Commissioning of the SNS Beam Instrumentation

Similar documents
Laser Based Diagnostics for Measuring H - Beam Parameters

BEAM DYNAMICS ISSUES IN THE SNS LINAC

LASER BASED DIAGNOSTICS FOR MEASURING H - BEAM PARAMETERS

IFMIF mini-workshop on Beam Instrumentation. Ciemat, Madrid (Spain) 2-3 July 2007

PIP-II Injector Test s Low Energy Beam Transport: Commissioning and Selected Measurements

Front end, linac upgrade, and commissioning of J-PARC. Y. Liu KEK/J-PARC, Japan

Beam Diagnostics for Low Energy Proton and H - Accelerators. Vic Scarpine Fermilab 2012 BIW April 16-19, 2012

Beam Extraction by the Laser Charge Exchange Method Using the 3-MeV LINAC in J-PARC )

Beam Diagnostics and Instrumentation JUAS, Archamps Peter Forck Gesellschaft für Schwerionenforschnung (GSI)

Working Group F: Diagnostics and Instrumentation for High-Intense Beams Summary

Diagnostic Systems for Characterizing Electron Sources at the Photo Injector Test Facility at DESY, Zeuthen site

The SARAF 40 MeV Proton/Deuteron Accelerator

II) Experimental Design

SPIRAL 2 Commissioning Status

Diagnostics at SARAF

DIAGNOSTIC TEST-BEAM-LINE FOR THE MESA INJECTOR

Short Pulse, Low charge Operation of the LCLS. Josef Frisch for the LCLS Commissioning Team

Beam dynamics studies of H-beam chopping in a LEBT for project X

Cornell Injector Performance

SRF GUN CHARACTERIZATION - PHASE SPACE AND DARK CURRENT MEASUREMENTS AT ELBE*

IFMIF High energy beam line design and beam expansion using non-linear multipole lenses and "step-like" magnet

PIP-II Injector Test Warm Front End: Commissioning Update

Linac4: From Initial Design to Final Commissioning

LCLS Injector Prototyping at the GTF

NEW DEVELOPMENT IN HIGH POWER RFQ ACCELERATORS*

ILC Laser-wires. G A Blair, RHUL Snowmass 17 th August 2005

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

A Low Energy Beam Transport Design with high SCC for TAC Proton Accelerator

Status of Proof-of-Principle Experiment of Coherent Electron Cooling at BNL

Chopping High-Intensity Ion Beams at FRANZ

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics. Linac4 chopper line commissioning strategy

Design Status of the PEFP RCS

The MAX IV Thermionic preinjector

Tuning Techniques And Operator Diagnostics for FACET at SLAC National Accelerator Laboratory. Chris Melton SLAC Accelerator Operations

Update on Development of High Current Bunched Electron Beam from Magnetized DC Photogun

RF BARRIER CAVITY OPTION FOR THE SNS RING BEAM POWER UPGRADE

HALO SIMULATION IN A REALISTIC PROTON LINAC DESIGN

Shielding calculations with MCNPX at the European spallation source

The TESLA Dogbone Damping Ring

Diagnostics Needs for Energy Recovery Linacs

FACET-II Design Update

Setting the Spiral2 control system for the on-going commissioning. Eric Lécorché/ Epics meeting 21/10/2014 1

1.5-GeV FFAG Accelerator as Injector to the BNL-AGS

The DAΦNE Beam Test Facility

Demonstration of Energy-Chirp Control in Relativistic Electron Bunches at LCLS Using a Corrugated Structure. Karl Bane, 7 April 2017,, KEK

Application of Carbon Nanotube Wire for Beam Profile Measurement of Negative Hydrogen Ion Beam

The Accelerator System for ReA3 the New Re-accelerated RIBs Facility at MSU

Low Energy RHIC electron Cooling (LEReC)

ThomX Machine Advisory Committee. (LAL Orsay, March ) Ring Beam Dynamics

Development of Large Scale Optimization Tools for Beam Tracking Codes

X-band Experience at FEL

The SARAF CW 40 MeV Proton/Deuteron Accelerator

How J-PARC recovered from the big earthquake

LOLA: Past, present and future operation

DEVELOPMENT OF LARGE SCALE OPTIMIZATION TOOLS FOR BEAM TRACKING CODES*

ERL FACILITY AT CERN FOR APPLICATIONS

R&D on µ-lom monitors for High intensity Linacs like LIPAc

Charge for WG2 (Optics and Beams)

OVERVIEW OF THE BEAM DIAGNOSTICS FOR THE DRIVER OF SPIRAL2

Accelerator Physics. Accelerator Development

VELA/CLARA as Advanced Accelerator Studies Test-bed at Daresbury Lab.

