MONTHLY PROGRESS REPORT FOR THE MONTH OF APRIL ( SEC - A & SEC - B) Specifica tions

Similar documents
Total No. of tests conducted till October'13

DETAILS OF LABORATORY TESTS CONDUCTED IN THE MONTH OF APRIL 2013

NHBRA SOIL LABORATORY SECTION INTERIM REVISED TEST RATES FOR THE MATERIALS LABORATORY

Construction aggregates : evaluation and specification Clive Mitchell Industrial Minerals Specialist

Mar 1, 2018 LAB MANUAL INDEX 1. Table of Contents Laboratory Testing Methods Reducing Aggregate Field Samples to Testing Size (Ver.

Influence of Aggregate Flakiness on Dense Bituminous Macadam & Semi Dense Bituminous Concrete Mixes

Chapter. Materials. 1.1 Notations Used in This Chapter

A Study on Suitability of Crusher Dust Stabilized Red Earth and Gravel as Subgrade and Sub Base Material

NOTTINGHAM DESIGN METHOD

Influence of Crushing Size of the Aggregates on Dense Bituminous Mix and Experimental Study on Mechanical Properties

Rigid pavement design

Chapter 2. The Ideal Aggregate. Aggregates

Australian Journal of Basic and Applied Sciences

KDOT Geotechnical Manual Edition. Table of Contents

A STUDY ON THE INFLUENCE OF SHAPE OF COARSE AGGREGATES ON STRENGTH OF DENSE BITUMINOUS MACADAM

Entrance exam Master Course

= 0.7 (6) = 0.62 (7) = 0.60 (8)

The Effect of Aging on Binder Properties of Porous Asphalt Concrete

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

1. ARRANGEMENT. a. Frame A1-P3. L 1 = 20 m H = 5.23 m L 2 = 20 m H 1 = 8.29 m L 3 = 20 m H 2 = 8.29 m H 3 = 8.39 m. b. Frame P3-P6

Mechanistic Investigation of Granular Base and Subbase Materials A Saskatchewan Case Study

ADVANCES in NATURAL and APPLIED SCIENCES

S E C T I O N 1 2 P R O D U C T S E L E C T I O N G U I D E - H E L I C A L S C R E W P I L E F O U N D A T I O N S

Effect of glass powder instead of mineral powder on asphalt mixture

Flexible Pavement Design

Influence of Variation in the Aggregate Gradation Range on Mix Design Properties of Bituminous Concrete (BC) Mixes used as Wearing Course

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

RESISTANCE OF AGED ASPHALTIC CONCRETE TO WAVE ATTACK

1. Two forces P and Q are acting at an angle as shown in the figure. In terms of these quantities, what are values of R and respectively?

Aggregates. AAPA training

MATERIALS FOR CIVIL AND CONSTRUCTION ENGINEERS

2012 MECHANICS OF SOLIDS

REGRESSION MODELING FOR STRENGTH AND TOUGHNESS EVALUATION OF HYBRID FIBRE REINFORCED CONCRETE

Design of Overlay for Flexible Pavement

Design of AAC wall panel according to EN 12602

Analysis of the horizontal bearing capacity of a single pile

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

Modified Dry Mixing (MDM) a new possibility in Deep Mixing

Geology 229 Engineering Geology. Lecture 7. Rocks and Concrete as Engineering Material (West, Ch. 6)

SEM-2016(01HI CIVIL ENGINEERING. Paper Answer all questions. Question No. 1 does not have internal choice,

2002 Design Guide Preparing for Implementation

Behavioral Study of Cylindrical Tanks by Beam on Elastic Foundation

Effects of Basalt Fibres on Mechanical Properties of Concrete

Comparative Study of Geotechnical Properties of Abia State Lateritic Deposits

Module 14. Tension Members. Version 2 CE IIT, Kharagpur

VOL. 2, NO. 11, Dec 2012 ISSN ARPN Journal of Science and Technology All rights reserved.

CEEN Laboratory 4 Aggregates for Base Layers, Portland Cement Concrete & Hot Mix Asphalt

CE : CIVIL ENGINEERING

Q. 1 Q. 5 carry one mark each.

2008 SEAUPG CONFERENCE-BIRMINGHAM, ALABAMA

CIVIL DEPARTMENT MECHANICS OF STRUCTURES- ASSIGNMENT NO 1. Brach: CE YEAR:

Commonwealth of Pennsylvania PA Test Method No. 709 Department of Transportation October Pages LABORATORY TESTING SECTION. Method of Test for

Wikipedia.org BUILDING STONES. Chapter 4. Materials of Construction-Building Stones 1

Schedule of Accreditation issued by United Kingdom Accreditation Service 2 Pine Trees, Chertsey Lane, Staines-upon-Thames, TW18 3HR, UK

