The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework

Similar documents
Task 2.4 on LHC Collective Effects Studies

Transverse beam stability and Landau damping in hadron colliders

HL-LHC OPERATIONAL SCENARIOS

COLLECTIVE EFFECTS IN THE LHC AND ITS INJECTORS

Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group

TRANSVERSE DAMPER. W. Höfle, CERN, Geneva, Switzerland. Abstract INTRODUCTION AND HIGHLIGHTS IN Controlled Transverse Blow-up

HL-LHC ALTERNATIVES SCENARIOS

Plans for 2016 and Run 2

OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE

LHC Run 2: Results and Challenges. Roderik Bruce on behalf of the CERN teams

CERN-ATS HiLumi LHC. FP7 High Luminosity Large Hadron Collider Design Study PUBLICATION

Beam-Beam DA Simulations for HL-LHC

DEBRIEFING AND FOLLOW-UP OF THE LPL REVIEW

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report SIMULATION MODELS FOR ENERGY DEPOSITION

HL-LHC: parameter space, constraints & possible options

LHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1

OPERATIONAL BEAMS FOR THE LHC

TRANSVERSE IMPEDANCE OF LHC COLLIMATORS

Simulations of single bunch collective effects using HEADTAIL

MD Landau Damping: Beam Transfer Functions and diffusion mechanisms

Elias Métral, LHC Collimation Working Group Meeting, 15/03/ /31

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

Luminosity Goals, Critical Parameters

LUMINOSITY LEVELLING TECHNIQUES FOR THE LHC

The Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory

ULTIMATE LHC BEAM. G. Arduini, CERN, Geneva, Switzerland

Raising intensity of the LHC beam in the SPS - longitudinal plane

Status of the LIU project and progress on space charge studies

The TESLA Dogbone Damping Ring

Beam instabilities (I)

Simulations of HL-LHC Crab Cavity Noise using HEADTAIL

Challenges and Plans for the Proton Injectors *

Main aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5)

LHC Luminosity and Energy Upgrade

DYNAMIC APERTURE STUDIES FOR HL-LHC V1.0 *

ACHIEVABLE SPACE-CHARGE TUNE SHIFT WITH LONG LIFETIME IN THE CERN PS & SPS

LHC Upgrade Plan and Ideas - scenarios & constraints from the machine side

THE PS IN THE LHC INJECTOR CHAIN

Electron cloud effects for PS2, SPS(+) and LHC

Beam Optics & Dynamics Studies for LHC

Summary of Group A: Beam Dynamics in High- Intensity circular machines

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

Overview of LHC Accelerator

Impedance and Collective Effects in Future Light Sources. Karl Bane FLS2010 Workshop 1 March 2010

Beam Physics at SLAC. Yunhai Cai Beam Physics Department Head. July 8, 2008 SLAC Annual Program Review Page 1

Impedance & Instabilities

CHAMONIX WORKSHOP, SESSION 5 LIU SUMMARY

Electron cloud observation in the LHC

SPACE CHARGE EXPERIMENTS AND BENCHMARKING IN THE PS

Numerical Methods II

Emittance Growth and Tune Spectra at PETRA III

Status and Outlook of the LHC

NUMERICAL MODELING OF FAST BEAM ION INSTABILITIES

e-cloud DAFNE T. Demma INFN-LNF

Status of the LHC Beam Cleaning Study Group

( ( )) + w ( ) 3 / 2

Run2 Problem List (Bold-faced items are those the BP Department can work on) October 4, 2002

FY04 Luminosity Plan. SAG Meeting September 22, 2003 Dave McGinnis

Beam. RF antenna. RF cable

LHC Beam Operations: Past, Present and Future

Electron Cloud in Wigglers

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

Sunday morning: Beam Dynamics Issues. Session highlights and outstanding questions. M. Pivi and D. Rubin ECLOUD10 October 8-12 Cornell University

TUNE SPREAD STUDIES AT INJECTION ENERGIES FOR THE CERN PROTON SYNCHROTRON BOOSTER

MEASUREMENT AND SIMULATION OF LUMINOSITY LEVELING IN LHC VIA BEAM SEPARATION

LHC. LHC Crabs, Status. Brief Overview. Status of Technology R&D. Status of Simulations & Experiments. Rama Calaga RFTECH, Dec 2-3, 2010

The Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy

Electron-Cloud Theory & Simulations

On behalf of: F. Antoniou, H. Bartosik, T. Bohl, Y. Papaphilippou (CERN), N. Milas, A. Streun (PSI/SLS), M. Pivi (SLAC), T.