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

Beam Dynamics for CSNS Linac. Jun Peng September. 18, 2012

Preliminary design studies of a 100 MeV H /H + LINAC as injector for SNS synchrotron/ads LINAC

China high-intensity accelerator technology developments for Neutron Sources & ADS

Accelerator Design of High Luminosity Electron-Hadron Collider erhic

The New Superconducting RF Photoinjector a High-Average Current & High-Brightness Gun

7th IPAC, May 8-13, 2016, Busan, Korea

Notes on the HIE-ISOLDE HEBT

12 GeV CEBAF Beam Parameter Tables

Developmental Studies of High Current Proton Linac for ADS Program

MEASURING AND CONTROLLING ENERGY SPREAD IN CEBAF

WG2 on ERL light sources CHESS & LEPP

Low slice emittance preservation during bunch compression

In-Flight Fragment Separator and ISOL Cyclotron for RISP

New Electron Source for Energy Recovery Linacs

Beam diagnostics: Alignment of the beam to prevent for activation. Accelerator physics: using these sensitive particle detectors.

Development of Cs 2 Te photocathode RF gun system for compact THz SASE-FEL

Accelerators and Lasers In Combined Experiments Susan Smith Daresbury Laboratory

CEPC Linac Injector. HEP Jan, Cai Meng, Guoxi Pei, Jingru Zhang, Xiaoping Li, Dou Wang, Shilun Pei, Jie Gao, Yunlong Chi

Proposal to convert TLS Booster for hadron accelerator

Developments of the RCNP cyclotron cascade

Development and application of the RFQs for FAIR and GSI Projects

6 Bunch Compressor and Transfer to Main Linac

Higgs Factory Magnet Protection and Machine-Detector Interface

A Project to convert TLS Booster to hadron accelerator 1. Basic design. 2. The injection systems:

RHIC Electron Lens Commissioning

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

Performance Studies of the Vibration Wire Monitor on the Test Stand with Low Energy Electron Beam

The VELA and CLARA Test Facilities at Daresbury Laboratory Peter McIntosh, STFC on behalf of the VELA and CLARA Development Teams

A high intensity p-linac and the FAIR Project

High Intensity Operation and Control of Beam Losses in a Cyclotron based Accelerator

Accelerator Design and Construction Progress of TPS Project

Accelerator R&D Opportunities: Sources and Linac. Developing expertise. D. Rubin, Cornell University

TTF and VUV-FEL Injector Commissioning

Small Isochronous Ring (SIR) project at NSCL, MSU. Eduard Pozdeyev NSCL, Michigan Sate University

Juliane Rönsch Hamburg University. Investigations of the longitudinal phase space at a photo injector for the X-FEL

PRELIMINARY TEST OF A LUMINESCENCE PROFILE MONITOR IN THE CERN SPS

Femto-second FEL Generation with Very Low Charge at LCLS

Development status of non-destructive assay of nuclear material by using laser Compton scattered gamma-rays

Transcription:

Commissioning of the SNS Beam Instrumentation Commissioning of the SNS Beam Instrumentation Tom Shea for the SNS Diagnostics Team Oak Ridge National Laboratory (ORNL), Oak Ridge, TN, USA

The Spallation Neutron Source Partnership ~113 M$ The SNS will begin operation in 2006 At 1.4 MW it will be ~8x ISIS, the world s leading pulsed spallation source 5000 hours per year at an availability of >90% (~ in 2009)

