THE ALIGNMENT OF THE LHC DURING THE SHUT-DOWN D. Missiaen, CERN, Geneva, Switzerland. Fiducialisation

Similar documents
PREPARING THE SPS COMPLEX ALIGNMENT FOR FUTURE LHC RUNS

THE LASER TRACKER : A MAJOR TOOL FOR THE METROLOGY OF THE LHC

MAINTENANCE OF THE GEOMETRY OF LEP IMPROVEMENT & OPTIMIZATION OF THE VERTICAL AND RADIAL SMOOTHING

METROLOGY AND SURVEYING AT CERN : RECENT NEWS AND FACTS

3-D METROLOGY APPLIED TO SUPERCONDUCTING DIPOLE MAGNETS FOR LHC

LHC operation in 2015 and prospects for the future

The LHC Collider. STOA lecture, Brussels, 27 th November 2012 Steve Myers Director of Accelerators and Technology, CERN

2 Closed Orbit Distortions A dipole kick j at position j produces a closed orbit displacement u i at position i given by q i j u i = 2 sin Q cos(j i ;

LHC status & 2009/2010 operations. Mike Lamont

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

The LHC: the energy, cooling, and operation. Susmita Jyotishmati

LHC Commissioning in 2008

RF System Calibration Using Beam Orbits at LEP

Status report on the Survey and Alignment of the accelerators at CERN

Preparing t he SPS complex alignment for fut ure LHC runs. Pat rick Best mann

Practical Lattice Design

LHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1

THE ACTIVE PREALIGNMENT OF THE CLIC COMPONENTS H. MAINAUD DURAND, T. TOUZE CERN

Status Report on Survey and Alignment Efforts at DESY

The CLIC active prealignment studies H. MAINAUD DURAND, T. TOUZE CERN

LHC Commissioning The good, the bad the ugly

ALIGNMENT METHODS DEVELOPED FOR THE VALIDATION OF THE THERMAL AND MECHANICAL BEHAVIOUR OF THE TWO BEAM TEST MODULES FOR THE CLIC PROJECT

IMPLEMENTATION AND EXPERIENCE WITH LUMINOSITY LEVELLING WITH OFFSET BEAM

LHC Status and CERN s future plans. Lyn Evans

The Alignment Concept For The Fermilab Recycler Ring Using Permanent Magnets

Status and Outlook of the LHC

Signaling the Arrival of the LHC Era December Current Status of the LHC. Albert De Roeck CERN Switzerland

THE MAGNETIC MODEL OF THE LARGE HADRON COLLIDER

LHC. Construction Understanding first the commissioning. Prospects for

Beam Dynamics. D. Brandt, CERN. CAS Bruges June 2009 Beam Dynamics D. Brandt 1

Beam losses versus BLM locations at the LHC

Alignment in Circular Colliders and Specific Requirements for LHC

HE-LHC Optics Development

Large Hadron Collider at CERN

STATUS REPORT ON STORAGE RING REALIGNMENT AT SLRI

Engines of Discovery

THE SPEAR3 UPGRADE PROJECT AT SLAC *

PERFORMANCE OF WIRE POSITION SENSORS IN A RADIATION ENVIRONMENT. CERN, Geneva, Switzerland

A Luminosity Leveling Method for LHC Luminosity Upgrade using an Early Separation Scheme

SPEAR3 Alignment Chapter For Nuclear Instrumentation and Methods in Physics Research, Section A June 25, 2004

The LHC. Part 1. Corsi di Dottorato Corso di Fisica delle Alte Energie Maggio 2014 Per Grafstrom CERN and University of Bologna

The Very Large Hadron Collider Beam Collimation System

Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group

ILC Beam Dynamics Studies Using PLACET

SURVEY AND ALIGNMENT FOR THE SYNCHROTRON LIGHT SOURCE ELETTRA

OVERVIEW OF THE LHEC DESIGN STUDY AT CERN

gf g \ \ \l\l\\\ \\ \\\ \\\I I\lI \\I$ 1IIIl\I \lil\i1 I CERN-AC Muons and the Electronics Caverns of the LHC Experiments