LHC Commissioning in 2008

Accelerator Physics. Accelerator Development

On-axis injection into small dynamic aperture

Beam-induced heat loads on the beam screens of the inner triplets for the HL-LHC

LHC operation in 2015 and prospects for the future

Minutes of the HSC section. 5th meeting on Wednesday 26/02/2014 (09:00, 6/2-004)

High performance computing simulations. for multi-particle effects in the synchrotons

SPS IMPEDANCE BUDGET

Electron cloud effects in KEKB and ILC

Calculation of Wakefields and Higher Order Modes for the New Design of the Vacuum Chamber of the ALICE Experiment for the HL-LHC

PBL (Problem-Based Learning) scenario for Accelerator Physics Mats Lindroos and E. Métral (CERN, Switzerland) Lund University, Sweden, March 19-23,

BEAM DYNAMICS STUDIES FOR HILUMI LHC

First propositions of a lattice for the future upgrade of SOLEIL. A. Nadji On behalf of the Accelerators and Engineering Division

A Luminosity Leveling Method for LHC Luminosity Upgrade using an Early Separation Scheme

ThomX Machine Advisory Committee. (LAL Orsay, March ) Ring Beam Dynamics

Numerical study of FII in the ILC Damping Ring

e + e Factories M. Sullivan Presented at the Particle Accelerator Conference June 25-29, 2007 in Albuquerque, New Mexico e+e- Factories

Aperture Measurements and Implications

COMBINER RING LATTICE

Operational Experience with HERA

UPDATE OF THE SPS KICKERS

NEXT GENERATION B-FACTORIES

On the future plan of KEK for ILC(International Linear Collider) Junji Urakawa(KEK) Contents

Es#ma#ons of Collec#ve Instabili#es for JLEIC

LHC Upgrade (accelerator)

Linear Collider Collaboration Tech Notes

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

Beam induced heat loads on the beam-screens of the twin-bore magnets in the IRs of the HL-LHC

(Lead) Ions in the LHC

Commissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department

Transcription:

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 CapaciBes Specific Programme, Grant Agreement 284404.

COLLECTIVE EFFECTS: STATUS AND PLAN Introduction The 5 main activities of Task 2.4 in 2012 Conclusion Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 1 /25

Considerable increase of LHC luminosity in 2011 and 2012 Peak luminosity record: ~ 7.7E33, i.e. 77% of design luminosity 4 / 7 = 57% of design energy ½ number of bunches (50 ns spacing instead of 25 ns): 1374 b ~ 1.6 10 11 p/b within ~ 2.2 µm (transv. r.m.s. norm. emittance) Bunch brightness: ~ (1.6 / 1.15) (3.75 / 2.2) ~ 2.4 times larger than nominal => ~ 2.4 times more critical for octupoles current Tight collimators settings in 2012 => Larger impedances and more critical instabilities (factor ~ 2.3 compared to 2011) => ~ 2.3 more octupoles needed Change of octupoles sign in July (see later why) => ~ 65% more current needed (assuming Gaussian transverse distribution) => Factor ~ 9 more octupoles current needed! 3 types of instabilities perturbed the intensity ramp-up Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 2 /25

ITEM 1): Definition of the work packages and distribution among the various collaborators and institutes ITEM 2): Intra-Beam Scattering (IBS) studies for the current LHC, nominal LHC and HL-LHC, and setting-up of a benchmarking case with all the IBS contributors ITEM 3): Evaluation of the impedance budget for the crab cavities to be installed in the HL-LHC, and dedicated impedance studies for other equipments ITEM 4): Follow-up of the LHC performance and participation to the LHC Machine Developments (MDs) via beam experiments in order to improve the understanding of collective effects in the present machine and assess our predictive power for the HL-LHC in terms of intensity limitations ITEM 5): Development of new ideas to push the machine performance Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 3 /25

All the information related to the Task 2.4 (objectives, description of the work, sub-tasks, milestones, deliverables, person-months from the collaboration, work breakdown structure, Gantt chart, mailing list of 29 people, meetings, publications, inputs needed, questions raised, etc.) can be found at the following link: https://espace.cern.ch/hilumi/wp2/task4/sitepages/home.aspx This web page is maintained by the Task leader and 3 Task 2.4 meetings took place until now Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 4 /25

