Status of IASI FM2 on METOP-A. Carole Larigauderie (CNES), Laurence Buffet (CNES), Dominique Montero (Eumetsat), Patrick Astruc (TAS)

Similar documents
IASI FM2 on METOP A Performances after 1.5 year in orbit

Angelika Dehn Rob Koopman 10 Years GOME on ERS-2 Workshop

The IASI instrument.

Anomaly Investigations. The following anomalies have occurred since Launch : SDPSS DPC4 error

SCIAMACHY OPERATIONS IN AN EXTENDED MISSION UP TO 2010

Operational Support by ESOC s GRAS Ground Support Network - Status and Outlook

Status report on current and future satellite systems by EUMETSAT Presented to CGMS-44, Plenary session, agenda item D.1

Status overview of the European scatterometer activities

Julia Figa-Saldaña & Klaus Scipal

GOES-16 & GOES-S: Natalia Donoho. Preparing Users for New Generation Satellites. WMO IPET-SUP-4 Geneva, Switzerland 26 February, 2018

The AEOLUS Mission - In Orbit Commissioning and Verification

The Quantum Sensor Challenge Designing a System for a Space Mission. Astrid Heske European Space Agency The Netherlands

ASCAT - Metop A developments, Metop B preparations & EPS-SG

Eutelsat practice & views on long term sustainability. COPUOS/SCST - LTS Workshop Vienna, 14 February 2013

Predicting Long-Term Telemetry Behavior for Lunar Orbiting, Deep Space, Planetary and Earth Orbiting Satellites

Gaia Status & Early Releases Plan

Metop-A GOME Annual In-Flight Performance Report 2014

ADCSS 2017: Sodern presentation

ALCATEL SPACE PLASMA PROPULSION SUBSYSTEM QUALIFICATION STATUS

CHANGE RECORDS ISSUE DATE CHANGE RECORDS AUTHOR

State of Passive Microwave Polar Stereographic Products. Walt Meier and polar stereographic product team

Status / Progress of the erosita X ray Observatory:

BepiColombo Project Status. Presentation for MESSENGER Science Team Meeting Via-Skype, 27 th March 2015

SBUV(/2) and SSBUV Solar Irradiance Measurements Matthew DeLand, Richard Cebula, Liang-Kang Huang Science Systems and Applications, Inc.

BRITE One Year in Orbit

OPTIMIZATION OF SUN-SYNCHRONOUS ORBITAL PLANES Report on Studies Conducted in the United States. Submitted by Dr. Lars Peter Riishojgaard, USA

ASCAT-B Level 2 Soil Moisture Validation Report

ASCAT NRT Data Processing and Distribution at NOAA/NESDIS

Figure 1. View of ALSAT-2A spacecraft

Long-Term Time Series of Water Vapour Total Columns from GOME, SCIAMACHY and GOME-2

Software BioScout-Calibrator June 2013

OVERVIEW ON 2012 SPACE DEBRIS ACTIVITIES IN FRANCE

GOME-2 / Metop-B instrument, PPF and auxiliary-data change history

LISA Pathfinder measuring pico-meters and femto-newtons in space

An Update on EUMETSAT Programmes and Plans. Dieter Klaes on behalf of EUMETSAT teams

EUMETSAT Activities Related to Climate

MONTHLY OPERATIONS REPORT

GOSAT mission schedule

Announcement of Opportunity AKARI (ASTRO-F)

Thermal Design and Analysis of the BroadBand Radiometer. Oliver Poyntz-Wright (Rutherford Appleton Laboratory, United Kingdom)

Update on the In-orbit Performances of GIOVE Clocks

IASI L1 NRT data quality monitoring at EUMETSAT Lars Fiedler, Yakov Livschitz, Denis Blumstein, Eric Pequignot, Tim Hultberg and Francois Montagner

EUMETSAT AGENCY REPORT 2014/15 GSICS ACTIVITIES

AVHRR Global Winds Product: Validation Report

EUMETSAT Satellite Status

PROBA 1. F. Teston ESA/ESTEC D/TEC-EL

BUILDING LOW-COST NANO-SATELLITES: THE IMPORTANCE OF A PROPER ENVIRONMENTAL TESTS CAMPAIGN. Jose Sergio Almeida INPE (Brazil)