Accelerator Overview Now Commissioned to 158 MeV through CCL RFQ DTL 65 kev 2.5 MeV 402.5 MHz 805 MHz 1 RFQ 6 DTL Tanks 4 CCL Modules CCL SRF, β=0.61 86.8 MeV186 MeV 387 MeV 1.0 GeV Ring Up to 1.3 GeV SRF, β=0.81 1000 MeV HEBT To Ring 11 Medium-β Cryomodules - 3 Nb cavities each 12 High-β Cryomodules - 4 Nb cavities each Proton energy on target 1.0 GeV Power on target 1.4 MW Pulse repetition rate 60 Hz Macro-pulse length 1 ms Ave. current in macro-pulse 26 ma H - peak current front end > 38 ma Peak current in ring 52 A Proton pulse width on tgt 695ns Energy per Pulse >17 kj Uncontrolled beam loss <1 W/m

Commissioning runs in parallel with installation 1 2 3 4 5 6 7 8 9 2002 2003 2004 2005 2006 Run #1: - RFQ at LBNL (2.5 MeV), Jan 25th through Feb 2002 - beam stop for design beam power Run #2: - Front End at LBNL (2.5 MeV), Apr 4 to May 31, 2002 - beam stop for design beam power Run #3: - Front End at ORNL (2.5 MeV), Nov 5, 2002 to Jan 31, 2003 - beam stop for design beam power Run #4: - Front End, DTL tank 1, D-Plate (7.5 MeV), Aug 26 to Nov 17, 2003 - beam stop and radiation shield for design beam power Run #5: - Front End & DTL tank 1,2,3 (39 MeV) Spring 2004 - Beam stop and radiation shield for reduced beam power (50us, 1Hz) Run #6 : - Front End, DTL, CCL modules 1,2,3 (158 MeV) Fall 2004 - Beam stop and radiation shield for reduced beam power (50us, 1Hz) Run #7 : - Front End, DTL, CCL, SCL (1 GeV), Fall 2005 Run #8 : - Front End, DTL, CCL, SCL, Ring (1 GeV), Early 2006 Run #9 : - Front End, DTL, CCL, SCL, Ring, Target (1 GeV), by June 30, 2006

RFQ at Berkeley - 2 Diagnostic Devices Commissioning: Jan 25 th through Feb 2002 1 2002 2003 2004 2005 2006 RFQ 1 Emittance (one plane) 1 Faraday Cup (scope) 8 ma transmitted on first pulse, 24 ma current on first day Emittance integrated with controls, all else via scopes

RFQ Commissioning at LBNL Emittance Vertical: 0.325 pi mm mrad (design goal: 0.3 pi mm mrad) Distribution has about 1% floor most likely due to scattering (not emittance in this case) J. Staples, LBNL

Front End at Berkeley - 16 Devices April 4, 2002 to May 31, 2002 2 2002 2003 2004 2005 2006 MEBT 6 Position 2 Current 5 Wires 1 Laser (test) 1 Emittance (0ne Plane) MEBT RFQ Ion Source All diagnostic systems were prototypes of linac systems Integrated with EPICS via portable channel access All integrated at LBNL within one week and delivered useful information for commissioning Photo Daryl Oshatz, LBNL

Carbon Wire Scanners This case: 20 ma debunched beam Compare measured rms transverse beam size to Trace3D simulation Virtually all measurements agree with model to within 10%, most within 5%

Beam Position Monitors Position met spec; Phase was not quite there EPICS screen app the the orbit orbit app app worked worked live live from from ORNL ORNL -- simply simply initialize with with the the Process Variable names names Channel Access Histogram of BPM1 BPM2 phase difference (goal <<1deg) Electrodes - LBNL Cables & install -LBNL Electronics, NAD software - LANL

Laser Photo-neutralization of H- Ions Horizontal Motor Switch Motor Lens Motor Vertical Motor Beam Pipe with view ports beam Calculated cross section for H- photoneutralization as a function of photon wavelength.* Nd:YAG laser has λ=1064nm where the cross section is about 90% of the maximum. *J.T. Broad and W.P. Reinhardt, Phys. Rev. A14 (6) (1976) 2159. Lens Motor Scan laser transversely across ion beam Plot one of the following vs. laser beam position: Missing current in H- beam Collected electrons liberated from H- beam

