb Collaboration

Accelerators. Lecture V. Oliver Brüning. school/lecture5

2008 JINST 3 S Main machine layout and performance. Chapter Performance goals

Main aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5)

LHC Run 2: Results and Challenges. Roderik Bruce on behalf of the CERN teams

Turn-around improvements

Modeling of beam-induced damage of the LHC tertiary collimators

The MD was done at 450GeV using beam 2 only. An MD focussing on injection of bunches with nominal emittance was done in parallel on beam 1.

AFP - TCL collimator studies

LHC operation in 2015 and prospects for the future

LHC ORBIT SYSTEM, PERFORMANCE AND STABILITY

Plans for 2016 and Run 2

Beam. RF antenna. RF cable

The LHC. Part 1. Corsi di Dottorato Corso di Fisica delle Alte Energie Maggio 2014 Per Grafstrom CERN and University of Bologna

Practical Lattice Design

Daniel Wollmann, CERN

ACHIEVABLE SPACE-CHARGE TUNE SHIFT WITH LONG LIFETIME IN THE CERN PS & SPS

Are we ready for the 2009 beam operation?

FLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR

Elias Métral, LHC Collimation Working Group Meeting, 15/03/ /31

STATUS OF LHC COMMISSIONING

RF System Calibration Using Beam Orbits at LEP

EuCARD-2 Enhanced European Coordination for Accelerator Research & Development. Conference/Workshop Paper

The LHC: the energy, cooling, and operation. Susmita Jyotishmati

Collimation method studies for next-generation hadron colliders

LHC Beam Operations: Past, Present and Future

New LSS optics for the LHC (status)

LHC Luminosity and Energy Upgrade

Simulations and Measurements of Secondary Electron Emission Beam Loss Monitors for LHC

OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

Merlin scattering models for the HL-LHC collimation system

Interface with Experimental Detector in the High Luminosity Run

TRANSVERSE DAMPER. W. Höfle, CERN, Geneva, Switzerland. Abstract INTRODUCTION AND HIGHLIGHTS IN Controlled Transverse Blow-up

CesrTA Status Report Mark Palmer for the CesrTA Collaboration March 4, 2009 ESR

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

Operational Experience with HERA

Lattice Design and Performance for PEP-X Light Source

Compensating Parasitic Collisions Using Electromagnetic Lenses

The Very Large Hadron Collider Beam Collimation System

LHC. Construction Understanding first the commissioning. Prospects for

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

First Measurements of Proton-Proton Elastic Scattering and Total Cross-Section at the LHC. EDS 2011 Qui Nhon, Vietnam

LHC Commissioning The good, the bad the ugly

SC magnets for Future HEHIHB Colliders

Simulation of the ILC Collimation System using BDSIM, MARS15 and STRUCT

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

LHC upgrade based on a high intensity high energy injector chain

Overview of LHC Accelerator

The Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory

1.1 Electron-Cloud Effects in the LHC

Sources of machine-induced background in the ATLAS and CMS detectors at the CERN Large Hadron Collider

Luminosity Goals, Critical Parameters

LHC Upgrade Plan and Ideas - scenarios & constraints from the machine side

Development of Large Scale Optimization Tools for Beam Tracking Codes

Results of UFO dynamics studies with beam in the LHC

LHC RUN 2: RESULTS AND CHALLENGES

Open Issues from the SPS Long-Range Experiments

Aperture Measurements and Implications

The Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy

LHC Upgrade (accelerator)

Simulations of single bunch collective effects using HEADTAIL

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report BEAM HALO SIMULATIONS

Tools of Particle Physics I Accelerators

Tobias Baer February, 9 th 2012

(Lead) Ions in the LHC

Thanks to all Contributors

Beam diagnostics: Alignment of the beam to prevent for activation. Accelerator physics: using these sensitive particle detectors.