PACS Wavelength Switching AOT release note

DETERMINATION OF SCIAMACHY LINE-OF-SIGHT MISALIGNMENTS

Solar Cycle 24 Variability Observed by Aura OMI Matthew DeLand and Sergey Marchenko Science Systems and Applications, Inc. (SSAI)

The In-Orbit Commissioning of MSG-1

GCOM-C/SGLI and its Lunar Calibration

STATUS OF JAPANESE METEOROLOGICAL SATELLITES AND RECENT ACTIVITIES OF MSC

BepiColombo. Project and MPO Status. Comprehensive Explora1on of Planet Mercury

EUMETSAT AGENCY REPORT 2014/15 INSTRUMENT CAL/VAL ACTIVITIES

GRUAN Station Report for Ny-Ålesund

Your Partner in Environment Monitoring

2.4m Space Telescopes

EUMETSAT STATUS AND PLANS

The time period while the spacecraft is in transit to lunar orbit shall be used to verify the functionality of the spacecraft.

Status of the Sentinel-5 Precursor Presented by C. Zehner S5p, S4, and S5 Missions Manager - ESA

FY-2 On-orbit Operational Calibration Approach (CIBLE) and its Benefit to FY-2D/E AMV Products

Operations Report. Tag B. Short, Director South Region Operations. Entergy Regional State Committee (ERSC) February 14, 2018

ENVISAT - AATSR CYCLIC REPORT #63

OVERVIEW OF EUMETSAT RADIO OCCULTATION ACTIVITIES

Princeton Astrophysics Community Meeting

ESA Status Report. ET-SAT-11, WMO, Geneva, CH, 4 April Prepared by Earth Observation Programmes Directorate

Implementation of the NPT Safeguards Agreement in the Republic of Korea

Latest new EUMETSAT Products: - A 15 year Reprocessed RO Data Set - GRAS Occultation Prediction

November 3, 2014 Eric P. Smith JWST Program Office

GOME-2 processor version 7 for reprocessing campaign R3 - Lessons learnt from CalVal

Impact of METOP ASCAT Ocean Surface Winds in the NCEP GDAS/GFS and NRL NAVDAS

Long term performance monitoring of ASCAT-A

Megha-Tropiques Mission Status. N. Viltard and the MT science team

Improving Space Surveillance with Space-Based Visible Sensor

GSICS UV Sub-Group Activities

INFLUENCE OF THE AVERAGING PERIOD IN AIR TEMPERATURE MEASUREMENT

IASI RADIANCES CLIMATOLOGY. Thierry PHULPIN* and Joaquin GONZALEZ** *Now at TIRSEC **Now at CNES/DLA

Update on SCOPE-Nowcasting Pilot Project Real Time Ocean Products Suman Goyal Scientist-E

The post launch assessment review confirmed the following previous assertions about the mission status:

A. Windnagel M. Savoie NSIDC

Land Data Assimilation for operational weather forecasting

Phillip Chamberlin NASA Goddard Space Flight Center Solar Physics Laboratory Greenbelt, MD USA

AVHRR Polar Winds Derivation at EUMETSAT: Current Status and Future Developments

Meteosat Third Generation (MTG): Lightning Imager and its products Jochen Grandell

THE MICRO ADVANCED STELLAR COMPASS FOR ESA S PROBA 2 MISSION

Lessons learnt from EPS Cal/Val. F. Montagner & H. Bonekamp EUMETSAT

Aeolus ESA s Wind Lidar Mission: Technical Status & Latest Results

Julia Figa-Saldaña. OVWST Meeting, May 2010, Barcelona Slide: 1

Climate working group

A summary of the weather year based on data from the Zumwalt weather station

EUMETSAT SAF NETWORK. Lothar Schüller, EUMETSAT SAF Network Manager

Using the moon as a calibration source for a fleet of satellites

onboard of Metop-A COSMIC Workshop 2009 Boulder, USA

GOSAT MISSION and SPACECRAFT PARTS REQUIRMENTS

Opportunities with the James Webb Space Telescope

NEW CGMS BASELINE FOR THE SPACE-BASED GOS. (Submitted by the WMO Secretariat) Summary and Purpose of Document

