NUMERICAL MODELLING OF THE BRUSNICE TUNNEL

Similar documents
GEOLOGY OF PRAGUE ITS INTERACTION WITH THE PRAGUE METRO

1 Introduction. Abstract

Stress and strain dependent stiffness in a numerical model of a tunnel

Observational Methods and

ON THE FACE STABILITY OF TUNNELS IN WEAK ROCKS

TC211 Workshop CALIBRATION OF RIGID INCLUSION PARAMETERS BASED ON. Jérôme Racinais. September 15, 2015 PRESSUMETER TEST RESULTS

NUMERICAL VERIFICATION OF GEOTECHNICAL STRUCTURE IN UNFAVOURABLE GEOLOGICAL CONDITIONS CASE STUDY

DESIGN AND CONSTRUCTION OF LARGE

Engineeringmanuals. Part2

Mechanical Behaviors of Cylindrical Retaining Structures in Ultra-deep Excavation

Monitoring of underground construction

Landslide FE Stability Analysis

REGARDING SOME DYNAMIC CHARACTERISTICS OF THE SOILS AND THE LIQUIFACTION POTENTIAL OF SANDS IN SOFIA

Analysis of the horizontal bearing capacity of a single pile

MEMORANDUM SUBJECT: CERTIFICATE IN ROCK MECHANICS PAPER 1 : THEORY SUBJECT CODE: COMRMC MODERATOR: H YILMAZ EXAMINATION DATE: OCTOBER 2017 TIME:

P16 Gravity Effects of Deformation Zones Induced by Tunnelling in Soft and Stiff Clays

PILE-SUPPORTED RAFT FOUNDATION SYSTEM

Effect of buttress on reduction of rock slope sliding along geological boundary

Canada Line Project. Stability of the Twin Bored Tunnels Under False Creek. Vancouver, British Columbia

Three-dimensional settlement analysis of a primary crusher station at a copper mine in Chile

Calculation and analysis of internal force of piles excavation supporting. based on differential equation. Wei Wang

Rock slope rock wedge stability

Talić Z. et al: Geotechnical characteristics... Archives for Technical Sciences 2014, 11(1), 33-39

Flin Flon Mining Belt

Further Research into Methods of Analysing the October 2000 Stability of Deep Open Pit Mines EXECUTIVE SUMMARY

Numerical analysis of swelling deformations in tunnelling a case study

The Preliminary Study of the Impact of Liquefaction on Water Pipes

Effect Of The In-Situ Stress Field On Casing Failure *

Haulage Drift Stability Analysis- A Sensitivity Approach

SOIL MODELS: SAFETY FACTORS AND SETTLEMENTS

Finite Element Investigation of the Interaction between a Pile and a Soft Soil focussing on Negative Skin Friction

GROUND RESPONSE AND SUPPORT MEASURES FOR PIR PANJAL TUNNEL IN THE HIMALAYAS

Finite element simulation of a tunnel excavation in an urban environment: case study of the CEVA project

DYNAMIC ANALYSIS OF PILES IN SAND BASED ON SOIL-PILE INTERACTION

PLAXIS 3D FOUNDATION Validation Manual. version 1.5

Numerical Modeling of Direct Shear Tests on Sandy Clay

3D FEM analysis of a NATM tunnel with shotcrete lining homogenization and stiffness anisotropy

A. V T = 1 B. Ms = 1 C. Vs = 1 D. Vv = 1

Geology and Soil Mechanics /1A ( ) Mark the best answer on the multiple choice answer sheet.

Experimental Research on Ground Deformation of Double Close-spaced Tunnel Construction

Analysis of a single pile settlement

Forces on piles preventing debris slope slips

Spread footing settlement and rotation analysis

GEOLOGY, SOILS, AND SEISMICITY

Predicting rock conditions ahead of the face

Rock slope stability planar shear failure

Boreholes. Implementation. Boring. Boreholes may be excavated by one of these methods: 1. Auger Boring 2. Wash Boring 3.

