Present status of RIBF accelerators at RIKEN

Similar documents
STATUS OF RIBF ACCELERATORS AT RIKEN

Heavy Ion Accelerators for RIKEN RI Beam Factory and Upgrade Plans. Upgrade Injector

Charge-state distribution measurements using gas charge stripper toward

2. Acceleration Scheme

Beam Diagnostics for RIBF in RIKEN

EXPERIENCE WITH STRIPPING HEAVY ION BEAMS

SC-ECR ion source for RIKEN RIBF

RARE-ISOTOPE BEAM FACILITIES IN ASIA

Progress of RAON Heavy Ion Accelerator Project in Korea

Status & Plans for the TRIUMF ISAC Facility

SPIRAL 2 Commissioning Status

Report on PIAVE G. Bisoffi

The RI Beams from the Tokai Radioactive Ion Accelerator Complex (TRIAC)

Design of a Sector Magnet for High Temperature Superconducting Injector Cyclotron

Progress in April December 2007 Schedule in Jan. March 2008

RCNP cyclotron facility

Developments of the RCNP cyclotron cascade

2.Ion sources for pulsed beam production(physics and technology) 2-1. Electron beam ion source 2-2. Laser ion source

NSCL and Physics and Astronomy Department, Michigan State University Joint Institute for Nuclear Astrophysics

Measurement of activation of helium gas by 238 U beam irradiation at about 11 A MeV

Development of the UNILAC towards a Megawatt Beam Injector

Nuclear Physics at RIBF

Perspectives in High Intensity Heavy Ion Sources for Future Heavy Ion Accelerators. L. Sun

SPES Conceptual Design Report

Activity Report on ANPhA (in place of Dong-Pil Ming)

SPIRAL-2 FOR NEUTRON PRODUCTION

Operational Experience in PIAVI-ALPI Complex. E. Fagotti INFN-LNL

Report from the RIKEN RIBF TAC meeting of November 17-19, 2005 February 12, 2006 Summary

Review of ISOL-type Radioactive Beam Facilities

Accelerators for the Advanced Exotic Beam Facility

Experimental Study of Stellar Reactions at CNS

INTENSE HIGHLY CHARGED HEAVY ION BEAM PRODUCTION

Wish-List for Large-Scale Simulations for Future Radioactive Beam Facilities

The SARAF 40 MeV Proton/Deuteron Accelerator

HTc-SQUID BEAM CURRENT MONITOR AT THE RIBF

DEVELOPMENT OF JINR FLNR HEAVY-ION ACCELERATOR COMPLEX IN THE NEXT 7 YEARS

Kirby W. Kemper. Current and new facilities for radioactive beam physics

Magnetic Field Design for a 2.45-GHz ECR Ion Source with Permanent Magnets

ECR ION SOURCES : A BRIEF HISTORY AND LOOK INTO THE NEXT GENERATION

Exotic Beam Summer School: Accelerators and Beams

The CIS project and the design of other low energy proton synchrotrons

The SARAF CW 40 MeV Proton/Deuteron Accelerator

ANURIB Advanced National facility for Unstable and Rare Ion Beams

Recent results at RIBF

HIRFL STATUS AND HIRFL-CSR PROJECT IN LANZHOU

Status of the EBIT in the ReA3 reaccelerator at NSCL

Operation of the Coupled Cyclotron Facility at Michigan State University

Preliminary Simulation of Beam Extraction for the 28 GHz ECR Ion Source

Decay Spectroscopy with EURICA in the region of 100 Sn

Direct-Current Accelerator

Section 4 : Accelerators

NSCL Operations and ReAcclerator Facility at MSU. Daniela Leitner Michigan State University

Development and application of the RFQs for FAIR and GSI Projects

OVERVIEW OF RECENT RFQ PROJECTS *

The Accelerator System for ReA3 the New Re-accelerated RIBs Facility at MSU

Rare Isotope Accelerator RIA Opportunities & Challenges. Richard C. York October 2004 MIT

Worldwide Direction on Nuclear Science and Application

DEVELOPMENT OF FFAG AT KYUSYU UNIVERSITY

GANIL STATUS REPORT. B. Jacquot, F. Chautard, A.Savalle, & Ganil Staff GANIL-DSM/CEA,IN2P3/CNRS, BP 55027, Caen Cedex, France.

Ion Beam Cocktail Development and ECR Ion Source Plasma Physics Experiments at JYFL

Chemistry GARIS

Materials issues in design, construction and operation of FRIB

The SCRIT electron scattering facility at RIKEN RI Beam Factory

NIRS. Outline HIMAC. Introduction Gantry developments. Superconducting magnets Construction of gantry structure. Future project.