Geotechnical Properties of Soil

Volumetric Tests. Overview

Technical information CONCRETE / SOLID STONE. Reaction resin mortar, epoxy-acrylate-based with styrene USAGE INSTRUCTIONS

THE STRUCTURAL DESIGN OF PILE FOUNDATIONS BASED ON LRFD FOR JAPANESE HIGHWAYS

Evaluation of Rutting Depth in Flexible Pavements by Using Finite Element Analysis and Local Empirical Model

Annex - R C Design Formulae and Data

DESIGN AND DETAILING OF COUNTERFORT RETAINING WALL

Landslide FE Stability Analysis

Malaysian Journal of Civil Engineering 29(3): (2017)

Nano Scale Organosilane Asphalt Applications

Geotechnical Engineering Study, Conifer Senior High School Football Field Improvements, Conifer, Colorado

SHEET PILE WALLS. Mehdi Mokhberi Islamic Azad University

SECTION AGGREGATE OR GRANULAR SUBBASE

International journal of Engineering Research-Online A Peer Reviewed International Journal Articles available online

TABLE OF CONTANINET 1. Design criteria. 2. Lateral loads. 3. 3D finite element model (SAP2000, Ver.16). 4. Design of vertical elements (CSI, Ver.9).

Concrete Pavements Conference August Aggregate interlock efficiency at concrete pavement joints

Appendix A. Producer Statement Advisory Note

Basic Examination on Assessing Mechanical Properties of Concrete That Has Suffered Combined Deterioration from Fatigue and Frost Damage

Chapter I Basic Characteristics of Soils

Engineering materials

Updating Bituminous Stabilized Materials Guidelines: Mix Design Report, Phase II

AF2903 Road Construction and Maintenance. Volumetric Analysis of Asphalt Mixtures

Centrifuge Shaking Table Tests and FEM Analyses of RC Pile Foundation and Underground Structure

DESIGN OF ULTRA-THIN BONDED HOT MIX WEARING COURSE (UTBHMWC) MIXTURES

Pavement Design Where are We? By Dr. Mofreh F. Saleh

Roadway Grade = m, amsl HWM = Roadway grade dictates elevation of superstructure and not minimum free board requirement.

LECTURE NO. 4-5 INTRODUCTION ULTRASONIC * PULSE VELOCITY METHODS

BACKFILL AND INTERFACE CHARACTERISTICS

Asphalt Mix Designer. Module 2 Physical Properties of Aggregate. Specification Year: July Release 4, July

1.The number of simultaneous equations to be solved in the slope deflection method,

INTRODUCTION TO PAVEMENT STRUCTURES

The study of ultrasonic pulse velocity on plain and reinforced damaged concrete


DESIGNING FOR DOWNDRAG ON UNCOATED AND BITUMEN COATED PILES

Module 6. Shear, Bond, Anchorage, Development Length and Torsion. Version 2 CE IIT, Kharagpur

Module 14. Tension Members. Version 2 CE IIT, Kharagpur

Presented at the 6 th Strassenkonferenz, Budapest 1988

AASHTO Rigid Pavement Design

APPENDIX H CONVERSION FACTORS

APPENDIX D SUMMARY OF EXISTING SIMPLIFIED METHODS

EFFECT OF AGGREGATE SHAPE FACTORS ON THE PERFORMANCE OF ASPHALT MIXES

Chapter 1 - Soil Mechanics Review Part A

Visit Abqconsultants.com. This program Designs and Optimises RCC Chimney and Foundation. Written and programmed

M/s Transstroy Obedullaganj Betul Tollways Private Limited

An Experimental Study and Evaluation of Thermal Stresses in Rigid Pavements using FE Method

Role of Force Resultant Interaction on Ultra-High Performance Concrete

Transcription:

