LHC Status and CERN s future plans. Lyn Evans

Similar documents
International Scientific Spring 2010, March 1-6, 1. R. Garoby. slhc

UPGRADE ISSUES FOR THE CERN ACCELERATOR COMPLEX

LHC Commissioning in 2008

slhc-project-report-0034

Marcos Dracos IPHC-IN2P3/CNRS Strasbourg. 2 December 2008 M. Dracos, BENE 1

LIS section meeting. PS2 design status. Y. Papaphilippou. April 30 th, 2007

Current and Future Developments in Accelerator Facilities. Jordan Nash, Imperial College London

LHC Luminosity and Energy Upgrade

Linac4: From Initial Design to Final Commissioning

Large Hadron Collider at CERN

The Large Hadron Collider Lyndon Evans CERN

The LHC: the energy, cooling, and operation. Susmita Jyotishmati

Status of the LIU project and progress on space charge studies

OVERVIEW OF THE LHEC DESIGN STUDY AT CERN

Optimization of the SIS100 Lattice and a Dedicated Collimation System for Ionisation Losses

The LHC Collider. STOA lecture, Brussels, 27 th November 2012 Steve Myers Director of Accelerators and Technology, CERN

LHC status & 2009/2010 operations. Mike Lamont

Tools of Particle Physics I Accelerators

Accelerators for Beginners and the CERN Complex

LHC upgrade based on a high intensity high energy injector chain

LHC operation in 2015 and prospects for the future

LHC. Construction Understanding first the commissioning. Prospects for

1.5-GeV FFAG Accelerator as Injector to the BNL-AGS

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

Accelerator Design and Construction Progress of TPS Project

Engines of Discovery

Thanks to all Contributors

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

REPORT OF THE HIGH INTENSITY PROTONS WORKING GROUP

ERL FACILITY AT CERN FOR APPLICATIONS

Review of ISOL-type Radioactive Beam Facilities

Plans for the LHC Luminosity Upgrade Summary of the CARE-HHHAPD-LUMI-05 workshop

Design Status of the PEFP RCS

Challenges and Plans for the Proton Injectors *

Much of this material comes from lectures given by Philippe Lebrun (head of CERN's Accelerator Technology Department), at SUSSP, Aug

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

Multi-Purpose Accelerator-Accumulator ITEP-TWAC for Nuclear Physics and Practical Applications

Plans for ions in the injector complex D.Manglunki with the help of I-LHC and LIU-PT teams

ELECTRON COOLING OF PB54+ IONS IN LEIR

The TESLA Dogbone Damping Ring

Short Introduction to CLIC and CTF3, Technologies for Future Linear Colliders

CERN & the High Energy Frontier

Overview of HEMC Scheme

Compressor Ring. Contents Where do we go? Beam physics limitations Possible Compressor ring choices Conclusions. Valeri Lebedev.

Status of the LHC Machine

Why are particle accelerators so inefficient?

A Project to convert TLS Booster to hadron accelerator 1. Basic design. 2. The injection systems:

Overview of LHC Accelerator

CEPC Linac Injector. HEP Jan, Cai Meng, Guoxi Pei, Jingru Zhang, Xiaoping Li, Dou Wang, Shilun Pei, Jie Gao, Yunlong Chi

STATUS OF BEPC AND PLAN OF BEPCII

ELIC: A High Luminosity And Efficient Spin Manipulation Electron-Light Ion Collider Based At CEBAF

Advanced Design of the FAIR Storage Ring Complex

Accelerators. There are some accelerators around the world Nearly all are for industrial (20 000) or clinical use (10 000)

Report on PIAVE G. Bisoffi

Status and Outlook of the LHC

NICA Project at JINR Nuclotron-based Ion Collider facility I.Meshkov for NICA team

RING-RING DESIGN. Miriam Fitterer, CERN - KIT for the LHeC study group

Physics 610. Adv Particle Physics. April 7, 2014

TUNE SPREAD STUDIES AT INJECTION ENERGIES FOR THE CERN PROTON SYNCHROTRON BOOSTER

First propositions of a lattice for the future upgrade of SOLEIL. A. Nadji On behalf of the Accelerators and Engineering Division

