Large deformations in squeezing ground in the Saint-Martin La Porte gallery along the Lyon-Turin Base Tunnel

Similar documents
Time Dependent Deformations in Squeezing Tunnels

Contact between a Tunnel Lining and a Damage-Susceptible Viscoplastic Medium

Back-analysis of the extreme squeezing conditions in the exploratory adit to the Lyon-Turin base tunnel

RESULTS OF THE SITE CHARACTERISATION OBTAINED AT THE TARIFA EXPERIMENTAL GALLERY

PLEASE DOWNLOAD THE FULL PRESENTATION AT

DESIGN AND CONSTRUCTION OF LARGE

Observational Methods and

NUMERICAL MODELLING OF THE BRUSNICE TUNNEL

Underground Excavation Design Classification

ON THE FACE STABILITY OF TUNNELS IN WEAK ROCKS

Building on Past Experiences Worker Safety

Weak Rock - Controlling Ground Deformations

Geotechnical Monitoring for Safe Excavation of Large Rock Cavern: A Case Study

Predicting rock conditions ahead of the face

GIBE II TUNNEL PROJECT - ETHIOPIA - 40 BARS OF MUD ACTING ON THE TBM

Time-dependent behaviour of Italian clay shales

Module 6: Stresses around underground openings. 6.2 STRESSES AROUND UNDERGROUND OPENING contd.

GROUND RESPONSE AND SUPPORT MEASURES FOR PIR PANJAL TUNNEL IN THE HIMALAYAS

1 Introduction. Abstract

Available online at ScienceDirect. Procedia Engineering 191 (2017 )

Mining in extreme squeezing conditions at the Henty mine

Scoping Calculations of TBM Advancement in Flysch and Breccias of Strait-of-Gibraltar Tunnel

CHAPTER 8 SUMMARY, CONCLUSIONS AND RECOMMENDATIONS

Structurally controlled instability in tunnels

Collaborating partners Smet Tunnelling

Seismic analysis of horseshoe tunnels under dynamic loads due to earthquakes

Real-time prediction during TBM advance.

25th International Conference on Ground Control in Mining

Session 3: Geology and Rock Mechanics Fundamentals

Further Research into Methods of Analysing the October 2000 Stability of Deep Open Pit Mines EXECUTIVE SUMMARY

Landslide FE Stability Analysis

Numerical analysis of swelling deformations in tunnelling a case study

Final design of Belesar III and Los Peares III Hydropower Projects. (Galicia, Spain).

Simplified Analysis of the Lining Behavior During Earthquakes in Deep Rock Tunnels

N.Nikolaev Antech TFA ltd, Sofia, Bulgaria. V.Parushev University of Mining and Geology, Sofia, Bulgaria. S.Nikolaev Antech TFA Ltd.

Ground support modelling involving large ground deformation: Simulation of field observations Part 1

1 of 46 Erik Eberhardt UBC Geological Engineering ISRM Edition

Influence of foliation on excavation stability at Rampura Agucha underground mine

South Toulon tunnel: Analysis of an instrumented section

Successful Construction of a Complex 3D Excavation Using 2D and 3D Modelling

Numerical modelling from laboratory to in situ scale: some examples

Effect of buttress on reduction of rock slope sliding along geological boundary

Numerical modeling of standard rock mechanics laboratory tests using a finite/discrete element approach

ENGINEERING GEOLOGY AND ROCK ENGINEERING

Rock slope rock wedge stability

Tunnel behaviour associated with the weak Alpine rock masses of the Driskos Twin Tunnel system, Egnatia Odos Highway

STRESSES AROUND UNDERGROUND OPENINGS CONTENTS

Experimental program in the URL

NNN99. Rock Engineering for the Next Very Large Underground Detector. D. Lee Petersen CNA Consulting Engineers

A PROBABILISTIC APPROACH FOR CHARACTERIZING THE COMPLEX GEOLOGIC ENVIRONMENT FOR DESIGN OF THE NEW METRO DO PORTO

Deep tunnelling in hardrock with large diameter TBM: What s up? An experience from the Gotthard Base Tunnel

Tunnels in weak rock. Introduction

Application of a transversely isotropic brittle rock mass model in roof support design

Some Aspects on the Design of Near Surface. Tunnels - Theory and Practice. Thomas Marcher¹, Taner Aydogmus²

ROCK MASS CHARACTERISATION IN ENGINEERING PRACTICE

THE INFLUENCE OF ROOF BOLTS LOCATION ON ITS INTERACTION WITH THE ROCK MASS.