Client Independent Engineer Concessionaire EPC Contractor Sub Contractor Sl No. 1 EARTH WORK : OGL : NATIONAL HIGHWAYS AUTHORITY OF INDIA : CDM SMITH Inc JV with WILBUR SMITH ASSOCIATES Pvt Ltd. : HK TOLL ROAD PVT. LTD. : RELIANCE UTILITY ENGINEERS PVT.LTD. : LARSEN & TOUBRO LIMITED-ECC DIVISION. 1.01 ATTERBERGS LIMIT OF CONSISTENCY IS 2720 Part 5 1test/250m 0 3 0 3 3 98000 534 0 534 534 98000 537 0 537 537 1.02 MODIFIED PROCTOR IS 2720 Part 8 1test/250m 0 3 0 3 3 115750 605 0 605 605 115750 608 0 608 608 1.03 GRADATION / SAND CONTENT IS 2720 Part 4 1test/250m 0 3 0 3 3 103750 557 0 557 557 103750 560 0 560 560 1.04 CBR IS 2720 Part 16 1test/250m 0 3 0 3 3 38500 243 14 257 243 38500 246 14 260 246 1.05 FREE SWELL INDEX IS 2720 Part 40 As 0 3 0 3 3 100750 530 1 531 530 100750 533 1 534 533 1.06 F.D.D. TEST FOR OGL (Nos) IS 2720 Part 28 1 test/1000 sqm 4256 67 0 67 67 626213 6512 39 6551 6512 630469 6579 39 6618 6579 2 EARTH WORK : Embankment/Subgrade (Borrow Area Soil ) 2.01 ATTERBERGS LIMIT OF CONSISTENCY IS 2720 Part 5 2 test/3000 cum 0 0 0 0 0 807000 545 0 545 545 807000 545 0 545 545 2.02 MODIFIED PROCTOR IS 2720 Part 8 2 test/3000 cum 0 0 0 0 0 808500 546 0 546 546 808500 546 0 546 546 2.03 FREE SWELL INDEX IS 2720 Part 40 As 0 0 0 0 0 805500 544 0 544 544 805500 544 0 544 544 2.04 GRADATION / SAND CONTENT IS 2720 Part 4 2 test/3000 cum 0 0 0 0 0 799500 540 0 540 540 799500 540 0 540 540 2.05 C.B.R. IS 2720 Part 16 1 test/3000 cum 0 0 0 0 0 1131000 413 19 432 413 1131000 413 19 432 413 2.06 DELETERIOUS CONTENT IS 2720 Part 27 1 test per Source 0 0 0 0 0 78000 44 0 44 44 78000 44 0 44 44 2.07 C AND ø VALUE IS 2720 Part 13 1 test/ 3000 Cum. 0 0 0 0 0 688500 254 0 254 254 688500 254 0 254 254 3 EARTH WORK : Embankment/Subgrade ( Control Sample) 3.01 ATTERBERGS LIMIT OF CONSISTENCY IS 2720 Part 5 2 test/3000 cum 7500 5 0 5 5 531000 335 0 335 335 538500 340 0 340 340 3.02 MODIFIED PROCTOR IS 2720 Part 8 2 test/3000 cum 7500 5 0 5 5 531000 335 0 335 335 538500 340 0 340 340 3.03 FREE SWELL INDEX IS 2720 Part 40 As 7500 5 0 5 5 531000 335 0 335 335 538500 340 0 340 340 3.04 GRADATION / SAND CONTENT IS 2720 Part 4 2 test/3000 cum 7500 5 0 5 5 531000 335 0 335 335 538500 340 0 340 340 3.05 C AND ø VALUE IS 2720 Part 13 1 test/ 3000 Cum. 0 0 0 0 0 276000 78 0 78 78 276000 78 0 78 78 3.06 C.B.R. IS 2720 Part 16 1 test/3000 cum 12000 4 0 4 4 468000 179 0 179 179 480000 183 0 183 183 3.07 F.D.D. TEST FOR Embankment (In Nos) IS 2720 Part 28 1 test/1000 sqm 115768 1550 0 1550 1550 4672871 55873 151 56024 55873 4788639 57423 151 57574 57423 3.08 F.D.D. TEST FOR SUBGRADE (In Nos) IS 2720 Part 28 1 test/500 sqm 59706 785 0 785 785 2664275 46679 147 46826 46679 2723981 47464 147 47611 47464 3.09 F.D.D. TEST FOR SHOULDER (In Nos) IS 2720 Part 28 1 test/500 sqm 0 0 0 0 0 239763 3875 18 3893 3875 239763 3875 18 3893 3875 4 GSB Design Mix (Including Stock Pile) Six Laning of Hosur - Krishnagiri Section of NH-7 from Km 33.130 to Km 93.000 (Length Km 59.87) in the State of Tamil Nadu under NHDP Phase V as BOT(Toll) on DBFOT Pattern IS tion /Method MONTHLY PROGRESS REPORT FOR THE MONTH OF APRIL - 2014 ( SEC - A & SEC - B) RPD/ID/MPR/T/81 in Current required cumulative cumulative done Current to 4.01 GRADATION Table 400-1,Gr1 0 0 0 0 158 5 163 158 158 5 163 158 4.02 ATTERBERGS LIMIT OF CONSISTENCY IS 2720 Part 5 0 0 0 0 154 0 154 154 154 0 154 154 4.03 MODIFIED PROCTOR IS 2720 Part 8 0 0 0 0 0 108211 17 0 17 17 108211 17 0 17 17 4.04 C.B.R. IS 2720 Part 16 0 0 0 0 11 0 11 11 11 0 11 11 4.05 10% FINES VALUE BS : 812 Part 3 0 0 0 0 34 1 35 34 34 1 35 34 4.06 WATER ABSORPTION IS 2386 Part 3 0 0 0 0 11 0 11 11 11 0 11 11 4.07 DELETERIOUS CONTENT IS 2720 Part 27 0 0 0 0 3 0 3 3 3 0 3 3

