MONTHLY CONSTRAINT REPORT - JUNE 2017

Similar documents
MONTHLY CONSTRAINT REPORT - JULY 2017

MONTHLY CONSTRAINT REPORT - APRIL 2017

MONTHLY CONSTRAINT REPORT - AUGUST 2017

August A report for the National Electricity Market

NEM CONSTRAINT REPORT 2016 FOR THE NATIONAL ELECTRICITY MARKET

SCHEDULING ERROR 3 AND 4 JULY 2011

UPDATE ELECTRICITY STATEMENT OF OPPORTUNITIES FOR THE NATIONAL ELECTRICITY MARKET

NATIONAL ELECTRICITY FORECASTING REPORT UPDATE FOR THE NATIONAL ELECTRICITY MARKET

February Industry Communique

Activation of unscheduled reserves for Victoria and South Australia 19 January 2018 May 2018

FORECAST ACCURACY REPORT 2017 FOR THE 2016 NATIONAL ELECTRICITY FORECASTING REPORT

MEDIUM TERM PASA PROCESS DESCRIPTION

SOUTH AUSTRALIAN WIND STUDY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING

POWER SYSTEM OPERATING PROCEDURE LOAD FORECASTING

Power System Seminar Presentation Wind Forecasting and Dispatch 7 th July, Wind Power Forecasting tools and methodologies

WIND INTEGRATION IN ELECTRICITY GRIDS WORK PACKAGE 3: SIMULATION USING HISTORICAL WIND DATA

Weekly Operational Constraints Update

November For the National Electricity Market

BLACK SYSTEM SOUTH AUSTRALIA 28 SEPTEMBER 2016 THIRD PRELIMINARY REPORT

Commissioning and Testing of AVR and PSS

Information Document Calculation of Pool Price and Transmission Constraint Rebalancing Costs During a Constraint Event ID # R

RESERVE LEVEL DECLARATION GUIDELINES

Bringing Renewables to the Grid. John Dumas Director Wholesale Market Operations ERCOT

The Use of EDD for Weather Normalisation

Summary of wool production estimates and forecasts for Australia. 2012/13 4th forecast 78.9

International Workshop on Wind Energy Development Cairo, Egypt. ERCOT Wind Experience

TRANSMISSION CONNECTION POINT FORECASTING REPORT FOR NEW SOUTH WALES AND TASMANIA

Summary of wool production estimates and forecasts for Australia. 2014/15 Fourth forecast

California Independent System Operator (CAISO) Challenges and Solutions

International Studies about the Grid Integration of Wind Generation

peak half-hourly New South Wales

peak half-hourly Tasmania

Reducing Contingency-based Windfarm Curtailments through use of Transmission Capacity Forecasting

VICTORIAN TERMINAL STATION DEMAND FORECASTS 2010/ /20

CAISO Participating Intermittent Resource Program for Wind Generation

Battery Energy Storage

High level review of transmission connection point forecasts: Victoria

MISO September 15 Maximum Generation Event Overview. October 11, 2018

Management of the GB System Overnight

Capacity Scarcity Condition Monday, September 3, 2018 Two primary factors led to the implementation of OP 4 event Significant generation outages and r

Whitepaper. All Currency, One Wallet!

AN78Lxx/AN78LxxM Series

Effect of wind generation on dispatch INVESTIGATION 2

Published by ASX Settlement Pty Limited A.B.N Settlement Calendar for ASX Cash Market Products

Energy and demand projections

December Australian Wool Production Forecast Report. Australian Wool Production Forecast Committee Summary

FIVE MINUTE ELECTRICITY DEMAND FORECASTING: NEURAL NETWORK MODEL DOCUMENTATION

IN FOCUS: WHEAT PRODUCTION OUTLOOK JULY 2017

elgian energ imports are managed using forecasting software to increase overall network e 칁 cienc.