In-Flight Fragment Separator and ISOL Cyclotron for RISP

HIGH INTENSITY ION BEAMS AT GANIL. ECOS facility meeting, may 16th 2013 GANIL - F. Chautard

9. RI Spin Laboratory

HIGH INTENSITY ION BEAMS AT GANIL F. Chautard, September 6th, Cyclotron 2010 Lanzhou, China, september F. Chautard

The accelerators at LNS - INFN and diagnostics aspects of the radioactive beams

A NOVEL DESIGN OF A CYCLOTRON BASED ACCELERATOR SYSTEM FOR MULTI-ION THERAPY

In-flight RI beam separator BigRIPS at RIKEN and elsewhere in Japan

Fission Properties of Neutron-Rich Nuclei

Present status of the heaviest elements study using GARIS at RIKEN

Heavy ion linac as a high current proton beam injector

A CYCLOTRON TEST SITE FOR NEUTRINO EXPERIMENTS

Study of Analyzing and Matching of Mixed High Intensity Highly Charged Heavy Ion Beams

A Project to convert TLS Booster to hadron accelerator 1. Basic design. 2. The injection systems:

RARE ISOTOPE ACCELERATOR (RIA) PROJECT*

Perspectives for Penning Trap Mass Measurements of Super Heavy Elements

Design Status of the PEFP RCS

HIGH-ENERGY HEAVY-ION ACCELERATORS

TAMU-TRAP facility for Weak Interaction Physics. P.D. Shidling Cyclotron Institute, Texas A&M University

Beam Diagnostics for Low Energy Proton and H - Accelerators. Vic Scarpine Fermilab 2012 BIW April 16-19, 2012

How J-PARC recovered from the big earthquake

Linac JUAS lecture summary

Experimental Approach to Explosive Hydrogen Burning with Low-Energy RI Beams

HIGH INTENSITY HIGH CHARGE STATE ECR ION SOURCES*

RFQ BEAM DYNAMICS DESIGN FOR LARGE SCIENCE FACILITIES AND ACCELERATOR-DRIVEN SYSTEMS

THE ACCULINNA AND ACCULINNA-2 RADIOACTIVE ION BEAM FACILITY AT DUBNA: STATUS AND PERSPECTIVES

Front end, linac upgrade, and commissioning of J-PARC. Y. Liu KEK/J-PARC, Japan

Nuclear Structure Studies along the Z=28 and 82 Closed Proton Shells using Radioactive Ion Beams

A high intensity p-linac and the FAIR Project

Proposal to convert TLS Booster for hadron accelerator


REVIEW OF HEAVY-ION CYCLOTRONS

Korea RI Accelerator

STATUS REPORT ON SPIRAL1 F. Chautard October 2 nd, 2007

Applications of Accelerators from Basic Science to Industrial Use

Beam optics analysis of large-acceptance superconducting in-flight separator BigRIPS at RIKEN RI Beam Factory (RIBF)

X = Z H + N n TBE. X = d 1 Z 2 + d 2 Z d 3 + d + d 4, where d i = f (Ci, A) 75 Se 75 Br. 75 Zn. 75 Ga. 75 Kr. 75 Ge 75 As

Transcription:

Present status of RIBF accelerators at RIKEN 1) Introduction to RIBF ( - 2007) 2) Improvements & Present status (2008-2010) 3) Recent results from RIBF (2008-2010) 4) Further developments & Plans (2009-2010) a: SC-ECR b: New Injector (RILAC2) c: Charge Strippers O. Kamigaito Accelerator Group, RIKEN Nishina Center

1) Introduction (- 07) RIKEN RI Beam Factory (RIBF) Old facility: 1975 ~ 1990 RIBF: 1997 ~ (2012)

SRC (Superconducting Ring Cyclotron) => World s first! K = 2,600 MeV Self Magnetic Shield Self Radiation Shield 3.8T (240 MJ) 18-38 MHz 8,300 tons Cooled by liquid He bath Indirectly cooled by two phase forced He flow

SRC (Superconducting Ring Cyclotron) => World s first! K = 2,600 MeV Self Magnetic Shield Self Radiation Shield 3.8T (240 MJ) 18-38 MHz 8,300 tons First beam of 345 MeV/u 27 Al 10+ extracted from SRC on Dec. 28, 2006 at 16:00 (A. Goto, Cyclotrons2007) Cooled by liquid He bath Indirectly cooled by two phase forced He flow

RIBF Accelerators frc 2 Injectors: RILAC & AVF 4 Booster Cyclotrons: RRC, frc, IRC, SRC from Hydrogen to Uranium => 345MeV/u CW-mode acceleration AVF RILAC RRC IRC Big-RIPS SRC RILAC-RRC-IRC-SRC(var. freq.):max 400 MeV/u RILAC-RRC-fRC-IRC-SRC(fixed freq.):345 MeV/u AVF-RRC-SRC(var. freq.):max 440 MeV/u

