BEST ESTIMATE PLUS UNCERTAINTY SAFETY STUDIES AT THE CONCEPTUAL DESIGN PHASE OF THE ASTRID DEMONSTRATOR

Similar documents
BEST-ESTIMATE METHODOLOGY

Assessment of an isolation condenser performance in case of a LOHS using the RMPS+ Methodology

Uncertainty Quantification of EBR-II Loss of Heat Sink Simulations with SAS4A/SASSYS-1 and DAKOTA

Authors : Eric CHOJNACKI IRSN/DPAM/SEMIC Jean-Pierre BENOIT IRSN/DSR/ST3C. IRSN : Institut de Radioprotection et de Sûreté Nucléaire

SENSITIVITY ANALYSIS FOR ULOF OF PGSFR

INVERSE PROBLEM AND CALIBRATION OF PARAMETERS

Stochastic optimization - how to improve computational efficiency?

Combining probability and possibility to respect the real state of knowledge on uncertainties in the evaluation of safety margins

An Integrated Approach for Characterization of Uncertainty in Complex Best Estimate Safety Assessment

PSA on Extreme Weather Phenomena for NPP Paks

Scope and Objectives. Codes and Relevance. Topics. Which is better? Project Supervisor(s)

Presenters: E.Keim/Dr.R.Trewin (AREVA GmbH) WP6.9 Task leader: Sébastien Blasset (AREVA-G) NUGENIA+ Final Seminar, Helsinki August, 2016

Modelling Under Risk and Uncertainty

Data analysis with uncertainty evaluation for the Ignalina NPP RBMK 1500 gas-gap closure evaluation

Basics of Uncertainty Analysis

Code Strategy for Simulating Severe Accident Scenario

Fuel BurnupCalculations and Uncertainties

Risk Analysis Framework for Severe Accident Mitigation Strategy in Nordic BWR: An Approach to Communication and Decision Making

SENSITIVITY ANALYSIS BY THE USE OF A SURROGATE MODEL IN LB-LOCA: LOFT L2-5 WITH CATHARE-2 V2.5 CODE

Research Article Assessment of an Isolation Condenser of an Integral Reactor in View of Uncertainties in Engineering Parameters

Advanced Simulation Methods for the Reliability Analysis of Nuclear Passive Systems

Task Group on the CSNI Safety Margins Action Plan (SMAP)

Safety Analysis of Loss of Flow Transients in a Typical Research Reactor by RELAP5/MOD3.3

APPLICATION OF THE COUPLED THREE DIMENSIONAL THERMAL- HYDRAULICS AND NEUTRON KINETICS MODELS TO PWR STEAM LINE BREAK ANALYSIS

Importance Analysis for Uncertain Thermal-Hydraulics Transient Computations

CALCULATING UNCERTAINTY ON K-EFFECTIVE WITH MONK10

State Nuclear Power Technology Research & Development Center, Beijing, China

Uncertainty Management and Quantification in Industrial Analysis and Design

Gradient Enhanced Universal Kriging Model for Uncertainty Propagation in Nuclear Engineering

Development of Multi-Unit Dependency Evaluation Model Using Markov Process and Monte Carlo Method

Study on Quantification Methodology of accident sequences for Tsunami Induced by Seismic Events.

ANALYSIS OF THE OECD PEACH BOTTOM TURBINE TRIP 2 TRANSIENT BENCHMARK WITH THE COUPLED NEUTRONIC AND THERMAL-HYDRAULICS CODE TRAC-M/PARCS

Research Collection. Basics of structural reliability and links with structural design codes FBH Herbsttagung November 22nd, 2013.