5 GSB (site sample) IS tion /Method in Current required cumulative cumulative done Current to 5.01 GRADATION Table 400-1,Gr1 1test/200 cum 6789 39 0 39 39 197300.27 1378 12 1390 1378 204089.27 1417 12 1429 1417 5.02 ATTERBERGS LIMIT OF CONSISTENCY IS 2720 Part 5 1test/200 cum 39 0 39 39 1373 0 1373 1373 1412 0 1412 1412 5.03 MODIFIED PROCTOR IS 2720 Part 8 As 2 0 2 2 31 0 31 31 33 0 33 33 5.04 C.B.R. IS 2720 Part 16 As 0 0 0 0 0 0 0 0 0 0 0 0 5.05 10% FINES VALUE BS : 812 Part 3 As 0 0 0 0 20 0 20 20 20 0 20 20 5.06 WATER ABSORPTION IS 2386 Part 3 As 0 0 0 0 0 0 0 0 0 0 0 0 5.07 DELETERIOUS CONTENT IS 2720 Part 27 As 0 0 0 0 2 0 2 2 2 0 2 2 5.08 F.D.D. TEST FOR G.S.B (In Nos) IS 2720 Part 28 1test/500 sqm 31449 340 0 340 340 721389.50 16260 122 16382 15785 752838.50 16600 122 16722 16125 6 WMM Mix Design 6.01 INDIVIDUAL GRADATION Table 400-11 0 0 0 0 79 0 79 79 0 79 6.02 COMBINED GRADATION Table 400-11 0 0 0 0 9 0 9 9 0 9 6.03 ATTERBERGS LIMIT OF CONSISTENCY IS 2720 Part 5 0 0 0 0 9 0 9 9 0 9 6.04 MODIFIED PROCTOR IS 2720 Part 8 0 0 0 0 8 0 8 8 0 8 6.05 E.I. & F.I. IS 2386 Part 1 0 0 0 0 7 0 7 7 0 7 6.06 A.I.V./L.A.A.V IS 2386 Part 4 0 0 0 0 7 0 7 7 0 7 6.07 WATER ABSORPTION IS 2386 Part 3 0 0 0 0 9 0 9 9 0 9 6.08 SOUNDNESS IS 2386 Part 5 0 0 0 0 1 0 1 1 0 1 7 WMM (Site sample) 7.01 GRADATION Table 400-11 1test/100 cum 10040 111 0 111 111 196709.22 3284 8 3292 3284 206749.22 3395 8 3403 3395 7.02 ATTERBERGS LIMIT OF CONSISTENCY IS 2720 Part 5 1test/100 cum 111 0 111 111 2981 0 2981 2981 3092 0 3092 3092 7.03 MODIFIED PROCTOR IS 2720 Part 8 As 2 0 2 2 31 0 31 31 33 0 33 33 7.04 E.I. & F.I. IS 2386 Part 1 1test/200 cum 83 0 83 83 2192 0 2192 2192 2275 0 2275 2275 7.05 A.I.V.or L.A.A.V IS 2386 Part 4 1test/200 cum 83 0 83 83 2203 0 2203 2203 2286 0 2286 2286 7.06 WATER ABSORPTION IS 2386 Part 3 As 0 0 0 0 0 0 0 0 0 0 0 0 7.07 SOUNDNESS IS 2386 Part 5 As 0 0 0 0 0 0 0 0 0 0 0 0 7.08 F.D.D. TEST FOR W.M.M. (In Nos) IS 2720 Part 28 1set/500sqm 47061 408 0 408 408 1528273 26767 67 26834 26767 1575334 27175 67 27242 27175 8 CONCRETE MATERIALS 8.01 GRADATION OF FINE AGGREGATES IS 383 1test/day 26 0 26 26 1028 0 1028 1028 1054 0 1054 1054 8.02 GRADATION OF AGGREGATE (20mm) IS 383 1test/day 26 0 26 26 1026 0 1026 1026 1052 0 1052 1052 8.03 GRADATION OF AGGREGATE (12.5 mm/10mm) IS 383 1test/day 26 0 26 26 1026 0 1026 1026 1052 0 1052 1052 8.04 COMBINED GRAD. OF AGGREGATE IS 383 1test/day 26 0 26 26 1022 0 1022 1022 1048 0 1048 1048 8.05 FI (20mm & 10.00mm) IS 2386 Part 1 As 5 0 5 5 457 0 457 457 462 0 462 462 8.06 A.I.V.or L.A.A.V IS 2386 Part 4 As 5 0 5 5 457 0 457 457 462 0 462 462 8.07 SPECIFIC GRAVITY IS 2386 Part 3 As 0 0 0 0 9 0 9 9 9 0 9 9 8.08 WATER ABSORPTION IS 2386 Part 3 As 0 0 0 0 9 0 9 9 9 0 9 9 8.09 PETROGRAPHIC EXAMINATION IS 2386 Part 8 As 0 0 0 0 3 0 3 3 3 0 3 3 8.10 ALKALI SILKA REACTIVITY IS 2386 Part 7 As 0 0 0 0 4 0 4 4 4 0 4 4

