This case study also provides recommendations for future lightning protection design for existing (brownfield) substation.

Similar documents
DIRECT STROKE LIGHTNING PROTECTION DESIGN

66kV & 220kV Substation Protection From Lightning by Fixed Angle, Rolling Sphere and Early Streamer Method

EFFECTIVENESS OF WORLDWIDE EXISTING ESE LIGHTNING PROTECTION SYSTEMS MANUFACTURED IN EUROPE

Proposed revisions to IEEE Standard 998 (1996) Guide for Direct Lightning Stroke Shielding of Substations

Correlation between Lightning Impacts and Outages of Transmission Lines. H-D. BETZ Nowcast GmbH Munich Germany

Available online at ScienceDirect. Reynaldo Zoro*

A Roadmap for Evaluation of Lightning Elimination Technologies

Lightning Flashover Rates of Overhead Distribution Lines Applying EMTP and IEEE Std.1410

Electric Distribution Storm Hardening Initiatives. Paul V. Stergiou Distribution Engineering October 14 th, 2015

IS YOUR BUSINESS PREPARED FOR A POWER OUTAGE?

Application of Lightning Location System Data for Designing the External Lightning Protection System

Study of Time Correlation Between Lightning Data Recorded by LLS and Relay Protection

Modeling of Transmission Line and Substation for Insulation Coordination Studies

Power System Research Group Electrical Engineering Dept., University of Saskatchewan Saskatoon, Canada

Aalborg Universitet. Published in: Cigré International colloquium on lightning and power systems, Lyon Publication date: 2014

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers

Increasing Transmission Capacities with Dynamic Monitoring Systems

EPRI Lightning Protection Design Workstation

Evaluation of the risk of failure due to switching overvoltages of a phase to phase insulation

DESIGN GUIDE FOR GLASS FIBER REINFORCED PLASTIC (GFRP) WIND TURBINE BLADES.

Influence of Grounding Material s Property on the Impulse Grounding Resistance of Grounding Grids

Role of Synchronized Measurements In Operation of Smart Grids

Lake Lure Community Meeting with Duke Energy

Business Case: UV Facility Backup Generator

Periodic Inspection and Testing of Electrical Installations Sample Test ( ) Version 1.3 July 2018

Lightning performance of EHV and UHV overhead transmission Lines in China southern power grid

INTERNATIONAL JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY (IJEET)

Photobiological safety of lamps and lamp systems

Reliability Assessment of Radial distribution system incorporating weather effects

LIGHTNING PHYSICS AND LIGHTNING PROTECTION: STATE OF ART 2013 Prof. Carlo Mazzetti di Pietralata

SkyScan EWS-PRO - Manual -

What is a short circuit?

Analysis of surge arresters failures in the installation of broadcasting transmitter

TAKE ROLL CALL TO DETERMINE IF THERE IS A QUORUM OF MEMBERS PRESENT

VKES. Contents. Page 2 No 213, 13th Main RBI Layout JP Nagar 7th Phase, Bangalore Vidyuth Kanti Engineering Services

DISTRIBUTION SYSTEM ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS

The UN-GGIM: Europe core data initiative to encourage Geographic information supporting Sustainable Development Goals Dominique Laurent, France

TEST REPORT IEC and/or EN Photobiological safety of lamps and lamp systems

Smart Grid Opportunities Being Pursued. Stephanie Hamilton Brookhaven National Laboratory June 5, 2013

Assessment of the interception efficiency of CVM-based lightning protection systems

The objective of a grounding system are: 1. To provide safety to personnel during normal and fault conditions by limiting step and touch potential.

Lightning Safety. MANSCEN Safety Office (573)

The PEAC-WMD Gamma Radiation Dose Calculator

INTRODUCING THE HALO PDCE LIGHTNING SUPPRESSOR. by EMP Solutions, Inc.

