Rock Sizing for Multi-Pipe & Culvert Outlets

Similar documents
Rock Sizing for Batter Chutes

Rock Sizing for Drainage Channels

Rock Sizing for Waterway & Gully Chutes

Rock Sizing for Small Dam Spillways

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Chutes Part 5: Rock linings

Stormwater Outlet Sediment Traps

Rock Sizing for Bank Stabilisation

Use of Rock in Stormwater Engineering. Version 3, July 2017

Coarse Sediment Traps

Instream Sediment Control Systems

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

Construction Exits Rock pads

Construction Exits Vibration grids

Rock & Aggregate Drop Inlet Protection

Instream Erosion Control General

Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils

U-Shaped Sediment Traps

Appendix F Channel Grade Control Structures

Sediment Weirs (Instream)

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Stormwater Inlet Sediment Traps

APPENDIX B WORKSHEETS & EXHIBITS

ONE ROCK DAM ORD. capture more sediment. The original ORD becomes the splash apron for the new layer. STEP 4: When ORD fills in, add a new layer

Flood and Stream Restoration

CE415L Applied Fluid Mechanics Laboratory

Degradation Concerns related to Bridge Structures in Alberta

Countermeasure Calculations and Design

Annual transport rates at two locations on the fore-slope.

Stage Discharge Tabulation for Only Orifice Flow

EROSION CONTROL FIELD GUIDE By Craig Sponholtz & Avery C. Anderson

Hydraulic Design of Energy Dissipators for Culverts and Channels HEC 14 September 1983 Metric Version

The Mechanics Of Sediment Basin Operation

Agenda. INDOT Office of Environmental Services. Describe Results of FHWA QAR. Landscape and Waterway Permitting Unit. Interviews Site Inspections

Chapter 3.8: Energy Dissipators. By Dr. Nuray Denli Tokyay

CASE STUDIES. Introduction

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK

TPDES: Soil, Erosion and Sedimentation Methods

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION

Lateral Inflow into High-Velocity Channels

NORTHUMBERLAND COUNTY, PA

Estimating Scour. CIVE 510 October 21 st, 2008

Why Geomorphology for Fish Passage

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

Why Stabilizing the Stream As-Is is Not Enough

**Temporary Erosion Control**

1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,

Section 4: Model Development and Application

Tom Ballestero University of New Hampshire. 1 May 2013

Sessom Creek Sand Bar Removal HCP Task 5.4.6

B805 TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES - OPSS 805

Module 2 Lecture 9 Permeability and Seepage -5 Topics

An environmentally sensitive erosion control technique in the Mekong River Delta: 10 years on

WQ Outlet Design Single Orifice Orifice diameter = 24. Perforated riser/orifice Plate Outlet area per perforation row = 4

Hydraulics Prof. Dr. Arup Kumar Sarma Department of Civil Engineering Indian Institute of Technology, Guwahati

A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA

Erosion and Sediment Control Measures 2.7 Silt Fences

WP2.1 BREACH FORMATION LARGE SCALE EMBANKMENT FAILURE

Stone Outlet Sediment Trap

HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE

APPENDIX A: EROSION & SEDIMENT CONTROL FORMS

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

Tanjung Priok GFPPEP. Presentation and discussion, 22 October 2009 PT. PLN (Persero) Jasa Enjiniring Office Jl. KS Tubun I/2 Petamburan, Jakarta

1 PROJECT BACKGROUND. August 14, Alberta Transportation Central Region #401, Street Red Deer, Alberta T4N 6K8

Upper Mississippi River Basin Environmental Management Program Workshop

Ways To Identify Background Verses Accelerated Erosion

Laboratory Investigation of Submerged Vane Shapes Effect on River Banks Protection

Independent Environmental Audit Erosion and Sediment Control

Assessment. Assessment

Vegetation effects on river hydraulics. Johannes J. (Joe) DeVries David Ford Consulting Engineers, Inc. Sacramento, CA

Fish Passage at Road Crossings

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water.

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

Addressing the Impact of Road-Stream Crossing Structures on the Movement of Aquatic Organisms

EROSION CONTROL NARRATIVE

Monitoring of suspended sediment concentration in discharge from regulated lakes in glacial deposits

Effect of Location and Angle of Cutoff Wall on Uplift Pressure in Diversion Dam

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

CONSTRUCTION EXIT SEDIMENT BARRIER

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE

Materials. Use materials meeting the following.