IS tion /Method 9 COMP.STRENGTH OF CUBES (SITE FOR STRUCTURES) (IN SETS) in Current required cumulative cumulative done Current to 9.01 M-15 (PCC) 328.5 41 0 41 41 10137.2 1221 0 1221 1221 10465.7 1262 0 1262 1262 9.02 28 Days 64 0 64 64 1968 0 1968 1968 2032 0 2032 2032 9.03 M-20 (Kerb) 510.0 33 0 33 33 1018.5 505 0 505 505 1528.5 538 0 538 538 9.04 28 Days 49 0 49 49 786 0 786 786 835 0 835 835 9.05 M-20 (PCC) 28.25 1 0 1 1 7232.3 690 0 690 690 7260.6 691 0 691 691 9.06 28 Days 1-5 cum=1 21 0 21 21 1263 0 1263 1263 1284 0 1284 1284 9.07 sample, 6 18 0 18 18 476 0 476 476 RCC M-25-15 cum=2 253.00 5066.1 5319.1 494 0 494 494 9.08 28 Days sample, 65 0 65 65 766 0 766 766 831 0 831 831 9.09 16-30cum= 21 0 21 21 1568 0 1568 1568 RCC M-30 3sample, 178.50 17030.4 17208.9 1589 0 1589 1589 9.10 28 Days 30-50 cum = 4 18 0 18 18 2596 2 2598 2596 2614 2 2616 2614 9.11 sample, 51cum 9 0 9 9 1524 0 1524 1524 1533 0 1533 1533 RCC M-35 and above 4+1 87.25 27418.7 27506.0 9.12 28 Days sample for every 27 0 27 27 3472 7 3479 3472 3499 7 3506 3499 9.13 M-35 Pile IS 516 50cum. 0.0 0 0 0 0 884.4 39 0 39 39 884.4 39 0 39 39 9.14 28 Days 0 0 0 2 91 0 91 91 91 0 91 91 9.15 RCC M-40 1698.75 167 0 167 167 13903.9 1505 0 1505 1505 15602.6 1672 0 1672 1672 9.16 28 Days 228 0 228 228 2585 12 2597 2585 2813 12 2825 2813 9.17 M 45 PSC 197.25 2 0 2 2 2600.7 98 0 98 98 2798.0 100 0 100 100 9.18 28 Days 11 0 11 11 226 4 230 226 237 4 241 237 9.19 M40 Paver Block 0 0 0 0 12 2 14 12 12 2 14 12 9.20 28 Days 6 0 6 6 15 2 17 15 21 2 23 21 9.21 0 0 0 0 0 0 0 0 0 0 0 0 PQC (M-40) Cube 150 m 3 = 2 Cubes 0.0 0.0 0.0 9.22 28 Days 0 0 0 0 0 0 0 0 0 0 0 0 9.23 PQC (M-40) 0 0 0 0 0 0 0 0 0 0 0 0 150 m 3 = 2 Beams 0.0 0.0 0.0 9.24 Flexure test 28 Days 0 0 0 0 0 0 0 0 0 0 0 0 9.25 D.L.C. 3 Cube/ 1000sqm 0.0 0 0 0 0 0.0 1 0 1 1 0.0 1 0 1 1 9.26 28 Days 0 0 0 0 0 0 0 0 0 0 0 0 9.27 Grouting 0 0 0 0 0 100 0 100 100 100 0 100 100 11 COMP.STRENGTH OF CUBES (FOR DESIGN MIX TRIALS-INSET) 11.01 M-15 0 0 0 0 51 0 51 51 51 0 51 51 11.02 28 Days 0 0 0 0 58 0 58 58 58 0 58 58 11.03 M-20 (Kerb) 0 0 0 0 6 0 6 6 6 0 6 6 11.04 28 Days 0 0 0 0 13 0 13 13 13 0 13 13 11.05 M-20 0 0 0 0 34 0 34 34 34 0 34 34 11.06 28 Days 0 0 0 0 80 0 80 80 80 0 80 80 11.07 M-25 0 0 0 0 34 0 34 34 34 0 34 34 11.08 28 Days 0 0 0 0 108 0 108 108 108 0 108 108 11.09 M-30 0 0 0 0 48 0 48 48 48 0 48 48 11.10 28 Days 0 0 0 0 119 0 119 119 119 0 119 119 11.11 0 0 0 0 57 0 57 57 57 0 57 57 M-35 11.12 28 Days 0 0 0 0 85 0 85 85 85 0 85 85 IS 516