How J-PARC recovered from the big earthquake

FAIR AT GSI. P. Spiller, GSI, Darmstadt, Germany

The FAIR Accelerator Facility

CLIC Detector studies status + plans

Chopping High-Intensity Ion Beams at FRANZ

Beam. RF antenna. RF cable

Statusreport. Status of the GSI accelerators for FRS operation. Jens Stadlmann (FAIR Synchrotrons)

Measurement and Compensation of Betatron Resonances at the CERN PS Booster Synchrotron

The LHC. Part 1. Corsi di Dottorato Corso di Fisica delle Alte Energie Maggio 2014 Per Grafstrom CERN and University of Bologna

Physics 736. Experimental Methods in Nuclear-, Particle-, and Astrophysics. - Accelerator Techniques: Introduction and History -

SC magnets for Future HEHIHB Colliders

A high intensity p-linac and the FAIR Project

SPIRAL 2 Commissioning Status

The CIS project and the design of other low energy proton synchrotrons

The 2015 erhic Ring-Ring Design. Christoph Montag Collider-Accelerator Department Brookhaven National Laboratory

Physics at Accelerators

Proposal to convert TLS Booster for hadron accelerator

Preliminary design of proton and ion linacs for SPPC Injector

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN - ACCELERATORS AND TECHNOLOGY SECTOR

Compressor Lattice Design for SPL Beam

BERLinPro. An ERL Demonstration facility at the HELMHOLTZ ZENTRUM BERLIN

Status & Plans for the TRIUMF ISAC Facility

Physics Potential of existing and future LBL ν beams

An Electron Linac Photo-Fission Driver for the Rare Isotope Program at TRIUMF

Superconducting Magnets for Future Electron-Ion Collider. Yuhong Zhang Thomas Jefferson National Accelerator Facility, USA

LC Commissioning, Operations and Availability

Low Energy RHIC electron Cooling (LEReC)

Overview of Acceleration

Muon Front-End without Cooling

Run II Status and Prospects

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

LHC Commissioning and First Operation

8 lectures on accelerator physics

SMR/ Summer School on Particle Physics June LHC Accelerators and Experiments (part I) Marzio Nessi CERN, Switzerland

On-axis injection into small dynamic aperture

AWAKE: The Proton Driven Plasma Wakefield Acceleration Experiment at CERN. Alexey Petrenko on behalf of the AWAKE Collaboration

(a) (b) Fig. 1 - The LEP/LHC tunnel map and (b) the CERN accelerator system.

Higgs Factory Magnet Protection and Machine-Detector Interface

CERN Ideas and Plans for a Neutrino Factory

Transcription:

LHC Status and CERN s future plans Lyn Evans

Machine layout L. Evans EDMS document no. 859415 2

Cryodipole overview 1250 1000 Equivalent dipoles 750 500 250 0 01-Jan-01 01-Jan-02 01-Jan-03 01-Jan-04 01-Jan-05 01-Jan-06 01-Jan-07 01-Jan-08 Cold masses delivered Cryodipoles cold tests passed Cryodipoles prepared for installation Cryodipoles assembled Cryodipoles assigned to position in ring Cryodipoles installed L. Evans EDMS document no. 859415 3

Short Straight Section overview 500 450 400 350 Equivalent SSS 300 250 200 150 100 50 0 01-Jan-01 01-Jan-02 01-Jan-03 01-Jan-04 01-Jan-05 01-Jan-06 01-Jan-07 01-Jan-08 Cold masses delivered SSS assembled SSS cold test passed SSS assigned to position in ring SSS prepared for installation SSS installed L. Evans EDMS document no. 859415 4

Bending strength of dipoles Cold mass 10.15 Firm 1 Firm 2 40 Int transf func (Tm/kA) 10.13 10.11 10.09 Firm 3 upper limit for single magnet (3 sigma) 20 0-20 Units 10.07 lower limit for single magnet (3 sigma) 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 Magnet progressive number AT-MAS -40 L. Evans EDMS document no. 859415 5

Completion of magnet cryostating & tests, 1 March 2007 Cryostating Cold tests 425 FTE.years 640 FTE.years L. Evans EDMS document no. 859415 6

Descent of the last magnet, 26 April 2007 30 000 km underground at 2 km/h! L. Evans EDMS document no. 859415 7

Dipole-dipole interconnect L. Evans EDMS document no. 859415 8

Dipole-dipole interconnect: electrical splices L. Evans EDMS document no. 859415 9