Expansion of nuclear world by RIBF protons Projectile Fragmentation In-flight U fission & P.F. neutrons

U-beam intensity and transmission in 2007 Improvement plan was started, but not fully executed due to lack of operation time in FY2007 frc β=0.0 β=0.16 4 35+ => 71+ RILAC 18% RRC U35+ ECRIS SRC 50 pna ~ 2 % excluding stripping efficiency. β=0.32 71+ => 86+ 28% IRC β=0.47 0.05 pna (2.8 10 8 pps) @345MeV/u (β=0.68)

2) Improvements (08-10) Beam phase stability RF stability Noise in phase probes Beam interlock system Accurate Faraday cups TOF monitors Actual value of RF voltage Charge strippers Oil contamination in refrigerators Phase probe noise Radial probe noise FT phase AND SO ON.. RILAC SC-ECR ECRIS EIC High Voltage frc RRC SRC IRC N. Fukunishi et al., PAC09 K. Yamada et al., HIAT09

Radial probe problems Inj. SRC 2007/6 238 U Ext. Zero Effect of secondary electrons + FT Noise

Radial probe improvements New differential electrode Tungsten 0.3mm 3mm BEAM SRC Differential probe modified SRC (,frc) Probe-shaft grounded on both sides IRC, SRC

Solved! Radial probe problems Inj. SRC 2007/6 U Ext. Zero Effect of secondary electrons + FT Noise SRC 2008/12 Ca Zero

Turn pattern in IRC FT-phase : +1deg 0deg 0.90 0.88 Other Improvements 0.86 0.84 RF system => N. Sakamoto, WEM2CCO02 0.82-20 -10 0 10 20 Beam monitor => T. Watanabe, WEM2CCO05 RF stability => K. Suda, MOPCP068 Beam phase => R. Koyama, MOPCP094 in out Single turn extraction => High quality beams

Transmission efficiencies for U beam (stripping efficiency exculded) 40 % ~75 % ~90 % ~90 % ~70 % 58 % 39 % N. Fukunishi et al., PAC09

Transmission efficiencies for Ca beam (stripping efficiency exculded) N. Fukunishi et al., LINAC10 62 % ~100 % 85 % 80 % ~70 % Transmission efficiencies for O beam in Jul. 2010 (stripping efficiency exculded) ~85 %

Achieved beam intensities pol-d(250 MeV/u):120 pna:may2009 4 He(320 MeV/u):1000 pna:oct2009 14 N(250 MeV/u):80 pna:may2009 18 O(345 MeV/u):1000 pna:jul2010 => 6.2 kw 48 Ca(345 MeV/u):230 pna:jun2010 => 3.8 kw 86 Kr(345 MeV/u):30 pna(<1min):nov2007 238 U(345 MeV/u):0.8 pna:dec2009

Operational statistics of RIBF Jul. 09 - Jul. 10 U238: Exp 287 h + Tuning 801 h Ca48: Exp 663 h + Tuning 490 h O18: Exp 310 h + Tuning 96 h He4: Exp 280 h + Tuning 121 h (c. f.rrc operation: 5238 hours) Machine Study: U238: 343 h (to RRC & frc) Xe136: 154 h (to RRC & frc) Zn70: 49 h (to RRC)

Operational statistics of RIBF Jul. 09 - Jul. 10 U238: Exp 287 h + Tuning 801 h Ca48: Exp 663 h + Tuning 490 h O18: Exp 210 h + Tuning 196 h He4: Exp 280 h + Tuning 121 h (c. f.rrc operation: 5238 hours) Machine Study: U238: 343 h (to RRC & frc) Xe136: 154 h (to RRC & frc) Zn70: 49 h (to RRC)

3) Recent results from RIBF 45 new isotopes from U-fission T. Ohnishi et al., JPSJ79, 073201 (2010)

4) Developments - a: SC-ECRIS Large plasma volume: 1100 cm 3 Flat B min configuration Construction started in October 2007. Successfully excited to the designed field in October 2008. Classical B min Flat B min Mirror Filed:3.8T/2.2T T. Nakagawa, ECRIS 08

SC-ECRIS on Cockcroft-Walton injector for RILAC (Dec. 2008) HV terminal (112 kv) SC- ECR(15 kv) Higher extraction voltage => Higher current is expected. Space-charge effect will be reduced. 5.6 kv 127 kv Acc. tube

Developments for U beam from SC-ECRIS in 2009 Apr 7: Evacuation of SCECR started May 11: First beam Jul 1: O6+ 150 eua Jul 14: Xe20+ 63 eua Sep 11: MEBT + RILAC acc. test Oct 16: Au30+ 17 eua Oct 29: Au30+ 30euA Oct 30: U test started Nov 9: U35+ 9 eua Nov 13 -: U35+ 10 eua U beam intensity in Nov. 2009 (2008 /ena) 2000 870 870 240 240 80 70 35 (2009 /ena) 12600 3800 3400** 670 480* 150* 130* 72 *: FC s have been improved. **: Overestimated.

