Example ATC Calculation Procedure (Rated System Path Method)

Similar documents
RTO Winter Resource Adequacy Assessment Status Report

Alectra Utilities List of Station Capacity

Winter Season Resource Adequacy Analysis Status Report

2015 Summer Readiness. Bulk Power Operations

APPENDIX 7.4 Capacity Value of Wind Resources

Electric Distribution Storm Hardening Initiatives. Paul V. Stergiou Distribution Engineering October 14 th, 2015

Prediction of Power System Balancing Requirements and Tail Events

16PESGM2316 Characterizing Transmission System Harmonic Impedances with R-X Loci Plots. David Mueller

System Impact Assessment Addendum #2 Greenfield & St. Clair Energy Centres

EE115C Digital Electronic Circuits Homework #4

Proper Security Criteria Determination in a Power System with High Penetration of Renewable Resources

Information Document Calculation of Pool Price and Transmission Constraint Rebalancing Costs During a Constraint Event ID # R

Outage Coordination and Business Practices

Applications of GIS in Electrical Power System. Dr. Baqer AL-Ramadan Abdulrahman Al-Sakkaf

Performance. 7. Aircraft Performance -Basics

Assessment of Available Transfer Capability Incorporating Probabilistic Distribution of Load Using Interval Arithmetic Method

Colorado PUC E-Filings System

Reliability Assessment of Radial distribution system incorporating weather effects

EE5250 TERM PROJECT. Report by: Akarsh Sheilendranath

DEMAND FORECASTING PROTOCOL

A possible notion of short-term value-based reliability

AESO Load Forecast Application for Demand Side Participation. Eligibility Working Group September 26, 2017

New Formulations of the Optimal Power Flow Problem

Role of Synchronized Measurements In Operation of Smart Grids

STATE ESTIMATION IN DISTRIBUTION SYSTEMS

EXERTIONAL HEAT ILLNESS PREVENTION

Wind power and management of the electric system. EWEA Wind Power Forecasting 2015 Leuven, BELGIUM - 02/10/2015

Ameren Missouri Peak Load Forecast Energy Forecasting Meeting, Las Vegas. April 17-18, 2013

4/26/94 Revised 12/26/96 5/9/99 7/30/01 WSCC UNSCHEDULED FLOW MITIGATION PLAN

Min-max Transfer Capability: A New Concept

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

Bringing Renewables to the Grid. John Dumas Director Wholesale Market Operations ERCOT

Reducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting

The North American Electric Reliability Corporation hereby submits Informational Filing of the North American Electric Reliability Corporation.

An improved methodology for determining MV to LV voltage unbalance transfer coefficient

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives

Integrated Electricity Demand and Price Forecasting

Base Cases for Assessing Risk in Transmission System Planning

PREDICTING OVERHEATING RISK IN HOMES

A Unified Framework for Defining and Measuring Flexibility in Power System

Dynamic characteristics Pertain to a system where quantities to be measured vary rapidly with time.

This case study also provides recommendations for future lightning protection design for existing (brownfield) substation.

A New Approach to Constructing Seasonal Nomograms in Planning and Operations Environments at Idaho Power Co.

Winter Season Resource Adequacy Analysis

PROJECT ECONOMIC ANALYSIS

FORECAST ACCURACY REPORT 2017 FOR THE 2016 NATIONAL ELECTRICITY FORECASTING REPORT

Ch 8. Three-phase systems

Probabilistic Assessment of Atc in the Deregulated Network

Recent US Wind Integration Experience

EE2351 POWER SYSTEM OPERATION AND CONTROL UNIT I THE POWER SYSTEM AN OVERVIEW AND MODELLING PART A

Security Monitoring and Assessment of an Electric Power System

Cost of Inflow Forecast Uncertainty for Day Ahead Hydropower Production Scheduling

Probabilistic production cost simulation. EG2200 Lectures 12 14, autumn 2015 Mikael Amelin

MEDIUM TERM PASA PROCESS DESCRIPTION

Branch Outage Simulation for Contingency Studies

The Dayton Power and Light Company Load Profiling Methodology Revised 7/1/2017

Reliability of Bulk Power Systems (cont d)

Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s

Contingency Analysis Enhancements

Operational event attribution

ML ML Digital to Analog Converters with Serial Interface

A combinatorial technique for weighbridge verification

Report on Phase 2: System Performance Evaluation. Prepared for:

PROPOSED STRATEGY FOR CAPACITOR ALLOCATION IN RADIAL DISTRIBUTION FEEDERS

Demand Forecasting Models

Analysis and the methods of forecasting of the intra-hour system imbalance

Procedure for Uncertainty Determination for Calibration Consoles

! Inverter Power. ! Dynamic Characteristics. " Delay ! P = I V. ! Tricky part: " Understanding I. " (pairing with correct V) ! Dynamic current flow:

WHAT SEISMIC HAZARD INFORMATION THE DAM ENGINEERS NEED FROM SEISMOLOGISTS AND GEOLOGISTS?

