Modeling and Simulation of Air Insulated and Gas Insulated Substations

Similar documents
Analysis of Very Fast Transients in EHV Gas Insulated Substations

Mitigation and Analysis of Very Fast Transient over Voltages (VFTOs) in 765/245kV Gas Insulated Substation (GIS) by Wavelet Transforms

Modeling of Transmission Line and Substation for Insulation Coordination Studies

STUDIES ON LIGHTNING CHARACTERISTICS

OR Explain thermal breakdown in solid dielectrics. How this mechanism is

Selecting the current rating for equipment

Study of Transient Behaviour of the Capacitor Voltage Transformer

PARTICLE TRAJECTORIES IN A THREE PHASE COMMON ENCLOSURE GAS INSULATED BUSDUCT WITH MONTE CARLO TECHNIQUE

Evaluation of the risk of failure due to switching overvoltages of a phase to phase insulation

A Novel Optimized Design for Busbar Structures using Finite Element Methods

Fatima Michael College of Engineering & Technology

UNIT I - INTRODUCTION SYLLABUS

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

SSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL

Film Capacitors. EMI suppression capacitors. Date: June 2018

Study of Time Correlation Between Lightning Data Recorded by LLS and Relay Protection

Fault Calculation Methods

TRANSIENTS POWER SYSTEM. Theory and Applications TERUO OHNO AKIH1RO AMETANI NAOTO NAGAOKA YOSHIHIRO BABA. CRC Press. Taylor & Francis Croup

INSTITUTE OF AERONAUTICAL ENGINERING DUNDIGAL ELECTRICAL AND ELECTRONICS ENGINEERING

SPECIFICATION SS 51/9 400KV COUPLING CAPACITORS FOR POWER LINE CARRIER SYSTEM

Electrical, Electronic and Computer Engineering ENEL4HB - High Voltage 2

Finite Element Method Application in Analyzing Magnetic Fields of High Current Bus Duct

O Plus Dry Bushing 69 kv system, 350 kv BIL, 3000 A. Table of contents

Conventional Paper-I-2011 PART-A

J. Electrical Systems 10-3 (2014): Regular paper

1. Explain the various methods of methods of grounding. In power system, grounding or earthing means connecting frame of electrical equipment (non-cur

Comparison of Radial Movement of Metallic Particles in a Single Phase Gas Insulated Busduct

INSTITUTE OF AERONAUTICAL ENGINERING DUNDIGAL ELECTRICAL AND ELECTRONICS ENGINEERING

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK

Request Ensure that this Instruction Manual is delivered to the end users and the maintenance manager.

Collation Studies of Sequence Impedances for Underground Cables with Different Layouts

VX25 Enclosure System. Technical documentation PE conductor connection, current carrying capacity

An Innovative Simple Test Circuit for Single-Phase Short Circuit Making Test of High-Voltage Switching Devices

PREDICTION OF TEMPERATURE VARIATIONS FOR INDUSTRIAL BUS DUCT SYSTEM UNDER FORCED CONVECTION COOLING WITH VARIOUS ASPECT RATIOS USING MATLAB

Railway Research. Study of Superconducting Fault Current Limiter Device in a AC Railway System. 1. Introduction. International Journal of

Numerical Calculation and Analysis on the Surface Electric Field Characteristics of Hot-Line Robot

VKES. Contents. Page 2 No 213, 13th Main RBI Layout JP Nagar 7th Phase, Bangalore Vidyuth Kanti Engineering Services

Estimation of Current Transformer Insulation Life with an Effect of Environmental Variables

EXPERIMENTAL AND THEORETICAL STUDY OF BREAKDOWN VOLTAGE INITIATED BY PARTICLE CONTAMINATION IN GIS


EE Branch GATE Paper 2010

Electric Field Stress Calculation for different spacer types in Bus Duct

Comparative Study of Synchronous Machine, Model 1.0 and Model 1.1 in Transient Stability Studies with and without PSS

Power System Analysis Prof. A. K. Sinha Department of Electrical Engineering Indian Institute of Technology, Kharagpur

Computation of Electric Field for FGM Spacer Using Di-Post Insulator in GIS

5SJ4...-.HG Circuit Breakers to IEC and UL 489

Copyright 2015 Elsevier S.A.