Chapter 3 AUTOMATIC VOLTAGE CONTROL

DEMAND FORECASTING PROTOCOL

Peak Reliability Delivering near real-time phase angle deltas using Inter-Control Center Communication Protocol (ICCP)

Short-Term Demand Forecasting Methodology for Scheduling and Dispatch

Outline. CEEM-ISCR Workshop on Electricity Industry Restructuring April Forecasting Wind Energy: Challenges and Solutions 1

Modern Power Systems Analysis

Cascading Outages in Power Systems. Rui Yao

Forecasting demand in the National Electricity Market. October 2017

NORDIC AND BALTIC GRID DISTURBANCE STATISTICS 2015

A Model for a Zonal Operating Reserve Demand Curve

WEATHER NORMALIZATION METHODS AND ISSUES. Stuart McMenamin Mark Quan David Simons

Chapter 2. Planning Criteria. Turaj Amraee. Fall 2012 K.N.Toosi University of Technology

AN OVERVIEW OF THE PROCESSES AND METHODOLOGY USED BY THE SYSTEM OPERATOR TO PREPARE THE FORECAST OF DEMAND.

AN78xx/AN78xxF Series

M E R C E R W I N WA L K T H R O U G H

2017 Settlement Calendar for ASX Cash Market Products ASX SETTLEMENT

For personal use only OZ MINERALS CARRAPATEENA COPPER GOLD PROJECT SOUTH AUSTRALIA 27 MARCH 2012

Aluminum Capacitors FEATURES APPLICATIONS PACKAGING

In data sheets and application notes which still contain NXP or Philips Semiconductors references, use the references to Nexperia, as shown below.

PROJECT ECONOMIC ANALYSIS

Deregulated Electricity Market for Smart Grid: A Network Economic Approach

Draft Wholesale Power Price Forecasts

Winter Season Resource Adequacy Analysis Status Report

Chapter 9: Transient Stability

Page No. (and line no. if applicable):

Price Correction Examples

Calibration for Settlement Areas. February 2016 Version 1.0

LEGAL DISCLAIMER. APG Coin (APG) White Paper (hereinafter 'the White Paper', 'the Document') is presented for informational purposes only

SMART GRID FORECASTING

An ASX listed Perth-based gold explorer focused on Ghana in West Africa

Module 6 : Preventive, Emergency and Restorative Control. Lecture 27 : Normal and Alert State in a Power System. Objectives

Estimation of extreme value dependence: application to Australian spot electricity prices. Nadezda Frolova

Software Tools: Congestion Management

DS3 System Services Scalar Design RECOMMENDATIONS PAPER. DS3 System Services Implementation Project


Aluminum Capacitors FEATURES APPLICATIONS PACKAGING

Pursuant to Section 205 of the Federal Power Act ( FPA ) 1 and the Commission s

August Australian Wool Production Forecast Report. Australian Wool Production Forecast Committee Summary

CHAPTER 5 - QUEENSLAND FORECASTS

A Comparison of Local vs. Sensory, Input- Driven, Wide Area Reactive Power Control

REVISED UPDATED PREPARED DIRECT SAFETY ENHANCEMENT COST ALLOCATION TESTIMONY OF GARY LENART SAN DIEGO GAS & ELECTRIC COMPANY AND

In data sheets and application notes which still contain NXP or Philips Semiconductors references, use the references to Nexperia, as shown below.

7. Transient stability

Maintenance/ Discontinued

Reading a GE PSLF *.epc into PWS. Tracy Rolstad Avista System Planning WECC PWSUG, 14 March 2012

Put the Weather to Work for Your Company

In data sheets and application notes which still contain NXP or Philips Semiconductors references, use the references to Nexperia, as shown below.

EVALUATION OF THE IMPACT OF POWER SECTOR REFORM ON THE NIGERIA POWER SYSTEM TRANSIENT STABILITY

Public Disclosure Copy. Implementation Status & Results Report Strengthening Institutional Capacity for Government Effectiveness Project (P149176)

In data sheets and application notes which still contain NXP or Philips Semiconductors references, use the references to Nexperia, as shown below.