LHC ORBIT SYSTEM, PERFORMANCE AND STABILITY

2008 JINST 3 S Main machine layout and performance. Chapter Performance goals

Luminosity for the 100 TeV collider

Polarised e ± at HERA

INCLINOMETER COMPARISON

Beam. RF antenna. RF cable

Simulations of HL halo loss and IR losses. R. Bruce, F. Cerutti, R. de Maria, A. Marsili, S. Redaelli

Ballistic Orbit at FLASH: Latest Results. P. Castro (MPY)

LHC Collimation and Loss Locations

TRAINING AT 7 TEV IN THE LHC

Drive Beam quadrupoles f or t he CLIC project: a novel method of fiducialisation and a new micromet ric adjust ment syst em

Analysis of KEK-ATF Optics and Coupling Using Orbit Response Matrix Analysis 1

Tools of Particle Physics I Accelerators

Physics A2 Practical Coursework. Investigating the effect of changing the volume of water on the force, acceleration and velocity of a water rocket

Optimization of the SIS100 Lattice and a Dedicated Collimation System for Ionisation Losses

BETATRON SQUEEZE: STATUS, STRATEGY AND ISSUES

Beam dynamics measurement during ALBA commissioning

Wolfgang Pauli, CERN, and the LHC. Rüdiger Voss Physics Department, CERN

LHC Beam Operations: Past, Present and Future

HL-LHC OPERATIONAL SCENARIOS

GEODETIC MEASUREMENTS FOR THE HERA PROTON RING, THE NEW EXPERIMENTS AND THE TESLA TEST FACILITY - A STATUS REPORT

FLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR

LHC Commissioning and First Operation

A PRELIMINARY ALIGNMENT PLAN FOR RIA AT MSU

Status Report on the Survey and Alignment efforts at DESY

DYNAMIC APERTURE STUDIES FOR HL-LHC V1.0 *

CERN EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH BEAM-BASED ALIGNMENT IN CTF3 TEST BEAM LINE

Status of the LHC Machine

The Compact Muon Solenoid Experiment. Conference Report. Mailing address: CMS CERN, CH-1211 GENEVA 23, Switzerland. Commissioning of the CMS Detector

The Alignment of BEPCII RING

The LHC Dipole Geometry as Built in Industry

INJECTION AND DUMP CONSIDERATIONS FOR A 16.5 TEV HE-LHC

STATUS OF LHC COMMISSIONING

Situation Analysis and Stability Evaluation of Large Electron Positron Collider in CERN* Abstract

Accelerators. Lecture V. Oliver Brüning. school/lecture5

Beam-induced heat loads on the beam screens of the inner triplets for the HL-LHC

THE SPEAR3 UPGRADE PROJECT AT SLAC * Abstract

Alignment of the Dipole Magnets in the Cornell Electron-Positron Storage Ring

FY04 Luminosity Plan. SAG Meeting September 22, 2003 Dave McGinnis

LHC Luminosity and Energy Upgrade

Ultra-Low Emittance Storage Ring. David L. Rubin December 22, 2011

The TESLA Dogbone Damping Ring

(a) (b) Fig. 1 - The LEP/LHC tunnel map and (b) the CERN accelerator system.

MAGNET INSTALLATION AND ALIGNMENT FOR THE FUJI TEST BEAM LINE AT KEKB

Will LHCb be running during the HL-LHC era? Burkhard Schmidt for the LHCb Collaboration

THERMALLY DRIVEN VERTICAL DISPLACEMENT OF IP QUADRUPOLE MAGNET

The Large Hadron Collider Lyndon Evans CERN

LHC HTS CURRENT LEADS

Status of the LHC Beam Cleaning Study Group

Beam-beam issues for LHC upgrade phases 1 and 2

LUMINOSITY LEVELLING TECHNIQUES FOR THE LHC

Commissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department

Correction of β-beating due to beam-beam for the LHC and its impact on dynamic aperture