Studies have been finalized and presented at the occasion of a Task 2.4 meeting, revealing no major issues with the current HL-LHC parameter set => Full report under publication, from Michaela Schaumann, John Jowett and Roderik Bruce A benchmarking case was also set-up to benchmark with other IBS codes in other labs Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 5 /25

Michaela Schaumann et al. IBS growth rates Calculations done with MADX and CTE (Collider Time Evolution) programs at injection (450 GeV) and collision (7 TeV) energy for various optics and beam parameter options => Both codes are in good agreement 2 ATS Optics version considered: ATS-V6.503 and SLHCV3.1b CTE simulations have included the evolution of beam parameters and luminosity with self-consistent IBS calculations, including non-gaussian longitudinal distributions and losses from the RF bucket, radiation damping and the loss of intensity due to luminosity production ( burn off ) Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 6 /25

Effect of the ATS Squeeze on IBS Growth Rates Michaela Schaumann et al. 45678#9"8&213&!!!"#$%&'()&*+",-.&/$-01&213& "#$%&#'()*!!! +#',%(-.%')*!!!!! +#',%(-.%')*! "#$%&#'()*!!!!!!! H!/0-'12#'!345! Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 7 /25

Michaela Schaumann et al. Beam and Luminosity Evolution O$#")(*"/6P:$)90+ A)/-)*"/6+!!!!!!"#$%&'()*+,()-+."/0+123+ 4"5/$&%+%$#")(*"/6+-7(%$'()+8+)(+95&:+9&7"'-*+ &),+%-7-%%");+ <&,"&'()+,&#=");+0&*+=(*"'7-+->-9/+()+ -#"?&)9-+;5(./0+&),+%-&,*+/(+5-,$9'()+(@+ :$)90+%-);/0+ A)/-)*"/6+%(**-*+&5-+,(#")&/-,+:6+%$#")(*"/6+ :$5)+(>+B+,-:$)90");+%(**-*+&5-+)-;%";":%-+ CD)*+:-&#+=5(,$9-*+#(5-+%$#")(*"/6+/0&)E*+ /(+/0-+0";0-5+")"'&%+:$)90+")/-)*"/6+ JCDH+ %(**-*+ FGH+ %(**-*+ L(5"M()/&%+3#"?&)9-+ JKCH++ ;5(./0+ N$)90+O-);/0+ JGDH+,-9&6+ I-:$)90");+ Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 8 /25

Will be discussed in detail during the talk of Benoit Salvant In particular, work was done by some collaborators Vacuum chamber in the CMS experiment Rainer Wanzenberg and Olga Zagorodnova (DESY) Broad-band kicker for SPS intra-bunch feedback system Mikhail Zobov et al. (LNF INFN) Some guidance for the impedance budget of the Crab Cavities was already given in 2011 at LHC-CC11 workshop by the different so-called compact Crab Cavity prototypes have been designed and built following these recommendations Following the 2011 LHC run with issues identified for some components with RF fingers, a dedicated task force was set up in 2012 to review all these equipments (see http://emetral.web.cern.ch/emetral/lrff/lrff.htm) => Recommendations should be made by the end of the year (both for the LHC and HL-LHC) Alexey Burov (LARP-LTV) and Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 9 /25

RF heating of some equipments is worrisome => Closely followed up and more MDs are needed to assess all the possible future limitations Benoit Salvant Some successful impedance reductions have however been already achieved, as for instance on one of the modules forming the injection kicker, but further modifications will be required for the HL-LHC era Hugo Day and Mike Barnes Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 10 /25

3 types of instabilities perturbed the intensity ramp-up: 1) during or at the end of the squeeze process 2) during the collapsing process (putting the beams into collision) 3) in collision (during the levelling process with parallel separation in LHCb, but for some specific bunches only) 2) Xavier Buffat 1) B1H osc. Ampl. LCMS LATLAS LLHCb Xavier Buffat 3) Gianluigi Arduini Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 11 /25