Transcription:

MONTHLY CONSTRAINT REPORT - JUNE 2017 FOR THE NATIONAL ELECTRICITY MARKET PUBLISHED JULY 2017 IMPORTANT NOTICE

IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about constraint equation performance and related issues, as at the date of publication. Disclaimer This document or the information in it may be subsequently updated or amended. This document does not constitute legal or business advice, and should not be relied on as a substitute for obtaining detailed advice about the National Electricity Law, the National Electricity Rules, or any other applicable laws, procedures or policies. AEMO has made every effort to ensure the quality of the information in this document but cannot guarantee its accuracy or completeness. Accordingly, to the maximum extent permitted by law, AEMO and its officers, employees and consultants involved in the preparation of this document: make no representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of the information in this document; and are not liable (whether by reason of negligence or otherwise) for any statements or representations in this document, or any omissions from it, or for any use or reliance on the information in it. Copyright 2017. Australian Energy Market Operator Limited. The material in this publication may be used in accordance with the copyright permissions on AEMO s website. Page 2 of 13 introduction AEMO July 2017

CONTENTS IMPORTANT NOTICE 2 1. INTRODUCTION 4 2. CONSTRAINT EQUATION PERFORMANCE 4 2.1. Top 10 binding constraint equations 4 2.2. Top 10 Market impact constraint equations 4 2.3. Top 10 violating constraint equations 5 2.4. Top 10 binding interconnector limit setters 6 2.5. Constraint Automation Usage 7 2.6. Binding Dispatch Hours 7 2.7. Binding Constraint Equations by Limit Type 8 2.8. Market Impact Comparison 9 2.9. Pre-dispatch RHS Accuracy 10 3. GENERATOR / TRANSMISSION CHANGES 12 3.1. Constraint Equation Changes 12 TABLES Table 2-1 Top 10 binding network constraint equations 4 Table 2-2 Top 10 market impact network constraint equations 5 Table 3 Top 10 violating constraint equations 5 Table 4 Reasons for Top 10 violating constraint equations 6 Table 2-5 Top 10 binding interconnector limit setters 6 Table 2-6 Top 10 largest Dispatch / Pre-dispatch differences 10 Table 3-1 Generator and transmission changes 12 FIGURES Figure 2-1 Interconnector binding dispatch hours 8 Figure 2-2 Regional binding dispatch hours 8 Figure 2-3 Binding by limit type 9 Figure 2-4 Market Impact comparison 10 Figure 3-1 Constraint equation changes 12 Figure 3-2 Constraint equation changes per month compared to previous two years 13 AEMO July 2017 Contents Page 3 of 13

