NEWS RELEASE New York AG March 28, 2016 Toronto FR Frankfurt FMV Mexico - AG. Announces Updated La Encantada NI Technical Report

Similar documents
FIRST MAJESTIC SILVER CORP. NEWS RELEASE

CROCODILE GOLD FILES TECHNICAL REPORTS FOR FOSTERVILLE AND COSMO GOLD MINES AND PROVIDES ANNUAL GENERAL MEETING INFORMATION

News Release. Infill Drilling Program

Highlights from the four holes announced in this news release include:

Minsud to recommence resource outline diamond drilling at the Chita Valley Cu- Au-Ag-Mo Project, San Juan, Argentina

MCEWEN MINING ANNOUNCES EXPLORATION UPDATE FOR EL GALLO 1, MEXICO

The new sulphide mineralization lies within a 1.4 kilometer long east-west trending

CROCODILE GOLD INTERSECTS 7.1 G/T AU OVER 4.5 METERS INCLUDING 11.2 G/T AU OVER 2.6 METERS AT THE UNION REEFS PROJECT, PROSPECT DEPOSIT

Fortuna Updates Reserves and Resources

CROCODILE GOLD INTERSECTS GRAMS PER TONNE GOLD OVER 2.05 METERS BELOW THE PROSPECT DEPOSIT AT UNION REEFS

EXPLORATION NEWS RELEASE MAGISTRAL DISTRICT: MORE GROWTH, MORE GOLD, MORE SILVER

Assay Results Highlights (as of November 16, 2017) representing approximately 4,500 metres ( m ) of drilling:

TROILUS GOLD CORP. INITIATES 30,000 METRE DRILL PROGRAM ON TROILUS PROPERTY

CROCODILE GOLD CONTINUES POSITIVE EXPLORATION RESULTS INTERSECTS HIGH GRADE GOLD AT UNION REEFS PROJECT

MANDALAY RESOURCES CORPORATION INCREASES MINERAL RESOURCES AND RESERVES AT ITS BJÖRKDAL GOLD MINE

Table 1: Mineral Resources at Costerfield, Inclusive of Mineral Reserves as of December 1, 2018 and December 31, 2017.

SilverCrest Expands Babicanora High Grade Footprint to 600 metres; New High Grade Vein Discoveries Highlight District Scale Potential

PRESS RELEASE NEW MINERAL RESOURCE UPDATE AT PRAIRIE CREEK MINE. Measured + Indicated and Inferred Resource Tonnages Increased

Probe Metals Intersects 3.2 g/t Gold Over 45.5 Metres At Val-d Or East

NEWS RELEASE. Mountain Province Diamonds Reports Additional Kimberlite Identified in Gahcho Kué Exploration Program

Red Pine Releases Inferred Resource Report Improves Grade and Tonnage for Wawa Gold Project

GOLDEN MINERALS DISCOVERS ADDITIONAL HIGH GRADE VEINS AT SANTA MARIA RESULTS UP TO 1.88 g/t Au and 648 g/t Ag

MINERA ALAMOS TO COMMENCE DRILLING AIMED AT EXPANDING AREAS OF DEFINED GOLD MINERALIZATION AT SANTANA/LOS VERDES PROPERTY, SONORA, MEXICO

Coro Reports a Significantly Increased Resource Estimate for the Marimaca Claim

This area in SE Sullivan Gulch was never mined by previous operators

NEWS RELEASE ORCA GOLD INDICATED AND INFERRED RESOURCES AT BLOCK 14 INCREASE BY 24% AND 48% RESPECTIVELY

NEWS RELEASE. Evrim announces initial drilling results at Cuale Gold Project in Mexico

North American Palladium Announces Positive Exploration Results from Lac des Iles Mine

SABINA GOLD &SILVER REPORTS COMPLETION OF DRILLING AT ECHO DEPOSIT, BACK RIVER, NUNAVUT.

Queenston Announces 112% Increase in Indicated Resource (to 1.5 M oz. gold) and 16% Increase in Inferred Resource (to 0.7 M oz. gold) at Upper Beaver

Probe Metals Continues to Expand Gold Zones At Val-d Or East

Probe Metals Continues to Intersect Significant Gold Mineralization in Expansion Drilling at Val-d Or East, including 4.1 g/t Gold Over 15.