Transcription:

THE ALIGNMENT OF THE LHC DURING THE SHUT-DOWN 2008-2009 D. Missiaen, CERN, Geneva, Switzerland. Abstract The first run of the LHC took place in September 2008 and, after only two weeks, was brutally interrupted by a major incident provoked by an electrical short circuit in an interconnection between two magnets. A shut down of one year was decided in order to repair the damaged equipment. The Survey team, involved in the repair of the damaged magnets, took advantage of this period to verify and improve the alignment of the components by their position in the arcs as well as in the Long Straight Sections (LSS). This paper will cover the different survey operations accomplished and the results obtained. INTRODUCTION A global survey of all the LHC was realised between the beginning of 2007 and September 2008, the starting date of the first LHC run. In the vertical direction, the operation was done, the magnets being under warm conditions but for the horizontal, all the magnets were cold. The methodology and some of the preliminary results were already presented [1]. The incident that happened in sector 34 of the LHC one week after the starting of the first run triggered a long shut-down of about one year in order to repair the damaged magnets and to take mitigation actions to prevent this unfortunate event to happen again. From the survey point of view, it gave also the opportunity to remeasure, under cold conditions, all the magnets in the arcs and to realise a better geometrical link between the arcs and the LSS, located on each part of the Interaction Points (Figure 1). A particular effort was also done to remeasure using standard instrumentation the final focus low beta quadrupoles and to link their geometry to the one of the LSS, including the data coming from the permanent monitoring system. Figure 1: The LHC Interaction Points REPAIR OF THE DAMAGED AREA IN SECTOR 34 An area of 700m comprising 53 magnets, 14 quadrupoles and 39 dipoles, was considered to have been damaged by the incident. These magnets were taken out of the tunnel and replaced by spare magnets which were to be prepared before their installation in the tunnel. Fiducialisation The metrological operations that have to be done on the magnets before their descent into the tunnel are the fiducialisation, the positioning of the BPM for the quadrupoles and the positioning of all the tubes, included the beam screen, for both types of magnets as it was done before the first alignment. The fiducialisation is the operation which determines the position of the fiducial marks used for the alignment in the tunnel with respect to a reference axis, the mechanical one for the dipoles [2] and the geo-magnetic one for the quadrupoles [3]. The main challenge was to restart these operations after two years of interruption. As a matter of fact, after the completion of the production of LHC magnets in 2007, the infrastructure of the fiducialisation benches has been dismantled, the software, running on old platform, remained without maintenance and even worse the contractor manpower has gone away from CERN. These problems were solved thanks to the good reactivity and the strong involvement of the CERN staff. After a period of re-learning the methodology, the operations were completed in four months at a rate of three dipoles and one quadrupole per week. The relational database containing all the measurement data and also used for the quality control of the magnets by the Magnet Evaluation Board (MEB) had also to be reactivated. The data structure, now under the responsibility of SU, was still working but the interface had to be modified to cope with newer versions of java. Alignment in the tunnel Even though it was not foreseen to use any longer the initial geodetic network, the magnets themselves constituting the best network, it was decided to use it for the initial alignment of the magnets because in this area there was no discrepancy detected between the smoothed position of the magnets and the geodetic network. The instruments and technologies used for this operation are the ones used for the first alignment of the whole LHC, i.e. optical levels, offsets to a stretched wire and EDM. Before authorizing the interconnection team to start their work, a local was then performed on a length of 100m, even if some magnets were missing.