1. INTRODUCTION This report details constraint equation performance and transmission congestion related issues for June 2017. Included are investigations of violating constraint equations, usage of the constraint automation tool and performance of pre-dispatch constraint equations. Transmission and generation changes are also detailed along with the number of constraint equation changes. 2. CONSTRAINT EQUATION PERFORMANCE 2.1. Top 10 binding constraint equations A constraint equation is binding when the power system flows managed by it have reached the applicable thermal or stability limit or the constraint equation is setting a Frequency Control Ancillary Service (FCAS) requirement. Normally there is one constraint equation setting the FCAS requirement for each of the eight services at any time. This leads to many more hours of binding for FCAS constraint equations therefore, these have been excluded from the following table. Table 2-1 Top 10 binding network constraint equations #DIs (Hours) Change Date N^^V_NIL_1 Out = Nil, avoid voltage collapse in Southern NSW for loss of the largest VIC generating unit or Basslink 3753 (312.75) 20/04/2017 V::S_SETB_TBSE_2 Out= one South East to Tailem Bend 275kV line (NOTE: with both Black Range series capacitors O/S or I/S); Vic to SA Transient Stability limit for loss of one of the Tailembend-South East 275kV lines (South East Capacitor Available). 506 (42.16) 14/02/2017 N_MBTE1_B Out= one Directlink cable, Qld to NSW limit 314 (26.16) 25/11/2013 T>T_TUNN3_110_1 Out= Tungatinah to New Norfolk No.3 110kV line, avoid O/L Meadowbank Tee 2 to New Norfolk 110kV line on trip of Tungatinah to Meadowbank Tee 1 to New Norfolk 110kV lines, Feedback 250 (20.83) 16/06/2016 Q>N-MUTE_758 Out= 758 T174 Terranora to H4 Mudgeeraba 110kV line, avoid O/L on remaining Terranora to Mudgeeraba line on trip of Condong generator. 224 (18.66) 15/06/2017 I_CTRL_ISSUE_TE DC Link Control Issue Constraint for Terranora 465 (38.75) S-SNWWF_0 Discretionary upper limit for Snowtown WF generation of 0 MW 410 (34.16) 21/12/2012 21/08/2013 Q:N_NIL_OSC Out= Nil, QNI oscillatory stability limit of 1200 MW, limit reduced to 950 MW when any one SEQ SVC POD is out, limit is reduced to 853 MW when all three SEQ SVCs or PODs out. 231 (19.25) 25/07/2013 Q:N_NIL_AR_2L-G Out=Nil, limit Qld to NSW on QNI to avoid transient instability for a 2L-G fault at Armidale 224 (18.66) 08/01/2014 Q:N_AR_CP2_AR_2L-G Out = Armidale capacitor bank (120MVAr), limit Qld to NSW on QNI to avoid transient instability on 2L-G fault at Armidale 204 (17.0) 08/01/2014 2.2. Top 10 Market impact constraint equations Binding constraint equations affect electricity market pricing. The relative importance of binding constraint equations are determined by their market impacts. Page 4 of 13 AEMO July 2017

The market impact of a constraint equation is derived by summarising the marginal value for each dispatch interval (DI) from the marginal constraint cost (MCC) re-run 1 over the period considered. The marginal value is a mathematical term for the market impact arising from relaxing the RHS of a binding constraint equation by one MW. As the market clears each DI, the market impact is measured in $/MW/DI. The market impact in $/MW/DI is a relative comparison but not otherwise a meaningful measure. However, it can be converted to $/MWh by dividing the market impact by 12 (as there are 12 DIs per hour). This value of congestion is still only a proxy (and always an upper bound) of the value per MW of congestion over the period calculated; any change to the limits (RHS) may cause other constraint equations to bind almost immediately after. Table 2-2 Top 10 market impact network constraint equations Marginal Values Change Date S-SNWWF_0 Discretionary upper limit for Snowtown WF generation of 0 MW 451,764 21/08/2013 V_MTMERCER_ZERO Mt Mercer Windfarm upper limit of 0 MW 183,517 22/10/2013 F_I+NIL_RREG NEM Raise Regulation Requirement 131,932 25/10/2016 S_TBL_0 Discretionary upper limit for The Bluff generation of 0 MW 123,406 21/08/2013 F_I+LREG_0120 NEM Lower Regulation Requirement greater than 120 MW 118,657 21/08/2013 S_NBH_0 Discretionary upper limit for North Brown Hill generation of 0 MW 116,733 21/08/2013 N^^V_NIL_1 F_T+NIL_MG_RECL_R6 Out = Nil, avoid voltage collapse in Southern NSW for loss of the largest VIC generating unit or Basslink Out = Nil, Raise 6 sec requirement for a Tasmania Reclassified Woolnorth Generation Event (both largest MW output and inertia), Basslink unable to transfer FCAS 74,133 20/04/2017 65,927 02/12/2016 F_I+NIL_MG_R6 Out = Nil, Raise 6 sec requirement for a NEM Generation Event 50,788 21/08/2013 S_SECB_LG3 Out= South East 132kV CB 6186 Or 6187, Oscillatory stability limit for the loss of Penola West-South East 132kV line, max generation of Ladbrok Grove Gen 1 and 2 to a total of 40 MW 49,485 26/05/2017 2.3. Top 10 violating constraint equations A constraint equation violates when NEMDE is unable to dispatch the entities on the left-hand side (LHS) so the summated LHS value is less than or equal to, or greater than or equal to, the right-hand side (RHS) value (depending on the mathematical operator selected for the constraint equation). The following table includes the FCAS constraint equations. Reasons for the violations are covered in 2.3.1. Table 3 Top 10 violating constraint equations #DIs (Hours) Change Date T^T_LFWA_1_DS Out = Lindisfarne to Waddamana 220 kv line, avoid voltage instability or violations for loss of the other Lindisfarne to Waddamana 220 kv line line, dispatch only 4 (0.33) 21/08/2013 VSML_-050 Vic to SA on ML upper transfer limit of -50 MW 1 (0.08) 08/01/2014 F_T+NIL_MG_RECL_R6 Out = Nil, Raise 6 sec requirement for a Tasmania Reclassified Woolnorth Generation Event (both largest MW output and inertia), Basslink unable to transfer FCAS 1 (0.08) 02/12/2016 NSA_Q_GSTONE34_150 Gladstone 3+4 >= 150 for Network Support Agreement 1 (0.08) 07/10/2015 1 The MCC re-run relaxes any violating constraint equations and constraint equations with a marginal value equal to the constraint equation s violation penalty factor (CVP) x market price cap (MPC). The calculation caps the marginal value in each DI at the MPC value valid on that date. MPC is increased annually on 1 st July. AEMO July 2017 Page 5 of 13