V Sample from C.O.D vein 15 metres southwest of V

INV METALS ANNOUNCES DRILL RESULTS AT LOMA LARGA AND INITIAL PROSPECTING RESULTS ON NEW REGIONAL PROPERTIES

SALAZAR ANNOUNCES AN UPDATED RESOURCE REPORT OF 5.53 MT INDICATED AND 1.46 MT INFERRED AT ITS HIGH GRADE VMS EL DOMO DEPOSIT

June 4, 2015 News Release Valley of the Kings Underground Infill Drilling Underway

MANN SILVER-COBALT MINE. PORE: TSXV PowerOre.com

GOLD REACH (GRV) ANNOUNCES A 141% INCREASE IN INDICATED AND 91% INCREASE IN INFERRED RESOURCES AT SEEL

EXCELLON ANNOUNCES LA PLATOSA EXPLORATION RESULTS: HIGH GRADES CONTINUE TO EXTEND MANTO SULPHIDES DRILL HOLE ENCOUNTERS SOURCE ENVIRONMENT INDICATORS

KIRKLAND LAKE GOLD ANNOUNCES 120 METRE DOWN-PLUNGE EXTENSION OF SWAN ZONE

Goldplay President and CEO Marcio Fonseca commented

AVION GOLD DJAMBAYE II ZONE, TABAKOTO PROJECT, MALI, RETURNS HIGH GRADE INTERCEPTS OF 7.56 G/T Au OVER 7.0 METRES AND G/T Au OVER 3.

July 15, 2015 News Release Valley of the Kings Underground Infill Drilling Progresses

Bellhaven Announces Updated NI Mineral Resource for La Mina Project, Colombia

FALCO PACIFIC COMPLETES INITIAL MODEL FOR THE HORNE 5 GOLD/SILVER/ZINC/COPPER DEPOSIT

CAUTIONARY STATEMENT

BOREAL EXPANDS DISCOVERY ZONE OF HIGH-GRADE ZINC, SILVER AND LEAD MINERALIZATION AT GUMSBERG PROJECT IN SWEDEN

DRILLING FURTHER EXTENDS MINERALIZATION AT EXETER S CASPICHE GOLD-COPPER PORPHYRY PROJECT IN CHILE

PRESS RELEASE WESDOME PLANS AGGRESSIVE DRILLING AND DEVELOPMENT PROGRAM IN 2011

June 4, 2014 News Release Valley of the Kings Exploration Program Underway; Project Update

Fura Gems Inc. FURA ANNOUNCES MAIDEN MINERAL RESOURCE ESTIMATE FOR THE COSCUEZ EMERALD MINE, A FIRST FOR THE COLOMBIAN EMERALD SECTOR

October 8, 2015 News Release Brucejack Regional Drilling Intersects Over 8,000 Grams Per Tonne Gold

ASANKO GOLD ANNOUNCES ENCOURAGING INITIAL DRILL RESULTS FROM NEW EXPLORATION TARGET

A B C PAD A HIGHLIGHTS

PRESS RELEASE. DUBUISSON NORTH DRILLING CUTS g/t AU OVER 5.0 METRES NEW S50 EAST DISCOVERY, 3.39 g/t AU OVER 25.9 METRES

Suite 1800 Two Bentall Centre 555 Burrard Street Vancouver, BC V7X 1M9 Tel: (604) Tel: (888) April 8, 2018 SBB NR SBB TSX

Sabina Gold & Silver Reports 2018 Drilling has Commenced at Back River Gold Project

Altynalmas Gold s new upgraded and confirmed Bakyrchik East Mineral Resource Gold deposit boosts total gold resources at Kyzyl Project in Kazakhstan

(416) Highlights include:

Probe Metals Confirms Continuity of Gold Mineralization on its Val-d Or East Project And Increases 2017 Drill Program to 75,000 metres