Beam-induced radiation in the compact muon solenoid tracker at the Large Hadron Collider

Measurements of Proton-Proton Elastic Scattering and Total Cross-Section at the LHC by TOTEM Diffraction 2012 Lanzarote, 15 September

Emittance Growth and Tune Spectra at PETRA III

SPACE CHARGE EXPERIMENTS AND BENCHMARKING IN THE PS

Transcription:

39 th ICFA Advance Beam dynamics Workshop High Intensity High Brightness Hadron Beams - HB 2006 Tsukuba, May 29 th - June 2 nd, 2006 Commissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department

Outline Introduction Collimation commissioning plan Performance of reduced systems Collimator setup at the SPS Conclusions S. Redaelli, HB2006 2

Good news from CERN! May 31st: First two transfer line collimators installed! First milestone towards a successful commissioning!! Pictures by R. Assmann S. Redaelli, HB2006 3

Introduction Initial LHC operation: Phase I collimation system 88 ring collimators + 13 in transfer lines (500 degrees of freedom!) Critical role for the machine protection Coherent settings required for element around the ring How do we commission this powerful (complex) system? How do we adjust collimators w.r. to beams? Initially: Trade-off between performance and operational efficiency! Cleaning Protection?? Setup time Operational efficiency Settings tolerance S. Redaelli, HB2006 4

Starting point: Staged LHC commissioning R. Bailey, Chamonix06 Stage I II III IV Hardware commissioning Machine checkout Beam commissioning 43 bunch operation? 75ns ops 25ns ops I Install Phase II and MKB 25ns ops II I 0.5x10 10 1.7x10 12 5x10 13 1.1x10 14 3.2x10 14 No beam Beam Beam What are the implications on the LHC collimation? R. Assmann No easy startup! 43-on-43 Tevatron and HERA Pilot at 7 TeV above damage limit However, collimation commissioning can profit from the staged intensity! Can we find reduced collimation systems that ensure the required cleaning at each intensity stage?? S. Redaelli, HB2006 5

Nominal collimation settings at 7 TeV 7.5 σ 6.0 σ 7.0 σ 10.0 σ 8.5 σ 10.0 σ Δ = 1σ 200 μm IP ARC Beam halo ARC Triplets ARC TCDQ (protection) Primary (robust) Secondary (robust) Absorber (W metal) Tertiary (W metal) Physics absorbers (Cu metal) Here: focus on 7 TeV operation (See also talk TUAZ03 for more details) Aperture bottleneck: only super-conducting triplets is the IP s (±8.5 σ) Nominal settings: ATCP = 6.0 σ / ATCS = 7.0 σ / ATCT = 8.5 σ + AABS = 10.0 σ Protection (TCDQ): APROT = 7.5 σ [must also protect the TCT s!] Assumptions on expected cold aperture not discussed here (orbit, optics,...) S. Redaelli, HB2006 6

Staging the LHC collimation system Staged intensity Adapt collimator number and settings! What s the minimum system that ensures the required cleaning vs. intensity? (1) Pilot 43x43 75ns 25ns (3) (2) (4) (5) R. Assmann Primary coll.(tcp) define the aperture Tertiary collimators (TCT) always protect the SC triplets TCDQ: protect against asynchronous firing of the beam dump They are needed with pilot at 7 TeV! All collimators in place! We propose to adapt the number of the ones to be used S. Redaelli, HB2006 (1) No collimators [Imax 5.6 x 10 9 p at 7 TeV] but protection (14) (2) One-stage cleaning (TCP) + protection 14 (3) One-stage + shower absorbers (TCLA) + protection 23 (4) Relaxed two-stage (TCS) + shower absorbers + protection 38 (5) Complete system at nominal settings [7 TeV] 38 Ncoll 7

Illustrative schemes of staged systems (3) One-stage cleaning + shower absorbers + protection ~8 σ ARC 6.0 σ out >10.0 σ 8.5 σ Beam halo ARC IP Triplet out ARC (4) Relaxed two-stage cleaning + absorbers + protection 7.5 σ 6.0 σ ~9.5 σ ~10.0 σ 8.5 σ 10.0 σ ARC Beam halo Δ > 3σ ARC IP Triplet ARC TCDQ Primary Secondary Absorber Tertiary Physics absorbers Nominal: 7.5σ 6.0σ 7.0σ 10σ 8.5σ 10σ What do we gain with this staged approach? S. Redaelli, HB2006 8

Advantages of the staged commissioning Machine protection not compromised Required cleaning vs. beam intensity achieved Next intensity stages not compromised (all hardware in place)! Understand better the machine when full system and precise setup will be required! Reduced number of elements Relaxed setting tolerances Optimize the setup time! Cleaning Protection Setup time Operational efficiency Settings tolerance What s the beam intensity that we can achieve in each scenario? Experience will tell, but we can try to predict what we will get! S. Redaelli, HB2006 9