Transverse Profiles measured with Laser at LBNL First measurement of SNS beam with by laser photo-neutralization Small Nd YAG laser system provided by BNL and installed at LBNL, measurements performed by ORNL Amplitude of missing beam current plotted vs Scanning mirror position

FE/MEBT at ORNL = 19 Devices Nov 5, 2002 through Jan 31, 2003 3 2002 2003 2004 2005 2006 Test of SCL laser system, gap measurement MEBT 6 Position 2 Current 5 Wires 2 Neutron 1 Emittance Horizontal 1 Fast Faraday Cup 1 SCL Laser Based on LBNL experience, added neutron detectors (first borrowed from LBNL, then part of INR collaboration)

Front End at ORNL Jan 2003 Laser Profile Monitor Results at 2.5 MeV Verification of electron collection for SCL laser profile monitor Reliable measurements to about 3 sigma Anti-reflection coating for final windows. May measure well beyond 3 sigma. Horizontal Profile 1/25/2003 13:06 Gaussian fit plotted out to 2.5x Sigma Sigma = 1.07 mm Signal from electron collector Top: laser intercepting beam core Bottom: laser intercepting beam tail

Through DTL Tank 1/D-Plate: 31 Devices August 26 through Nov 17, 2003 4 2002 2003 2004 2005 2006 last run at full power until beam on target Diff BCM (analog) MEBT 6 Position 2 Current 5 Wires 2 Thermal Neutron 1 Fast Faraday Cup 1 Faraday/Beam Stop Differential BCM Test BSM Migration to EPICS IOC core, structured LabVIEW DTL/D-Plate 2 Position 1 Current 2 Wire 7 Ion Chamber 4 Thermal 3 Semi 2 Faraday Cup 1 Bunch 1 Video 1 Halo 3 Neutron 1 Beam Stop Faraday Cup 1 Emittance (Slit and Collector) Differential BCM

DTL Faraday Cup First beam through DTL-1 Tank was seen on console in control room. Typical Faraday Cup (energy degrader removed)

Commissioning through first 3 (of 6) DTL Tanks: 54 Diagnostic Devices 5 2002 2003 2004 2005 2006 D-plate removed Added D-box to MEBT for inline emittance and others MEBT 6 Position 2 Current 5 Wires 2 Thermal Neutron 1 Emittance Horizontal 1 Emittance Vertical 1 Faraday/Beam Stop D-box emittance D-box beam stop D-box aperture Differential BCM Improved phase performance of all BPMs DTL 5 Position 3 Wire 3 Faraday Cup 3 Current 7 Loss Ion Chamber Differential BCM 4 Thermal 3 Semiconductor

BPM delivers Position and Phase DTL3 Results Pulse-to-Pulse Phase Jitter LLRF Goal: 0.5 degrees (at 402.5 MHz) Measurements as low as 0.1 degrees at 805 MHz (0.05 deg @ 402.5) indicate that BPM/Phase diagnostics are meeting spec (also validates new LLRF systems) Histogram of measured beam phase with respect to RF reference

CCL commissioning: 136 Devices 6 2002 2003 2004 2005 2006 MEBT 6 Position 2 Current 5 Wires 2 Thermal Neutron 1 Emittance Horizontal 1 Emittance Vertical 1 Mode-locked Laser 1 Faraday/Beam Stop D-box emittance D-box beam stop D-box aperture Differential BCM CCL 10 Position 9 Wire 8 Neutron, 3 BSM, 2 Thermal 28 Loss 3 Bunch 1 Faraday Cup 1 Current 1 Dump DTL 10 Position 5 Wire 12 Loss 5 Faraday Cup 6 Current 6 Thermal and 12 PMT Neutron Differential BCM Tools to support large scale deployment: database configuration control, Altiris, Windows XP, collaboration with IT Migrate to fiber distribution of Diagnostics RF reference

Position and loss measurements through CCL Beam trajectory from RFQ exit to CCL beam dump. Vertical scale +/- 1mm Beam loss distribution along the linac. Raw data with beam on (left), no beam (center), With beam on and subtracted background (right). Now integrated with machine protect system.