5. ROADSIDE AND MEDIAN CHANNELS

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP

Saudi Journal of Civil Engineering

*** ***! " " ) * % )!( & ' % # $. 0 1 %./ +, - 7 : %8% 9 ) 7 / ( * 7 : %8% 9 < ;14. " > /' ;-,=. / ١

Selected Site BMPs: Why s the Water Muddy? John C. Hayes, Ph.D., P. E. Biosystems Engineering Clemson University

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

Application of Energy Approach to Estimating Scour Depth

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

ENGINEERING HYDROLOGY

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

FUTURE MEANDER BEND MIGRATION AND FLOODPLAIN DEVELOPMENT PATTERNS NEAR RIVER MILES 200 TO 191 OF THE SACRAMENTO RIVER PHASE III REPORT

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

CONCEPTS Conservational Channel Evolution and Pollutant Transport System

Culvert and Pipe Phasing

SCOUR AND EROSION ALONGSIDE BANK PROTECTION WORK: CASE STUDIES FROM BANGLADESH

Report for Area Drainage Studies for 1320 MW (2x660 MW) THERMAL POWER PROJECT AT MIRZAPUR, U.P.

Sensitivity Analysis of the Effective Parameters with Respect to Cantilever Type Failure in Composite Riverbanks

Sediment Trap. At multiple locations within the project site where sediment control is needed.

Transcription:

Rock Sizing for Multi-Pipe & Culvert Outlets STORMWATER AND WATERWAY MANAGEMENT PRACTICES Photo 1 Rock pad outlet structure at end of a duel stormwater pipe outlet Photo 2 Rock pad outlet structure at end of a multi-cell box culvert 1. Introduction The hydraulic forces generated by multiple pipe/cell outlets are higher than those expected at single pipe/cell outlets. Consequently the rock sizes required within outlet structures can be significantly different from those used on single pipe outlets. The primary performance objectives are to minimise the risk of soil erosion at the outlet and to prevent undermining of the structure. The critical design parameters are the mean rock size (d 50 ) and length of rock protection (L). The rock sizing design charts and tables presented in this fact sheet are based on the acceptance that some degree of rock movement (rearrangement) will likely occur following installation, and that some degree of bed scour will still occur downstream of the rock pad during major flows. The minimum pad length is based on practicality issues and will not necessarily prevent all bed scour, especially when high tailwater levels exist and the culvert is operating in outlet control conditions. 2. Sizing rock downstream of pipe and culvert outlets Recommended mean (d 50 ) rock sizes are presented in tables 2 & 3. These values have been rounded up to the next 100 mm increment in consideration of the limited availability of rock sizes and the high variability of expected outcomes. Mean rock sizes are also presented graphically in Figure 1. Some minor variations should be expected between Figure 1 and the tabulated values. A 36% increase in rock size is recommended if rounded rocks are used instead of angular rock. The recommended minimum length of rock protection (L) may be determined from tables 4 & 5. A typical layout of the rock pad is shown in Figure 2. The rock pad should be straight and aligned with the direction of the discharge. The recommended minimum width of the rock pad, W = B + 0.6 (Figure 2) is presented as a guide only. In most cases the width of rock protection will be limited by the width of the receiving channel. In circumstance where the width of the rock pad is governed by the width of the receiving channel, then the rock protection may need to extend partially up the banks of the channel if suitable vegetation cannot be established on the channel banks. The thickness of the rock pad should be based on at least two layers of rock. This typically results in an overall pad thickness as presented in Table 1. Catchments & Creeks Pty Ltd Version 3 August 2017 Page 1

Figure 1 Sizing of rock pad outlet structures for multi-pipe and box culvert outlets Figure 2 Typical layout of a rock pad for multiple pipe and box culverts (plan view) Table 1 Minimum thickness (T) of rock pad Min. thickness (T) Size distribution (d 50 /d 90 ) Description 1.4 d 50 1.0 Highly uniform rock size 1.6 d 50 0.8 Typical upper limit of quarry rock 1.8 d 50 0.67 Recommended lower limit of distribution 2.1 d 50 0.5 Typical lower limit of quarry rock [1] d 50 = nominal rock size (diameter) of which 50% of the rocks are smaller (i.e. the mean rock size). Catchments & Creeks Pty Ltd Version 3 August 2017 Page 2