Probabilistic assessment of danger zones using a surrogate model of CFD simulations

Evaluating the Core Damage Frequency of a TRIGA Research Reactor Using Risk Assessment Tool Software

Sequential Importance Sampling for Rare Event Estimation with Computer Experiments

Monte Carlo Simulation-based Sensitivity Analysis of the model of a Thermal-Hydraulic Passive System

Simulation optimization via bootstrapped Kriging: Survey

In-Flight Engine Diagnostics and Prognostics Using A Stochastic-Neuro-Fuzzy Inference System

Application of the Stress-Strength Interference Model to the Design of a Thermal- Hydraulic Passive System for Advanced Reactors

ANALYSIS OF THE OECD MSLB BENCHMARK WITH THE COUPLED NEUTRONIC AND THERMAL-HYDRAULICS CODE RELAP5/PARCS

Uncertainty of the Level 2 PSA for NPP Paks. Gábor Lajtha, VEIKI Institute for Electric Power Research, Budapest, Hungary

NUCLEAR SAFETY AND RELIABILITY WEEK 3

Sensitivity Analyses of the Peach Bottom Turbine Trip 2 Experiment

However, reliability analysis is not limited to calculation of the probability of failure.

SITRON: Site risk assessment approach developed for Nordic countries Ola Bäckström

Uncertainty quantification and visualization for functional random variables

Steady-State and Transient Neutronic and Thermal-hydraulic Analysis of ETDR using the FAST code system

A Hybrid Deterministic / Stochastic Calculation Model for Transient Analysis

LOCAL FUSION OF AN ENSEMBLE OF SEMI-SUPERVISED SELF ORGANIZING MAPS FOR POST-PROCESSING ACCIDENTAL SCENARIOS

Experiment for Justification the Reliability of Passive Safety System in NPP

Analysis of Transient Overpower Scenarios in Sodium Fast Reactors

b) (1) Using the results of part (a), let Q be the matrix with column vectors b j and A be the matrix with column vectors v j :

Severe accident risk assessment for Nuclear. Power Plants

In-Vessel Retention Analysis for Pressurised Heavy Water Reactors (PHWR) under Severe Core Damage Accident (SCDA)

ULOF Accident Analysis for 300 MWt Pb-Bi Coolled MOX Fuelled SPINNOR Reactor

Dynamic Event Trees for Probabilistic Safety Analysis

Inverse Uncertainty Quantification using the Modular Bayesian Approach based on Gaussian Process, Part 2: Application to TRACE

Correspondance: (M. Margulis); (E. Gilad)

PSA Quantification. Analysis of Results. Workshop Information IAEA Workshop

Using Fuzzy Logic as a Complement to Probabilistic Radioactive Waste Disposal Facilities Safety Assessment -8450

Uncertainty Quantification and Validation Using RAVEN. A. Alfonsi, C. Rabiti. Risk-Informed Safety Margin Characterization.

Probabilistic assessment of geotechnical objects by means of MONTE CARLO METHOD. Egidijus R. Vaidogas

Uncertainty Quantification of an ORC turbine blade under a low quantile constrain

Multi-Unit Nuclear Plant Risks and Implications of the Quantitative Health Objectives

Algorithms for Uncertainty Quantification

EFFICIENT SHAPE OPTIMIZATION USING POLYNOMIAL CHAOS EXPANSION AND LOCAL SENSITIVITIES

Scaling Analysis as a part of Verification and Validation of Computational Fluid Dynamics and Thermal-Hydraulics software in Nuclear Industry

Raven Facing the Problem of assembling Multiple Models to Speed up the Uncertainty Quantification and Probabilistic Risk Assessment Analyses

Research Article Approaches, Relevant Topics, and Internal Method for Uncertainty Evaluation in Predictions of Thermal-Hydraulic System Codes

Chapter 8. Design of Pressurizer and Plant Control

Study of X-ray diagnostics for corium-sodium interaction during severe accident scenario

Importance of uncertainties in dose assessment to prove compliance with radiation protection standards

PART I INTRODUCTION The meaning of probability Basic definitions for frequentist statistics and Bayesian inference Bayesian inference Combinatorics

Profile SFR-10 CARNAC FRANCE Saint Paul Lez Durance FRANCE

Investigating Effects of Sensitivity Uncertainties

Lesson 14: Reactivity Variations and Control

Sensitivity Analysis of a Nuclear Reactor System Finite Element Model

VERIFICATION OF A REACTOR PHYSICS CALCULATION SCHEME FOR THE CROCUS REACTOR. Paul Scherrer Institut (PSI) CH-5232 Villigen-PSI 2

5.5.3 Statistical Innovative Trend Test Application Crossing Trend Analysis Methodology Rational Concept...

ANALYSIS OF THE COOLANT DENSITY REACTIVITY COEFFICIENT IN LFRs AND SFRs VIA MONTE CARLO PERTURBATION/SENSITIVITY

The moderator temperature coefficient MTC is defined as the change in reactivity per degree change in moderator temperature.