Determination of the Lightning Current from its Thermal Effects

Peterborough Distribution Inc Ashburnham Drive, PO Box 4125, Station Main Peterborough ON K9J 6Z5

Optimal Placement of Line Surge Arresters Based on Predictive Risk Framework Using Spatiotemporally Correlated Big Data

Modular contactors for installation into distribution

Photobiological safety of lamps and lamp systems

Northwest Hydro Tech Session_2017

URD Cable Fault Prediction Model

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory

Lightning performance of distribution lines: sensitivity to computational methods and to data

M2 SERIES THERMOSTATS 0 F to 240 F, Narrow Differential, Hermetically Sealed ½

High Power MicroClamp 1-Line ESD and Surge Protection

TEST REPORT IEC and/or EN Photobiological safety of lamps and lamp systems

2-input AND gate with open-drain output. The 74AHC1G09 is a high-speed Si-gate CMOS device.

Information Reception: Decision Support Standards: Public Notification Plan: Protection Program: Education:

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1

O Plus Dry Bushing 69 kv system, 350 kv BIL, 3000 A. Table of contents

THE DIMENSIONING OF ELECTRICAL CONDUCTORS FOR USE IN "PANEL BOARDS" ADDRESSED TO HAZARDOUS AREAS - PART THREE

Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes

Temperature range Name Description Version XC7SET32GW 40 C to +125 C TSSOP5 plastic thin shrink small outline package; 5 leads; body width 1.

TEST REPORT IEC Photobiological safety of lamps and lamp systems

Measurements with the new PHE Neutron Survey Instrument

Assessing Sea Level Rise, Storm Surge and Flooding Risks at the Ogunquit Wastewater Treatment Facility COMMITMENT & INTEGRITY DRIVE RESULTS

Electrical, Electronic and Computer Engineering ENEL4HB - High Voltage 2

Power System Engineering Prof. Debrapriya Das Department of Electrical Engineering Indian Institute of Technology, Kharagpur

2-input EXCLUSIVE-OR gate

G R O U N D R E S I S TA N C E T E S T I N G P R I N C I P L E (Fall of Potential 3-Point Measurement)

Power Resistor for Mounting onto a Heatsink Thick Film Technology

Commissioning and Testing of AVR and PSS

VALE # DATED. Name: Phil Langlois Position: Lead Electrical Engineer REVISIONS. App Thom. App PC. App Sud HL 2015/01/30

Multi Hazard Evaluation of a High Voltage Transmission Network. John Eidinger 1 and Leon Kempner 2

Electrical, Electronic and Computer Engineering ENEL4HB - High Voltage 2

API 11E - Specification for Pumping Units

Instruction. Vacuum Circuit Breaker Operator Module. Type 3AH 4.16kV to 38kV. Power Transmission & Distribution

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur

D14. Volcanic Viewshafts and Height Sensitive Areas Overlay

INTERNATIONAL STANDARD

Reliability of Bulk Power Systems (cont d)

74HC2G34; 74HCT2G34. The 74HC2G34; 74HCT2G34 is a high-speed Si-gate CMOS device. The 74HC2G34; 74HCT2G34 provides two buffers.

Standard Practice for Heat Aging of Plastics Without Load 1

A Novel Optimized Design for Busbar Structures using Finite Element Methods

T: E:

Alectra Utilities List of Station Capacity

Report on the U.S. NLDN System-wide Upgrade. Vaisala's U.S. National Lightning Detection Network

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT

A Unified Framework for Defining and Measuring Flexibility in Power System

XC7SET General description. 2. Features. 3. Applications. Ordering information. Inverting Schmitt trigger

SUPPLY, ERECTION & COMMISSIONING OF 2 X 3.15 MVA 33/11KV SUB-STATION at Khuntlipalli,Bargarh ( PACKAGE - B )

SUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006)

Lightning Insulation Coordination Study


Quantification of Risk Reduction Due to the Installation of Different Lightning Protection Solutions for Large Atmospheric Storage Tanks

Power Resistor for Mounting onto a Heatsink Thick Film Technology

Ref: HLSR 16-PW; HLSR 32-PW; HLSR 40-PW-000; HLSR 50-PW-000,

Compliance with the National requirements of EUROPEAN GROUP DIFFERENCES AND NATIONAL DIFFERENCES for EN 62471:2008.