A New Direction. Copper-Gold Deposit at Thor TSX.V:COL. August 11, May 2013

Press Release Thunder Bay: August 2, 2018

(TSXV: GPLY, OTCQB: GLYXF

Exploring for Precious and Base Metals in Sweden. Barsele Minerals Corp. (TSX.V: BME) June 2017

CANARC RESOURCE CORP Howe Street Vancouver, BC V6C 2T6. News Release

Altynalmas Gold announces a 50% increase in Indicated Mineral Resources at the Kyzyl Gold Project in Kazakhstan

IDM Mining s Underground Drilling Intersects g/t Au and g/t Ag over 6.80 Meters True Width at the Red Mountain Gold Project

- 2 - TABLE 1. INDICATED AND INFERRED GOLD AND SILVER RESOURCES. All Indicated

Sept 20, 2012 TSX Venture Exchange Tier 1 Trading Symbol: OK

Exploring for Precious and Base Metals in Sweden. Barsele Minerals Corp. (TSX.V: BME) December, 2016

August 20, 2018 SBB NR SBB TSX

Plateau Extends Falchani East Lithium Deposit Community Agreements Executed and Three Drill Rigs Active at Falchani West

MINERAL RESERVE AND MINERAL RESOURCE STATEMENT PROVEN AND PROBABLE MINERAL RESERVES

Comparison Between July 2012 Technical Report and December 2012 Mineral Resource Statement July 2012 December 2012 Percentage Difference.

Mineral reserves and resources

MEXICAN GOLD INTERSECTS 7.18 G/T GOLD EQUIVALENT (2.00 G/T AU, G/T AG, 3.05 % CU) OVER 14.0 METERS AT LAS MINAS DIKE CONTACT ZONES

For personal use only OZ MINERALS CARRAPATEENA COPPER GOLD PROJECT SOUTH AUSTRALIA 27 MARCH 2012

July Exploring for Canadian Gold in the Rainy River District of Ontario

TRENCHING AT LAS DOLORES EXTENDS STRIKE LENGTH TO OVER 1,000 METRES, INTERSECTING

NEWS RELEASE ORCA GOLD REPORTS CONTINUED SUCCESS AT GSS

GOLDPLAY ANNOUNCES FURTHER SAMPLING RESULTS FROM SAN MARCIAL HISTORICAL CORE; CONFIRMS OPEN PIT TARGET NEAR SURFACE WITH gpt AgEq.

Wallbridge Options 100% of the Beschefer Project near Fenelon Gold

Canadian Gold Miner Grab Sample Returns 29.5 Grams per tonne Gold from South Kirkland Project

OSISKO METALS INTERSECTS 10.49% ZINC+LEAD OVER METRES AND 12.15% ZINC+LEAD OVER METRES AT PINE POINT

Strategic Phase 2 Exploration Program Launched at Island Gold High-Grade Resource Potential Identified Laterally and at Depth

930 West 1 st Street, Suite 202, North Vancouver, BC V7P 3N4. Tel: (604) Tel:

2016 Annual Mineral Reserve and Resource Statement

Wallbridge Completes Successful Initial Drill Program at Beschefer

Fission s Initial Resource Totals at PLS: 79.6M lbs Indicated and 25.9M lbs Inferred

Probe Metals Intersects 1,122 g/t Gold Over 0.7 Metres in New Zone at Val-d Or East

Coeur Mining Provides Silvertip Exploration Update

EXPLORATION NEWS RELEASE

Cove Gold Project 2201 Discovery Update, May 2014

April Exploring for Canadian Gold in the Rainy River District of Ontario

CENTRAL ZONE CONTINUES TO EXPAND AT EL GALLO 1 MINE REGIONAL DRILLING DELIVERS HIGH SILVER GRADES OVER GOOD WIDTHS NEW RESOURCE UPDATE PENDING

Northern Dynasty Minerals Ltd.

Mineral reserves and resources

Blox, Inc. Announces New Drilling Target Defined at Mansounia Gold Project.