Magnet interconnections 100% General Advancement of Interconnects per Sector 16-July-2007 Close W & Jumper 90% Weld Package I & VAC tests 80% N-Line Package 70% 60% 50% Cryo-Lines Welding & Testing Electrical Interconnects & QA per halfcell IC preparation 40% 30% 20% 10% 0% sector 1-2 sector 2-3 sector 3-4 sector 4-5 sector 5-6 sector 6-7 sector 7-8 sector 8-1 L. Evans EDMS document no. 859415 10

Global pressure test of Sector 4-5, 12 May 2007 L. Evans EDMS document no. 859415 11

Flushing machine - Wk 2 January 07 Before After Kapton bits Metal strips 50 h + 8 L of Water L. Evans EDMS document no. 859415 12

Q1.R8 L. Evans EDMS document no. 859415 13

Cooldown of Sector 7-8 From RT to 80K precooling with LN2. 1200 tons of LN2 (64 trucks of 20 tons). Three weeks for the first sector. From 80K to 4.2K. Cooldown with refrigerator. Three weeks for the first sector. 4700 tons of material to be cooled. From 4.2K to 1.9K. Cold compressors at 15 mbar. Four days for the first sector. L. Evans EDMS document no. 859415 14

Large helium refrigerator for cooling down to 4.5 K 33 kw @ 50 K to 75 K 23 kw @ 4.6 K to 20 K 41 g/s liquefaction 600 kw precooling to 80 K with LN2 (up to ~5 tons/h) L. Evans EDMS document no. 859415 15

First cool-down of Sector 7-8 LHC sector 78 - First cooldown Temperature (K) 300 280 260 240 220 200 180 160 140 120 100 Return temperature Magnet temp. Supply temperature Active cooling in all thermal shields and cryogenic tranfer lines. All magnets isolated. Thermal shield temp. Active cooling in all thermal shields and cryogenic tranfer lines. All magnets isolated. 80 60 40 20 0 15/01/07 18:00 21/01/07 18:00 27/01/07 18:00 Re-start of active cooling for cryogenic transfer lines 02/02/07 18:00 08/02/07 18:00 Re-start of active cooling for magnets 14/02/07 18:00 20/02/07 18:00 26/02/07 18:00 04/03/07 18:00 Time (UTC) 10/03/07 18:00 Supply temperature Return temperature Magnet temperature (average over sector) Thermal shields temp. (average over sector) L. Evans EDMS document no. 859415 16

Hydrodynamic cold compressors for 1.8 K refrigeration 120 g/s GHe from 15 mbar with 4 stages L. Evans EDMS document no. 859415 17

First cool-down of Sector 7-8 Magnet temperature profile along Sector 7-8 during final cool down to He II L. Evans EDMS document no. 859415 18

Sector 7-8 Cooldown L. Evans EDMS document no. 859415 19

First powering of main quadrupoles L. Evans EDMS document no. 859415 20

Cool-Down until Saturday 14-7-7 Cool-Down Speed Avg. Cold Mass Temperature 300 280 260 240 220 200 180 160 140 7/5/07 6:00 7/6/07 6:00 7/7/07 6:00 7/8/07 6:00 7/9/07 6:00 7/10/07 6:00 7/11/07 6:00 7/12/07 6:00 7/13/07 6:00 7/14/07 6:00 7/15/07 6:00 7/16/07 6:00 7/17/07 6:00 7/18/07 6:00 7/19/07 6:00 Date planned [K] measured [K] data S7-8 [K] L. Evans EDMS document no. 859415 21

Installation & equipment commissioning Procurement problems of remaining components (DFBs, collimators) now settled Good progress of installation and interconnection work, proceeding at high pace in tunnel Numerous non-conformities intercepted by QA program, but resulting in added work and time Technical solutions found for inner triplet problems and repair well underway. Commissioning of first sectors can proceed by isolating faulty triplets, but will have to be re-done with repaired triplets (needing additional warm-up/cooldown cycles) First sector cooled down to nominal temperature and operated with superfluid helium; teething problems with cold compressor operation have now been fixed. Second sector being cooled down. Power tests have started. L. Evans EDMS document no. 859415 22