Measurement method for the proficiency testing program

Transcription:

A Case Study for Substation Lightning Strike Risk Evaluation Stephen Chuang 111 Dunsmuir Street #400, Vancouver, BC V6B 5W3 604-6644123 Stephen.chuang@amecfw.com Abstract Shielding of substations from direct lightning strokes is a common practice used to protect equipment from damage and reduce the number of system outages caused by lightning. However, when a substation is being upgraded, installation of lightning masts and shielding wires across the substation for full coverage may not be realistic as the necessary outages may not be available. This paper is a case study for the lightning shielding design of a substation transformer addition and feeder section expansion project. By analyzing the lightning exposure level of the area and risk evaluation of direct lightning strokes to a substation, it is possible to design from a practical perspective of approaching substantial but not complete shielding coverage of the station; hence reduce the outage zone required during construction. This case study also provides recommendations for future lightning protection design for existing (brownfield) substation. Index Terms Fixed angle method, ground flash density, lightning mast, risk evaluation, rolling sphere method, shield wire, substation.

1.0 Introduction In early 2012, Amec Foster Wheeler started a capacity addition project. The area of the substation was expanded to accommodate a new 25 kv feeder section and a new 69 kv/25 kv power transformer where the fixed angle method was originally used to protect the substation when it was built in 1964. The project scope included upgrading the substation lightning projection to use the rolling sphere method, in accordance with IEEE 998 and to conform to the owner s latest engineering standards on lightning protection and enhance the coverage of the expanded new substation area. Rolling sphere is a simplified technique for applying the electrogeometric theory to the shielding of substations. The technique involves rolling an imaginary sphere of prescribed radius over the surface of a substation. The sphere rolls up and over (and is supported by) lightning masts, shield wires, fences, and other grounded metal objects intended for lightning shielding. A piece of equipment is protected from a direct stroke if it remains below the curved surface of the sphere by virtue of the sphere being elevated by shield wires or other devices. Equipment that touches the sphere or penetrates its surface is not protected [1]. Following the calculation method provided in IEEE 998, Annex B, the design for the rolling sphere method would require six lightning masts with shield wire around the perimeter and crisscrossing the switchyard. Figure 1 shows the station fully covered from lightning strikes with masts and shield wires by using rolling sphere method. The detailed design was progressed using the rolling sphere method. However, it was noted in the constructability review with the client that the outage on transformer T2 might not be available at the time of construction. To avoid the risk of delaying the project and modifying the design greatly, Amec Foster Wheeler performed a detailed study of the possibility of switching to the fixed angle method using the pre-determined locations of lightning masts and surrounding shield wires that were selected based on the rolling sphere method. A risk evaluation between the rolling sphere method and the fixed angle method, as well as the failure rate of each method, were performed and are noted in later sections.

Figure 1: Lightning Protection for the Substation - Rolling Sphere Method 2.0 Shielding Coverage with Fixed Angle Method Fixed angle method is a technique that uses vertical angles to determine the number, position, and height of shielding wires or masts. The protection angle is selected based on the acceptable level of exposure. This fixed angle of protection forms a cone around masts or spires. The protection zone around shield wires forms a triangular prism beneath shield wire. For the fixed angle method, the value of the angle alpha that is commonly used is 45 degrees. Both 30 degrees and 45 degrees are widely used for angle beta [1]. Horvath [2] suggests a protective angle of 40 degrees to 45 degrees for heights up to 15 m, 30 degrees for heights between 15 and 25 m, and less than 20 degrees for heights to 50 m. With this recommendations, a failure rate of 0.1 to 0.2 shielding failures/100 km/year was assumed. The protective angle used for this substation is α = 45⁰, β = 45⁰. Using the lightning mast locations determined by the rolling sphere method, the coverage area in figure 2 indicates that a large portion of the 25 kv switchyard remains exposed. Although the risk evaluation in the later sections shows that this is acceptable for this location, adding an additional mast to improve the coverage was also considered (figure 3).