Entrance exam Master Course

Minimization Solutions for Vibrations Induced by Underground Train Circulation

Appraisal of Soil Nailing Design

Foundations of High Rise Buildings

Numerical Study of Relationship Between Landslide Geometry and Run-out Distance of Landslide Mass

Seismic analysis of horseshoe tunnels under dynamic loads due to earthquakes

Weak Rock - Controlling Ground Deformations

Analysis and measurements of settlement for heavy loaded rigid footing

Large deformations in squeezing ground in the Saint-Martin La Porte gallery along the Lyon-Turin Base Tunnel

EXPANSIVE CLAYS IN TRACK SUBGRADE IN DEEP CUT (SECTION TŘEBOVICE RUDOLTICE, CZECH REPUBLIC)

Application of the fractal fragmentation model to the fill of natural shear zones

The Mine Geostress Testing Methods and Design

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

UNIVERSITA` DEGLI STUDI DI PADOVA

Finite difference modelling in underground coal mine roadway

NNN99. Rock Engineering for the Next Very Large Underground Detector. D. Lee Petersen CNA Consulting Engineers

GIBE II TUNNEL PROJECT - ETHIOPIA - 40 BARS OF MUD ACTING ON THE TBM

Internal C Unit Dilatanc y

CHAPTER 8 ANALYSES OF THE LATERAL LOAD TESTS AT THE ROUTE 351 BRIDGE

Seabed instability and 3D FE jack-up soil-structure interaction analysis

Prevention and remediation of rockslide at left portal of north tunnel of Da Nang Qu ang Ngai expressway in Quang Nam, Vietnam

3D ANALYSIS OF STRESSES AROUND AN UNLINED TUNNEL IN ROCK SUBJECTED TO HIGH HORIZONTAL STRESSES

Influence of the undercut height on the behaviour of pillars at the extraction level in block and panel caving operations

Table of Contents Development of rock engineering 2 When is a rock engineering design acceptable 3 Rock mass classification

THE STRUCTURAL DESIGN OF PILE FOUNDATIONS BASED ON LRFD FOR JAPANESE HIGHWAYS

THREE DIMENSIONAL NUMERICAL INVESTIGATION OF BAGHDAD METRO PASSING UNDER TIGRIS

Verification Manual GT

City, University of London Institutional Repository

Safe bearing capacity evaluation of the bridge site along Syafrubesi-Rasuwagadhi road, Central Nepal

PRO GEO GEOTECHNICAL CONSULTANTS SHORT PRESENTATION BARCELONA, SPAIN

Effect of Subsurface Conditions on the Behavior of Retaining Walls

A Unique Metro Accident in Brazil Caused by Multiple Factors

Geotechnical Monitoring for Safe Excavation of Large Rock Cavern: A Case Study

Successful Construction of a Complex 3D Excavation Using 2D and 3D Modelling

Single Pile Simulation and Analysis Subjected to Lateral Load

Central Queensland Coal Project Appendix 4b Geotechnical Assessment. Environmental Impact Statement

Critical Borehole Orientations Rock Mechanics Aspects

South Toulon tunnel: Analysis of an instrumented section

Module 9 : Foundation on rocks. Content

Application of coupled modeling to slope stability assessment

Ground support modelling involving large ground deformation: Simulation of field observations Part 1

CALCULATION OF A SHEET PILE WALL RELIABILITY INDEX IN ULTIMATE AND SERVICEABILITY LIMIT STATES

A Constitutive Framework for the Numerical Analysis of Organic Soils and Directionally Dependent Materials

ANALYSIS OF LATERALLY LOADED FIXED HEADED SINGLE FLOATING PILE IN MULTILAYERED SOIL USING BEF APPROACH

ELASTIC CALCULATIONS OF LIMITING MUD PRESSURES TO CONTROL HYDRO- FRACTURING DURING HDD

Numerical modelling for estimation of first weighting distance in longwall coal mining - A case study

10. GEOTECHNICAL EXPLORATION PROGRAM

vulcanhammer.net This document downloaded from

1 of 46 Erik Eberhardt UBC Geological Engineering ISRM Edition

SIDE FRICTION OF DRILLED PILES IN COBBLE LAYERS

Structural reliability analysis of deep excavations

Effect of embedment depth and stress anisotropy on expansion and contraction of cylindrical cavities

Evaluation of dynamic behavior of culverts and embankments through centrifuge model tests and a numerical analysis

Transcription:

NUMERICAL MODELLING OF THE BRUSNICE TUNNEL Matouš Hilar 1, Jakub Nosek 2 1 D2 Consult Prague and FCE CTU, Zelený pruh 95/97, Prague 4, 140 00, Czech Republic 2 D2 Consult Prague, Zelený pruh 95/97, Prague 4, 140 00, Czech Republic KEYWORDS Numerical modelling, NATM, FEM. 1. INTRODUCTION Basic information Brusnice tunnel is a part of the Blanka tunnel complex, the significant construction of the northwestern section of the Prague City Circle Road. The constructed tunnel complex consists of two parallel one-way tunnel tubes with length over 6 km and constitutes an extension of existing ring road at Malovanka intersection, where the Strahovský tunnel results in. The tunnel alignment passing Hradčanská underground station proceeds to Letná area to divert beneath the Stromovka Park and go under the Vltava River. The trace is terminated by connection to existing road network at Pelc-Tyrolka intersection situated in the vicinity of Barikádníků Bridge. The Blanka tunnel complex comprises mined tunnels (approx. 2,7 km) and cut-and-cover tunnels (approx. 3,3 km). The mined tunnels are constructed in two different sections. Excavation of Špejchar Pelc Tyrolka tunnel with length 2,2 km was started as a first. The second section is characterized by Brusnice tunnel consisting of two triple-line tubes with length of about 550 m and connecting Myslbekova a Prašný most open pits. The New Austrian Tunnelling Method (NATM) was used as an excavation technique for Brusnice tunnel tubes. Except the section of the northern tunnel tube (NTT) both tubes were mined downwards from the Myslbekova portal. NTT was excavated from the Prašný Most portal after the collapse of the overburden in a Ministry of Culture garden happened. Excavated profile area of each tube is approximately 170 m 2 and their overburden thickness is about 25 m along the majority of tunnel line. Separation distance between tubes is approx. 17 m. The Blanka tunnel complex contractor is Metrostav a.s., designer Satra and investor Prague the capital. Geological conditions Results of engineering geological survey confirmed that geological and geotechnical conditions along the Brusnice tunnel line are very complex and highly variable. The bedrock in area of interest consists of the Ordovician Letná formation structurally described as sandy schists with sandy concretions. Finely to coarsely micaceous schists are bedded in thick layers. Interlayers of fine-grained quartzite with thickness 6 20 cm are often to encounter. Depending on measure of tectonical failure the moderately to highly fissured rock predominate at construction lot. Individual degrees of weathering are designated from W5, weathered schist composed of cohesive soil with character of clay with variable content of schist fragments, to W1, hard non-weathered thickly bedded schist.

The Quaternary cover consists of anthropogenic (AN), eolic (EO), deluvial (DE) and fluvial (FL) sediments. The rock overburden thickness ranges along the tunnel alignment from 12 to 19 m. About 450 TM behind the Myslbekova portal the rock thickness falls to value of about 5 m. Hard and slightly weathered schists (W1 to W2) have been encountered the most of the tunnel line. A layer of moderately weathered schists (W3 to W4) descended into the tunnel profile in the vicinity of Prašný Most portal. Excavation conditions in the NTT were getting worse in this area because of downcoming of weathered (decomposed) schists (W5) into the profile. 2. TUNNEL EXCAVATION (CONSTRUCTION PROCESS) A vertical excavation sequence was originally designed for the excavation of both tunnel tubes. On the basis of lowering of a tunnel level and subsequent reaching of better geological conditions the horizontal sequence in detailed design was taken into account. The excavation commenced with opening of the NTT top heading from Myslbekova portal in October 2009 using horizontal sequence. In January 2010 started the STT excavation in a same direction with prescribed vertical sequence (first 50 TM) including left and right side-drifts and completion of a central pillar. After finishing of these 50 TM the horizontal sequence in accordance with NTT was adopted. Over a period of technical discussions about a continuation with horizontal sequence the NTT without complications reached a chainage 396 TM, where the excavation sequence on account of deterioration of geological conditions was changed to vertical subdivision. On 06/07/2010 the overburden between chainages 403 and 435 collapsed during a bottom completion and removal of internal side-drift walls. Excavation process was consequently stopped on both tunnel tubes (STT at chainage 374 TM). The NTT excavation was finished from Prašný Most portal with vertical sequence simultaneously with reconstruction works. The excavation operations were completed at STT using horizontal sequence with vertical subdivision of top heading. 3. NUMERICAL MODELS Because of the fact that geological conditions from Myslbekova portal to Prašný Most portal were getting worse the excavation method for following meters were often taken into consideration. Set of numerical models of tunnel excavation carried out at D2 Consult Prague s.r.o. served as base for technical discussions. All models were performed using software Plaxis V8. Finite element mesh composes of 15- noded triangle elements and the mechanical behavior of a ground was simulated using linear elastic ideally plastic Mohr Coulomb constitutive model. Primary lining was modeled by linear elasticity using beam elements. Analysis of chainage 220TM In a distance of 220 m from Myslbekova portal a numerical model representing presupposed geological conditions and expected primary reinforcement was prepared (Fig. 1). The overburden thickness above the tunnel tubes reaches 25 m (NTT) and 26 m (STT). In simulated cross-section using the 3 NATM technological support category was expected with corresponding 30 cm thickness of primary lining. The tunnel profile is 16,5 m width and 12,7 m high with area of 169 m 2.