#DIs (Hours) Change Date F_T+NIL_WF_TG_R6 Out= Nil, Tasmania Raise 6 sec requirement for loss of a Smithton to Woolnorth or Norwood to Scotsdale tee Derby line, Basslink unable to transfer FCAS 1 (0.08) 12/04/2016 F_T+NIL_MG_R6 Out = Nil, Raise 6 sec requirement for a Tasmania Generation Event (both largest MW output and inertia), Basslink unable to transfer FCAS 1 (0.08) 12/04/2016 N>N-X_96H+9W2+9W5_1 Out= Coffs Harbour-Koolkhan (96H) & Raleigh-Kempsey(9W2) & Macksville-Kempsey(9W5), avoid O/L Armidale-Coffs Harbour (96C) on trip of Armidale-Coffs Harbour (87), Swamp out when all 3 directlink cable O/S,Feedback, TG formulation in PD/ST 1 (0.08) 27/01/2017 2.3.1. Reasons for constraint equation violations Table 4 Reasons for Top 10 violating constraint equations T^T_LFWA_1_DS VSML_-050 F_T+NIL_MG_RECL_R6 NSA_Q_GSTONE34_150 F_T+NIL_WF_TG_R6 F_T+NIL_MG_R6 N>N-X_96H+9W2+9W5_1 Constraint equation violated for 4 Dis on 15/06/2017 between 0805 hrs and 0820 hrs. Max violation of 291.75 MW occurred at 0805 hrs. Constraint equation violated due to insufficient voltage support at the time while Gordon units reached their maximum availability and Meadowbank unit not available. Constraint equation violated for 1 DI on 04/06/2017 at 1715 hrs with a value of 17.17 MW. Constraint equation violated due to competing requirement on Murraylink import limit (SVML_ROC_80). Constraint equation violated for 1 DI on 12/06/2017 at 2110 hrs with a violation of 9.25 MW. Constraint equation violated due to Tasmania raise 6 sec service availability less than requirement. Constraint equation violated for 1 Di on 12/06/2017 at 0635 hrs with a violation of 3.75 MW. Constraint equation violated due to Gladstone units 3 and 4 were limited by their ramp up rate. Constraint equation violated for 1 DI on 23/06/2017 at 0130 hrs with a violation of 2.69 MW. Constraint equation violated due to Tasmania raise 6 sec service availability less than requirement. Constraint equation violated for 1 DI on 11/06/2017 at 0145 hrs with a value of 0.48 MW. Constraint equation violated due to Tasmania raise 6 sec service availability less than requirement. Constraint equation violated for 1 DI on 19/06/2017 1805 hrs with a violation of 0.15 MW. Constraint equation violated due to competing requirement with Terranora interconnector import limit (Q>NIL_MUTE_757) 2.4. Top 10 binding interconnector limit setters Binding constraint equations can set the interconnector limits for each of the interconnectors on the constraint equation left-hand side (LHS). Table 2-5 lists the top (by binding hours) interconnector limit setters for all the interconnectors in the NEM and for each direction on that interconnector. Table 2-5 Top 10 binding interconnector limit setters Interconnec tor #DIs (Hours) Average Limit (Max) N^^V_NIL_1 VIC1-NSW1 Import Out = Nil, avoid voltage collapse in Southern NSW for loss of the largest VIC generating unit or Basslink 3753 (312.75) -257.54 (-1062.07) N^^V_NIL_1 V-S-MNSP1 Export Out = Nil, avoid voltage collapse in Southern NSW for loss of the largest VIC generating unit or Basslink 3701 (308.42) 7.52 (149.15) F_MAIN++NIL_MG_R5 T-V-MNSP1 Export Out = Nil, Raise 5 min requirement for a Mainland Generation Event, Basslink able transfer FCAS 1595 (132.92) -198.56 (406.67) Page 6 of 13 AEMO July 2017

