New Transmission Options Case Study Superconductor Cables. Transmission Policy Institute Sheraton Downtown Denver, Colorado April 20-21, 2011

Similar documents
Status and Future Direction of HTS Power Application in KEPCO

Hydra Fault Current Limiting HTS Cable to be Installed in the Consolidated Edison Grid

High-Performance 2G HTS Wire for an Efficient and Reliable Electricity Supply

Grid Issues and Challenges Addressed by High Temperature Superconductor (HTS) Technology

Status and Progress of a Fault Current Limiting HTS Cable To Be Installed In The Consolidated Edison Grid

HTS Roadmap for Electric Power Systems October 2015

EPRI Technology Watch 2010 Superconducting Cables Fault Current Limiters

URD Cable Fault Prediction Model

Superconducting cables Development status at Ultera

Superconductivity project at IASS

Superconducting Fault Current Limiters

Cryogenic and Electrical Test Results of a 30 M HTS Power Cable

Some socio-economic aspects of long-distance energy transport by superconducting power lines with a focus on MgB 2

Physics 5K Lecture 7 Friday May 18, Superconductivity. Joel Primack Physics Department UCSC. Friday, May 18, 12

R&D of 22.9kV/50MVA HTS Transmission Power Cable in Korea

Combined HTS Cable and Fault Current Limiter Project in Germany

Superconducting Fault Current Limiters

Applications Using SuperPower 2G HTS Conductor

2G HTS Wire Status in the USA

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc.

The Present Status and Prospective of the power transmission by Superconductors in China

Current Lead Optimization for Cryogenic Operation at Intermediate Temperatures. L. Bromberg, P.C. Michael, J.V. Minervini and C.

Railway Research. Study of Superconducting Fault Current Limiter Device in a AC Railway System. 1. Introduction. International Journal of

HTS Cable Integration into Rural Networks with Renewable Energy Resources

Conductor Requirements for Superconducting Fault Current Limiters

KIT-ENERGY CENTRE. KIT The research University in the Helmholtz Association

Renewables and the Smart Grid. Trip Doggett President & CEO Electric Reliability Council of Texas

Transforming the Grid with Superconductivity

Keywords: Superconducting Fault Current Limiter (SFCL), Resistive Type SFCL, MATLAB/SIMULINK. Introductions A rapid growth in the power generation

Electric Distribution Storm Hardening Initiatives. Paul V. Stergiou Distribution Engineering October 14 th, 2015

Communique. International Superconductivity Industry Summit (ISIS)-20 Gonjiam Resort, Korea October 2011

INSTALLATION AND COMMISSIONING OF TRIAX HTS CABLE

Superconducting Cables

The influence of thermal properties on power transmission characteristics of HVDC cables a factor analysis

Superconducting Fault Current Limiter in DC Systems with MLI Fed to IM

Latest Status of High Temperature Superconducting Cable Projects

Fault Current Limiters

Two examples of efficient superconducting cable applications

Feasibility of HTS DC Cables on Board a Ship

HTS Roadmap for the Electric Power Sector Brian Marchionini

Study Overview. the nassau hub study. The Nassau Hub

Analytical and Experimental Studies on the Hybrid Fault Current Limiter Employing Asymmetric Non-Inductive Coil and Fast Switch

Worked Example for the Calculation of Earthing Current and Electric Shock Hazard Potential Difference in a Rod and Grid Earthing System

3/31/2006 9:36:15 AM RECENT DEVELOPMENT SUPERCONDUCTIVITY: THE FUTURE OF POWER TRANSMISSION

Development of 2G HTS Wire for Demanding Electric Power Applications

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK

Experimental Study on the Cyclic Ampacity and Its Factor of 10 kv XLPE Cable

Mitigation of Distributed Generation Impact on Protective Devices in a Distribution Network by Superconducting Fault Current Limiter *

RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER

A short overview of superconductivity Dr. Jean Botti EADS Chief Technical Officer Tunisia, May Slide 1

Studies on hyper scaling dielectric loss of grading capacitors of 500kv breakers

Drivetrains. Direct Drive Generators High Temperature Superconductor Based Machines. Daniel McGahn Senior Vice President

Short-circuit protection to a fault: Superconducting fault current limiters

Wind power and management of the electric system. EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015

