Commissioning and Testing of AVR and PSS

Similar documents
ISM Evolution. Elscolab. Nederland BV

Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, Wind Power Forecasting tools and methodologies

Chapter 3 AUTOMATIC VOLTAGE CONTROL

Power System Security. S. Chakrabarti

Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s

Expedited Filing Draft August 22, 2017

Economic Operation of Power Systems

Power System Stability GENERATOR CONTROL AND PROTECTION

Electric Distribution Storm Hardening Initiatives. Paul V. Stergiou Distribution Engineering October 14 th, 2015

Safety analysis and standards Analyse de sécurité et normes Sicherheitsanalyse und Normen

1. Wind turbines are designed to operate within specified design criteria. Often the operating environment extends beyond these limits and causes

GIS Solution For Electric Utilities With Integration With Distribution Management System

Quantification and Management of Grid Interaction Effects on Turbo- Generator Sets

QFT Framework for Robust Tuning of Power System Stabilizers

Model M3484 Industrial Line Noise Filter Module Customer Reference Manual

Overview of Control System Design

Derogation Criteria for the Requirements for Generators Network Code

February Industry Communique

Report on El Paso Electric Company Weather-Related Issues in February 2011

Technical Application Guide

CECOER. Renewable Energy Control Center. How technologies have boosted remote operations. Agder Energi-konferansen

Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation

Self-Tuning Control for Synchronous Machine Stabilization

Beam. RF antenna. RF cable

System Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres

Simulating a Power System

LB1846M, 1848M. Low-Voltage/Low Saturation Voltage Type Bidirectional Motor Driver

Cascading Outages in Power Systems. Rui Yao

Chapter 9: Transient Stability

Superconducting cables Development status at Ultera

STATIC GAS MONITOR Type SGM/DEW Revision A of 20 aprile 2016

Performance Of Power System Stabilizerusing Fuzzy Logic Controller

Failure Analysis of Medium Voltage Capacitor Banks: The Egyptian Experience

Hydra Fault Current Limiting HTS Cable to be Installed in the Consolidated Edison Grid

Dynamic simulation of a five-bus system

Integration of ArcFM UT with SCADA, SAP, MAXIMO and Network Calculation

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives

Introduction to State Estimation of Power Systems ECG 740

DYNAMIC RESPONSE OF A GROUP OF SYNCHRONOUS GENERATORS FOLLOWING DISTURBANCES IN DISTRIBUTION GRID

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc.

Multi-Objective Optimization and Online Adaptation Methods for Robust Tuning of PSS Parameters

BOXA-II ON-STREAM X-RAY FLUORESCENCE ANALYZER. Technical Description Version 2 BGRIMM AUTOMATION

Aldi Mucka Tonin Dodani Marjela Qemali Rajmonda Bualoti Polytechnic University of Tirana, Faculty of Electric Engineering, Republic of Albania

APPLICATIONS OF CONTROLLABLE SERIES CAPACITORS FOR DAMPING OF POWER SWINGS *

Determination of stability limits - Angle stability -

PUB NLH 185 Island Interconnected System Supply Issues and Power Outages Page 1 of 9

Quanser NI-ELVIS Trainer (QNET) Series: QNET Experiment #02: DC Motor Position Control. DC Motor Control Trainer (DCMCT) Student Manual

Generators. What its all about

7. Transient stability

Cyber Physical Power Systems Power in Communications

This Capstone Project will address the analysis and diagnosis of the Steam Turbo-Generator (STG) machine vibration problems in Thermal Power Plant

DAMPING OF SUBSYNCHRONOUS MODES OF OSCILLATIONS

Alectra Utilities List of Station Capacity

Periodic Inspection and Testing of Electrical Installations Sample Test ( ) Version 1.3 July 2018

DESIGNING POWER SYSTEM STABILIZER WITH PID CONTROLLER

Improving Forecasting Through Accurate Data. Jim Blatchford Sr. Policy Issues Representative. Rizwaan Sahib Telemetry Engineer CAISO.

11.1 Power System Stability Overview

International Studies about the Grid Integration of Wind Generation

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5

Chapter 5. System Reliability and Reliability Prediction.