Full-Maxwell Simulations of Very Fast Transients in GIS: case study to compare 3D and 2D-axisymmetric models of 1100 kv test set-up

Transient Behavior of

ANALYSIS OF SUBSYNCHRONOUS RESONANCE EFFECT IN SERIES COMPENSATED LINE WITH BOOSTER TRANSFORMER

Electric Filed Simulation and Structure Optimization for 40.5kV GIS Based on Finite Element Method

Superconducting Fault Current Limiters

Harmonic Modeling of Networks

ELECTROMANETIC PULSE PROPAGATION IN A COAXIAL CABLE

Modeling of Power System Components During Electromagnetic Transients

66kV & 220kV Substation Protection From Lightning by Fixed Angle, Rolling Sphere and Early Streamer Method

Impedance relay and protection assemblies

Electrical, Electronic and Computer Engineering ENEL4HB - High Voltage 2

90 MCB MODULAR CIRCUIT BREAKERS FOR CIRCUIT PROTECTION

The Lightning Study of Overhead Transmission Lines

Lightning Insulation Coordination Study

URD Cable Fault Prediction Model

and cables for offshore wind connection

GIS 101: AN INTRODUCTION TO GAS INSULATED SUBSTATIONS

SECTION 3 BASIC AUTOMATIC CONTROLS UNIT 12 BASIC ELECTRICITY AND MAGNETISM

The Effect of Harmonic Distortion on a Three phase Transformer Losses

Effects of Capacitor Bank Installation in a Medium Voltage (MV) Substation

Experimental Study of the Artificial Neural Network Solutions for Insulators Leakage Current Modeling in a Power Network

IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 22, NO. 1, JANUARY /$ IEEE

Calculations of Capacitance for Transposed Bundled Conductor Transmission Lines

Fault Analysis Power System Representation

Mitigation of Distributed Generation Impact on Protective Devices in a Distribution Network by Superconducting Fault Current Limiter *

PUB NLH 185 Island Interconnected System Supply Issues and Power Outages Page 1 of 9

The objective of a grounding system are: 1. To provide safety to personnel during normal and fault conditions by limiting step and touch potential.

ESTIMATION OF CAPACITOR BANK SWITCHING OVERVOLTAGES USING ARTIFICIAL NEURAL NETWORK

Energy saving in electromechanical equipment with power coefficient correction. Dimitris Al. Katsaprakakis Aeolian Land S.A.

DISTRIBUTION SYSTEM ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS

ECE 585 Power System Stability

O Plus Dry Bushing 25 kv system, 150 kv BIL, 3000 A

Influence of Grounding Material s Property on the Impulse Grounding Resistance of Grounding Grids

PD Analysis in Cylindrical Void With Respect To Geometry of the Void

Narapareddy Rama Rao 1, J.Amarnath 2, E.Arunkumar 3, T.Srinivas 4

Transient analysis of the behaviour of grounding systems consisted by driven rods

Suppressor film capacitor Highlight and Application in Series with the main

Comparison of Transient Simulations on Overhead Cables by EMTP and FDTD

Effective Design of Large Grounding Systems

THREE PHASE CAPACITOR For WIND TURBINES

DIRECT STROKE LIGHTNING PROTECTION DESIGN

Evaluation of Capacitance in Motor Circuit Analysis Findings. Howard W Penrose, Ph.D., CMRP President, SUCCESS by DESIGN

Determination of Fault Location in Shunt Capacitor Bank through Compensated Neutral Current

By choosing to view this document, you agree to all provisions of the copyright laws protecting it.

YMCA UNIVERSITY OF SCIENCE AND TECHNOLOGY, FARIDABAD SCHEME OF STUDIES & EXAMINATIONS B.TECH 2 nd YEAR (SEMESTER IV) ELECTRICAL ENGINEERING ( )

TEST CERTIFICATES OR REPORTS ISSUED BY VEIKI-VNL LTD.