TRANSIENTS POWER SYSTEM. Theory and Applications TERUO OHNO AKIH1RO AMETANI NAOTO NAGAOKA YOSHIHIRO BABA. CRC Press. Taylor & Francis Croup

Resiliency of Power Grids After Earthquakes

Design and Application of Superconducting Fault Current Limiter in A Multi-terminal HVDC System

Alectra Utilities List of Station Capacity

Fault Current Limiter Based on Coated Conductor

TRANSMISSION LINES. All aluminum alloy conductor (AAAC) Aluminum conductor alloy reinforced (ACAR)

TRANSFORMERS. Pascal Tixador. Grenoble INP - Institut Néel / G2Elab. Introduction

Materials in high-temperature superconducting cables Dag Willén nkt cables

RECENT DEVELOPMENT OF HIGH-TEMPERATURE SUPERCONDUCTING (HTS) CABLE IN SUMITOMO ELECTRIC INDUSTRIES, LTD.

2 nd Generation High-Temperature Superconducting Wires for Fault Current Limiter Applications

ECEN 460 Exam 1 Fall 2018

International Studies about the Grid Integration of Wind Generation

VHD Daily Totals. Population 14.5% change. VMT Daily Totals Suffolk 24-hour VMT. 49.3% change. 14.4% change VMT

Experiences with Superconducting Cable & Fault Current Limiter in a German City Center Mark Stemmle

The 3V Approach. Transforming the Urban Space through Transit Oriented Development. Gerald Ollivier Transport Cluster Leader World Bank Hub Singapore

TYPE TESTING OF A 13.2 KV, 69 MVA TRIAX HTS CABLE

Role of Synchronized Measurements In Operation of Smart Grids

Tutorial 2: Modelling Transmission

Commissioning testing of a 1 MVA Superconducting transformer featuring 2G HTS Roebel cable

Progress in Scale-up of 2G HTS Wire at SuperPower Part III

Using MRI devices for the energy storage purposes

SuperPower s path to leadership in clean, green and smart energy technology

International Superconductivity Industry Summit ISIS -14. Tsukuba, Japan. October 27-28, Joint Communique

THE SPATIAL DATA WAREHOUSE OF SEOUL

DC Circuits I. Physics 2415 Lecture 12. Michael Fowler, UVa

4-3-1 Earthquake and Tsunami Countermeasures of Tokyo s

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Milestone Report. Cryogenic Scenarios for the Cold Powering System

Selecting the current rating for equipment

Compact Systems for future HVDC applications Dr. Denis Imamovic

Applications of GIS in Electrical Power System

Critical parameters of

New Generation of DC Power Transmission Technology Using HTS Cables

Fault Calculation Methods

THIRD GENERATION SYSTEM PROTECTION SCHEME PROJECT FOR ZEYA HYDRO POWER PLANT

Russian Development Program on HTS Power Cables

1. Explain the various methods of methods of grounding. In power system, grounding or earthing means connecting frame of electrical equipment (non-cur

Innovative fabrication method of superconducting magnets using high T c superconductors with joints

Transient Analysis of a 150 kv Fault Current Limiting High Temperature Superconducting Cable

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur

5. Positive charges one another.

About the Author: Abstract:

Future long distance electricity transmission using HTS HVDC cables

Development of 2 MVA Class Superconducting Fault Current Limiting Transformer (SFCLT) with YBCO Coated Conductors

Enterprise GIS to Support ADMS ESRI GeoConx EGUG 2016 Parag Parikh

VALIDATION OF AN INTEGRATED METHODOLOGY FOR DESIGN OF GROUNDING SYSTEMS THROUGH FIELD MEASUREMENTS

OPALCO Outage Analysis. December 2017 Board Meeting

Transcription:

New Transmission Options Case Study Superconductor Cables Transmission Policy Institute Sheraton Downtown Denver, Colorado April 20-21, 2011 1

What is a Superconductor? Superconductors 100/25 Superconductors are materials that exhibit unique electrical characteristics: - Little to no resistance to the flow of electricity - Ability to carry hundreds of times as much electrical current as copper - Repel magnetic fields Current Capacity Equivalents These characteristics require: - Cooling below a critical temperature - Current levels below a critical current Above these critical levels the material quenches, and current must flow elsewhere New, ceramic high temperature superconductor (HTS) material discovered in 1986 - Requires less cooling; cost effective liquid nitrogen may be used Development of HTS has enabled utility commercial applications