MetConsole AWOS. (Automated Weather Observation System) Make the most of your energy SM

Hydrogen & Chlorine monitoring for the Chlor-Alkali Industry

Centralized Forecasting Registration and Communication Requirements for Distribution Connected Variable Generators. IESO Training

Turbine Meter TRZ 03 PRODUCT INFORMATION. Reliable Measurement of Gas

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2015

TOSHIBA Field Effect Transistor Silicon N Channel MOS Type SSM3K02F

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Interconnection for Wind Energy ) Docket No. RM

Oscillation energy based sensitivity analysis and control for multi-mode oscillation systems

Analogue Meters CQ2x07 series

Research on the synchronous vibration of the non-integral. mechanism under the vibration environment

B1-1. Closed-loop control. Chapter 1. Fundamentals of closed-loop control technology. Festo Didactic Process Control System

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience

UNIT-I Economic Operation of Power Systems -1

Control Loop Investigations

5-V Low Drop Fixed Voltage Regulator TLE 4275

An Introduction to Insulation Resistance Testing

Using a TCSC for Line Power Scheduling and System Oscillation Damping Small Signal and Transient Stability Studies

Comparative Study of Synchronous Machine, Model 1.0 and Model 1.1 in Transient Stability Studies with and without PSS

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur

Technical Requirements. Version No. 1.0 Effective Date 10/1/2008

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

After publication, this Indian Standard will supersede the following Indian Standards:

The Vaisala AUTOSONDE AS41 OPERATIONAL EFFICIENCY AND RELIABILITY TO A TOTALLY NEW LEVEL.

Digital Stored Grain Quality Management. BinMaster Level Controls Lincoln, Nebraska, USA

TOSHIBA Field Effect Transistor Silicon P Channel MOS Type 2SJ168. DC I D 200 ma Pulse I DP 800

HiPace 300 with TC 110 and power supply pack OPS 100, DN 100 CF-F

Safety Precautions WARNING If critical situations that could lead to user s death or serious injury is assumed by mishandling of the product.

Anti-surge Chip Resistors

Transient Stability Analysis with PowerWorld Simulator

Real-Life Observations of Power System Dynamic Phenomena Some Interesting Aspects

SSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL

Predicting, controlling and damping inter-area mode oscillations in Power Systems including Wind Parks

IEEE 9 Bus System Example

Predicting Long-Term Telemetry Behavior for Lunar Orbiting, Deep Space, Planetary and Earth Orbiting Satellites

CHAPTER 2 MODELING OF POWER SYSTEM

OPALCO Outage Analysis. December 2017 Board Meeting

PHASED OUT. LED light engine / OLED LED compact. Umodule SLE G4 15mm 2000lm 9x0 H EXC D50

DC/DC regulator Input V Output up to 16 A

Robust Tuning of Power System Stabilizers Using Coefficient Diagram Method

Transcription:

Commissioning and Testing of AVR and PSS Excitation System Upgrade and commissioning challenges Vetti Bala Principal C&I Engineer G E N E S I S E N E R G Y L I M I T E D

Contents Asset Testing - AVR AVR routine testing requirements Life Cycle Management Excitation System Replacement Related opportunities PSS Function Advantage of tuning PSS correctly Challenges AVR testing challenges 2. 1 5 D E C E M B E R 2 0 1 7 C o m m i s s i o n i n g a n d t e s t i n g o f A V R a n d PSS

Asset Testing - AVR What prompts for the testing Analogue AVRs 5 yearly cycle Digital AVRs 10 yearly cycle Replacement of AVR (asset life cycle management) Life cycle management Improve reliability Archive compliance Protect asset with better limiter controls 3. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement 4. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement Challenges with life cycle management Takes over two years to achieve it; justification, status of asset condition, budget allocation, resources availability, etc.. Key milestones replacement project Project approvals Technical spec ready / Tendering Contract award Design phase Build phase (inc FAT) Outage work Commissioning system AVR Testing 2 year prior 6-12 months 9 months prior 6 months 5 months 4 weeks 5 days 1 day 5. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement First activity: prepare for Model building Key information required for proposed model build; (in addition to technical spec) Generator parameters Gen Transformer parameters Grid info at the connection point Possible sources for Model input data; PTI Reports ACS Previous commissioning data New equipment specification Injection point Grid data (from SO) 6. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement Design and design approvals Design Phase New system supplier system design Customer interface design (DCS or SCADA interface) control, etc.. Grid requirements (dialogue with SO) Design approval Owner s requirements approval SO approvals for the proposed AVR settings (3 months) 7. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement - Asset Life Cycle Management DC Exciter AVR Cabinet Original DC exciter from 40 s coupled to the main shaft Analogue AVR installed over 25 years ago Electronics drifting with ageing 8. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement - Replacement digital excitation system Digital AVR Cabinets Excitation Transformer 9. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement - Decommission old equipment Removal of exciter Removal of old AVR cabinets and cables 10. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement Related activities A replacement project brings other opportunities or requirements Unit ultimate over-speed protection replacement Carbone dust extraction system (if required) Removal of previously decommissioned equipment 11. 1 5 D E C E M B E R 2 0 1 7