Jinzhou Power Supply Company, Liaoning Electric Power Company Limited, State Grid, China

Damping resistor design consideration

POWER SEMICONDUCTOR BASED ELECTRIC DRIVES

Analysis of surge arresters failures in the installation of broadcasting transmitter

MCB NB1-63H Miniature Circuit Breaker

SWITCHGEAR: design concepts, testing, standards and safety of persons and installations

SHORT CIRCUITS IN 3kV DC SYSTEM: STRESSES ON VEHICLES AND INFRASTRUCTURE ELECTRIC EQUIPMENT

Transcription:

International Journal of Electrical Engineering. ISSN 0974-2158 Volume 11, Number 2 (2018), pp. 177-187 International Research Publication House http://www.irphouse.com Modeling and Simulation of Air Insulated and Gas Insulated Substations Dipali Kamthe 1 PG Student, Department of Electrical Engineering, Government College of Engineering Aurangabad, Maharashtra, India. Dr. N. R. Bhasme 2 Associate Professor, Department of Electrical Engineering, Government College of Engineering Aurangabad, Maharashtra, India. Abstract This paper presents modeling and simulation of gas insulated substation and air insulated substation. Performance analysis is carried out on the basis of obtained results and case study. Key property of AIS unit is step-up systems in connection with power stations and transformer substation in the extra high voltage transmission system. Whereas the gas insulated substation works on the principle operation of completely enclosure of all the energized parts in metallic encapsulation compressed within sulphur hexafluoride gas. Both the substations have equal merits and demerits in different aspects. In this paper equivalent circuit of substation is designed in MATLAB/Simulink software to calculate the Very Fast Transient Overvoltage. Other parameters like medium of insulation, construction/space requirement, environmental impact and maintenance are also discussed in this paper. Keywords: Substations, AIS, GIS, Sulphur hexafluoride gas, VFTO, MATLAB Software. I. INTRODUCTION Providing power has become a challenge to the power companies, the power companies take care of generation, transmission as well as distribution of power through various reliable power plants. As the electricity demand is increasing day by day, the power companies are giving their active participation in fulfilling consumer demand. The design of power substation is classified as air insulated substation and gas insulated substation. An AIS unit is basically a conventional switchgear technology where air is used as primary dielectric for insulation whereas; in GIS unit

178 Dipali Kamthe, Dr. N. R. Bhasme sulphur hexafluoride gas is used as the primary dielectric medium for insulation. Key property of AIS unit is step up systems in connection with power stations and transformer substations in the extra high voltage transmission system. Gas insulated substation are preferred for 72.2 kv, 145 kv, 245 kv, 420 kv and above with all its equipments encapsulated in a metal enclosure compressed with SF6 in it. [1]. As the dielectric strength of SF6 is three times more than that of the dielectric strength of air, the overall size of complete gas insulated substation and the size of equipments can be reduced to 10% of the conventional air insulated substation [2]. As GIS substation is encapsulated in a metal enclosure free from the external environmental impacts and faults due to the natural environmental hazards, this property of GIS unit makes it more efficient and reliable as compared to the AIS unit. Although GIS has numerous advantages but if any switching operation or faults occur in GIS, high transient overvoltages get produced. These transients are called as very fast transient overvoltages (VFTO). These VFTOs are in the range of nano seconds. These VFTOs are produced due to closing and opening operations of disconnector switch. VFTOs adversely affect the system by decreasing the insulation life and also by affecting the external equipment like transformers where in-turn insulation is stressed out with a higher voltage than under chopped lightening impulse voltages [3]. Considering all the merits and demerits of both the substations a comparative analysis is made. The parameters to be compared are discussed below: 1. Very Fast Transient Overvoltage Figure 1. Classification of VFTO