Smoothing of the whole sector The of the whole sector was then realised in September 2009, the magnets being under cold conditions, in the Vertical and in the Horizontal direction. ALIGNMENT MAINTENANCE The LHC being such a critical machine from the point of view of the aperture in both H and V directions, it was always claimed by the SU management that during the first three years after its installation, survey measurements have to be performed regularly in order to detect any important movement due to ground motion and to improve the smooth position of the magnets. This unforeseen long shut-down of the LHC was therefore an opportunity to start a complete campaign of measurements. Roll angle measurements Before measuring the magnets in V or in H, the roll angles of all the magnets are measured and eventually corrected in case their deviation to the nominal exceeds 0.1 mrad. Figure 2 : Vertical position of magnets in sector 34 The deviations of the magnets to their theoretical position and to the smooth curve calculated by the PLANE software [1] are shown on Figure 2. 49 magnets were realigned which corresponds to 22% of the sector. This is exactly the average of displaced magnets during the first of the LHC [1]. No more displacements in the damaged area than elsewhere in the sector. Figure 3 shows the horizontal deviations with respect to their nominal position. 41 magnets had to be realigned as their position with respect to the smooth curve was bigger than a threshold of 0.25 mm. This is also a consistent value comparing to what was seen during the first in 2008. It can also be seen that one magnet is at more than 1.5 mm far from its nominal. This is the Entry point of the dipole MB.A29L4, it is not in the damaged area and there are no explanation concerning the reason of this important deviation. No realignment was done because of the risk of provoking a leak in the interconnection. Figure 3: Horizontal position of magnets in sector 34 Figure 4: Roll angle deviations Figure 4 shows the difference between the roll angle measured in 2008 and the one measured in 2009. The most perturbated sector was sector 34 due to the incident, even though the damaged area was not taken into account for this comparison. The others magnets where the movement was important are always located in the LSS and are mostly the so called semi-standalone magnets which are directly linked to the cryogenic line and where a strong effort due to vacuum is applied. In sector 67, a deviation of 0.8 mrad was found on the MQ.8R6. It appeared that in this area there was a problem with the concrete floor which had to be reinforced. An average of 55 magnets per sector had to be realigned except in sector 34 (damaged area) and 78 (hole) where almost 100 magnets were concerned by a roll angle realignment. Vertical of the whole LHC The vertical measurements were performed for all the sectors of the LHC, all the magnets being under cold conditions. The sector 34 has been measured after the reinstallation of the damaged magnets as explained above. In sector 78, the hole that was discovered at the beginning of the 1990 s at the time of the LEP (Large Electron Positron) and which was not visible during the first of the LHC in 2007, was observed again this year as shown on Figure 5.

measurements being taken at a distance not far from 26.5 m which was discovered later as a critical distance for the DNA03. Nevertheless the relative position of the magnets with respect to their neighbours is more critical for the beam aperture and for the interconnections. That is why, sector by sector, a smooth curve was calculated with PLANE [1] and the magnets which were more than 0.20 mm away from this line where realigned. Table 1: Vertical Figure 5 : Vertical position of magnets in sector 78. The sinking is in the range of 2 mm on a length of about 600m. This is a long wave movement and it can be seen that the smooth curve follows closely measured deviations. It should have been left with this shape as, from the physics point of view as well as for the aperture one, there is no impact. But as this movement is expected to be in the range of 2 mm per year it was decided to realign all the concerned area on the nominal position. This realignment took place without warm up of the magnets and by small steps of maximum 0.5 mm to avoid any damage at the level of the interconnection. A total of 70 magnets (50 for the hole ) were displaced during this operation. This is, without any doubt, an operation which will have to foresee during every shut-down. The measurements of all the LHC sectors were put all together and the closure was +2.42 mm. After a compensation calculation, a translation was applied so that the average of the deviations is equal to 0. The deep references located around each Interaction Point (IP) were not considered as fixed points. The graph of the vertical position of the magnets, calculated with the previous described hypothesis, can be seen on Figure 6. Figure 6: Vertical shape of the LHC magnets The mountainous vertical shape of the magnets is coming from the fact that the first alignment of the magnets was done with respect to the geodetic network including the deep references. The closure of the levelling traverse, done in 2004 in order to determine the altitude of these references, was not very good, most of the Sector r.m.s after 2008 r.m.s before r.m.s after 12 0.10 mm 0.16 mm 0.09 mm 63 23 0.12 mm 0.16 mm 0.09 mm 53 34 0.11 mm 0.17 mm 0.10 mm 49 45 0.11 mm 0.13 mm 0.10 mm 26 56 0.10 mm 0.13 mm 0.09 mm 48 67 0.10 mm 0.14 mm 0.09 mm 36 Realigned magnets 78 0.11 mm 0.13 mm 0.11 mm 70 (hole) 81 0.11 mm 0.14 mm 0.09 mm 63 Table 1 shows the deviations of the magnets with respect to the smooth curve. From the columns 2 and 3, it can be seen that there is no important degradation in the alignment in a period of almost one year. From column 3, it can be seen that our specification of 0.15 mm at 1 sigma was almost reached for all sectors, without realigning any magnet. Then columns 4 and 5 shows that, with a total of ~400 magnets realigned (23%), the position of the magnets is at 0.1 mm at 1 from their ideal position. Columns 2 and 4 show also that the position after in 2009 is slightly better than the one after 2008. These very encouraging results shows that the stability of the magnets is excellent and that with our regular measurement campaigns, such an accurate position is achievable, but with a non negligible effort. Vertical survey of the low beta quadrupoles Around point 1, 2, 5 and 8, where the huge LHC experiments are located, the standard levelling measurements were combined with the measurements issued from HLS and WPS installed to monitor permanently the position of the low beta quadrupoles [4]. The measurements were linked on the deep references inside the accelerator tunnel and to cavern references. In any case it was possible to link both side of the experiments with standard measurements. The calculation was fixed on the deep reference(s).