Figure 2: Lightning Shield Coverage Area, α = 45⁰, β = 45⁰

Figure 3: Lightning Shield Coverage Area, α = 45⁰, β = 45⁰, with a Lightning Mast Table 1 shows the amount of unshielded area within the substation with two different scenarios. Options Coverage Area (m 2 ) Option 1: α = 45⁰, β = 45⁰, with a lightning mast 1010 Option 2: α = 45⁰, β = 45⁰, without lightning mast 1581 Table 1: Unshielded Area with Fixed Angle Method

3.0 Risk Evaluation The risk of a direct strike to equipment associated with each lightning protection method is directly related to the lightning activity at the location, exposure rate of the selected scheme, and total equipment area being protected. 3.1 Lightning Activity at the Location Lightning activity is based on historical data and quantified as the ground flash density (GFD), which is the number of lightning strikes per square km per year. The Canadian Lightning Detection Network has been collecting data between 1999 to 2013. The GFD at the project site is: 3.2 Exposure Rate of the Selected Scheme N K = 0.04 flashes/km 2 /year [3] Without direct stroke lightning protection, the failure rate is determined by the number of flashes predicted to strike within the station area [1]. As shown in figure 4, the equipment area of the substation is 2930 m 2 or 0.002930 km 2 and thus the total expected strikes within the substation is: 3.3 Tolerable Risk for a Substation X = 0.04 flashes/km 2 /year x 0.002930 km 2 X = 1.172 x 10-4 flashes/year or 8,532 years between flashes IEC Standard 62305-2 2010 [5] identifies the tolerable risk R T for a substation, where the risk level is affected by different types of losses. Referring to table 2, the risk level for a substation is defined in L2, loss of service to the public, R T = 10-3 [4]. Types of loss R T (y -1 ) L1 Loss of human life or permanent injuries 10-5 L2 Loss of service to the public 10-3 L3 Loss of cultural heritage 10-4 L4 Loss of economic value Cost/benefit comparison Table 2 Typical Values of Tolerable Risk R T Based on the risk evaluation and low incidence of strikes in this region, the overall risk with the station unprotected can be kept within acceptable risk levels per IEC 62305-2.

Figure 4: Substation Equipment Area 4.0 Risk Evaluation for Each Method 4.1 Rolling Sphere Method The rolling sphere method is typically small with a 0.05% failure rate [1]. If masts and shield wires were installed as per the original design, the probability of a strike reaching the equipment or bus is: X = 1.172 x 10-4 flashes/year x 0.0005 X = 5.86 x 10-8 flashes/year or 17,064,846 years between flashes that strike the equipment or bus 4.2 Fixed Angle Methods A normally accepted failure rate for α and β = 45⁰ is approximately 0.2% [1]. Complete coverage using fixed angle with α and β = 45⁰ results in the probability of a strike reaching the equipment or bus: X = 1.172 x 10-4 flashes/year x 0.002

X = 2.344 x 10-7 flashes/year or 4,266,211 years between flashes Since the fixed angle method design is based on the pre-determined location of lightning masts and surrounding shield wires that were selected based on the rolling sphere method, the station will be partially exposed. 4.2.1 Risk Evaluation with an Additional Lightning Spire, Option 1 Referring to figure 3, the unshielded area within the substation is 1349 m 2 and the shielded area is 1581 m 2. The probability of a lightning strike within the unshielded area is: X = 0.04 flashes/km 2 /year x 0.001349 km 2 X = 5.396 x 10-5 strikes/year The probability of a strike hitting the shielded area is: Combining these probabilities, we have: X = 0.04 flashes/km 2 /year x 0.001581 km 2 x 0.002 X = 1.265 x 10-7 strikes/year Total probability of strike = 5.396 x 10-5 + 1.265 x 10-7 = 5.409 x 10-5 strikes/year or 18,489 years between strikes. 4.2.2 Risk Evaluation with Fixed Angle Method of α = 45⁰, β = 45⁰ only, Option 2 Referring to figure 2, without the lightning spire, the unshielded area within the substation is 1920 m 2 and the shielded area is 1010 m 2. The probability of a strike hitting the unshielded area is: X = 0.04 flashes/km 2 /year x 0.001920 km 2 X = 7.68 x 10-5 strikes/year The probability of a strike hitting the shielded area is: Combining these probabilities, we have: X = 0.04 flashes/km 2 /year x 0.001010 km 2 x 0.002 X = 8.1 x 10-8 strikes/year Total probability of strike = 7.68 x 10-5 + 8.1 x 10-8 = 7.69 x 10-5 strikes/year or 13,007 years between strikes.