Modeling and Simulation of Air Insulated and Gas Insulated Substations 179 Study of fast transient voltage is a very important aspect in gas insulated substation. VFTO are generated mainly due to the closing and opening operation of the disconnector switch [6]. Classification of VFTO is shown in figure 1 [7]. According to IEC 71-1, the overvoltages are classified as temporary overvoltages and transient overvoltages based on their duration [8]. Temporary overvoltages are long duration overvoltages, which are damped or slightly damped. Transient overvoltages are short duration overvoltages, which are highly damped transient overvoltage. In gas insulated substation, VFTOs can be caused by switching operation and also due to faults. Switching operation generates fast front transients and because of its travelling nature in GIS, produces internal and external transients. The internal transients are with respect to bus duct and enclosure that is; wherever it experiences impedance change in the internal bus duct which is enclosed, these fast front transients is produced. External transients are produced with respect to the enclosure discontinuities that is, between enclosure and ground at GIS to air interface. Because of these external transients enclosure voltages will be produced. So the overhead lines which are connected to the substation will be affected because of these transients. These transients also cause stresses and electromagnetic interference (EMI) in the secondary equipments. During closing and opening operation, the voltages across the breaker contacts collapse within nanoseconds and the surge interacted between two contacts, travels in either direction of bus duct. These surges when experiences an impedance change it gets reflected and refracted near the terminals. Due to these reflections, over voltages are generated, these overvoltages are known as VFTO. VFTO are developed with different magnitude at each re-strike. Maximum magnitude of VFTO appears to be 2.5 pu with very short rise time of 4-100 nano seconds. 1.1 Modeling of GIS and AIS The equivalent circuit is constructed by using MATLAB software. By using the circuit, transients are calculated for 10 meters length of GIS (132 kv). The transients are generated not only due to switching but also by the 3- phase faults occurring on the line. The line capacitance, Inductance and the surge impedance are calculated using the following formula [9]. By calculating values of the circuit parameters, an equivalent circuit is constructed by using MATLAB software. The modeling diagram of 145kV substation is shown in figure 2. The capacitance of the GIS is calculated to be 90 pf per unit length and a line inductance is calculated to be 0.4µH per meter and a resistance of 1 ohm is connected in series with the circuit breaker. The voltage of equivalent circuit developed on MATLAB software is taken in 1.0p.u. and -1.0 p.u. Depending upon the closing time and opening time of the circuit breaker contacts the load side voltage magnitude changes. The line parameters used in the MATLAB design are mentioned in table 1.

180 Dipali Kamthe, Dr. N. R. Bhasme 1.1.1 Capacitance calculation The capacitance is calculated with the assumption that the conductors are cylindrical. Capacitance is calculated using the following formulae. C= 2πε 0ε r l ln ( b a ) Where ε 0 = 8.854 10-12, & ε r = 1 b = radius of outer cylinder a = radius of inner cylinder l = length of the section 1.1.2 Inductance calculation The inductance of the bus duct can be calculated by using formulae given below, where b and a are the outer radii and inner radii of the conductor respectively. L = μ 0 ln (b a ) 2π Where μ 0 = 4π 10-7 Table 1. Line Parameters of AIS and GIS Parameters AIS GIS Line voltage 145 kv 145 kv Line capacitance 101.6 pf 90 pf Line inductance 0.43 µh 0.12 µh Line impedance 62.7 Ω 36.5 Ω Phase voltage 118.39 kv 118.39 kv Phase current 2.0 A 3.243 A

Modeling and Simulation of Air Insulated and Gas Insulated Substations 181 Figure 2. Simulink Model of 145 kv Substation 1.2 Simulation results The various transient voltages at different switching operations (closing and opening) are shown in the results. The inductance of the line is calculated from the diameter of the enclosure and the conductors. The transient overvoltages and over current due the opening operation are shown in figure 3 and figure 4 respectively. From the graph the peak voltages of all the three phases are obtained as 1.2p.u., 1.2p.u. and 1.2p.u. and current of all three phases is obtained as 0.03p.u., 0.03 p.u., and 0.03 p.u. Figure 3. Transient Voltage Waveform during opening operation

182 Dipali Kamthe, Dr. N. R. Bhasme Figure 4. Transient Current Waveform during opening operation Figure 5. Transient Voltage Waveform during closing operation Figure 6. Transient Current Waveform during closing operation