Expected cleaning performance Larger β* operation TCP TCS TCLA TCT TCDQ Educated guesses of the expected performance Nominal β* operation 43-on-43 operation R. Assmann et al., Chamonix 2006 Work ongoing: simulate in detail these operational scenarios and assess the cleaning performance. S. Redaelli, HB2006 10

Performance of the reduced system 10 11 Full system No Secondary collimators Loss rate per unit length [ p/m/s ] 10 10 10 9 10 8 10 7 TCP s IP7 TCS s Warm Cold TCLA s Assumed quench limit TCP s IP7 TCLA s C. Bracco ~x10 10 6 19.8 19.9 20 20.1 20.2 20.3 20.4 20.5 s [ km ] Power in the SC magnets Preliminary results from M. Santana x7 19.8 19.9 20 20.1 20.2 20.3 20.4 20. s [ km ] One-stage cleaning + shower absorbers is ~10 times above the quench limit allow physics with 43 on 43 operation! Detailed studies ongoing for other scenarios. S. Redaelli, HB2006 11

Outline Introduction Collimation commissioning plan Performance of reduced systems Collimator setup at the SPS Conclusions S. Redaelli, HB2006 12

The collimator test with beam at the SPS Goal of the test: Demonstrate the required functionalities of the LHC collimator prototype (mechanical movements, impedance, vacuum, ) Low intensity test: E b = 270 GeV N b 1.1x10 11 p I b = (1-16) x N b (TOTEM beam) ε x 1 µm σ x 0.4 mm High intensity test: E b = 270 GeV N b 1.1x10 11 p I b = 4 x 72 x N b (LHC beam) ε x 3.75 µm σ x 0.7 mm Horizontal collimator (SPS point 5) Many tests performed (mostly reported at PAC05): Mechanical functionality and basic control, beam-based setup, halo dynamics and beam shaping, systematics of BLM system, impedance and trapped modes, tune shift vs. collimator gap, vacuum, out-gassing,... S. Redaelli, HB2006 13

What do we want to setup collimators? Normalized collimator settings must be converted to positions in [mm]: Center the two collimator jaws Know the orbit! Adjust the gap to the correct setting Know the beam size! xbeam(s), ybeam(s), σx(s), σy(s) Normalized settings Gaps in millimetres β-beat! Closed orbit Primary 6 σ Secondary 7 σ Secondary 7 σ S. Redaelli, HB2006 14

How do we center the collimator jaws Beam-based alignment relies on dedicated sets of BLM s mounted at each collimator. 1. Move one jaw in 2. Scrape the beam (sharp edge) 3. Move the other jaw until you see a signal on the BLM S. Redaelli, HB2006 Take profit from the the two-sided design! Alignment rely on the reading of downstream beam loss monitors The step size Δx sets the precision of the final alignment! Move one jaw corner at the time to adjust angles? 15

Beam-based centering of the collimator jaws Δx = 50 µm Signal of beam loss monitor [ Gy ] 0.12 0.10 0.08 0.06 0.04 0.02 Right jaw Left jaw Δx = 100 µm (σ x 0.7 mm) 0.00 0 50 100 150 200 250 Relative increase of jaw position [ µm ] S. Redaelli, HB2006 First centering with high-intensity beams: 1h. 50 μm centering accuracy demonstrated! Then, 10-15 minute (precision of 50 μm). Less time for less precise settings. Setting of gap values relied on good optics model + emittance measurements. 16

Local beam size at the collimator Full beam scraping at the collimator Example of SPS measurements Jaw position Expected beam size : σ = βε = 700 μm Fitted beam size : (665±52) μm More studies this year at the SPS... S. Redaelli, HB2006 Beam intensity Method: accurate but destructive and long! Repeat it at each collimator? How scales from injection to 7 TeV? However, can be a solution if the optics model is not good enough! 17

Conclusions Commissioning of the LHC collimation system discussed Reduced systems proposed for various LHC stages Insure required cleaning versus beam intensity Safety not compromised Use a smaller number of collimators Positioning tolerance relaxed Proposed scenarios are validated with detailed simulations Setup of collimator successfully achieved at the SPS Centering to the 50 μm level routinely achieved Methods to adjust the collimator gaps were worked out LHC issues (start the discussion?): Infer 7 TeV settings from setup at 450 GeV Relative retraction of many collimators at different places What is the expected halo population of the LHC beams? Precise setup of skew collimators S. Redaelli, HB2006 18