General schedule Engineering run originally foreseen at end 2007 now precluded by delays in installation and equipment commissioning. 450 GeV operation now part of normal setting up procedure for beam commissioning to high-energy General schedule has been revised, accounting for inner triplet repairs and their impact on sector commissioning All technical systems commissioned to 7 TeV operation, and machine closed April 2008 Beam commissioning starts May 2008 First collisions at 14 TeV c.m. July 2008 Luminosity evolution will be dominated by our confidence in the machine protection system and by the ability of the detectors to absorb the rates. No provision in success-oriented schedule for major mishaps, e.g. additional warm-up/cooldown of sector L. Evans EDMS document no. 859415 23

LHC General Schedule, 5 July 2007 General schedule Baseline rev. 4.0 Global pressure test &Consolidation Cool-down Powering Tests Interconnection of the continuous cryostat Leak tests of the last sub-sectors Inner Triplets repairs & interconnections Global pressure test &Consolidation Flushing Cool-down Warm up Powering Tests L. Evans EDMS document no. 859415 24

European Strategy Group (1/2) [Quotes from the official statement July 14, 2006] Consolidation and upgrade of injectors LHC upgrade and maximum performance injectors L. Evans EDMS document no. 859415 25

European Strategy Group (2/2) [Quotes from the official statement July 14, 2006] R & D for LHC upgrade and ν facility preparation for ν facility L. Evans EDMS document no. 859415 26

CERN accelerator complex L. Evans EDMS document no. 859415 27

Upgrade procedure 1. Lack of reliability: Ageing accelerators (PS is 48 years old!) operating far beyond initial parameters need for new accelerators designed for the needs of SLHC 2. Main performance limitation: Excessive incoherent space charge tune spreads ΔQ SC at injection in the PSB (50 MeV) and PS (1.4 GeV) because of the high required beam brightness N/ε*. ΔQ SC with N ε N ε b X, Y b X, Y R 2 βγ : number of : normalized transverse emittances R : mean radius of protons/bunch the accelerator βγ :classical relativistic parameters need to increase the injection energy in the synchrotrons Increase injection energy in the PSB from 50 to 160 MeV kinetic Increase injection energy in the SPS from 25 to 50 GeV kinetic Design the PS successor (PS2) with an acceptable space charge effect for the maximum beam envisaged for SLHC: => injection energy of 4 GeV L. Evans EDMS document no. 859415 28

Upgrade components Proton flux / Beam power 50 MeV 160 MeV Linac2 Linac4 1.4 GeV 4 GeV PSB LPSPL Output energy 26 GeV 50 GeV 450 GeV 1 TeV PS SPS PS2 SPS+ LPSPL: Low Power Superconducting Proton Linac (4 GeV) PS2: High Energy PS (~ 5 to 50 GeV 0.3 Hz) SPS+: Superconducting SPS (50 to1000 GeV) SLHC: Superluminosity LHC (up to 10 35 cm -2 s -1 ) DLHC: Double energy LHC (1 to ~14 TeV) 7 TeV ~ 14 TeV LHC / SLHC DLHC L. Evans EDMS document no. 859415 29

Layout of the new injectors SPS PS2 SPL PS Linac4 L. Evans EDMS document no. 859415 30

Linac4 building and infrastructure klystron hall (above ground) H - source & RFQ accelerating tunnel L. Evans EDMS document no. 859415 31

Linac4 and SPL buildings SPL tunnel Linac4 klystron hall SPL klystron gallery Linac4 tunnel L. Evans EDMS document no. 859415 32

Stage 1: Linac4 (1/3) Linac4 beam characteristics Ion species H - Output energy 160 MeV Bunch frequency 352.2 MHz Max. repetition rate 2 Hz Beam pulse duration 0.4 ms Chopping factor (beam on) 62% Source current 80 ma RFQ output current 70 ma Linac current 64 ma Average current during beam pulse 40 ma Beam power 5.1 kw Particles p. pulse 1.0 10 14 Transverse emittance (source) 0.2 mm mrad Transverse emittance (linac) 0.4 mm mrad L. Evans EDMS document no. 859415 33

Stage 1: Linac4 (2/3) Linac4 structures 3 MeV 50 MeV 102 MeV 160 MeV H - source RFQ chopper DTL CCDTL PIMS 352.2 MHz L. Evans EDMS document no. 859415 34