Final Presentation of Assessment Star Tracker for Asteroid Search. By Peter Davidsen

Joint Polar Satellite System. 3 rd Post-EPS User Consultation Workshop Mike Haas

SOLAR ROCKET PROPULSION Ground and Space Technology Demonstration. Dr. Michael Holmes, AFRL/PRSS

Transcription:

Status of IASI FM2 on METOP-A Carole Larigauderie (CNES), Laurence Buffet (CNES), Dominique Montero (Eumetsat), Patrick Astruc (TAS)

Introduction This presentation is based on a common CNES/EUMETSAT work which is done on a bi-annual basis. This is reflected in a document, which was presented for the CNES IASI Annual Performance Review (REVEX) in September 2008 at CNES, updated in April 2009 for the September 2008- February 2009 period (available on CNES and EUM web sites) The results presented here cover the period from the last ASSFTS13 workshop (Nov. 2007) up to end of February 2009 (16 months). Carole Larigauderie 2

IASI FM2 main events during the period Monthly calibrations A regular monthly external calibration is performed every 29 days (412 orbits) over the same part of the Earth for data comparability reasons. 16 events caused a total of roughly 63 hours of mission outage. Moon avoidance Occasionally a request for an additional external calibration is necessary when the moon is expected to enter in the IASI field-of-view. The typical duration of this activity is between 15 and 24 hours. During the period, there was 4 events for a total mission outage of a little bit more than 4 days. An optimized sequence of operation for moon avoidance events is under study with EUM to reduce drastically the outage. Carole Larigauderie 3

IASI FM2 main events during the period (cont.) Decontamination The decontamination lines heat the different parts of the Cold Box Subsystem (the three passive radiator stages and the sunshield) up to a temperature of 200 K (-73 C) for a duration of 4 hours. Then during the cooling down of the first and second stages, the third stage is maintained at -93 C in order to avoid re-deposition of ice on the cold optics. About 1.5 day later, when the second stage reaches -131 C, the third stage decontamination line can be switched off and the cooling of the first stage begins. It takes about 4 days to cool down the CBS third stage from -73 C to -181.8 C, the final temperature being exactly the same as before the outgassing phase. CBS 1 st stage sunshield Performed during PL-SOL recovery, on the 21st of March 2008, leading to a mission outage of less than 5 days. CBS 2 nd stage CBS 3 rd stage PLSOL MetOp Carole Larigauderie 4

IASI FM2 main events during the period (cont.) On-board processing configuration updates 2008-03-03 Reduced spectra update mission outage: 00:16:35 2009-02-24 Reduced spectra update mission outage: 00:32:58 SEU (Single Event Upset) The effect of SEU (heater refuse) leads to small mission outage, thanks to the turbo procedure developped end of 2007. An update of on-board software will soon decrease again this mission outage from 3 hours/anomaly to less than 5 min. Date Event Description Class Mission Outage 21/07/2008 Heater Refuse SEU in DPS subsystem (DPC Pixel-1 Suspend) SEU 0 days 03:03:22 09/12/2008 Standby Refuse SET in the main converter (CV1) supplying DPCs and FMU SET 2 days 15:22:55 29/12/2008 IASI EQSOL SEU of high energy particles impacting the IMS SRAM and /Suspend generating a waterfall effect of lower energy radiations SEU 2 days 16:20:10 from launch to 10/31/07: 3 heater refuse (SEU) 3 days 14:26:42 from 11/01/07 to 02/28/09: 5 heater refuse (SEU), 2 STBY refuse (SET), 1 EQSOL (SEU) 10 days 18:11:36 Carole Larigauderie 5

geo-located plot of IASI SEU/SET anomalies 2007-05-15-13:18 SEU laser 2008-12-09-20:28 SET DPS Main 2007-11-01-13:35 SEU DPC 4A 2007-11-08-11:03 SEU DMC memory 2008-07-21-23:44 SEU DPC 1A 2008-02-09-10:37 SEU DPC 3B 2007-11-18-01:31 SET DPS DMC Converter 2007-06-13-10:23 SEU DMC memory 2007-07-20-04:31 SEU DPC 3A 2008-02-04-12:46 SEU CCM ALU 2008-12-29-22:50 EQSOL Carole Larigauderie 6