Sabina Announces More Positive Drill Results from 2012 Drilling at the Back River Gold Project, Nunavut

NEWS RELEASE FULLER PROPERTY CONTINUES TO DELIVER GOOD RESULTS 2.53 GRAMS PER TONNE GOLD OVER METRES

Transcription:

FIRST MAJESTIC SILVER CORP. Suite 1805 925 West Georgia Street Vancouver, B.C., Canada V6C 3L2 Telephone: (604) 688-3033 Fax: (604) 639-8873 Toll Free: 1-866-529-2807 Web site: www.firstmajestic.com; E-mail: info@firstmajestic.com NEWS RELEASE New York AG March 28, 2016 Toronto FR Frankfurt FMV Mexico - AG Announces Updated La Encantada NI 43-101 Technical Report FIRST MAJESTIC SILVER CORP. (the "Company" or First Majestic ) is pleased to provide an updated NI 43-101 Technical Report including Mineral Reserve and Resource estimates for the La Encantada Silver Mine located in the State of Coahuila, Mexico. First Majestic is reporting Mineral Resources inclusive of Mineral Reserves; readers are cautioned of this change since the Company had previously reported La Encantada s Mineral Resources exclusive of Mineral Reserves in its previous Technical Report. The silver price used for reserve estimates was reduced to $17.50/oz, or 12.5% lower compared to the previous estimate of $20.00/oz. All amounts are in U.S. dollars unless stated otherwise. REPORTED HIGHLIGHTS Proven and Probable Reserves totalling 6.7 million tonnes containing 30.6 million ounces of silver with an average silver grade of 143 g/t, including 1.5 million tonnes containing 10.1 million ounces of silver with an average silver grade of 214 g/t Measured and Indicated Resources of 6.1 million tonnes containing 31.4 million ounces of silver Inferred Resources totalling 0.9 million tonnes containing 7.2 million ounces of silver Life of Mine (LOM) of 8.5 years assuming tailings reprocessing with roaster, with a Net Present Value of $28.6 million based on a 5% discount rate. Increase of silver recoveries in tailings from 15% to 70% using roasting Additional exploration potential around Ojuelas deposit and skarn dome Keith Neumeyer, CEO and President, states: It s great to see that despite our production of over 23 million ounces of silver since our last 43-101 report seven years ago, reserve and resources have held up very well. The potential at La Encantada for discovery and development of additional ounces is high, however, as a result of reduced budgets in this low metal price environment, exploration and development are two of the areas of the business that have been most critically affected. As the environment improves in the coming years, the Company s intention is to increase investment in these areas in order to improve grades and Life of Mine. The La Encantada Silver Mine, located in northern Mexico in the State of Coahuila, consists of 22 mining concessions covering 4,076 hectares (10,072 acres). La Encantada is an underground silver mine comprised of two processing facilities, 180 houses for accommodation of employees, offices, warehouses, a recreational club, restaurants, guest houses, three schools, a church, a hospital, water wells and an airstrip. Since its prior Technical Report cut-off date of October 1, 2008, to the effective cut-off date of December 31, 2015 used for the Mineral Reserves and Resource estimates, First Majestic has led several exploration programs at La Encantada which has generated 89,426 metres of diamond drilling over a total of 591 holes. Underground drilling consisted of 68,371 metres in 469 holes in addition to 21,056 metres of surface drilling in 122 holes. The most important underground areas drilled over this period of time include the NE-trending