Concerning 2) and 3), possible explanation => Landau octupoles (with negative sign) and beam-beam long-range fought against each other For this reason the polarity of the Landau octupoles was changed in July, as proposed by Stephane Fartoukh. Studies also from Xavier Buffat et al. Furthermore, the gain of the transverse damper was increased to about its maximum damping rate (50 turns) and the chromaticity (initially kept to a few units) set to ~ 15-20 units Since then the beam dumps linked to the instabilities disappeared and the intensity could be increased, but then instabilities at the very the end of the squeeze reappeared (mainly B1V. With the other sign, it was mainly in H ) More Landau octupoles current is needed during the physics fills (i.e. with 2 beams) than in dedicated MDs with only one beam. In particular, the octupole current used in operation is close to its maximum value of 550 A, which is currently a major concern for HL-LHC => Ongoing studies: Two-beam effects such as two-beam impedances: MD foreseen (using cogging ), proposed by Stephane Fartoukh Interplays impedances / beam-beam effects => See talk from Simon White Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 12 /25

Organization and detailed analysis of the single-beam MDs (still ongoing) by Nicolas Mounet Fill Number date time beam(s) present stage beam affected 2744 (MD) 19/06/2012 11:48:00 PM 2 before squeeze 2 bunches affected by losses Instab. Plane intensity per bunch number of bunches beginning of batches + some in the middle of batches + complete 12 bunches batch V 1.50E+011 1380 2771 (MD) 23/06/2012 07:06:00 PM 2 after squeeze 2 all over the place V 1.43E+011 1380 2771 (MD) 23/06/2012 08:19:00 PM 2 after squeeze 2 close to the end of trains plus a few in the middle V 1.40E+011 1380 2771 (MD) 23/06/2012 08:49:00 PM 2 after squeeze 2 all over the place V 1.40E+011 1380 2771 (MD) 23/06/2012 09:55:00 PM 2 after squeeze 2 all over the place V 1.37E+011 1380 note: emittance measured at injection! then +0.5 mm.mrad for B2H (from V. Kain, CMAC talk, Aug 2012), the rest + 10% (~arbitrary - see also same talk) focusing octupole current [A] Qx/Qy Q'x/Q'y emit x/y [mm.mrad] ADT damping time x/ y [turns] (rate [omega_s]) Total bunch length [ns] Headtail mode number Rise time [s] Instability visible on available ADT data? 8.35 +/- 0.05 100 / 200 (0.7 / -100 0.28/0.31 4.1 +/- 0.3 2? / 2? 0.35) 1.2-1 (BBQ) 6.3 (BBQ) no 11 +/- 2-20 0.308/0.32 4 +/- 0.5 2 / 2 50 / 100 (1.4 / 0.7) 1.23 0? (BBQ) 20 (BBQ) no -1.9 +/- 1.3-240 0.308/0.32-5 +/- 0.5 2 / 2 50 / 100 (1.4 / 0.7) 1.24-1? (BBQ) 14 (BBQ) no 8 +/- 2-60 0.308/0.32 1 +/- 0.5 2 / 2 50 / 100 (1.4 / 0.7) 1.26-2? (BBQ) 16 (BBQ) no 2.8 +/- 0.6 Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012-400 0.308/0.32 2.4 +/- 0.6 2 / 2 inf / inf (0 / 0) 1.26-1? (BBQ) 3.6 (BBQ) no 13 /25

Example of current instability (with the new, positive sign of the Landau octupoles), max. damper gain and chromas at ~ 15-20 units Tatiana Pieloni Nicolas Mounet Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 Very reproducible => At the end of the squeeze (β* = 0.6 m), after ~ 16 min from the start of the squeeze 14 /25

The new values of the transverse damper gain and chromaticity were suggested after a new analytical approach => Nested Head-Tail (NHT) Vlasov Solver developed Alexey Burov (LARP-LTV) It assumes arbitrary multi-bunch beam with arbitrary train structure, arbitrary impedance, arbitrary frequency profile of the damper gain, arbitrary transverse and longitudinal nonlinearities and beam-beam collision scheme. The corresponding functions are supposed to be provided in any form The program computes all the relevant coherent modes with their head-tail, radial and couple-bunch structure for a given gain amplitude and beam chromaticity After that, the threshold strength of the Landau elements is computed by means of pre-calculated stability diagrams The NHT is under construction, being extended, upgraded and anti-bug checked day after day Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 15 /25

1.4 50 turns damper gain Valley with 0 octupoles Same as SB Q 2 nominal impedance Valley is lost Same as SB Alexey Burov Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 16 /25