Superconductor Cable s ELECTRICAL Characteristics Very high power transfer capability compared to conventional cables solves many siting problems Very low impedance reduces loading on parallel lines and equipment Minimal magnetic field and elimination of heat simplifies placement concerns, minimizes right-of-way, and is easy on the environment Optional HTS cables with fault current management capabilities eliminate need to upgrade existing equipment HTS Cables offer unique capabilities

Superconductor Cables Driving to Commercial Adoption 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 US/EPRI 115kV (50m) US/Southwire 12.5kV (30m) DENMARK 36kV (30m) China/SGCC 110kV (1km) JAPAN 66kV (30M) Korea/KEPCO 154kV (1km) US/DTE 24kV (120m) Korea 22.9kV (3km) KOREA 22.9kV (30m) CHINA 35kV (30m) JAPAN 77kV (500m) CHINA 10.5kV (75m) KOREA 22.9kV (100m) US/Nat. Grid 34.5kV (400m) US/AEP 13.8 kv (200m) US/LIPA Phase I 138kV (600m) MEXICO 15kV (30m) SPAIN 10kV (30m) KOREA 22.9kV (100m) RUSSIA 35 kv (30m) CHINA 110 kv (30m) JAPAN 66kV (250m) US/ConEd 13.8 kv (220m) US/LIPA Phase II 138 kv (600m) SPAIN 20kV (30m) KOREA/KEPCO 22.9kV (500m) KOREA/KEPCO 154kV (100m) SHANGHAI PROJECT (SECRI) US/TresAmigas-200kVdc(10km) Powered by AMSC wire Powered by other wire Undecided Project list updated 4-2010 Dozens of successful HTS cable projects globally in service or in process 4

Key HTS Cable PHYSICAL Characteristics Familiar Physical Characteristics Looks like conventional cable May be spliced May be placed in ducts or direct buried Must be cooled with liquid nitrogen No thermal constraints for placement Unique Electrical Characteristics Very high power transfer capability Very low impedance Minimal magnetic field Elimination of heat HTS cables with fault current management HTS Cables offer unique capabilities in a familiar package

Power Transfer Equivalency of Superconductor Cables 345kV 230kV 138kV 69kV 34.5kV 13.8kV XLPE HTS XLPE XLPE HTS XLPE HTS XLPE XLPE HTS 0 200 400 600 800 1000 Power Transfer Capability - 3-phase MVA Same Voltage, More Power - Greatly increased power transfer capacity at any voltage level Same Power, Lower Voltage - New MV versus HV Siting Opportunity MV Transmission Ideal for NIMBY & ROW sparse environments * No XLPE cable de-rating factors applied. Superconductor rating based on conventional 4000A breaker rating Superconductor cables provide transmission-level power transfer at medium voltage

Simplifying Transmission Siting One MV HTS Cable can replace: Many conventional underground circuits Overhead transmission line Photo courtesy Consolidated Edison HTS Cables Offer New Options to Siting Power Lines

Background Holbrook Superconductor

LIPA 3 LIPA is a NYS Authority established in 1998 as the primary electric service provider for LI 1207 sq. mi. (roughly 100 miles by 12 miles) Nassau, Suffolk and the Rockaway Peninsula Population of about 3 million 1.1 million residential customers 100,000 commercial customers Since 1998, 5.7% population growth (172,000 more people) $2.0 billion invested in system upgrades and improvements LIPA owns the assets All T&D operations and most IS systems are outsourced

LIPA Transmission System

Why was LIPA Interested in a Superconductor Cable? LIPA Long Term Needs Must meet increasing power demands in existing ROWs Load continues to increase LIPA expects 1200 MW of new load by 2020 - Major transmission reinforcements will be required Project Provides Potential Tool to Meet LIPA s Long Term Needs ROW Congestion - HTS Cables provide increased power transfer capability within existing ROWs (2-5 times the capacity in the same space) Overhead Permitting Problems Potential cost savings compared to upgrading to 345 kv transmission system Site Specific East / West transfer capability increase required by upcoming power insertions

Land and Route Port Jefferson Shoreham Wading River Miller Place Terryville Centereach Superconductor Holbrook Substation

Superconductor Example: 138 kv, 575MW Capacity 200 ft ROW Self contained thermal envelope No thermal de-rating Minimal magnetic field No parallel line derating Lower Impedance Longer practical distance 4 ft ROW Superconductor Cables Simplify Placement and Offer New Options to Siting Lines