IS tion /Method in Current required cumulative cumulative done Current to IS 516 11.13 M-35 Pile 0 0 0 0 7 0 7 7 7 0 7 7 11.14 28 Days 0 0 0 0 12 0 12 12 12 0 12 12 11.15 M-40 0 0 0 0 14 0 14 14 14 0 14 14 11.16 28 Days 0 0 0 0 22 0 22 22 22 0 22 22 11.17 M-45 PSC 0 0 0 0 19 0 19 19 19 0 19 19 11.18 28 Days 0 0 0 0 23 0 23 23 23 0 23 23 11.19 PQC (M-40) Cube 0 0 0 0 9 0 9 9 9 0 9 9 11.20 28 Days 3 0 3 3 12 0 12 12 15 0 15 15 11.21 PQC (M-40) 0 0 0 0 7 0 7 7 7 0 7 7 11.22 Flexure test 28 Days 0 0 0 0 23 0 23 23 23 0 23 23 11.23 D.L.C. 0 0 0 0 0 0 0 0 0 0 0 0 11.24 28 Days 0 0 0 0 0 0 0 0 0 0 0 0 12 12.01 CONSISTENCY IS 12269 4 0 4 4 158 0 158 158 162 0 162 162 12.02 INITIAL SETTING TIME IS 12269 4 0 4 4 157 0 157 157 161 0 161 161 12.03 FINAL SETTING TIME IS 12269 4 0 4 4 158 0 157 157 162 0 161 161 12.04 SOUNDNESS TEST IS 12269 4 0 4 4 145 0 145 145 149 0 149 149 12.05 FINENESS IS 12269 Every batch 0 0 0 0 67 0 67 67 67 0 67 67 12.06 COMPRESSIVE STRENGTH IS 12269 12.07 3 days 3 0 3 3 151 0 151 151 154 0 154 154 12.08 7 days 3 0 3 3 155 0 155 155 158 0 158 158 12.09 28 days 4 0 4 4 139 0 139 139 143 0 143 143 12.10 LIME SATURATION IS 12269 0 0 0 0 11 0 11 11 11 0 11 11 12.11 Al2O3/Fe2O3 IS 12269 Once per source 0 0 0 0 11 0 11 11 11 0 11 11 12.12 INSOLUBLE RESIDUE IS 12269 0 0 0 0 11 0 11 11 11 0 11 11 12.13 MgO (%) IS 12269 0 0 0 0 11 0 11 11 11 0 11 11 13 CEMENT (OPC 53 Grade) REINFORCEMENT STEEL (FE500D TATA, FE 500 / FE500D SAIL & JSW ) 13.01 DIAMETER OF BAR TESTED(mm) IS 1786 Every Lot 7 0 7 7 139 0 139 139 146 0 146 146 13.02 YIELD STRESS/0.2% PROOF STRESS (N/mm 2 ) IS 1786 7 0 7 7 139 0 139 139 146 0 146 146 13.03 TENSILE STRENGTH (N/mm 2 ) IS 1786 7 0 7 7 139 0 139 139 146 0 146 146 13.04 ELONGATION (%) IS 1786 7 0 7 7 139 0 139 139 146 0 146 146 13.05 MASS PER METER RUN (kg/m) IS 1786 Every Lot 7 0 7 7 139 0 139 139 146 0 146 146 13.06 BEND TEST IS 1786 7 0 7 7 139 0 139 139 146 0 146 146 13.07 REBEND TEST IS 1786 7 0 7 7 139 0 139 139 146 0 146 146 13.08 DIAMETER IS 1786 7 0 7 7 139 0 139 139 146 0 146 146 13.09 CARBON % IS 1786 7 0 7 7 139 0 139 139 146 0 146 146 13.10 SULPHAR % IS 1786 Every Lot 7 0 7 7 139 0 139 139 146 0 146 146 13.11 PHOSPHORAS % IS 1786 7 0 7 7 139 0 139 139 146 0 146 146 13.12 SULPHAR + PHOSPHORAS % IS 1786 7 0 7 7 139 0 139 139 146 0 146 146