Difference orbit through CCL first try Model vs measurements Plots by P. Chu

Difference orbit after correcting integrated field values in model Plots by P. Chu

Effect of beam loading in the Linac Bunch Shape Monitor results Cavity field and phase droop with feedback alone (left) and feedback + feedforward (right) beam loading compensation. Phase width of the bunch along the pulse with feedback alone (left) and feedback + feedforward (right). Phase width in CCL is larger than design value.

Simulated beam envelope compared to Carbon wire scanners results in DTL and CCL First try In model, increase longitudinal emittance x 3 and Increase Quad QH102 by 6%: Plots by J. Galambos

Mode Locked Laser First Longitudinal Measurements 2.5 MeV H-, 402.5 MHz bunching freq, TiSapphire laser phase-locked @ 1/5 th bunching freq; collected electron signal plotted vs. phase Measured and predicted bunch length vs. cavity phase setting

Global view provided by Channel 13 An example supervisory layer application W. Blokland M. Sundaram C. Long

Complete Linac: 326 Devices Commissioning begins late summer 2005 7 2002 2003 2004 2005 2006 MEBT 6 Position 2 Current 5 Wires 2 Thermal Neutron 1 Emittance Horizontal 1 Emittance Vertical 1 Fast Faraday Cup 1 Mode-locked Laser 1 Faraday/Beam Stop D-box video D-box emittance D-box beam stop D-box aperture Differential BCM CCL 10 Position 9 Wire 8 Neutron, 3 BSM, 2 Thermal 28 Loss 3 Bunch 1 Faraday Cup 1 Current 1 Dump DTL 10 Position 5 Wire 12 Loss 5 Faraday Cup 6 Current 6 Thermal and 12 PMT Neutron Differential BCM CCL/SCL Transition 2 Position 1 Wire 1 Loss 1 Current SCL 32 Position 86 Loss 8 Laser Wire 7 PMT Neutron HEBT 11 Position 5 Wire 17 BLM, 3 FBLM 2 Current LDump 6 Loss 6 Position 1 Wire,1 BCM

Ring then to Target: 602 Devices Commissioning in first half of 2006 8 9 2002 2003 2004 2005 2006 MEBT 6 Position 2 Current 5 Wires 2 Thermal Neutron 1 Emittance Horizontal 1 Emittance Vertical 1 Fast Faraday Cup 1 Mode-locked Laser 1 Faraday/Beam Stop D-box video D-box emittance D-box beam stop D-box aperture Differential BCM DTL 10 Position 5 Wire 12 Loss 5 Faraday Cup 6 Current 6 Thermal and 12 PMT Neutron Differential BCM IDump RING 1 Position 44 Position 2 Ionization Profile 1 Wire 70 Loss 1 Current 1 Current 5 Electron Det. 12 FBLM 6 BLM 2 Wire 1 Beam in Gap 2 CCL Video 1 Tune 10 Position 9 Wire EDump 8 Neutron, 3 BSM, 1 Current 4 Loss 2 Thermal 1 Wire 28 Loss 3 Bunch 1 Faraday Cup 1 Current 1 Dump RTBT 17 Position 36 Loss 4 Current 5 Wire 1 Harp SCL 3 FBLM HEBT 32 Position 86 Loss 29 Position 11 Wire 8 Laser Wire 46 BLM, 3 FBLM LDump 7 PMT Neutron 4 Current 6 Loss CCL/SCL Transition 6 Position 2 Position 1 Wire 1 Wire,1 BCM 1 Loss 1 Current

Summary The SNS Diagnostics Team has deployed a variety of instruments that is unprecedented at this stage of commissioning. Interleaving commissioning and installation has been challenging, but based on experience from early commissioning runs, several systems have already been added or upgraded. System readiness, controls integration, and general performance has been outstanding. 50% of our beam instrumentation is installed; 25% is commissioned with beam. All partner laboratories have completed their work and Oak Ridge now has full responsibility. It will be a busy year.