Interconnec tor #DIs (Hours) Average Limit (Max) F_MAIN++NIL_BL_L60 T-V-MNSP1 Import Mainland Lower 60 second Requirement for loss of Basslink, Basslink flow into Tas 658 (54.83) -388.95 (-468.0) F_MAIN++NIL_MG_R6 T-V-MNSP1 Export Out = Nil, Raise 6 sec requirement for a Mainland Generation Event, Basslink able transfer FCAS 605 (50.42) -153.98 (-52.0) F_MAIN++ML_L5_0400 T-V-MNSP1 Import Out = Nil, Lower 5 min requirement for a Mainland Load Event, ML = 400, Basslink able transfer FCAS 570 (47.5) -177.23 (-476.39) V::S_SETB_TBSE_2 V-SA Export Out= one South East to Tailem Bend 275kV line (NOTE: with both Black Range series capacitors O/S or I/S); Vic to SA Transient Stability limit for loss of one of the Tailembend-South East 275kV lines (South East Capacitor Available). 506 (42.17) -18.17 (94.78) I_CTRL_ISSUE_TE N-Q-MNSP1 Export DC Link Control Issue Constraint for Terranora 465 (38.75) -79.0 (-46.2) F_MAIN++NIL_MG_R60 T-V-MNSP1 Export Out = Nil, Raise 60 sec requirement for a Mainland Generation Event, Basslink able transfer FCAS 463 (38.58) -196.07 (431.41) N_MBTE1_B N-Q-MNSP1 Import Out= one Directlink cable, Qld to NSW limit 314 (26.17) -155.51 (-175.9) 2.5. Constraint Automation Usage The constraint automation tool is an application in AEMO s energy management system (EMS) that generates thermal overload constraint equations based on the current or planned state of the power system. It is currently used by on-line staff to create thermal overload constraint equations for power system conditions where there are no existing constraint equations or the existing constraint equations did not operate correctly. The following section details the reason for each invocation of the non-real time constraint automation constraint sets and the results of AEMO s investigation into each case. Non-real time constraint automation was not used. 2.5.1. Further Investigation Non-real time constraint automation was not used. 2.6. Binding Dispatch Hours This section examines the number of hours of binding constraint equations on each interconnector and by region. The results are further categorized into five types: system normal, outage, FCAS (both outage and system normal), constraint automation and quick constraint equations. In the following graph the export binding hours are indicated as positive numbers and import with negative values. AEMO July 2017 Page 7 of 13