14.A IS tion /Method in Current required cumulative cumulative done Current to 14.01 INTERNAL DIAMETER PF PIPE (mm) IS 458-2003 0 0 0 0 23 0 23 23 23 0 23 23 14.02 BARREL WALL THICKNESS (mm) IS 458-2003 0 0 0 0 23 0 23 23 23 0 23 23 14.03 LENGTH (m) IS 458-2003 0 0 0 0 23 0 23 23 23 0 23 23 14.04 THREE EDGE BEARING TEST IS 458-2003 Every Lot 0 0 0 0 0 228 16 0 16 16 228 16 0 16 16 14.05 HYDROSTATIC TEST IS 458-2003 0 0 0 0 1 0 1 1 1 0 1 1 14.06 WATER ABSORP. / PERMEABILITY TEST IS 458-2003 0 0 0 0 0 0 0 0 0 0 0 0 14.07 TOTAL WEIGHT OF REINFORCEMENT/m IS 458-2003 0 0 0 0 15 0 15 15 15 0 15 15 14.B HUME PIPE NP-4 HUME PIPE NP-3 14.01 INTERNAL DIAMETER PF PIPE (mm) IS 458-2003 0 0 0 0 324 0 324 324 324 0 324 324 14.02 BARREL WALL THICKNESS (mm) IS 458-2003 0 0 0 0 324 0 324 324 324 0 324 324 14.03 LENGTH (m) IS 458-2003 0 0 0 0 324 0 324 324 324 0 324 324 14.04 THREE EDGE BEARING TEST IS 458-2003 Every Lot 0 0 0 0 0 5063 73 0 73 73 5063 73 0 73 73 14.05 HYDROSTATIC TEST IS 458-2003 0 0 0 0 36 0 36 36 36 0 36 36 14.06 WATER ABSORP. / PERMEABILITY TEST IS 458-2003 0 0 0 0 8 0 8 8 8 0 8 8 14.07 TOTAL WEIGHT OF REINFORCEMENT/m IS 458-2003 0 0 0 0 19 0 19 19 19 0 19 19 15 Bitumen (VG-30) 15.01 Penetration IS:1203-1978 Every Lot 35 0 35 35 901 0 901 901 936 0 936 936 15.02 Softening IS:1205-1978 Every Lot 35 0 35 35 901 0 901 901 936 0 936 936 15.03 Absolute Viscosity at 60 o C (Poise) IS:1206-1978 Once in a week 638.76 17 0 17 17 15988.13 177 0 177 177 16626.89 194 0 194 194 15.04 Kinematic Viscosity at 135 o C (cst) IS:1206-1978 Every Lot 18 0 18 18 620 0 620 620 638 0 638 638 15.05 Specific Gravity IS:1203-1978 Once in a week 0 0 0 0 0 0 0 0 0 0 0 0 15.06 Third party tests 0 0 0 0 5 0 5 5 5 0 5 5 16 CRMB -60 16.01 Penetration IS:1203-1978 35 0 35 35 445 0 445 445 480 0 480 480 16.02 Softening IS:1205-1978 1 Test per Lot 35 0 35 35 447 0 447 447 482 0 482 482 16.03 Elastic Recovery IS:1208-1978 302.68 35 0 35 35 4454.544 440 0 440 440 4757.224 475 0 475 475 16.04 Separation IS:1205-1978 1 0 1 1 113 0 113 113 114 0 114 114 16.05 TFOT IS:9382-1979 Once in a week 1 0 1 1 32 0 32 32 33 0 33 33 16.06 Specific Gravity IS:1203-1978 0 0 0 0 2 0 2 2 2 0 2 2 19 Dense Bitumenous Macadam (Grade - II) 19.01 Bitumen Extraction Test 1 Test/400MT 38 0 38 38 1405 0 1405 1405 1443 0 1443 1443 19.02 Gradation of Ext. Aggregate Table 500-18, Grad.II 1 Test/400MT 38 0 38 38 1405 0 1405 1405 1443 0 1443 1443 19.03 Gradation of Dry Mix Aggregate Table 500-18, Grad.II 1 Test/400MT 38 0 38 38 1386 0 1386 1386 1424 0 1424 1424 19.04 FI+EI IS 2386 Part 1 1 Test/50M3 6236.435 55 0 55 55 249085.616 2458 0 2458 2458 255322.051 2513 0 2513 2513 19.05 AIV IS 2386 Part 4 1 Test/50M3 55 0 55 55 2460 0 2460 2460 2515 0 2515 2515 19.06 Marshall Density (In Set) ASTM D 2726 1 Test/400MT 38 0 38 38 1246 0 1246 1246 1284 0 1284 1284 19.07 Core Density ASTM D 2726 1 Test/250sqm 164 0 164 164 6891 0 6891 6891 7055 0 7055 7055 19.08 Water Sensitivity Test 0 0 0 0 1 0 1 1 1 0 1 1