Laboratory tests and numerical simulations of brittle marble and squeezing schist at Jinping II hydropower station, China

Pit Slope Optimization Based on Hydrogeologic Inputs

10. GEOTECHNICAL EXPLORATION PROGRAM

Finite element simulation of a tunnel excavation in an urban environment: case study of the CEVA project

EXAMINATION PAPER MEMORANDUM

Quantitative Classification of Rock Mass

Explicit representation of rock reinforcement in 3D DEM models for foliated ground

EOSC433: Geotechnical Engineering Practice & Design

Progress with the excavation and support of the Mingtan power cavern roof

Flin Flon Mining Belt

Significance of of Fault Zones

Geotechnical project work flow

POLITECNICO DI TORINO

Introduction and Background


Geotechnical Assessment of Polymeric Materials as Skin Reinforcement in Underground Mines

Carlos Baião Cenorgeo DESIGN AND CONSTRUCTION OF THE MACHICO-CANIÇAL CANIÇAL EXPRESSWAY TUNNELS

ASSESSING THE INTERACTION BETWEEN THE EXCAVATION OF A LARGE CAVERN AND EXISTING TUNNELS IN THE ALPS.

Ground Support in Mining and Underground Construction

Defining the role of elastic modelling in underground mine design

In situ fracturing mechanics stress measurements to improve underground quarry stability analyses

Investigating rock mass conditions and implications for tunnelling and construction of the Amethyst Hydro Project, Harihari

The Italian approach for the design and the excavation of conventional tunnels: the case of the Fabriano tunnel.

STRESS DROP AS A RESULT OF SPLITTING, BRITTLE AND TRANSITIONAL FAULTING OF ROCK SAMPLES IN UNIAXIAL AND TRIAXIAL COMPRESSION TESTS

ENVIRONMENTAL EFFECTS OF EARLY AGE AND LONG TERM RESPONSE OF PCC PAVEMENT

H.Öztürk & E.Ünal Department of Mining Engineering, Middle East Technical University, Ankara, Turkey

Module 9 : Foundation on rocks. Content

Design and Construction of Tunnels

Haulage Drift Stability Analysis- A Sensitivity Approach

A Unique Metro Accident in Brazil Caused by Multiple Factors

STABILITY CHECK AND SUPPORT DESIGNING FOR THE GR-2011 EXPLORATION DRIFT

Monitoring of underground construction

NEW DEVELOPMENTS FOR THE DESIGN AND CONSTRUCTION OF TUNNELS IN COMPLEX ROCK MASSES

A NEW ROCK BOLT CONCEPT FOR UNDERGROUND EXCAVATIONS UNDER HIGH STRESS CONDITIONS

REINFORCEMENT DESIGN AND CONTROL OF ROCK SLOPES ABOVE TUNNEL PORTALS IN NORTHERN ITALY

Discrete Element Modelling of a Reinforced Concrete Structure

COMPARING THE RMR, Q, AND RMi CLASSIFICATION SYSTEMS

Failure and Failure Theories for Anisotropic Rocks

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE COAL MINING OPTION

A METHOD TO ESTIMATE THE TANGENTIAL STRESSES AROUND UNDERGROUND OPENINGS

Empirical Design in Geotechnical Engineering

Use of Launched Soil Nails to Stabilize Landslides in Summit County, Ohio

THREE DIMENSIONAL NUMERICAL INVESTIGATION OF BAGHDAD METRO PASSING UNDER TIGRIS

Collaborating partners: NAGRA (CH), L3S (FR), G3S (FR), KUL (B), EPFL (CH), SOLEXPERTS (CH)

Transcription:

Underground Space the 4 th Dimension of Metropolises Barták, Hrdina, Romancov & Zlámal (eds) 2007 Taylor & Francis Group, London, ISBN 978-0-415-40807-3 Large deformations in squeezing ground in the Saint-Martin La Porte gallery along the Lyon-Turin Base Tunnel J. Triclot Scetauroute DTTS, Pringy, France M. Rettighieri LTF-SAS, Torino, Italy G. Barla Politecnico di Torino, DISTR, Torino, Italy ABSTRACT: Within the context of the Lyon-Turin railway project, the excavation of the Saint-Martin La Porte inclined gallery (section 80 m 2 length 2000 m) has encountered a highly fractured Carboniferous rock mass. Different ground support systems were implemented and convergence measurements confirmed the squeezing behaviour of the rock mass. Convergences of approximately two meters were observed as soon as the cover reached three hundred meters. As a result significant changes in the excavation and ground support systems were required. After setting up a ground support system adapted to the squeezing ground, the rate of convergence reached 40 mm per day in the zone of the face and 2 to 4 mm per day at a distance of approximately 60 metres from the face. Due to the difficulties encountered and with consideration given to the exploratory nature of the work, new support systems and organisation works were implemented, combined with an extensive monitoring programme. 1 INTRODUCTION The Lyon-Turin railway programme requires the excavation of a 53 km long Base Tunnel. The dual national company Lyon Turin Ferroviaire (LTF), a subsidiary company of RFF and RFI, has been appointed to carry out preliminary studies and works involving the excavation of inclined galleries and exploration adits. The Saint-Martin La Porte inclined gallery is the closest drive to thewest portal of the base tunnel. It is to reach the level of the Base Tunnel situated at a distance of 2300 meters from the portal. The cross sectional area of the gallery ranges between 80 and 100 m 2. The gallery is situated near an important zone of difficult ground and is designed to fulfil several objectives: provide additional geological and geotechnical data on the rock mass conditions to be encountered during the excavation of the main tunnel; quantify the uncertainties associated with the difficult ground to be excavated; provide access for the future tunnelling work. When the tunnel will be in operation, this inclined gallery will be used for access by emergency teams and also for maintenance and ventilation purposes. Participants in the programme are: Owner: LTF Lyon Turin Ferroviaire SAS; Project management: Group Scetauroute (agent), Antea and Alpina; Contractor: Razel inter-company group (agent), Pizzarotti, Bilfinger Berger, Granulats Rhone- Alpes; Sub-contractor: Fondazioni Speciali/GD Test. 2 GEOLOGICAL AND GEOTECHNICAL CONDITIONS The Saint-Martin La Porte gallery is situated near the contact between the Briançonnaise zone, composed of limestone, marl and dolomite, and the Briançonnaise Carboniferous zone, composed of schists, Carboniferous schist and coal (Fig. 1). Between the two zones a transition zone is present comprising anhydrites (Fig. 1). The contact area between the Carboniferous and the Briançonnaise zone was found after excavating a tunnel length of 800 m and presented characteristics in line with predictions. Also encountered during excavation was a zone with fluvio glacial alluvium under a cover of 1093

Figure 1. Geological profile. Figure 3. Appearance of the Carboniferous rock mass during excavation. Chainage 1350 m. with a specific monitoring programme. As the gallery became deeper, leading away from the valley (Fig. 1), the overburden increased. The tests carried out have confirmed the limitations of the support system adopted when subjected to the high stress conditions expected with an overburden depth in excess of 250 m. 3 SUPPORT SYSTEMS AND GROUND BEHAVIOUR Figure 2. Appearance of the Carboniferous rock mass at the face. Chainage 1414 m. 150 to 200 meters. This required staged excavation (top heading and bench) and pre-treatment of the ground. Once the excavation of this latter zone was completed, the gallery encountered the Productive Carboniferous Formation, composed of schists, clays, highly tectonised sandstone and coal. A characteristic feature of the ground in this zone is the highly heterogeneous, disrupted and fractured condition of the rock mass, which exhibits extremely to very severe squeezing problems, Hoek, 2001, Barla, 2001 (see Figs. 2 and 3). As a crude approximation, the GSI (Geological Strength Index, Hoek and Marinos, 2000) is in the range 20 30 (short term conditions) down to 10 20 (long term conditions). The conditions encountered made the different parties involved in the work to define first a support system based on heavy steel sets (HEB 180) with invert, combined with fibreglass dowel pre-reinforcement at the face, together with a concrete ring approximately 50 cm thick. Under these conditions, the excavation resumed at a rate of 2 to 3 meters per day and was associated 3.1 Adoption of the yielding support system Several support systems were used following the initial application of a stiff support, as underlined above. It soon became apparent that a stiff support would not be feasible in the severe squeezing conditions encountered, with very high stresses developing in the concrete lining as the overburden increased. Finally, the design concept chosen was to allow the support to yield in a controlled manner, with the following pre-reinforcement, full face excavation, and support sequence being adopted: 1. fibreglass dowel face pre-reinforcement; 2. full face excavation (1 m face advance); 3. use of yielding steel ribs with sliding joints (TH, Toussaint-Heintzmann type); 4. installation of rock bolts along the excavation perimeter, including the invert, requiring 400 linear meters of rock bolts per meter excavation. 3.2 Considerations on the observed behaviour The excavation-support system, adopted over a length of approximately 100 metres, was marked by high convergences of up to 2 metres, with the radial strains of the tunnel wall ranging between 8% and 16% at a distance of 20 m behind the face. More specifically, with a progress rate of 1 m per day, convergence rates of 1094