Stage 1: Linac4 (3/3) Direct benefits of the new linac Stop of Linac2: End of recurrent problems with Linac2 (vacuum leaks, etc.) End of use of obsolete RF triodes (hard to get + expensive) Higher performance: Space charge decreased by a factor of 2 in the PSB => potential to double the beam brightness and fill the PS with the LHC beam in a single pulse, => easier handling of high intensity. Potential to double the intensity per pulse. Low loss injection process (Charge exchange instead of betatron stacking) High flexibility for painting in the transverse and longitudinal planes (high speed chopper at 3 MeV in Linac4) First step towards the SPL: Linac4 will provide beam for commissioning LPSPL + PS2 without disturbing physics. Benefits for users of the PSB Good match between space charge limits at injection in the PSB and PS => for LHC, no more long flat bottom at PS injection + shorter flat bottom at SPS injection: easier/ more reliable operation / potential for ultimate beam from the PS More intensity per pulse available for PSB beam users (ISOLDE) up to 2 More PSB cycles available for other uses than LHC L. Evans EDMS document no. 859415 35

Stage 2 2 CDR2 LPSPL for SPS & LHC SPL 3 different designs: Stage 2: LPSPL + PS2 (1/3) LPSPL and SPL beam characteristics Energy (GeV) 3.5 4 5 Beam power (MW) 4 0.19 4-8 Rep. frequency (Hz) 50 2 50 Protons/pulse (x 10 14 ) 1.4 1.2 1 Av. Pulse current (ma) 40 20 40 Pulse duration (ms) 0.57 1.9 0.4 Bunch frequency (MHz) 352.2 352.2 352.2 Physical length (m) 430 ~460 535 CDR2 (2006) based on 700 MHz high-gradient cavities LPSPL for LHC (2007) with low beam power, for the needs of the LHC SPL at higher energy, for the needs of neutrino production L. Evans EDMS document no. 859415 36

Stage 2: LPSPL + PS2 (2/3) PS2 Injection energy kinetic (GeV) 4.0 1.4 Extraction energy kinetic (GeV) ~ 50 13/25 Circumference (m) 1346 628 Maximum intensity LHC (25ns) (p/b) 4.0 x 10 11 1.7 x 10 11 Maximum intensity for fixed target physics (p/p) 1.2 x 10 14 3.3 x 10 14 Maximum energy per beam pulse (kj) 1000 70 Max ramp rate (T/s) 1.5 2.2 Repetition time at 50 GeV (s) ~ 2.5 1.2/2.4 Max. effective beam power (kw) PS2 beam characteristics PS 400 60 L. Evans EDMS document no. 859415 37

Stage 2: LPSPL + PS2 (3/3) Direct benefits of the LPSPL + PS2 Stop of PSB and PS: End of recurrent problems (damaged magnets in the PS, etc.) End of maintenance of equipment with multiple layers of modifications End of operation of old accelerators at their maximum capability Safer operation at higher proton flux (adequate shielding and collimation) Higher performance: Capability to deliver 2.2 the ultimate beam for LHC to the SPS => potential to prepare the SPS for supplying the beam required for the SLHC, Higher injection energy in the SPS + higher intensity and brightness => easier handling of high intensity. Potential to increase the intensity per pulse. Benefits for users of the LPSPL and PS2 More than 50 % of the LPSPL pulses will be available (not needed by PS2) => New nuclear physics experiments extension of ISOLDE (if no EURISOL) Upgraded characteristics of the PS2 beam wrt the PS (energy and flux) Potential for a higher proton flux from the SPS L. Evans EDMS document no. 859415 38

Stage 2 : SPL Upgrade the LPSPL into an SPL (multi- MW beam power at 2-52 GeV): 50 Hz rate with upgraded infrastructure (electricity, water, cryo-plants, ) 40 ma beam current by doubling the number of klystrons in the superconducting part Possible users EURISOL (2 nd generation ISOL-type RIB facility) => special deflection system(s) out of the SPL into a transfer line => new experimental facility with capability to receive 5 MW beam power => potential of supplying β-unstable isotopes to a β-beam facility Neutrino factory => energy upgrade to 5 GeV (+70 m of sc accelerating structures) => 2 fixed energy rings for protons (accumulator & compressor) => accelerator complex with target, μ capture-cooling-acceleration (20-50 GeV) and storage L. Evans EDMS document no. 859415 39

Planning 3 MeV test place ready Linac4 approval CDR 2 SPL & PS2 approval Start for Physics L. Evans EDMS document no. 859415 40