R. W. Erickson. Department of Electrical, Computer, and Energy Engineering University of Colorado, Boulder

Integrating Wind Resources Into the Transmission Grid

SN54HC138, SN74HC138 3-LINE TO 8-LINE DECODERS/DEMULTIPLEXERS

Probabilistic weather hazard forecast guidance for transoceanic flights based on merged global ensemble forecasts

A Model for a Zonal Operating Reserve Demand Curve

Contents Economic dispatch of thermal units

ELECTRIC SYSTEM RELIABILITY ANNUAL REPORT

Variable Selection in Predictive Regressions

Chapter 7 Forecasting Demand

15-30 Chapter 15: Homework Problems

Scot Siegel, Planning and Building Services Director Leslie Hamilton, Senior Planner

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience

The Study of Overhead Line Fault Probability Model Based on Fuzzy Theory

Fault Calculation Methods

ECE 585 Power System Stability

Peak Load Forecasting

U.S. ARMY CORPS OF ENGINEERS

THE electric power system is a complex cyber-physical

MISO September 15 Maximum Generation Event Overview. October 11, 2018

Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

Real-Time Course. Clock synchronization. June Peter van der TU/e Computer Science, System Architecture and Networking

R O B U S T E N E R G Y M AN AG E M E N T S Y S T E M F O R I S O L AT E D M I C R O G R I D S

HAZUS-MH: Earthquake Event Report

Section 5. TADS Data Reporting Instruction Manual DRAFT Section 5 and Associated Appendices With Proposed Event Type Numbers

Predicting Future Energy Consumption CS229 Project Report

EIA411 May 1, A Report to the Office of Energy Emergency Operations Department of Energy Under EIA-411

2011 Summer Operating Expected Conditions. Bulk Power Operations Power Coordination Center

Future State Visualization in Power Grid

Tutorial 2: Modelling Transmission

Weekly Operational Constraints Update

Transcription:

Example T alculation Procedure (Rated System Path Method) Seasonal ase ase 71 61 18 MV MV Max Rating 33 28 power transfer from to has been proposed and this example will attempt to demonstrate how the maximum possible reliable transfer is determined. This illustration displays flows that would be obtained from a seasonal base case power flow model, and represent the branches of the Identified - Path. Red quantities are maximum allowable flows based on most limiting equipment.,, & represent areas or points in the system that contain generation and/or distributed load. Note for this example: Total Transfer apability (TT) for each segment is considered equal to the maximum flow rating. Existing Transmission ommitments (ET) for each segment is equal to the flow shown here resulting from the base case power flow simulation.

Power Transfer from to Simulated during Normal System onditions 0.575 172 94 0.100 620 22 MV 78 TF 78 61 40 IT 0.425 61 0.425 233 51 50 0.450 0.550 158 This is the limiting element because it can accommodate the least total transfer. In other words, if the generator and load were increased to 158MW, this branch would have MV flowing, and the flows on all other branches would be less than maximum. This figure illustrates how branch flows in the transfer path would change for an arbitrary but realistic interchange of 40MW. The flows shown here are during N-0 or normal system conditions with all elements in service. linear analysis is then used to calculate the maximum possible transfer: 1. alculate the Transfer istribution Factor (TF) for each branch. TF represents what fraction of the total transfer appears on a given segment. 2. alculate the Incremental Transfer apability (IT) for each branch. IT represents the maximum total transfer each branch could accommodate over and above base flows. 3. The branch with the lowest IT will be the limiting element for this transfer. 4. alculate the T for that limiting element: T = TT ET** 5. The T of this limiting element is considered the T for this - path during normal system conditions. Segment - is the limiting element in transfer path - with an IT = 158MV, therefore the T for path - is TT ET for this element. T = 28 = 87MV during N-0 onditions. Notice that simply calculating TT- ET for each branch and using the minimum would not yield the same results. **(TRM and M neglected and considered zero in this example)