Morden Unit Over-speed Protection - Unit Safety and Reliability issues Original Mechanical Over-speed device from 40 s Single centrifugal switch to shut down the Unit Moving parts, shown wear and tear issues Unreliable and hidden failure 12. 1 5 D E C E M B E R 2 0 1 7

Morden Unit Over-speed Protection - Replacement tooth wheel and pickup sensors Built in redundancy, 2 out of 3 electronic system Fail safe and monitored of any failures High level of reliability Ease of routine testing 13. 1 5 D E C E M B E R 2 0 1 7

Excitation System Replacement Related activities The consequence of exciter removal Re-check Unit Balance Re-check Unit Vibration New speed probes and tooth wheel commissioning Unit Start / Stop sequence - recommission Unit creep detection and shutdown - recommission Complete functional trip test of ultimate over-speed protection by running the turbine to over-speed set point thresholds. 14. 1 5 D E C E M B E R 2 0 1 7

Commissioning and AVR Testing 15. 1 5 D E C E M B E R 2 0 1 7

AVR Testing Commissioning new system Site acceptance test (owner s requirements) Verify Local / Remote controls Functional trip test Demonstrate reactive power (MVAr) controls 16. 1 5 D E C E M B E R 2 0 1 7

AVR Testing From Asset testing companion guide Purpose of Test: As stipulated in the ancillary services contract, testing is required to determine if the service meets the performance standards. The system operator needs to ensure the integrity of the voltage-support ancillary-service provision by issuing requirements to service providers for assessing the voltage support capability of their assets. To ensure the asset complies with the performance standards outlined in ancillary services contract Outcome: The required outcome of AVR testing is to provide the system operator with a verified mathematical model that describes the steady state and dynamic behaviour of the equipment. An accurate representation allows the system operator to model interactions with the system and other generating stations, when subjected to disturbances on the system, and thereby control the voltage stability of the system. To validate the mathematical model 17. 1 5 D E C E M B E R 2 0 1 7

AVR Testing AVR Compliance testing Intense AVR testing Model validation Test EIPC requirements Demonstrate reactive power support 18. 1 5 D E C E M B E R 2 0 1 7

AVR Testing Generator Capability Diagram with limiters 19. 1 5 D E C E M B E R 2 0 1 7

AVR Testing Demonstrate Exporting Reactive Power Capability: Minimum of +50% reactive power at the Grid injection point of the maximum continuous MW capability in the voltage range of -10% to +10% +50% MVAr 220kV: 198kV to 242kV 110kV: 99kV to 121kV Importing Reactive Power Capability: Minimum of 33% reactive power at the Grid injection point of the maximum continuous MW capability in the voltage range of -5% to +10% -33%MVAr 220kV: 209kV to 242kV 110kV: 104.5kV to 121kV 20. 1 5 D E C E M B E R 2 0 1 7

AVR Testing EIPC Testing requirements Offline from -10% to +10% of nominal voltage Offline step responses Online step responses at unity power factor Online step responses from under excited regions Online step responses from over excited regions Under excited limiter tests Over excited limiter tests Field voltage rise time Tests PSS Performance tests Unsychronised Unsychronised UPF UER OER UEL OEL 21. 1 5 D E C E M B E R 2 0 1 7

PSS Power System Stabilizer 22. 1 5 D E C E M B E R 2 0 1 7

PSS Advantage of modern system with PSS and tuning it correctly The PSS function improves the stability of the generator and the transmission system as a whole by using the excitation to damp power oscillations PSS is not very effective in low power range PSS is intended for the improvement of the damping of the electromechanical oscillations by appropriate influencing the AVR control loop Increase the working range of the generators MW smoothing from hydraulic instability or spikes Reduce maintenance issues Integrated PSS should be available with modern excitation system 23. 1 5 D E C E M B E R 2 0 1 7

PSS

PSS Advantage of PSS function MW oscillation due to hydraulic instability PSS On smooths out MW oscillation Rangipo 32. 1 5 D E C E M B E R 2 0 1 7

AVR Testing In summary Testing is typically takes a full day and is a very intense activity External customers satisfied (Transpower) A dialogue is essential during the testing with SO to ensure the attained data is acceptable by SO Ensure the dispatch is met by the new excitation system Internal customers satisfied (Genesis Ops) Ensure the PSS tuning and resultant unit behaviour is acceptable by the operations Ensure the MVAr support is acceptable by the operations (the operational regions generator capability) 33. 1 5 D E C E M B E R 2 0 1 7

AVR Testing Challenges 34. 1 5 D E C E M B E R 2 0 1 7

AVR Testing Challenges Challenges during testing Peak hours Grid emergency Parallel activities (other major outages) Ops shift change Weak Grid Plant / hydrology limitations 35. 1 5 D E C E M B E R 2 0 1 7

Thank you G E N E S I S E N E R G Y L I M I T E D