The surface elevation of the downstream end of the rock pad should be level with the invert of the receiving channel, i.e. the rocks should be recessed into the outlet channel to minimise the risk of erosion around the outer edges of the rock pad. The placement of filter cloth under the rock pad is generally considered mandatory for all permanent structures; however, if heavy sedimentation is expected within the rock voids, then the need for the filter cloth is reduced. The placement of filter cloth is essential in circumstances where it is only practical to place a single layer of rock. 3. Selecting the appropriate length of rock protection In circumstances where it is essential to minimise the risk of bed scour downstream of the culvert, then the length of the rock pad should be twice that presented in tables 4 & 5; however, little value is gained from extending the rock protection any further. When the outlet is submerged (TW > H) a floating outlet jet can pass over the rock pad with minimal energy loss. In such cases the rock pad still provides essential scour protection adjacent the culvert, but extending the rock protection beyond the nominated minimum length may not necessarily provide any significant increase in energy dissipation or scour protection. High outlet jets can cause bank erosion problems if the outlet is aimed at a downstream embankment. Typically, such problems only occur if an unprotected embankment is less than 10 to 13 times the pipe diameter away from the outlet. Figure 3 Rock pad recessed into the receiving channel 4. Background to rock sizing for multi-cell culverts The mean rock sizes presented in tables 2 and 3 are based on a complex derivation. Unfortunately, most of the research has been carried out on single pipe outlets; however, it is suspected that the hydraulic energy produced by multi-cell and wide, flat-bed culverts is significantly greater than that observed for single pipe outlets. To improve the stability of rock pad outlet structures downstream of multi-cell outlets, the results presented for single pipe outlets were supplemented with work of Isbash (1936) based on low turbulent flow conditions. It was also recognised that for small culverts there would be insufficient flow energy to displace the large diameter rocks suggested by the Isbash equation. Consequently, the rock size was arbitrarily limited to the diameter/height of the outlet (or the next 100 mm increment as appropriate). 5. Reference Isbash, S.V. 1936, Construction of dams by depositing rock in running water, Transactions, Second Congress on Large Dams, Washington, D.C. USA. Catchments & Creeks Pty Ltd Version 3 August 2017 Page 3

Outflow (m/s) Table 2 Mean rock size, d 50 (mm) for culvert outlet scour protection 300 375 450 525 600 750 900 0.50 100 100 100 100 100 100 100 1.00 100 100 100 100 100 100 100 1.50 100 100 100 100 100 200 200 2.00 200 200 200 200 200 200 200 2.50 200 200 200 200 200 200 200 3.00 300 300 300 300 300 300 300 3.50 300 400 400 400 400 400 400 3.75 300 400 400 400 400 400 400 4.00 300 400 500 500 500 500 500 4.25 300 400 500 500 500 500 500 4.50 300 400 500 600 600 600 600 4.75 300 400 500 600 600 600 600 5.00 300 400 500 600 600 700 700 5.25 300 400 500 600 600 800 800 5.50 300 400 500 600 600 800 800 5.75 300 400 500 600 600 800 871 6.00 300 400 500 600 600 800 900 Table 3 Mean rock size, d 50 (mm) for culvert outlet scour protection Outflow (m/s) 1050 1200 1350 1500 1800 2100 2400 0.50 100 100 100 100 100 100 100 1.00 100 100 200 200 200 200 200 1.50 200 200 200 200 200 300 300 2.00 200 200 200 200 300 300 300 2.50 200 300 300 300 300 400 400 3.00 300 300 300 300 400 500 500 3.50 400 400 400 400 500 500 500 3.75 400 400 400 400 500 500 600 4.00 500 500 500 500 500 600 600 4.25 500 500 500 500 600 600 600 4.50 600 600 600 600 600 600 600 4.75 600 600 600 600 600 600 700 5.00 700 700 700 700 700 700 700 5.25 900 900 900 900 900 900 900 5.50 900 900 900 900 900 900 900 5.75 900 900 900 900 900 900 900 6.00 1000 1000 1000 1000 1000 1000 1000 Catchments & Creeks Pty Ltd Version 3 August 2017 Page 4