Introduction to Gaussian-process based Kriging models for metamodeling and validation of computer codes

DEVELOPMENT AND ASSESSMENT OF A METHOD FOR EVALUATING UNCERTAINTY OF INPUT PARAMETERS

Safety Envelope for Load Tolerance and Its Application to Fatigue Reliability Design

IMPACT OF THE FISSION YIELD COVARIANCE DATA IN BURN-UP CALCULATIONS

Research Article Uncertainty and Sensitivity Analysis of Void Reactivity Feedback for 3D BWR Assembly Model

Advanced Simulation: applications for fast reactors

Design for Reliability and Robustness through probabilistic Methods in COMSOL Multiphysics with OptiY

Safety Analyses for Dynamical Events (SADE) SAFIR2018 Interim Seminar Ville Sahlberg

Y/DD-972. Methodology for Determination of the Upper Safety Limit for Criticality Calculations for Criticality Safety Analyses

CRITICAL LOADING CONFIGURATIONS OF THE IPEN/MB-01 REACTOR WITH UO 2 GD 2 O 3 BURNABLE POISON RODS

PWR CONTROL ROD EJECTION ANALYSIS WITH THE MOC CODE DECART

Availability analysis of nuclear power plant system with the consideration of logical loop structures

Spatio-temporal correlations in fuel pin simulation : prediction of true uncertainties on local neutron flux (preliminary results)

An approach for the host rock assessment methodology. based on URLs site investigation data

SAFETY MARGIN SENSITIVITY ANALYSIS FOR MODEL SELECTION IN NUCLEAR POWER PLANT PROBABILISTIC SAFETY ASSESSMENT ABSTRACT

The Role of Uncertainty Quantification in Model Verification and Validation. Part 2 Model Verification and Validation Plan and Process

Utilizing Adjoint-Based Techniques to Improve the Accuracy and Reliability in Uncertainty Quantification

ROYAL INSTITUTE OF TECHNOLOGY SENSITIVITY AND UNCERTAINTY ANALYSIS OF BWR STABILITY

Transcription:

BEST ESTIMATE PLUS UNCERTAINTY SAFETY STUDIES AT THE CONCEPTUAL DESIGN PHASE OF THE ASTRID DEMONSTRATOR M. Marquès CEA, DEN, DER F-13108, Saint-Paul-lez-Durance, France Advanced simulation in support to GIF reactor design studies Contribution of HPC and UQ SNA-MC2013 Conference Sunday October 27th Workshop PAGE 1

CONTENTS Best Estimate Plus Uncertainty (BEPU) Analysis Application of BEPU analysis to ASTRID demonstrator Some issues of the BEPU analysis PAGE 2

BEST ESTIMATE PLUS UNCERTAINTY (BEPU) ANALYSIS

BEPU VERSUS CONSERVATIVE METHODS IN SAFETY ANALYSIS Conservative method Context : licensing calculations used conservative method owing to the difficulty of modeling complicated physical phenomena with limited computer capacity and a lack of adequate data. Use of conservative codes with conservative input data, No insurance that combination of conservatism give the most conservative response No realistic evaluation of the safety margin Realistic approach with taking account uncertainties (BEPU) Context: as more experimental data have become available, and with advances in code development Use of realistic calculation codes (B-E = best-estimate) Evaluation of uncertainties Realistic evaluation of the safety margin Enable the identification of the important contributors 7 MARS 2014 PAGE 4

VARIOUS OPTIONS FOR COMBINATION OF A COMPUTER CODE AND INPUT DATA Reference: Deterministic Safety Analysis for Nuclear Power plants, Specific Safety Guide, n SSG2, IAEA Safety Standards, Vienna, 2009 7 MARS 2014 PAGE 5