SW update The SW was successfully tested: makes an automatic reset of DPS when DPS is suspended (SEU) It will be uploaded before summer holidays An in-orbit verification will be observed before the EEPROM programming on the 2 others models on-ground This update will cure only SEU leading to heater refuse Any anomaly leading to STBY refuse has at least 2 days and 14 hours of mission outage, due to the temperature behavior (passive cooling down) Carole Larigauderie 7

IASI mode budget Carole Larigauderie 8

FM2 health check Temperature and power of the instrument are very stable. They are daily monitored by EUMETSAT, weekly, monthly and annually reported for long term trend. No special degradation on the instrument to be reported until now. Very stable routine performances are achieved (see V. Lonjou slides) Carole Larigauderie 9

Conclusion IASI FM2 still in very good health at the mid-term of its expected life duration (5 years from the launch) It is fully operational The instrument configuration is still the nominal one The outage is minimised, and actions are taken to minimise it further more Performances are guaranteed by CNES Technical Expertise Centres and EUMETSAT IASI data are fully available for weather centres and scientists Carole Larigauderie 10

Overview of heath check of IASI on METOP-B and C Carole Larigauderie (CNES), Laurence Buffet (CNES), Gokhan Kayal (Eumetsat), Gilles Bonnetto (TAS)

Introduction Every year, a IASI health check is performed at Astrium, in Friedrischaffen, where MetOp-B and MetOp-C are in a clean room storage. Since the last meeting, the health check was performed in February 2008 and 2009 for PFM-R and in May 2008 for FM3 (should be done in October 2009, depending on next AIT schedule). AFT (Abbreviated Functional Test) : IASI instrument is not in operational mode, the CCM (Cube Corner Mechanism) is locked. Carole Larigauderie 12

FM3 Erratic behavior of 2 thermistors on the redundant part discovered in May 2008: The first one is used for thermal regulation of instrument structure (ENT0030, -Y wall, active), the second one is a monitoring sensor of the optical bench (ENU0002, OBU middle, passive). Carole Larigauderie 13

Fenwall thermistors Anomalies on FM3 These 2 thermistors are Fenwall 526-31-BS012-153 Variant 32. They are concerned by the alert raised on Fenwall thermistors. The Y wall thermistor, which is easily accessible, could be replaced. The OBU thermistor is inaccessible without dismounting the instrument and will not be probably changed. As it is not the only point of measure for the optical bench, this is not considered mandatory. We recall that on nominal part, an other thermistor is concerned by this alert (RAU) and will not be changed neither. Carole Larigauderie 14

FM3 A tiger team was set-up to recommend actions following fenwall anomalies discovered on FM3 model. It should give its conclusion by the end of may for PFM-R and FM3. It is expected to change no more than 1 or 2 thermistors on FM3, without major impact on the instrument. Nothing, as preventive action) on PFM-R. Some on-board monitoring will be updated in the next SW release (PFM-R and FM3), to take into account a possible failure on identified thermistors. Carole Larigauderie 15

PFM-R No anomaly was found during the annual health check, in particular the fenwall anomaly was not discovered on this model Next test for PFM-R: before, during and after the TV test in March 2010 The IASI PFM-R will be stored in its storage container after the TV test, waiting the reassembly before launch. The TV test preparation is on-going. A very good estimate of the instrument performance should be obtained during this test. Carole Larigauderie 16

Conclusion IASI PFM-R in good functional health. This is the next instrument to be launched, in April 2012. Next steps until the launch for the instrument: Software update (automatic reset as for FM2, on-board monitoring update, put the SW at the same level as the inflight one) TV test in March/April 2010 Storage period. IASI FM3 needs hardware update and workaround are identified. Launch date planned in 2016. Carole Larigauderie 17

Thank you for your attention! Visit our web site: http://www.cnes.fr and http://smsc.cnes.fr/iasi/ and Ether one: http://ether.ipsl.jussieu.fr EUMETSAT site: www.eumetsat.int TAS site: www.thalesonline.com/space Carole Larigauderie 18