Table 2: Vertical position (mm) of low beta quadrupoles IP Stability tunnelcavern Q3L Q2L Q1L Q1R Q2R Q3R 1.12 -.04 -.25 -.36 -.55 -.36 -.14 2.43.51.14.05 -.04 -.04 -.06 5.41.51.29 -.04 -.24.17.13 8.02.13.36.19 -.35 -.49 -.03 Table 2 shows in column 2 that the stability between the deep references of the tunnel and the cavern references is very good for IP1 and 8, but for IP2 and 5, it seems that there is a movement between the tunnel and the cavern. Either the tunnel is going downwards or the cavern upwards. The first hypothesis seems more plausible even though, these references are anchored 25 m below the surface of the tunnel in very stable rocks. Concerning the position of the magnets, it has to be mentioned that for: IP1: the magnets have a tendency to go down as they are closer to the IP. This was already detected during the previous survey; IP2 : same remark than for IP1 on the Left side, very good alignment on the Right side; IP5 : same remark than for IP1 on both sides; IP8 : the magnets are a bit too high on the left side and a bit low on the Right side. The same tendency was detected during the previous survey. All the low beta quadrupoles magnets have been realigned remotely to their theoretical position with a deviation lower than 0.1 mm at 1. Horizontal of the LSS The LSS are the Long Straight Sections of about 500m located on each side of the Interaction Points and containing various equipment, such as separator magnets, stand-alone quadrupoles, low beta quadrupoles, accelerating cavities, collimators, dumps, etc. It was decided to realise a major survey in these areas to improve the relative position of these critical equipment before they become highly radioactive. As already explained [1], the horizontal in the standard LHC arcs is done with respect to a stretched wire, the length of this wire being limited to 120 m because of the curvature of the tunnel and the size of our instrumentation. In the LSSs, this limitation doesn t exist and longer stretched wires of 160 m, made of Vectran, were used with an overlap between the wires of 100 m to strengthen the geometry. The measurements were done for all the IPs between the Q8 on the left side (Q8Ln) to the Q8 of the right side (Q8Rn). Two types of LSS have to be considered: These containing an LHC experiment around IP1, 2, 5 and 8 (Figure 1). These without experiment where the geometrical link is always possible as it is the case for IP3, 4, 6 and 7 (Figure 1). For the LSS with experiment, as a direct metrology to link both sides is not possible, the following measurements were performed and added to the calculation: the permanent monitoring systems (WPS) linking one side to the other through the Survey galleries for points 1 and 5 [4]; the position of the fiducials used for the permanent monitoring with respect to the ones used for the standard measurements; a standard metrological survey through the Alice experiment in IP2; The calculations were done taking as a fixed point the Q2Ln and as an orientation the Q2Rn. Radial constraints of 1mm were added around the Q8Ln and Q8Rn in order to have a smoothed shape at the junction between the standard arc and the LSS. Figure 7 : Horizontal position of LSS1 In LSS1, Figure 7 shows that the smoothed shape was improved by realigning a significant number of magnets on both sides and the low betas quads mainly on the Right side. Figure 8 : Horizontal position of LSS2 In LSS2, it can be seen that the displacements done of the low beta on the right side were not done properly,