PRINCIPLE OF THE BEPU ANALYSIS It must be verified that a high percentile of the load distribution (typically 95%, covered with a high confidence level, typically 95%) is less than the acceptance criterion 7 MARS 2014 PAGE 6

OBJECTIVES OF THE BEPU ANALYSIS AT THE DESIGN PHASE Evaluate the safety margin by a realistic evaluation taking into account the uncertainties Quantify the contribution of each input uncertainty to the uncertainty of the safety margin Guide the research for reducing the uncertainties of the biggest contributors by complementary tests or calculations or, if this reduction is not possible, in limiting their impact through design changes 7 MARS 2014 PAGE 7

IMPLEMENTATION OF THE BEPU ANALYSIS Identification and quantification of the uncertainties of the input parameters Uncertainties propagation: Monte-Carlo simulation Percentile evaluation with a high confidence level Wilks method Bootstrap method Sensitivity analysis PAGE 8

EVALUATION OF THE PERCENTILE M 95,95 Wilks method For an ordered sample of size N: M (1),..., M (N) of the random variable M following an unknown probability distribution, the probability P that the value M (N-1+r) (where r is the order) represents the percentile % with a confidence level equal to % Noting M α, this percentile, it follows that: Prob [ Prob (M M α, ) = α ] Number of simulations N and order r are linked by: For evaluating M 95,95 : 59 calculations necessary at order 1, 93 at order 2, 124 at order 3 Bootstrap method Generates a large number of samples (called replicas), by random selection with replacement, from an original simulation sample of size N From the set of replicas created by bootstrap, various statistical estimation are performed as if these replicas were samples coming from the original Mean Original sample 2 3 4 6 9 4.8 Replica 1 2 2 4 6 6 4 Replica 2 3 4 6 9 9 6.2 Replica 3 2 3 4 6 6 4.2 Mean 4.8 Standard-deviation 1.22 In particular: evaluation of the -percentile of each replica and deduce, from the set of replicas, M α,, the -percentile of the response M with a confidence level 7 MARS 2014 PAGE 9

APPLICATION OF BEPU ANALYSIS TO ASTRID DEMONSTRATOR

Advanced Sodium Technological Reactor for Industrial Demonstration GEN IV SFR Demonstrator 600 MWe Pool type Enhanced safety features : Innovative core design (CFV concept) proposed with the objective to minimize sodium void effect on the reactivity Allow testing of new fuels and structural materials Improved and robust safety demonstration 24/09/12 7 MARS SNA + 2014 MC 2013 Conference, La Cité des Sciences et de l Industrie, Paris, France, October 27-31, 2013 PAGE 11

CONTEXT OF THE BEPU ANALYSIS (1/2) Design objective is to have a natural behavior of the core favorable for transients of unprotected loss of flow and loss of heat sink Target criteria for the design: no sodium boiling for transient of Unprotected LOss of Flow due to a Station Blackout (ULOF/SBO): loss of the primary flow (loss of the primary pumps) loss of heat sink (loss of the secondary pumps) no scram. Margin = gap between the maximal temperature of the sodium at core exit and the boiling temperature of sodium. 7 MARS 2014 PAGE 12

CONTEXT OF THE BEPU ANALYSIS (2/2) ULOF/SBO transient belongs to the accidental category situation of prevention of severe accidents (SP) having a very low frequency of occurrence (less than 10-7 ), For these SP situations, the safety demonstration is no more based on a deterministic demonstration with conservative assumptions on models and parameters but on a BEPU approach The probabilistic criterion has been fixed: percentile M 5,95 margin to sodium boiling, which has a probability 95% to be exceeded, obtained with a confidence level of 95%. Risk diagram From: P. Lo Pinto et al., Preliminary safety orientations of ASTRID, Proceedings of ICAPP 13, Jeju Island, Korea, 1-18 April 2013. 7 MARS 2014 PAGE 13