5.0 Comparison between Rolling Sphere Method and Fixed Angle Method The rolling sphere method provides superior protection from strikes to the substation s equipment, however, the low historical GFD and the small equipment area mean there is a low anticipated frequency of strikes within the equipment area. The comparison proves that fixed angle method with α and β = 45⁰ reduces the strike probability to a value which is several orders of magnitude below accepted values of R T = 10-3 y -1. Table 3 shows the comparison of failure rate among each method. Failure Rate (y -1 ) IEC 62305-2 L3 No Lightning Protection Lightning Protection - Rolling Sphere Method Lightning Protection Fixed Angle Method, Option 1 Lightning Protection Fixed Angle Method, Option 2 10-3 1.2 x 10-4 5.9 x 10-8 5.4 x 10-5 7.7 x 10-5 Table 3: Comparison of Failure Rates for Various Protection Methods 5.1 Comparison between Fixed Angle Method Option 1 and Option 2 Option 1 offers greater lightning shielding coverage. However, the costs and construction risks of installing a 15.2 m tower inside the substation, together with the low incidence of strikes in this region makes option 2 more favorable. Although option 2 has a higher probability of having lightning strike on the equipment or bus, the likelihood of such an event is still extremely small. Furthermore, one should also consider for the fact that most instances of a strike to equipment or bus would not lead to a full station outage if N-1 redundancy is available. Replacing the damaged equipment is likely the worst case scenario if lightning were to strike it. Table 4 gives a comparison between these two options.

Option 1 New 60 ft. Spire Option 2 No Change to Existing Design, only perimeter masts and shield wires and existing internal spires Pros Greater station protection. Lower probability of direct strike to equipment Adequate station protection achieved (several magnitudes lower than IEC 62305-2) Does not need to modify existing design Have the option of using rolling sphere method should an outage be available during construction No additional cost if rolling sphere method cannot be implemented during construction Cons Installing the spire would require outages. Higher probability of future strikes to equipment compared to option 1 Increased congestion in the switchyard due to new spire Construction costs and risks erecting spire near equipment Table 4: Comparison between Option 1 and Option 2 6.0 Conclusion The risk evaluations performed in this case study are useful for future projects. Fixed angle method may be suggested as a mean of lightning protection to the client where their facilities are located in areas with low incidence of lightning strikes. This case study also serves as a good example of the considerations for upgrading lighting protection schemes within brownfield substations. It highlights the importance of preparing the construction staging plan in the early stages of projects. Being able to identify the availability of required outages allows the design team to ensure their design is constructible. Any modification due to unforeseen circumstances during construction often means the delay of schedule, as well as significant amount of costs. It is also important to agree upon a minimum acceptable failure rate for substations with the owner and operator based on the substation size and importance of the station to help determine the overall required system protection levels. This allows alternative lightning protection design methods, such as the fixed angle method, to be considered.

7.0 References [1] IEEE Guide for Direct Lightning Stroke Shielding of Substations, IEEE Std. 998-2012, 2012. [2] Horvath, T., Computation of Lightning Protection, Taunton, Somerset, England: Research Studies Press, 1991. [3] Lightning Activity in Canadian Cities, 4 July 2013. [Online]. Available: https://ec.gc.ca/foudrelightning/default.asp?lang=en&n=4871aae6-1. [4] Protection against lightning Part 2: Risk Management, IEC 62305-2:2010, 2010. [5] IEC International Standard, Protection Against Lightning Part 2: Risk Management, IEC 62305-2, Edition 2.0, 2010-12.