Fig. 1: Excavation model in chainage 220 TM This model was prepared before commencement of excavation operations in period of valid final design with proposed vertical sequence for both tunnel tubes in their entire length. For that reason both considered profile subdivisions were modeled and compared. In a simulation with horizontal sequence the NTT top heading excavation was modeled first followed by bench and invert simultaneously. The aim of this procedure was a fast closing of whole tunnel as supposed in final design. The STT excavation was simulated in the same way. Aforementioned phases were divided into phase of unreinforced profile loaded with 30 % of unbalanced forces and phase of lined profile with complete load applied. In a simulation with vertical sequence, phases of the NTT excavation as stated below were modeled first, followed by same phases for STT. 1. Top Heading excavation of 1. Side-drift 2. Completion of 1. Side-drift 3. Top Heading excavation of 2. Side-drift 4. Completion of 2. Side-drift 5. Middle Top Heading excavation 6. Bottom and Invert excavation Each of phases was divided again into two phases as in a case of the horizontal sequence. The tunnel excavation passed this cross-section using horizontal sequence and with regard to favourable monitoring results without requirements on fast profile closing. In addition to existing model with horizontal sequence one with separated phases of bottom and invert was prepared. This model is in result table stated as realized horizontal sequence. Geotechnical parameters of rock mass types employed in analyses are subject of Table 1. Tab. 1: Geotechnical parameters in cross-section 220 TM Layer depth g E c f n K 0 [m] [kn/m3] [MPa] [kpa] [ ] [ - ] [ - ] AN 0-4 20,0 11 10 19,6 0,399 0,66 EO 4-7 19,5 10 20 17,9 0,409 0,69 DE 4-7 19,5 20 8 23 0,379 0,61 W5 7-9 21,0 30 12 24,8 0,367 0,58 W4-W3 9-14 22,5 90 20 24,8 0,31 0,58 W2 14-18 24,5 220 40 26,6 0,25 0,55 W1b 18-80 26,3 500 140 32,9 0,23 0,46

Predictions of surface settlements and tunnel deformations obtained with horizontal sequence with fast closing and vertical excavation sequence produce small differences between individual methods (order of millimeters). Additional model with realized horizontal sequence confirmed reliability of simulations in this cross-section. Predicted and measured values differ minimally (see Tab. 2). Tab. 2: Comparison of predictions and monitoring data Vertical sequence Horizontal sequence Realized horizontal sequence Monitoring data Max. vertical deformation 24 27 38 39 [mm] Max. horizontal deformation 7 4 6 - [mm] Max. bending moment 87 55 68 - [knm] Max. axial force 2270 1280 1420 - [kn] Max. surface settlement 13 15 26 33 [mm] Analysis of chainage 361 TM Further analysis was realized in cross-section of chainage 361 TM. The simulation was performed in May 2010 after the NTT top heading and bench passed the simulated cross-section and stopped at chainage 394 TM. 220 meters were excavated in STT top heading at the same time. The goal of presented simulations was provide so exact predictions of rock mass behavior within the STT pass and NTT invert finishing as possible. Both variants horizontal and vertical excavation sequence were considered again. From Myslbekova portal in distance of 361 m the model representing presupposed geological conditions and primary tunnel reinforcement was set up. The overburden thickness is 24 m. Since ground surface and geological strata are in-situ only slightly inclined the model could be simplified to horizontal. In simulated section using the 5a NATM technological support category was expected with corresponding 40 cm thickness of primary lining. The profile is 16,5 m width and 12,7 m high with area of 174 m 2. Initial simulation of NTT excavation was carried out with geotechnical parameters of individual layers based on characteristic values (see Tab. 3). Fig. 2: Excavation model at chainage 361 TM