Safety exchanger Pump «BEST-ESTIMATE» CALCULATION WITH CATHARE2 The ULOF/SBO accident sequence is simulated with the CATHARE2 code: Model includes : the core, the entire primary system, the secondary circuits, boundary conditions at the secondary of the steam generators. Core Secondary circuit Tertiary circuit Turbine Primary circuit During the entire conceptual design phase, work focused on improving the modelling: modelling of the core and fuel pins based on GERMINAL calculations, modelling of the secondary circuit, reducing some bias (large volumes considered as isotherm) by comparison with CFD calculations primary pumps characteristics (information from the manufacturer) 7 MARS 2014 PAGE 14

UNCERTAIN PARAMETERS Identification and quantification of the uncertainties based on bibliographic analysis, on experience feedback on the existing SFRs and expert elicitation 7 MARS 2014 PAGE 15

UNCERTAINTY PROPAGATION Monte Carlo simulation Each transient calculation with CATHARE2 : 4 hours Simulation in parallel on a computer cluster (38 nodes) Workable number of simulations: several hundreds Example: evolutions of the gap to sodium boiling obtained during a ULOF/SBO transient Result of the uncertainty propagation Statistical results Moyenne Ecart-type Mini Maxi M 5,95 5% 10% 46 18.6 0 99. 12 18 25 PAGE 16

COMPARISON WILKS / BOOTSTRAP For an accurate estimation of the percentile M 5,95, at least 300 simulations with the CATHARE2 code are necessary: both methods would give equivalent results With only 100 simulations performed with the CATHARE code (number of simulations workable at the conceptual phase of the ASTRID project, where the models and the hypothesis are often modified), bootstrap method will provide a slightly conservative result 7 MARS 2014 PAGE 17

GLOBAL SENSITIVITY ANALYSIS Using of Standard Regression Coefficient: relation between the output (margin to sodium boiling) and the input parameters is quite linear (determination coefficient R 2 close to 1) Example: Rank Input parameter SRC SRC 2 1 Primary pumps inertia 0.43 0.19 2 Doppler coefficient -0.41 0.17 3 Fuel-clad thermal exchange 0.39 0.15 4 Control rods anti-reactivity 0.33 0.11 5 Emptying time of steam generator -0.25 0.06 6 Pump friction -0.25 0.06 7 Initial reactor power 0.16 0.02 Importance of inertia of the primary pumps, of Doppler coefficient and of fuelclad thermal exchange, in this type of scenario 7 MARS 2014 PAGE 18

SOME ISSUES OF THE BEPU ANALYSIS

PERCENTILE EVALUATION WITH A HIGH CONFIDENCE LEVEL One safety criterion to fulfill: Wilks method or Bootstrap Several safety criteria to fulfill simultaneously: Wald method : extension of the Wilks method increases significantly the number of simulations validity when the responses (associated to the criteria) are dependent? result depends on the order of elimination of the extreme values GRS method: evaluation of the probability to fulfill all the criteria Wilks method applied to the probability 7 MARS 2014 PAGE 20

EXPENSIVE CALCULATION TIME Problematic Each simulation lasts from several hours (for system code) to several months (CFD codes) The number of simulations to obtain a stability of the percentile may be high If the relation between the response of interest and the input uncertain parameters is not linear nor monotonous Sensitivity analysis based on variance decomposition (SOBOL indices) : several thousands of simulation required Metamodels Metamodels with good prediction quality in the zone of interest (percentile) : i.e. Polynomials, splines, neural networks, Gaussian Process (GP) Adaptive sampling: improvement of the GP predictivity, controled importance sampling Problem: persistent suspicion of regulators towards use of metamodels HPC: parallel Monte Carlo simulations easy to implement 7 MARS 2014 PAGE 21

OPTION 4 (RISK INFORMED REGULATION) Option 3: BEPU + conservative assumptions on the availability of safety systems (SS) envelop scenario Option 4 (BEPU + PSA): methodology which includes the availability of systems in the uncertainty analysis Event tree from an Initiating Event: If all the sequences i=1,,m fulfill the acceptance criteria, the IE also fulfills the same criteria with the same tolerance level For the non-failed sequence: verification that there is no cliff edge effect (small deviations in plant parameters that could give rise to large variations in plant conditions) Static event tree Dynamic event tree: ex. Monte Carlo Dynamic Event Tree (MCDET) from GRS: dynamic-stochastic interactions 7 MARS 2014 PAGE 22