Hours Binding Hours Binding Figure 2-1 Interconnector binding dispatch hours 400 300 15 Quick 200 100 229 310 Constraint Automation 0 51-62 -38-17 -18 52 FCAS -100-200 -204-313 Outage -300-12 System Normal -400 N-Q-MNSP1 NSW1-QLD1 T-V-MNSP1 V-S-MNSP1 V-SA VIC1-NSW1 The regional comparison graph Figure 2-2 uses the same categories as in Figure 2-1 as well as non-conformance, network support agreement and ramping. Constraint equations that cross a regional boundary are allocated to the sending end region. Global FCAS covers both global and mainland requirements. Figure 2-2 Regional binding dispatch hours 800 700 Ramping 600 NSA 500 400 300 58 25 720 Constraint Automation Non Conformance FCAS 200 100 0 414 314 40 74 42 53 11 NSW Qld SA Tas Vic Global FCAS Misc Outage System Normal 2.7. Binding Constraint Equations by Limit Type Figure 2-3 shows the percentage of DIs in June 2017 that the different types of constraint equations bound. Page 8 of 13 AEMO July 2017

Figure 2-3 Binding by limit type Voltage Stability 23% Discretionary 0% Unit Zero 6% FCAS 50% Transient Stability 6% Thermal 6% Ramping 0% Quick 2% Outage Ramping 1% Other 3% Oscillatory Stability 2% Network Support 0% Non-Conformance 0% 2.8. Market Impact Comparison Figure 2-4 compares the cumulative market impact (calculated by summating the marginal values from the MCC re-run the same as in section 2.2) for each month for the current year (indicated by type as a stacked bar chart) against the cumulative values from the previous two years (the line graphs). The current year is further categorised into system normal (NIL), outage, network support agreement (NSA) and negative settlements residue constraint equation types. AEMO July 2017 Page 9 of 13

Market Impact Figure 2-4 Market Impact comparison $70,000,000 $60,000,000 $50,000,000 $40,000,000 $30,000,000 $20,000,000 $10,000,000 $0 NIL Outage NSA Neg Res 2016 Total 2015 Total 2.9. Pre-dispatch RHS Accuracy Pre-dispatch RHS accuracy is measured by the comparing the dispatch RHS value and the pre-dispatch RHS value forecast four hours in the future. Table 2-6 shows the pre-dispatch accuracy of the top ten largest differences for binding (in dispatch or pre-dispatch) constraint equations. This excludes FCAS constraint equations, constraint equations that violated in Dispatch, differences larger than ±9500 (this is to exclude constraint equations with swamping logic) and constraint equations that only bound for one or two DIs. AEMO investigates constraint equations that have a Dispatch/Pre-dispatch RHS difference greater than 5% and ten absolute difference that have either bound for more than 25 DIs or have a greater than $1,000 market impact. The investigations are detailed in section 2.9.1. Table 2-6 Top 10 largest Dispatch / Pre-dispatch differences #DIs % + Max Diff % + Avg Diff N^^V_NIL_1 Out = Nil, avoid voltage collapse in Southern NSW for loss of the largest VIC generating unit or Basslink 810 772,442% (340.79) 1,531% (137.66) N^^V_DDSM1 Out = Dederang to South Morang 330 kv line, avoid voltage collapse in Southern NSW for loss of the largest VIC generating unit or Basslink 12 260% (189.15) 106.47% (92.) N^^V_MSUT_1 Out = Murray to Upper Tumut 330 kv line, avoid voltage collapse in Southern NSW for loss of the largest VIC generating unit or Basslink 14 175% (152.13) 106.01% (130.21) V>>V_NIL_8 Out = Nil, avoid O/L DDTS to WOTS 330kV line for trip of LowerTumut-Wagga (051) + (991,990,99P) or (990,99M,970) ex_yass lines - status switched ; Feedback 3 173% (65.2) 147.36% (55.01) Q>NIL_MUTE_758 Out= Nil, ECS for managing 758 H4 Mudgeeraba to T174 Terranora 110kV line, Summer and Winter ECS ratings selected by SCADA status. 10 98.33% (99.95) 93.45% (99.95) Page 10 of 13 AEMO July 2017