Finally, initial tests with bunches spaced by 25 ns (instead of 50 ns as used now) were encouraging with respect to the mechanisms linked to electrons cloud, but this beam still needs to be studied in more detail in the LHC to identify possible bottlenecks In parallel, the operating experience with electron cloud clearing electrodes at DAFNE has been reviewed, revealing a very beneficial impact of clearing electrodes Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 17 /25

ECLOUD studies in the LHC with 25 ns beam 2<=6>$ 6?=@6$ @5=@6$ 25A23=@6$ 36.#$ %+''$,-./00123$41,().5$)6$789$".-,$!!"# $!"#$%&'(&"#&%$)(*+$,!&$ -.-/"0$%&'$()$'&*%$-.$,!&$"('#$1$ Giovanni Iadarola, Giovanni Rumolo et al. 23.#$,!(&#!*0%$ 4536$7&8$ 23.#$,!(&#!*0%$49:3$;&8$ Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 18 /25

!"#$%&'()*+!+!!"# $,-./+0(+%&'$ 1&//./+2.34 5 6#+$)7&408+9.&#:+ ;.&*$<.#.)0*+!+0=.+.).<>?+%(**+4.<+9$)7=+ "*+(90&")./+@<(#+0=.+*0&9%.+4=&*.+*="A+ BCC;+ ()"!$%$ Obtained from an energy balance for the e-cloud G. Iadarola, G. Rumolo, J.E. Muller, E. Shaposhnikova et al. Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 19 /25

G. Iadarola, G. Rumolo, J.E. Muller, E. Shaposhnikova et al. Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 20 /25

E-cloud clearing electrodes at DAΦNE Mikhail Zobov et al. In wigglers Lower tune spread In bending magnets Weaker instability No transverse blow up Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 21 /25

The use of circular modes and flat emittance beams has been proposed by Alexey Burov (LARP-LTV), as an alternative plan, which seems promising and deserves to be studied in more details Conventional X / Y betatron oscillations can be referred to as a planar optics Instead of X / Y eigenmodes in uncoupled case, we may have clockwise / counter-clockwise optical modes = Circular optics To have circular optics => Focusing has to be rotationally invariant in the transverse plane 2 possible applications, which need to be studied in detail (IBS issues, preservation of circular optics, etc.) Space charge => Limit from bigger emitt. (circular) vs. smaller emitt. (planar)! Luminosity => Inversely proportional to the sqrt of smaller emittance Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 22 /25

Even if there were neither deliverables nor milestones foreseen for this reference period, the overall progress of the various activities is satisfactory Next steps Try and understand the cause of the instability at the end of the squeeze and all the means to raise the intensity threshold => Important MDs in past block #3 and next block #4 before the long SD N. Mounet et al. Impedance model for HL-LHC (still several scenarios for collimators) 2 big current issues/questions: RF heating? and octupoles current? The 2 milestones MS29 and MS30 are for month 24 (01/11/2013) and month 30 (01/05/2014), with initial estimates of the machine impedance and intensity limitations, respectively The deliverable D2.4 attached to Task 2.4 is a report expected for month 36 on (01/11/2014) on Beam intensity limitations Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 23 /25

Going from 4 TeV to 7 TeV => Factor 7/4 = 1.75 in energy With the same settings for the collimators (in mm) and same materials Impedance will be the same and the transverse instabilities will be ~ 1.75 times less critical BUT, the effect of the octupoles will be (7/4)^2 ~ 3.1 times more critical => The overall situation should be 1.75 more critical. As 550 A is the maximum octupoles current, it means that it corresponds to a maximum value of ~ 300 A at 4 TeV For collimators closer to the beam => Situation will be worse! For higher brightnesses (intensities / emittances) => Situation will be worse! Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 24 /25

In the future, if we can t have enough octupoles current, we might want to Come back to the previous sign of the octupoles. 1 st, one would like to check if with the high chromaticities and transverse damper gain the situation is better than before => MDs requested but not approved Reduce the time during which we have the critical situations => Go faster through the colliding process Use beta star levelling (see beam-beam talk) to profit from the huge beam beam head-on tune spread Increase the bunch length to have more (longitudinal) Landau damping helpful for transverse instabilities Optimize collimators settings and beta star Elias Métral, 2nd Joint HiLumi LHC-LARP Annual Meeting, Frascati, 14-16/11/2012 25 /25

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 CapaciBes Specific Programme, Grant Agreement 284404.