Table 4 Minimum length (L) of rock pad relative to cell height (H) for culvert outlet protection [1,2] Outflow (m/s) 300 375 450 525 600 750 900 0.50 3 3 3 3 3 3 3 1.00 3 3 3 3 3 3 3 1.50 3 3 3 3 3 3 3 2.00 3 3 3 3 3 3 3 2.50 3 3 3 3 3 3 3 3.00 3 3 3 3 3 3 3 3.50 3 3 3 3 3 4 4 3.75 3 3 3 3 4 4 4 4.00 3 3 3 4 4 4 4 4.25 3 3 4 4 4 4 4 4.50 3 4 4 4 4 4 4 4.75 3 4 4 4 4 4 5 5.00 4 4 4 4 4 4 5 5.25 4 4 4 4 4 5 5 5.50 4 4 4 6 6 6 6 5.75 4 4 6 6 6 6 6 6.00 4 6 6 6 6 6 6 Table 5 Minimum length (L) of rock pad relative to cell height (H) for culvert outlet protection [1,2] Outflow (m/s) 1050 1200 1350 1500 1800 2100 2400 0.50 3 3 3 3 3 3 3 1.00 3 3 3 3 3 3 4 1.50 3 3 3 3 3 4 4 2.00 3 3 3 3 4 4 4 2.50 3 4 4 4 4 4 4 3.00 4 4 4 4 4 4 4 3.50 4 4 4 4 5 5 5 3.75 4 4 4 4 5 5 5 4.00 4 4 5 5 5 5 5 4.25 4 5 5 5 5 5 5 4.50 5 5 5 5 5 5 5 4.75 5 5 5 5 5 5 5 5.00 5 5 5 5 6 6 5.25 6 6 6 6 6 6 5.50 6 6 6 6 6 5.75 6 6 6 6 6 6.00 6 6 6 6 6 [1] Values represent the recommended minimum length of rock protection to prevent significant scour; however, some degree of soil erosion should be expected downstream of the rock protection. [2] Under high tailwater conditions (TW > D/2) outlet jetting may extend beyond the rock protection during high tailwater conditions resulting in bed and/or bank erosion downstream of the rock protection. Extending the length of the rock protection will not necessarily reduce the risk of downstream bank erosion under high tailwater conditions. Catchments & Creeks Pty Ltd Version 3 August 2017 Page 5

Multiple pipe detention/retention basin outlets Five pipes stacked vertically Ten pipes stacked in two columns Ten pipes stacked in two rows Nine pipes stacked in three columns Multiple pipes stacked in a single column If a stormwater detention basin has a multi-pipe outlet with the pipes stacked along a vertical column, then such an outlet should be treated as for a single pipe outlet. Therefore, rock sizing (d 50 ) and the length of scour protection (L) for 5 x 375 mm pipes stacked in a single column should be based on a single-pipe 375 mm outlet. The equivalent pipe diameter remains as 375 mm in this case. Multiple pipes stacked in two columns If two or more pipes are stacked in vertical columns, the individual outlet jets will join to form a single outlet jet with energy dissipation governed by the width of this outlet jet (the smaller dimension). Thus for 10 x 375 mm pipes stacked in two columns, adopting a multi-pipe 375 mm outlet will provide the lower limit for rock sizing, while adopting the equivalent pipe diameter of a square block of 4 x 375 mm pipes (i.e. 750 mm) based on a single-pipe outlet will provide the upper limit for the rock size and pad length. Multiple pipes stacked in multiple columns In the case shown left, energy dissipation downstream of the outlet will be dictated by the depth of the combined outlet jet. Thus for 10 x 375 mm pipes stacked in two rows, adopting a multi-pipe 375 mm outlet will provide the lower limit for the rock size and pad length, while adopting the equivalent pipe diameter of a square block of 4 x 375 mm pipes (i.e. 750 mm), and using a multi-pipe outlet, will provide the upper limit for the rock size and pad length. Multiple pipes stacked in a group such that the effective depth and width of the outlet jet are similar In the case shown left, the individual outlet jets will combine to form a single circular outlet jet with a diameter equivalent to the combined flow area of the pipes. Thus, for 9 x 375 mm pipes, the equivalent pipe diameter = (9 x 375 2 ) 0.5 = 1125 mm. Therefore, rock sizing (d 50 ) and the length of scour protection (L) for 9 x 375 mm pipes should be based on a single-pipe 1125 mm outlet. Catchments & Creeks Pty Ltd Version 3 August 2017 Page 6

Common construction problems Inadequate rock size Rock of inadequate size can readily be displaced downstream of the outlet causing erosion to threaten the structure. Placement on dispersive soils (below) Outlet scour protection often fails when placed directly on a dispersive soil. The formation of a cut-off wall at the downstream end of the concrete apron can reduce the risk of structural failure, especially if placed on dispersive soils. Displacement of rock pad Undermining of outlet Same outlet eight years later Poor placement of rock If the rocks sit above the invert of the outlet, then: sediment is likely to collect within the pipes, and the outlet jet may be deflected towards the creek banks by the rocks. The rocks need to be recessed such that the upper surface of the rocks is level with the concrete apron. Inappropriate rock placement Outlet jetting During periods of high tailwater, the outlet jet can float along the water surface with minimal energy dissipation. Floating outlet jets can travel at speed around 10 to 15 times the jet diameter depending on the exit and the spacing between the pipes. Outlet too close to opposite bank Catchments & Creeks Pty Ltd Version 3 August 2017 Page 7