system of veins (Buenos Aires, Azul y Oro, 990, 990-2, El Regalo and San Francisco dike), the Milagros area (San Javier breccia, Milagros breccia and Milagros intrusion) and the recently discovered Ojuelas deposit and skarn dome. The updated Mineral Resource and Mineral Reserve estimates for La Encantada are shown below and are classified in accordance with the CIM Definition Standards for Mineral Resources and Mineral Reserves (May 2014). Proven and Probable Mineral Reserves, with an effective date of December 31, 2015 Proven (UG) Oxides 251 247-247 1,991 1,991 Probable (UG) Oxides 1,473 214-214 10,120 10,120 Probable (UG) Oxides - Flotation 809 147 2.35 196 3,817 5,093 Probable (Tailings) Oxides 4,138 110-110 14,633 14,633 Total Proven and Probable Oxides + Tailings 6,670 143 0.29 148 30,561 31,837 (1) Mineral Reserves have been classified in accordance with the CIM Definition Standards on Mineral Resources and Mineral Reserves, whose definitions are incorporated by reference into NI 43-101. (2) Metal prices considered for Vein System and other Minor Deposits, San Javier and Milagros Breccias and Tailings Deposit was $17.50 USD/oz Ag, and for Ojuelas were $18.00 USD/oz Ag, $0.90 USD/lb Pb. (3) Cut-off grade considered for the Veins System, other minor deposits and the San Javier and Milagros Breccias was 140 g/t Ag and is based on actual and estimated operating and sustaining costs. (4) Cut-off considered for Ojuelas was a NSR $53.91/t and is based on estimated operating cost, sustaining costs and the production schedule ran in PCBC. (5) Cut-off grade considered for Tailings Deposit No. 4 was 85 g/t Ag and is based on estimated operating cost and sustaining costs. (6) Silver metallurgical recovery used was 58% for the Veins System, other minor deposits and the San Javier and Milagros Breccias. (7) Metallurgical recovery used for Ojuelas was 67% for silver and 60% for lead. (8) Metallurgical recovery used for Tailings Deposit No. 4 was 53% for silver. (9) Metal payable used for the Veins System, other minor deposits, the San Javier and Milagros Breccias and Tailings Deposit No. 4 was 99.6%. (10) Metal payable used for Ojuelas was 95% for silver and 95% for lead. (11) Tonnage is expressed in thousands of tonnes, metal content is expressed in thousands of ounces. (12) Totals may not add up due to rounding. (13) Dilution for Veins System and other Minor deposits was estimated at 15%, dilution for San Javier and Milagros Breccias was estimated at 40%, dilution for Ojuelas was estimated at 20% and dilution for Tailing Deposit No. 4 was estimated at 3%. (14) Mineral Reserves estimates for the Ojuelas area, the San Javier Breccia, Milagros Breccia, Vein Systems areas were prepared under supervision of Ramon Mendoza Reyes, PEng, QP Mining for First Majestic. Measured and Indicated Mineral Resources, with an effective date of December 31, 2015 Measured (UG) Oxides 283 267-267 2,433 2,433 Indicated (UG) Oxides 854 299-299 8,198 8,198 Indicated (UG) Oxides - Flotation 734 246 4.07 325 5,795 7,662 Indicated (Tailings) Oxides 4,222 110-110 14,931 14,931 Total Measured and Indicated (UG) Oxides + Tailings 6,093 160 0.49 170 31,357 33,224 Inferred Mineral Resources, with an effective date of December 31, 2015 Inferred Ojuelas (UG) Oxides 35 292 0.78 305 325 340 Inferred other deposits (UG) Oxides 871 244-244 6,829 6,829 Inferred Total (UG) Oxides 905 246 0.03 246 7,154 7,169