100 0 200 300 400 500 600 Convergence (mm) 700 800 900 1000 1100 1200 1300 1400 1500 1600 1252ext 1260c 1265c 1700 1272c 1278c 1284c 1800 1291c 1297c 1311c 1900 2000 0 10 20 30 40 50 60 Distance from the face (m) Figure 4. Tunnel convergences measured along the horizontal between chainage 1260 and 1320 m. Stress (MPa) 0 2 4 6 8 10 12 14 16 18 15/11/05 e1 e2 i1 16/12/05 Figure 5. 1229 m. i2 i3 16/1/06 e3 e6 i6 16/2/06 i4 i5 e4 e5 19/3/06 19/4/06 20/5/06 e1 e2 i3 e5 20/6/06 Time 21/7/06 simulation e1 simulation e2 simulation i3 simulation e5 Stress distribution in the lining at chainage approximately 40 to 50 mm per day were observed. These decreased when moving away from the face and resulted in values of 2 to 4 mm/day at distances between 80 m and 100 m from the face (Fig. 4). In order to gain in the understanding of the deformational behaviour of the rock mass along the tunnel length, it is of interest to pay attention to the extensometer measurements carried out at chainage 1330 m. It is shown that the zone characterised by a significant strain gradient (say where the strain value is in excess of 0.5%) is un-symmetrically distributed around the opening, with the maximum extent (18 m) being attained at the right rib, in line with the rock mass anisotropic structure (Figs. 2 and 3). Also to be emphasised, as a means for appreciating the severity of the squeezing conditions being encountered, is the state of stress in the concrete lining at chainage 1229 m as shown in Fig. 5. The vibrating wire strain-meters embedded in the concrete give tangential stresses in the lining, that are still increasing 21/8/06 21/9/06 22/10/06 22/11/06 23/12/06 23/1/07 Figure 6. Re-profiling operations of the opening to the original tunnel profile followed by concrete placing behind steel plates. 8 months following installation with a maximum long term value estimated up to 16 MPa. The mechanical behaviour of the Carboniferous zone has been shown to be significantly less favourable than anticipated in the design documents. Based on the information gained so far through performance monitoring and back analysis (Barla and Panet, 2006) the ground was found to exhibit a unique deformational response distinguishing between a short term and a long term behaviour. In the short term (just behind the face), if the face advance does not stop, the rock mass exhibits a negligible time-dependent behaviour. The tunnel and face deformation can be computed by using an elastic plastic constitutive law. In the long term, the time-dependent behaviour cannot be neglected and an elastic viscous plastic law needs be adopted in order to reproduce the deformational response satisfactorily (Barla and Panet, 2006; Sulem et al, 1987). 3.3 Improvement of the yielding support system Due to the conditions being met, work progress was interrupted for long periods of time, as the reduction in cross section made it necessary to re-profile of the opening to the original tunnel profile. With systematic re-profiling operations taking place section by section up to chainage 1325 m, concrete behind the steel plates was placed as soon as possible after completion of the remedial work. Fig. 6 gives a clear view of the reprofiling operations being undertaken with adaptation of the cross section shape. The observations made, associated with the experience gained during tunnelling in the squeezing ground conditions encountered, made it mandatory to consider a number of possible options for driving the tunnel. The aim was to be able to improve the previous phase of yielding support application, while seeking a different 1095

work organisation in order to adapt to the increased cover and to the necessity to contain the residual deformations at a certain distance from the face. The main objectives to be achieved were as follows: reduce/control, where possible, the amount of convergence in the tunnel and the disturbance of the surrounding rock mass; use excavation and support systems compatible with the increased overburden to be experienced in the future (up to 600 m) along the inclined gallery and in the base tunnel; optimise the pre-reinforcement, excavation and support sequence, including the distance from the face where to install the concrete lining; assess the residual deformations to be expected following support installation and the long term state of stress in the concrete lining. 3.4 Phase 3 Phase 2 Phase 1 Phase 0 Figure 7. Schematic representation of the adapted pre-reinforcement, excavation, support sequence. Main adaptations required Considering the consequences in terms of the tunnel excavation and support costs, including the time delays in completion of the inclined gallery, the following adaptations were made: reorientation of the gallery alignment in order to drive nearly perpendicular to the geological structure; change the shape of the opening to a near circular section; implementation of a pre-reinforcement, excavation and support sequence leading to avoid the need for important re-profiling to the original tunnel section; control of the extent of the disturbed zone around the tunnel, thus reducing the ground timedependent deformations. 3.5 Figure 8. View of the deformable elements installed between the joints of the TH steel ribs. Pre-reinforcement, excavation, and support sequence adopted The new pre-reinforcement, excavation, and support sequence finally adopted can be summarised as follows (Fig. 7): Phase 0 face pre-reinforcement, including a ring of grouted fibreglass dowels around the opening perimeter, designed to reinforce the rock mass over a 2 to 3 metres thickness. Phase 1 mechanical excavation carried out in segments of one meter length, with installation of support consisting of systematic bolting (length 8 m) along the perimeter, including the invert, and yielding steel ribs with sliding joints (TH, Toussaint-Heintzmann type). Phase 2 application of 20 to 30 cm shotcrete with 8 longitudinal slots fitted with HDC (High Deformable Concrete) elements designed to undergo a total tangential strain of 50%, while maintaining a support pressure of 8.5 MPa with controlled movement (Figs. 8 and 9). Figure 9. Photograph taken during Phase 2 implementation. Phase 3 installation of a coffered concrete ring when the rate of convergence is low enough to allow this, and outside the zone of influence of the face (Fig. 10). The guidelines followed for the selection of the excavation-support sequence above were developed 1096