instead of moving Q1, it would have been preferable to move Q2 and Q3. Figure 9 : Horizontal position of LSS5 In LSS5, the situation was almost the same as in IP1. Many magnets were displaced of the left side, included Q1 and Q3 which were displaced by about +0.3 and -0.3 mm respectively. On the right side, after displacement, the Q1 didn t reach its expected position because of inconsistency between standard and WPS measurements which were available six months later than the standard ones. Figure 10 : Horizontal position of LSS8 In LSS8, the calculation was done independently for each side, the Q2 been taken as a fixed point and the Q8 as an orientation. Very small realignments were realised, these area was always very well smoothed. The main difficulties of these realignments were: The fact the WPS data were available in some case very late because of some maintenance on the permanent sensors system. Some inconsistent measurements between the standard and WPS fiducials, these last ones being foreseen at the origin only to measure relative movements. Nevertheless, the smooth position of the cryo-magnets located in these LSS was significantly improved as well as the link between the LSS and the low betas quads. For the LSS without experiment, the long wires were stretched all along the LSS between Q8L and Q8R without any interruption. Table 3 shows that with a small number of wires, the residuals of the measurements after adjustment were not bigger than 0.07 mm at 1. A limited number of magnets were realigned. Table 3 : Horizontal of LSS3, 4, 6 and 7 LSS Residuals (mm) Wires measured Magnets realigned (%) 3 0.06 10 15 4 0.07 13 25 6 0.04 14 15 7 0.03 8 28 CONCLUSIONS The unforeseen shut-down of the LHC was firstly devoted to the realignment of the damaged area in the sector 34. It also permitted to detect or confirm some unstable areas with the roll angle and the levelling measurements. The vertical has improved significantly the relative position of adjacent magnets and the deviations to a smooth curve has reach a value 0.1 mm at 1 but has not shown any big misalignment. In the horizontal direction, for the first time, stretched wires of 160 m have been successfully used in the LSS with a precision never reached before. This technique has proved once again its efficiency to improve accurate relative alignment. The LHC has started to run in November 2009. The first closed orbit has been captured and the deviations were 1.33 mm in H and 0.93 mm in V at 1 without any correctors activated. Very quickly some collisions were realised at an energy of 3.5 TeV by beam. The LHC will continue to run until the end of 2011, hoping that the quality of the alignment will not degrade too much during these two years of run. In the mean time, the position of the low beta will be monitored permanently and realignments realised remotely, if needed. In 2012, another long shut-down of one and a half year will be used to smooth again the whole LHC in both planes as well as its transfer lines. REFERENCES [1] D. Missiaen and al, The final alignment of the LHC, IWAA08, Tsukuba, February 2008. [2] D. Missiaen, J.P. Quesnel, Fiducialisation of LHC Dipole Magnets, LHC-G-ES-0002, EDMS 110632, March 2000. [3] P. Bestmann, D. Missiaen, J.P. Quesnel, Final Geomagnetic fiducialisation of the LHC Short Straight Sections, LHC-G-TP-0006, EDMS 790018, October 2006. [4] H. Mainaud and al, The remote positioning of the LHC inner triplets, IWAA08, Tsukuba, February 2008.