Long Island Power Authority Cable System Energized in April 2008 World s first HTS transmission voltage cable system in the grid Longest, most powerful superconductor cable in the world Able to carry 574 MW of power in a four-foot-wide right of way Landmark cable installation proving high power, transmission level applications Over 15 years of HTS Cable Experience 16

Next Step?? Holbrook Superconductor

Proposed Future Project Required to Support East/West Power Flows Extend 138kV superconductor cable to meet future transmission requirements Located between Holbrook and Central Islip substations (6.2 miles) Originally planned for summer 2012 delayed due to lower load growth ALL underground; eliminates need for conventional overhead-underground hybrid

Present Status and Future Direction of HTS Power Application in KEPCO Y o u n g - J i n W O N P o w e r G r i d P l a n n i n g T e a m, K E P C O 19

Ⅱ. Why? HTS System in KEPCO? High cost for Civil works Difficulty of excavating roads for const n conduit or culvert NIMBY for the construction of new substations To cope with continuous increasing of fault current Countermeasures to renew the aged power cables Large Capacity & Low loss + Eco-friendly HTS Cable & SFCL 8

Supplying the huge buildings with electric power by HTS cables Replacing 22.9kV conventional cables(2~3lines) with the superconducting cables using the existing conduit or culverts without additional civil works 22.9 kv Superconducting Cables to replace 154 kv conventional cables 154 kv S/S in the suburbs SFCL Downtown Area 22.9 kv SW/S Circuit Breaker (Normal open) ~ SFCL 22.9 kv SW/S 22.9 kv Superconducting Cables to replace 22.9kV conventional cables SFCL Superconducting Transformers 22.9 kv SW/S

Superconducting Power System (SPS) applying distributed switching stations for metropolitan areas Apply superconducting power devices (cables, transformers, FCLs) to real power system 154kV transmission power system 22.9kV superconducting power system Replace 154kV substations in downtown with 22.9kV underground switching stations Replace 154kV conventional cables with 22.9kV superconducting cables Bulk power transfer by superconducting cables and transformers & Fault current reduction by SFCL 154kV conventional cables 154kV S/S 154kV S/S Suburb 154kV S/S Downtow n 154kV S/S Skip substations Reduce construction costs Environmentfriendly 154kV conventional cables 154kV S/S 22.9kV SW/S 22.9kV SW/S Suburb 22.9kV SW/S 22.9kV SW/S Downtow n 154kV S/S Avoid civil petitions 22.9kV SW/S 22.9kV SW/S 22.9 kv Superconducting cables

One of solutions for the site problem No substations & Compact size Easy to find a site for power facilities in downtown Underground switching stations Make a park on the switching stations Economic benefits Reduction of cost for buying land The site for 22.9kV switching stations is less than 30%, compared to 154kV substations. No additional construction cost We can use established underground facilities such as existing electric power conduit pipes. Environmental and social benefits Environment-friendly Avoid the trend of NIMBY No oil for cooling the system Free of the explosion danger (Superconducting transformer) No additional construction Reduce the construction cost and ease traffic congestion High efficiency and loss of superconductor Save energy and reduce CO2 emission

DC Superconductor cables for long distance transmission 25

Superconductor Advantages with DC Power When carrying DC current, superconductors themselves are perfectly lossless - Regardless of length - Regardless of power rating Benefits - No power limitations based on current-based losses - Allows lower voltage, higher current transmission - Allows underground construction Superconductors open the door for a true underground transmission system

Superconductor PowerPipes Superconductor PowerPipes combine: Superconductor cables DC power transmission The result: A high capacity electric transmission pipeline that is: Underground and easy to site Highly efficient Offers greater security than other technologies Provides for multiple power on- and off-ramps

Today s Key Energy Challenge: Carrying 100 s of Gigawatts of Green Power to Market Many Issues Multiple Sources Multiple Destinations Cost Allocation Siting Transmission Across Interconnections Losses The challenge of moving renewable power long distances needs another option 28