Tab. 3: Geotechnical parameters for cross-section at chainage 361 TM Layer Depth g E c f n K 0 [m] [kn/m 3 ] [MPa] [kpa] [ ] [ - ] [ - ] AN 0-5 20.0 11.0 13 24 0.372 0,59 EO 5-14 41048,0 10.0 25 22 0.385 0,63 W5 14-16 21.0 30 15 30 0.333 0,50 W3-W4 16-23 41051,0 90 25 30 0.31 0,50 W2 23-29 41053,0 220 50 32 0.25 0,47 W1a 29-65 25.75 300 125 37 0.25 0,40 Initial analysis was performed in five phases (in parenthesis the appropriate loading stated): 1. NTT Top Heading excavation (30%) 2. Lining installation of NTT Top Heading (50%) 3. Lining installation of Invert of NTT Top Heading (100%) 4. NTT Bench excavation (20%) 5. Lining installation of NTT Bench (100%) After completion of aforementioned phases for NTT, excavation and lining installation of top heading and bench, monitoring data were analyzed. From surface settlement trough points measured by leveling, points at lining and measurements of an extensometer located above the crown, was determined maximal surface settlement of 17 mm and max. crown deformation of 43 mm. Fig. 3: Comparison of measured surface settlement with tuned model predictions Surface settlements predicted with original parameter set were overpredicted on 140 % and 170 % of measured values. Based on these results the model was tuned and a good agreement with monitoring data was achieved by Young modulus increasing to 160 % of original value for each layer (Fig. 3). The tuned model was used for simulation of the NTT invert excavation and subsequently the STT vertical or horizontal excavation sequence. In case of horizontal sequence the phases of simulation were as follow: 6. NTT Invert excavation and lining installation (100%) 7. STT Top Heading excavation (30%) 8. Lining installation of STT Top Heading (50%) 9. Lining installation of Invert of STT Top Heading (100%) 10. STT Bench excavation (20%) 11. Lining installation of STT Bench (100%) 12. STT Invert excavation and Lining installation (100%)

In case of vertical sequence model the calculation continued with phase 6 NTT Invert excavation and lining installation and further followed the STT vertical subdivision used for chainage 220 TM (see above). In-situ the typical horizontal excavation sequence corresponding to modeled phases was applied. Simulation results are concluded with monitoring data in Tab. 4 together. Tab. 4: Comparison of predictions and monitoring data Settlement in STT axis Horizontal sequence Vertical sequence Monitoring data Tunnel 42 31 49 [mm] Surface 21 15 22 [mm] The assumption, that horizontal subdivision in simulated tunnel section is applicable, was confirmed based on obtained analysis results. Horizontal sequence leads only to slight increase of surface settlement of 5 mm when compared with vertical model. Since the increase of surface settlement did not represent any risk for surrounding buildings the horizontal sequence was applied with regard to time and economical profitability. 4. CONCLUSION Numerical analyses quantified the effect of face subdivision on deformations of rock mass caused by tunnel excavation. Horizontal sequence has proved to be convenient solution in modeled tunnel sections and predicted deformations were in conformity with measured data. Brusnice tunnel excavation, including also the dealing with collapse, has been successfully completed. ACKNOWLEDGEMENTS Financial support by the research grants TACR TA01011816 and GACR P105/12/1705 is gratefully acknowledged. REFERENCES Hilar, M. - Pruška, J. (2008), Statistical Analysis of Input Parameters on the Modelling of Underground Structures. Acta Polytechnica 48/5, pp. 3-8. Barták, J. - Hilar, M. - Pruška, J. (2002): Numerical Modelling of the Underground Structures. Acta Polytechnica. 42/1, pp. 53-58.