(1) Mineral Resources have been classified in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum ( CIM ) Definition Standards on Mineral Resources and Mineral Reserves, whose definitions are incorporated by reference into National Instrument 43-101 Standards of Disclosure for Mineral Projects ( NI 43-101 ). (2) Metal prices considered for all deposits were $18.50 USD/oz Ag, with the exception of Ojuelas which used $18.00 USD/oz Ag and $0.95 USD/lb Pb. (3) Cut-off grade considered for the Veins System, other Minor Deposits, the San Javier and Milagros Breccias was 130 g/t Ag, cut-off grade for Ojuelas was 135 g/t Ag-Eq, and cutoff grade for Tailings Deposit No. 4 was 85 g/t Ag. Cut-off estimates are based on actual and budgeted operating and sustaining costs. (4) Metallurgical recovery of silver was assumed 58% for the Veins System, other Minor Deposits and the San Javier and Milagros Breccias. (5) Metallurgical recovery used for Ojuelas was 67% for silver and 60% for lead. (6) Metallurgical recovery of silver for Tailings Deposit No. 4 was assumed at 53%. (7) Metal payable used for the Veins System, other minor deposits, the San Javier and Milagros Breccias and Tailings Deposit No. 4 was 99.6%. (8) Metal payable used for Ojuelas was 95% for silver and 95% for lead. (9) Silver equivalent grade for Ojuelas is estimated as: Ag-Eq = Ag Grade + (Pb Grade x Pb Recovery x Pb Payable x Pb Price x 2204.62) / (Ag Recovery x Ag Payable x Ag Price / 31.1035). (10) Tonnage is expressed in thousands of tonnes, silver content in thousands of ounces and lead content in thousands of pounds. (11) Totals may not add up due to rounding. (12) Measured an Indicated Mineral Resources are reported inclusive or Mineral Reserves. (13) Mineral Resources estimates for the San Javier Breccia, Milagros Breccia, Vein Systems areas and Tailings Deposit No. 4 were prepared under supervision of Jesus M. Velador Beltran, QP Geology for First Majestic and estimates for the Ojuelas area were prepared under supervision of Peter Oshust, P.Geo. of Amec Foster Wheeler. The updated Mineral Reserve and Resource estimate consists of 30.6 million ounces of silver in the Proven and Probable Reserve category, representing a 9% increase primarily due to the upgrading of tailings to reserves, offset by annual depletion and the lower silver price assumption; 31.4 million ounces of silver in Measured and Indicated Resources, representing a decrease of 15% from the previous estimate; plus 7.2 million silver ounces in Inferred Resources representing a 23% decrease from the previous estimate due to the upgrading of the tailings resource to reserves. There is further upside potential for total ounces assuming exploration success and conversion of the Inferred Resource to Measured and Indicated Resources or Proven and Probable Reserves through additional drilling and development. IMPROVING RECOVERIES WITH ROASTING Since 2012, the Company has evaluated numerous technologies and milling procedures to improve metallurgical recoveries of the existing aboveground tailings. The Company began testing ore samples using an onsite 50 tpd roasting furnace in early 2013. Initial test results showed substantial improvements in silver recoveries, increasing from approximately 15% to 70%. However, due to the high cost of diesel used as the energy source for roasting, the Company deemed the project uneconomical and continued testing alternative heating sources. In 2015, an instrumented 25 tpd roasting pilot plant was built offsite to test the use of propane and results confirmed the improvement in silver recoveries, in addition, leaching times were reduced from 72 hours to less than 36 hours. The Company also began testing the use of coal, routinely used as a heating source in roasters in the cement industry in Mexico, as a source of low cost energy. Preliminary results indicate that the roasting project using coal is economical at current silver prices, allowing the Company to proceed with additional operational and economic studies as well as full-scale plant design. The estimated capital investment to construct a roasting plant and its satellite facilities would be approximately $8.8 million and take 12 months to bring into production. The Company is expected to make a construction decision, pending the results of the additional studies, by the end of 2016. In addition to improving recoveries, there are a number of cost reduction initiatives being implemented at La Encantada to help offset the decrease in revenues due to lower silver prices including the migration of fuel for power generation, from diesel to liquid natural gas (LNG), optimization of the development layouts, and renegotiation of development and haulage contracts with suppliers. The newly constructed LNG facility has now passed its testing phase and is expected to be fully operational in April. The facility will supply 100% of the power requirement to the operation and the existing diesel generators will be put on care and maintenance. The Company expects to realize a 20% reduction in power costs as a result of the switch to LNG. Furthermore, the Company anticipates utilizing the same LNG technology at the Santa Elena mine in order to further reduce operating costs. LIFE OF MINE