#DIs % + Max Diff % + Avg Diff V::S_SETB_TBSE_2 Out= one South East to Tailem Bend 275kV line (NOTE: with both Black Range series capacitors O/S or I/S); Vic to SA Transient Stability limit for loss of one of the Tailembend-South East 275kV lines (South East Capacitor Available). 102 78.31% (50.29) 13.18% (9.42) V^^S_SETB_TBSE_2 Out= one South East to Tailem Bend 275kV line (NOTE: with both Black Range series capacitors O/S or I/S); Vic to SA Long Term Voltage Stability limit for loss of one of the Tailembend-South East 275kV lines (South East Capacitor Available). 7 34.37% (40.93) 11.28% (13.13) T::T_NIL_4 Out = NIL, prevent poorly damped TAS North - South oscillations following fault and trip of Palmerston to Sheffield 220 kv line, Tamar CCGT OOS. Swamped if Tamar CCGT in service 19 32.88% (148.86) 18.26% (98.67) Q>N-MUTE_758 Out= 758 T174 Terranora to H4 Mudgeeraba 110kV line, avoid O/L on remaining Terranora to Mudgeeraba line on trip of Condong generator. 32 24.83% (25.24) 8.66% (8.21) N_X_MBTE_3B Out= all three Directlink cables, Terranora_I/C_import <= Terranora_Load 2.9.1. Further Investigation The following constraint equation(s) have been investigated: 15 24.5% (9.8) 11.85% (4.72) Q>N-MUTE_758: Investigated. Mismatch was due to difference between modeling of Terranora control scheme and line status between DS and PD. No improvement can be made to the constraint equation at this stage. N^^V_NIL_1: The Pre-dispatch for this constraint equation was recalculated in early May 2014 (with an update to the limit advice). No further improvements can be made at this time. N^^V_DDSM1: Investigated and no improvement can be made to the constraint equation at this stage. N^^V_MSUT_1: Investigated and no improvement can be made to the constraint equation at this stage Q>NIL_MUTE_758: Investigated. Mismatch was due to difference between modeling of Terranora control scheme and line status between DS and PD. No improvement can be made to the constraint equation at this stage. V::S_SETB_TBSE_2: Investigated and no improvement can be made to the constraint equation at this stage. AEMO July 2017 Page 11 of 13

3. GENERATOR / TRANSMISSION CHANGES One of the main drivers for changes to constraint equations is power system changes, whether this is the addition or removal of plant (either generation or transmission). Table 3-1 details changes that occurred during June 2017. Table 3-1 Generator and transmission changes Project Date Region Notes Ballarat to Moorabool No.2 220 kv line commissioned 09 June 2017 Victoria 3.1. Constraint Equation Changes Figure 3-1 Constraint equation changesfigure 3-1 indicates the regional location of constraint equation changes. For details on individual constraint equation changes refer to the Weekly Constraint Library Changes Report [2] or the constraint equations in the MMS Data Model. [3] Figure 3-1 Constraint equation changes Vic, 22, 12% NSW, 81, 45% SA, 65, 36% Quick, 5, 3% Qld, 5, 3% Other, 2, 1% Figure 3-2 compares the constraint equation changes for the current year versus the previous two years. The current year is categorised by region. 2 AEMO. NEM Weekly Constraint Library Changes Report. Available at: http://www.nemweb.com.au/reports/current/weekly_constraint_reports/ 3 AEMO. MMS Data Model. Available at: http://www.aemo.com.au/electricity/it-systems/nem Page 12 of 13 AEMO July 2017

Number of changes Figure 3-2 Constraint equation changes per month compared to previous two years 3400 3200 3000 2800 2600 2400 2200 2000 1800 1600 1400 1200 1000 800 600 400 200 0 Con Auto SA Qld Tas Vic FCAS NSW 2016 Total 2015 Total AEMO July 2017 Page 13 of 13