rapidly under stress, with a maximum overall deformation being attained in the HDC elements of 20%, i.e. with a reserve for further deformation of up to 25 30% before reaching the limit design value. As a result, phase 2 is being moved closer to the face, to a distance of 15 20 m. Future observations of the overall system behaviour and response will allow one to decide if phase 2 could be implemented at a shorter distance from the face. A special coffer was designed for the project. It was assembled inside the gallery and served to install the concrete lining in 5-metre long segments, as shown in Fig. 10. Figure 10. Concrete lining installation. based on numerical simulations by using both elastic plastic and elastic viscous plastic constitutive laws, with rock mass parameters defined on the basis of performance monitoring. In this context, the support design needs be continuously reassessed according to the results of monitoring and experience feedback from the work site. It is important to note that the distance from the face at which phase 2 is implemented will depend on the efficiency of the support measures adopted and on the convergence values observed at the face. Diameter reduction for this section is limited to 600 mm. Beyond these values, the shotcrete lining would be overstressed too soon and require repair work on the support structure. 3.6 First lessons learned Use of monitoring equipment during the ongoing work makes it possible to perform back analysis and acquire the experience feedback required for the project. Systematic convergence monitoring takes place continually in both phases 1 and 2. So far also monitored in detail are the strains experienced by the HDC deformable elements installed in phase 2, in conjunction with the tangential stresses induced in shotcrete. The ground response around the excavation in both phases 1 and 2 is being monitored by using multi-point extensometers 24 m long. Monitoring has shown that the pre-reinforcement and support measures implemented during Phases 0 and 1 have resulted in a better distribution of convergences, while maintaining a tunnel deformation (convergence/diameter ratio) of approximately 2% to 5% at a distance of 20 meters from the face. Phase 2 (Fig. 9) has been first implemented at a distance of 35 m from the face. The shotcrete ring was 4 CONCLUSIONS The inclined gallery is currently under construction and is faced with exceptional difficulties over a significant length. This calls for a continuous reflection on the resources and methods to be used. The feedback from experience will be directly used for the excavation of the main tunnel, which is expected to be driven in similar conditions, with a cover close to that to be experienced at the bottom of the inclined gallery. One of the main challenges ahead lies in the definition of the optimal time for installing the final lining ring, and also in the assessment of the long term state of stress for design. Consequently, particular attention needs to be paid in identifying the long term behaviour and the mechanical properties of the squeezing rock mass. The application of the interactive observational design approach, including design analyses and systematic performance monitoring, become essential for achieving this objective. REFERENCES Barla G. and Panet M., 2006, Avis sur les conditions de soutènement de la descenderie de Saint Martin La Porte dans les Schiste Houiller, Rapport interne LTF. Barla G., 2001, Tunnelling under squeezing rock conditions. Tunnelling Mechanics. Eurosummerschool, Innsbruck, 2001, D. Kolymbas (Editor), pp.169 268. Hoek E., 2001, Big tunnels in bad rock. Journal of Gotechnical and Geoenvironmental Engineering, vol. 127, 9, pp. 726 740. Hoek E. and Marinos P., 2000, Predicting tunnel squeezing problems in weak heterogeneous rock masses. Tunnels and Tunnelling International, pp. 45 51: part 1; pp.33 36: part 2. Sulem J., Panet M. and Guenot A., 1987. Closure analysis in deep tunnels. Int. Jour. Rock Mech Min. Sc. & Geom. Abstr., vol. 24, 3, pp.145 154. 1097