The 8.5 year life of mine (LOM) plan is based on an annual processing rate of 660,000 tonnes of plant feed consisting of mineralized material from underground reserves in the first four years and an annual rate of 660,000 tonnes of tailings to be roasted and reprocessed beginning in 2018. The estimated LOM represents a Net Present Value (NPV) of $28.6 million based on a 5% discount rate. There are several aspects that could increase the LOM while maintaining current production levels, including the conversion of Inferred Resources into Proven and Probable Reserves (historic conversion factor has been approximately 50%), and production from areas not included in reserves. The La Encantada plant has a crushing and grinding capacity in excess of 990,000 tonnes per year and the operation has historically mined and processed at these higher production levels by including ore from outside of known reserves and resources which demonstrates not only the Company s ability to identify and process undefined reserves but the exploration potential of this prolific region of Coahuila. Over the past three years, approximately 60% of the plant feed came from reserves with the difference coming from aboveground screened stockpiles and ore from undefined/unknown underground resources. In addition, exploration around the Ojuelas deposit and the skarn dome continue to show great potential to increase the volume and confidence classification of the resource. RECOMMENDATIONS The Company s Qualified Persons are of the opinion that the La Encantada property has the potential for hosting additional resources at the skarn dome south of the Ojuelas deposit and around the known vein systems, San Javier and Milagros breccias. Additional step out drilling is recommended to be completed to explore the potential of massive sulphide replacements between the skarn dome and Ojuelas deposit. A previous drill intercept from hole EC-05, which ended while still encountering mineralization approximately 500 metres southwest of the Ojuelas deposit, intersected 1.7 metres averaging 244 g/t silver highlighting the potential to build additional resources in this prolific area. Mr. Ramon Mendoza Reyes, Vice President Technical Services for First Majestic, is a "qualified person" as such term is defined under National Instrument 43-101, and has reviewed and approved the technical information disclosed in this news release. First Majestic is a mining company focused on silver production in México and is aggressively pursuing the development of its existing mineral property assets and the pursuit through acquisition of additional mineral assets which contribute to the Company achieving its corporate growth objectives. FOR FURTHER INFORMATION contact info@firstmajestic.com, visit our website at www.firstmajestic.com or call our toll free number 1.866.529.2807. FIRST MAJESTIC SILVER CORP. signed Keith Neumeyer, President & CEO SPECIAL NOTE REGARDING FORWARD-LOOKING INFORMATION This news release includes certain "Forward-Looking Statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. When used in this news release, the words anticipate, believe, estimate, expect, target, plan, forecast, may, schedule and similar words or expressions, identify forward-looking statements or information. These forward-looking statements or information relate to, among other things: the price of silver and other metals; the accuracy of mineral reserve and resource estimates and estimates of future production and costs of production at our properties; estimated production rates for silver and other payable metals produced by us, the estimated cost of development of our development projects; the effects of laws, regulations and government policies on our operations, including, without limitation, the laws in Mexico which currently have significant restrictions related to mining; obtaining or maintaining necessary permits, licences and approvals from government authorities; and continued access to necessary infrastructure, including, without limitation, access to power, land, water and roads to carry on activities as planned. These statements reflect the Company s current views with respect to future events and are necessarily based upon a number of assumptions and estimates that, while considered reasonable by the Company, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially

different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements or information and the Company has made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: fluctuations in the spot and forward price of silver, gold, base metals or certain other commodities (such as natural gas, fuel oil and electricity); fluctuations in the currency markets (such as the Canadian dollar and Mexican peso versus the U.S. dollar); changes in national and local government, legislation, taxation, controls, regulations and political or economic developments in Canada, Mexico; operating or technical difficulties in connection with mining or development activities; risks and hazards associated with the business of mineral exploration, development and mining (including environmental hazards, industrial accidents, unusual or unexpected formations, pressures, cave-ins and flooding); risks relating to the credit worthiness or financial condition of suppliers, refiners and other parties with whom the Company does business; inability to obtain adequate insurance to cover risks and hazards; and the presence of laws and regulations that may impose restrictions on mining, including those currently enacted in Mexico; employee relations; relationships with and claims by local communities and indigenous populations; availability and increasing costs associated with mining inputs and labour; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses, permits and approvals from government authorities; diminishing quantities or grades of mineral reserves as properties are mined; the Company s title to properties; and the factors identified under the caption Risk Factors in the Company s Annual Information Form, under the caption Risks Relating to First Majestic's Business. Investors are cautioned against attributing undue certainty to forward-looking statements or information. Although the Company has attempted to identify important factors that could cause actual results to differ materially, there may be other factors that cause results not to be anticipated, estimated or intended. The Company does not intend, and does not assume any obligation, to update these forward-looking statements or information to reflect changes in assumptions or changes in circumstances or any other events affecting such statements or information, other than as required by applicable law.