20 Bituminous Concrete (Grade-II) IS tion /Method in Current required cumulative cumulative done Current to 20.01 Bitumen Extraction Test 1 Test/400MT 34 0 34 34 387 0 387 387 421 0 421 421 20.02 Gradation of Ext. Aggregate Table 500-10, Grad.I 1 Test/400MT 34 0 34 34 387 0 387 387 421 0 421 421 20.03 Gradation of Dry Mix Aggregate Table 500-10, Grad.I 1 Test/400MT 7531.11 29 0 29 29 96290.63 336 0 336 336 103821.74 365 0 365 365 20.04 FI+EI IS 2386 Part 1 1 Test/50M3 49 0 49 49 720 0 720 720 769 0 769 769 20.05 AIV IS 2386 Part 4 1 Test/50M3 49 0 49 49 720 0 720 720 769 0 769 769 20.06 Marshall Density (In Set) ASTM D 2726 1 Test/400MT 33 0 33 33 387 0 387 387 420 0 420 420 20.07 Core Density ASTM D 2726 1 Test/250sqm 223 0 223 223 3699 0 3699 3699 3922 0 3922 3922 22 Mastic Asphalt 22.01 Bitumen Extraction Test 1 Test / day 0 0 0 0 0 0 0 0 0 0 0 0 22.02 Individual Gradation of Coarse Agg. (13mm) Table-500-30 1 Test / day 0 0 0 0 5 0 5 5 5 0 5 5 22.03 Com. Gradation of Stone Dust & Filler (Lime) Table-500-31 1 Test / day 0 0 0 0 1 0 1 1 1 0 1 1 22.04 Aggregate Impact Value IS 2386 Part 4 1 Test / day 0 0 0 0 1 0 1 1 1 0 1 1 22.05 Casting of Moulds(set) IS 1195 2 Test/day 0 0 0 0 3 0 3 3 3 0 3 3 23 Bitumen Emulsion (SS-1) 23.01 Viscosity test IS:8887 Every Lot 3 0 3 3 46 0 46 46 49 0 49 49 23.02 Rate of Spread for Prime Coat Table-500-1 1 test / 500sqm 14356 37 0 37 37 465029.1 2276 0 2276 2276 479385.1 2313 0 2313 2313 24 Bitumen Emulsion (RS-1) 24.01 Viscosity test IS:8887 Every Lot 3 0 3 3 65 0 65 65 68 0 68 68 24.02 Rate of Spread for Tack Coat Table-500-2 1 test / 500sqm 75066 183 0 183 183 2011790.0 5352 0 5352 5352 2086856 5535 0 5535 5535 25 Elastomeric Bearing IRC-83 25.01 Axial Load Test 1Test per Lot 0 0 0 0 3 0 3 3 3 0 3 3 25.02 Ultimate Compressive Strength 1Test per Lot 0 0 0 0 3 0 3 3 3 0 3 3 25.03 Adhesion strength 1Test per Lot 0 0 0 0 3 0 3 3 3 0 3 3 25.04 Shear Modulus 1Test per Lot 0 0 0 0 3 0 3 3 3 0 3 3 26 Aggregate Stone Polish valuve 1 Test per Source 0 0 0 0 3 0 3 3 3 0 3 3 27 Admixture IS 9103 1Test per Lot 0 0 0 0 26 0 26 26 26 0 26 26 28 Water IS 3025 1 Test per Source 3 0 3 3 5 0 5 5 8 0 8 8 29 Lime IS 1514 1 Test per Source 0 0 0 0 3 0 3 3 3 0 3 3 30 Anti Stripping Agent IS 14982 1 Test per Source 1 0 1 1 7 0 7 7 8 0 8 8 31 Bitumen VG-30 IS 73-2006 3 0 3 3 16 0 16 16 19 0 19 19 32 Bitumen CRMB - 60 IRC SP 53-2002 0 0 0 0 3 0 3 3 3 0 3 3 33 CEMENT (OPC 53 Grade) 2 0 2 2 28 0 28 28 30 0 30 30 34 TATA HT STANDS 0 0 0 0 3 0 3 3 3 0 3 3 35 GEO GRID 0 0 0 0 22 0 22 22 22 0 22 22 36 PERMEABILITY TEST (GSB) IS 11209-1985 0 0 0 0 1 0 1 1 1 0 1 1 37 NITO BAND EPOXY 0 0 0 0 1 0 1 1 1 0 1 1 38 ROCK CORE SAMPLE 0 0 0 0 6 0 6 6 6 0 6 6 39 Thermoplastic paint 0 0 0 0 1 0 1 1 1 0 1 1 40 PAVER BLOCK 0 0 0 0 2 0 2 2 2 0 2 2