Developments for U beam from SC-ECRIS in 2009 Apr 7: Evacuation of SCECR started May 11: First beam Jul 1: O6+ 150 eua Jul 14: Xe20+ 63 eua Sep 11: MEBT + RILAC acc. test Oct 16: Au30+ 17 eua Oct 29: Au30+ 30euA Oct 30: U test started Nov 9: U35+ 9 eua Nov 13 -: U35+ 10 eua U beam intensity in Nov. 2009 SC-ECRIS status => T. Nakagawa, WEM1CIO02 (2008 /ena) 2000 870 870 240 240 80 70 35 (2009 /ena) 12600 3800 3400** 670 480* 150* 130* 72 *: FC s have been improved. **: Overestimated.

frc AVF RRC RILAC IRC Big-RIPS (RIBF) SRC

frc AVF RRC RILAC IRC Big-RIPS (RIBF) SRC

frc AVF RRC RILAC GARIS (SHE) IRC Big-RIPS (RIBF) SRC

b: New injector (RILAC2) frc AVF RRC RILAC GARIS (SHE) IRC Big-RIPS (RIBF) SRC Independent operation of RIBF and SHE research

RILAC2 Layout SC-ECR Upgraded to 28 GHz M/q=7 680 kev/u 100 kev/u 3.3 kev/u Prebuncher 18.25 MHz DTL1-3(QWR) 36.5 MHz RFQ(4-rod) 36.5 MHz AVF cyclotron To RRC

4-rod RFQ 33.3 MHz Successfully excited at designed power in August. H. Fujisawa, NIM A345 (1994) 23 36.5 MHz

DTL cavity => NC-QWR DTL1 DTL3

RILAC2 in the AVF room DTL3 Amp. Amp. DTL2 DTL1 DQ

RILAC2 in the AVF room DTL3 Amp. Amp. RILAC2 status => K. Yamada, MOPCP025 DTL2 DTL1 DQ Commissioning will start in December. => 5 pna of U beam in FY2011

4) Developments - c: Charge stripper for U beam 345 MeV/u U 35+ 71+ 86+ Carbon Foil 300 μg/cm 2 => Lifetime < 12 hours Lifetime of fast rotating foil (100 rpm) < several min. 2008 2009

Slowly rotating stripper (Apr. 2010) Before irradiation After irradiation 0.05 rpm, 38 hours @ 1.4 eμa => Survived! Fluctuation observed

Gas stripper (2009) Xe beam => N 2 -gas stripper can be used. U beam => The average charge state in the N 2 -gas stripper was far below the acceptable state in the frc. Xe U Acceptable in frc Acceptable in frc

Electron capture and stripping of U in He gas (Apr. 2010) Low-Z gas stripper with high pressure! => 50-100 pna of U-beam will be possible 66+ @ 11 MeV/u 73+ @ 14 MeV/u 75+ @ 15 MeV/u Eq. Charge state in N 2 : 56+ @ 11 MeV/u Acceptable with frc: 69+

Accelerator Group, RIKEN Nishina Center S. Arai, T. Dantsuka, M. Fujimaki, T. Fujinawa, H. Fujisawa, N. Fukunishi, A. Goto, H. Hasebe, Y. Higurashi, K. Ikegami, E. Ikezawa, H. Imao, T. Kageyama, O. Kamigaito, M. Kase, M. Kidera, M. Komiyama, H. Kuboki, K. Kumagai, T. Maie, M. Nagase, T. Nakagawa, M. Nakamura, J. Ohnishi, H. Okuno, N. Sakamoto, K. Suda, H. Watanabe, T. Watanabe, Y. Watanabe, K. Yamada, H. Yamasawa, S. Yokouchi, and Y. Yano Thank you for your attention! SHI Accelerator Service Ltd. T. Aihara, S. Fukuzawa, M. Hamanaka, S. Ishikawa, K. Kobayashi, Y. Kotaka, R. Koyama, T. Nakamura, M. Nishida, M. Nishimura, T. Ohki, K. Oyamada, J. Shibata, M. Tamura, N. Tsukiori, A. Uchiyama, K. Yadomi, H. Yamauchi