Power Transfer Capability, GW % Losses (Est.) AC Overhead Transmission Higher power and longer distances require higher 5GW of Renewable Energy Transmission voltages Losses Limited power flow control Power transmission characteristics Public opposition Dominant form of transmission, but many challenges 16% 14% 12% 10% 8% 6% 4% 2% 0% Miles 100 200 300 400 500 600 700 800 900 1000 5.0 4.0 3.0 2.0 1.0 Range of Losses for Various 765kV Overhead Line Designs Transfer Capability Versus Distance of a 765 kv Overhead Line 0.0 0 200 400 600 800 1000 Line Length in Miles 29 Courtesy Argonne National Lab

Existing Transmission Options TRANSMISSION LINE POWER AND DISTANCE SUITABLE TRANSMISSION SOLUTIONS Overhead Solutions Underground Solutions Point-to- Point HVDC Multiterminal VSC HVDC Point-to- Point HVDC Multiterminal VSC HVDC REQUIREMENTS AC AC Low Power (<1GW) Short (<100 mile) lines Low Power (<1GW) Moderate (100-400 mile) lines Low Power (<1GW) Long (>400 mile) lines Moderate Power (1-5GW) Short (<100 mile) lines Moderate Power (1-5GW) Moderate (100-400 mile) lines Moderate Power (1-5GW) Long (>400 mile) lines High Power (>5GW) Short (<100 mile) lines High Power (>5GW) Moderate (100-400 mile) lines High Power (>5GW) Long (>400 mile) lines Multi-Terminal Superconductor Pipeline No suitable solution for high power, long distance, underground transmission 30

HVDC Superconductor Cables TRANSMISSION LINE POWER AND DISTANCE SUITABLE TRANSMISSION SOLUTIONS Overhead Solutions Underground Solutions Point-to- Point HVDC Multiterminal VSC HVDC Point-to- Point HVDC Multiterminal VSC HVDC Multi-Terminal Superconductor Pipeline REQUIREMENTS AC AC Low Power (<1GW) Short (<100 mile) lines Low Power (<1GW) Moderate (100-400 mile) lines Low Power (<1GW) Long (>400 mile) lines Moderate Power (1-5GW) Short (<100 mile) lines Moderate Power (1-5GW) Moderate (100-400 mile) lines Moderate Power (1-5GW) Long (>400 mile) lines High Power (>5GW) Short (<100 mile) lines High Power (>5GW) Moderate (100-400 mile) lines High Power (>5GW) Long (>400 mile) lines Fit of DC superconductor cables for underground, long distance, high power, multi-terminal transmission 31

Losses (% of 5GW) Operational Opportunities for DC Superconductor Cables: ELECTRICAL EFFICIENCY 14% 12% 10% 8% 6% 4% 2% 765kV OH, 2 Lines 765kV OH, 3 Lines +/-300kV Underground DC [6] Overhead +/-800kV DC [7] +/-200kV Superconductor Pipeline Optimized 765kV, 3 Lines [8] Losses for 5GW Transmission 0% 0 100 200 300 400 500 600 700 800 900 1000 Length (miles) Converter losses 2%, cooling losses 22kW/km Overall losses 2.75% for 5GW @1600km (2.4% for 10GW) Loss advantage increases with distance and MW rating 32

Rights of Way Already Exist for Superconductor Electricity Pipelines 33

Cost Analysis 5GW, 1000 mile Superconductor DC Cable System - US$8.8 Million/mile two pole cable - Costs include DC terminals, refrigeration, installation - Doubling capacity to 10GW increases cable cost by only 50% (extra converters not included) Cost Competitive with EHV AC - US$2.5 - $5.5 Million/mile - 2 to 3 lines needed for same capacity Long distance, high power superconductor DC cables are cost competitive with EHV AC lines 34

Advantages of DC Superconductor Cables Highest power capacity Highest efficiency (lowest power losses) of any transmission technology Ideal for very long distances Capable of transferring power across the three U.S. interconnections Able to accept power from multiple distributed sources, and precisely deliver power to multiple distributed destinations Underground construction with minimum right of way requirement Simplified cost allocation due to precise controllability of DC terminals Minimizes interaction with existing AC grid, reducing costs and increasing operational flexibility Cost competitive DC Superconductor PowerPipes are uniquely and ideally suited to move renewable energy to distant load centers

Tres Amigas SuperStation Project Western Interconnection Eastern Interconnection Texas Interconnection Unique 3-way DC project to link the three U.S. Interconnections

Tres Amigas Project to Use Superconductor Electricity Pipeline 37

Summary AC and DC superconductor cables offer new option for high power, underground, transmission of electric power Transmission Grid of the Future 38