Power Transfer from to Simulated during N-1 onditions (Loss of a Single Transmission Element) Standards state that T values shall be valid during normal system conditions (N-0) and single contingency conditions (N-1). Therefore, all significant outages within the system must be considered, and the previous analysis effectively repeated to determine the limiting path element during outage conditions. The following figures will attempt to demonstrate this analysis process. lthough only the five branch segments in this example are opened and the power transfer analyzed, the real power system must consider many more outages greatly exceeding those in the transfer path. FF 132 This is how much the flow changed 132 61 71 This was the flow on the outaged branch 173 173 132 FTF 40 132 FIT 28-0.68-30 MV 167 42 MV 10 50-0.32 0.31 22 78 317 0.70 93 Line Segment Out of Service The flows shown here are during N-1 or single outage conditions. The same linear analysis is performed to calculate the maximum possible transfer for this outage: 1. Introduce and calculate yet another quantity called First ontingency istribution Factor (FF) for each branch. FF represents what fraction of the flow that was on the outaged branch shifts and flows on the given branch. This value will be particularly useful when calculating Ts for slightly varying system conditions. 2. alculate the First ontingency Transfer istribution Factor (FTF) for each branch. FTF represents what fraction of the total transfer appears on a given segment. 3. alculate the First ontingency Incremental Transfer apability (FIT) for each branch. FIT represents the maximum total transfer each branch could accommodate, over and above base flows. 4. The branch with the lowest FIT will be the limiting element for this transfer and this outage. ranch - is the limiting element for this outage with an IT of 28MW. This means that during this outage, with these system conditions, only 28MW of total transfer would be possible. (neglecting TRM and M)

132 0.69 60 MV 38 173 77 MV 47 51 9-0.31 75 26 0.60 90 249 Line Segment Out of Service -0.50 62 68 83 0.39 0.53 0.53 206 175 89 42 18 0.50-0.56 63 38 0.53 120 0.50 194 Line Segment Out of Service

-0.27 62 42 MV 0.73 69 0.24 254 79 59 MV 89 93 0.60 152 61 53 102 Line Segment - Out of Service 0.32-0.68-1 MV 51-0.36 0.75 120 110 13 MV 263 63 363 61 102 43 Line Segment - Out of Service

Interpreting the Results N-0 NLYSIS Segment - was the limiting branch in the Transfer Path because the Incremental Transfer apability was the smallest at IT=158. Therefore, the T for this - path during normal system conditions is: T for Path = TT for this branch - ET for this branch (pre-transfer) T = 28 = 87MV N-1 NLYSIS Looking at the results of all outages, indicates that branch - is the limiting element for an outage of -. - had the smallest IT of 28, meaning that only 28MV of total transfer is possible if branch - is out of service. Therefore, the T for this - path during single outage conditions is: T for Path = TT for this branch - ET for this branch (pre-transfer, post-outage) T = 132 = 28MV The minimum of N-0, N-1 T determines the Overall T rating for this - path for these modeled system conditions. FINL RESULT.. Path - T = 28MV

alculating T for Varying System onditions fter the T analysis and istribution Factors are calculated, the T for this path can be determined for moderately varying system conditions. Using N-0 flows (possibly real time or historical S) on the worst outage element (-) and limiting element (-), a new T can be determined. onsider the known or predicted flows shown in the different normal system conditions figure below. What would be the resulting T for this - path? 48 44 FF FTF 92 = 44+(1.0)*48.0 18 29 22 Forecasted Normal onditions Worst Outage onditions New Flow = Old Flow + FF*(pre-outage element flow) Using the Worst Outage results shows that - would have 92 MV of flow for worst outage conditions. With Total Transfer apacity of, these determine T = 92 = 68 MV. There is 68MV of apacity left on this line for further commercial activity. Since the FTF of this line is, means that 68/1.0 = 68MW of total transfer would be possible. If 68MW of total transfer is occurring, branch - would be loaded to MV while all other branches are less than maximum loaded. Other branch loadings could also be predicted using the istribution Factors calculated in the detailed T analysis. elow are the results which agree well with power flow model. + 68 MW 34.8 MV 33.6 84.5 + 68 MW Maximum Transfer uring Worst Outage Predicted onditions uthor: dan.lyons@aquila.com Use it any way you like