Modeling and Simulation of Air Insulated and Gas Insulated Substations 183 The transient overvoltages and over current due the closing operation are shown in figure 5 and figure 6 respectively. From the graph the peak voltages of all the three phases are obtained as 1.8p.u., 1.8p.u. and 1.8p.u. and current of all three phases is obtained as 0.3p.u., 0.3 p.u., and 0.3 p.u. The magnitudes of transient overvoltages and current at closing and opening operation are tabulated in table 1. Table 2. Transients due to switching operations Mode of operation Peak magnitude of voltage (p.u.) Peak magnitude of current (p.u.) VR VY VB IR IY IB Closing operation 1.8 1.8 1.8 0.3 0.3 0.3 Opening operation 1.2 1.2 1.2 0.03 0.03 0.03 2. Medium of Insulation From years the conventional medium of insulation is preferred to air. Air is used as the primary dielectric medium for insulation in the conventional switchgear substation or air insulated substation. Whereas the advanced technique of substation i.e. the gas insulated substation utilizes a greater dielectric medium, sulphur hexafluoride gas (SF6). The high voltage conductors, current transformers, voltage transformers, circuit breaker interrupters, and switches are placed in a metal enclosure which is compressed within SF6 gas. Air as insulation medium is used in a conventional switchgear substation, where air is required in meters for insulation. SF6 is an inert, colorless, nontoxic, tasteless, odorless and nonflammable gas comprising of a sulphur atom surrounded and firmly bounded to six fluorine atoms the combination of which makes an electronegative gas. SF6 gas is about five times heavier than air [4]. When a free electron comes in collision with an unbiased gas molecule, the electron is attracted by that gas molecule and negative ion is formation takes place. As the negative ions so formed are heavy they do not attain sufficient energy to contribute to ionization of the gas. This property gives a good dielectric property [5]. Dielectric strength of SF6 is 3 times more than that of air. Dielectric strength of air is 3 kv/mm. The metal enclosure of GIS unit is filled with SF6 under the minimum operating pressure of 400 kpa. As the AIS unit is constructed under the open air, there is no concern of air to be filled under certain pressure. According to the IEC standards, Minimum operating pressure is 400 kpa, maximum operating pressure is 580 kpa and the burst pressure is greater than or equal to 3000 kpa. 3. Construction/ Space requirement Air insulated substation are the conventional substations which are constructed over a large area mostly in the outskirts of the city. Whereas a GIS unit being compact in size can be constructed in the city as well for the voltage rating of 72.2kV, 145kV, 245kV, 420kV. Considering space as one of the parameters to be compared, again

184 Dipali Kamthe, Dr. N. R. Bhasme there exist merits and demerits of both the substations. Taking into the consideration of substation layout and its working operation the air insulated substation has advantageous key features. In an air insulated substation the primary choice for selection of space/area can be made as per the requirement. This system is possible with a quality design due to its low cost of switchgear and low cost of construction. Also it takes less time for construction. In contrast, GIS uses less space as there is reduced distance between active and non active switchgear parts of the system. From figure 7 the overall space required by the substations can be estimated. The dimensions of substations are mentioned in meters (see figure 7). If total area of the respective substations is calculated, it is observed the area occupied by an AIS unit is 1359 m 2 and area occupied by a GIS unit is 22.81 m 2, through which one can conclude that area occupied by GIS unit is much lesser than the area occupied by that of an AIS unit. 50 45 40 35 30 25 20 15 10 5 0 45.3 12 AIS 30 6.77 3.37 2.55 GIS length (m) height (m) width (m) Figure 7. Dimensions of AIS and GIS unit in meters 4. Environmental Impact The impact of environment in the field of transmission substation has become more essential for the study of both, the increase in world energy demand and also the considerable effect of human action on the nature. Transmission system presently should be more reliable, smart, efficient and furthermore environment friendly. An environmental comparison of GIS and AIS are studied so as to conclude which substation is having more environmental impact. The AIS unit considered is a particular 220 kv substation in Aurangabad region in Maharashtra state. And the GIS unit considered is a particular 132 kv substation in Aurangabad region in Maharashtra state. The analysis is based on the fault occurring frequency in the past one year due to the environmental disturbances. As the GIS substation includes a building that holds 145 kv installations does not come in direct contact of the environmental disturbances whereas an AIS unit faces a huge loss of equipments when any environmental disturbances such as lightening strokes, heavy wind strokes or transients come in contact with the live parts of the substation. In such conditions major breakdown of AIS unit happens. Two major breakdowns occurred in past one

Modeling and Simulation of Air Insulated and Gas Insulated Substations 185 year in the AIS unit shown in table 3. According to the study no such breakdown has occurred in the GIS unit from the past 10 years. But GIS unit is supposed to trip if any external line faults occur in the system. Table 3. Major Breakdown in an AIS unit occurred due to environmental disturbances Sr. no. Month Duration Reason of Breakdown 1 August 43 minutes R phase CT burst due to heavy lightening stroke. 2 October 4 Hours 26 minutes Single phase (R) to earth fault due to transients occurred by heavy winds. Table 3 shows the major breakdown occurred in the AIS unit in the past one year. One of the major breakdowns which lasted for 43 minutes occurred due to the heavy lightening stroke and current transformer of the R phase burst out. In the month of June to October these faults occur frequently due to the rainy season. Another major breakdown which lasted for 4 hours and 26 minutes occurred due to a line to ground fault. Here it was an R phase to ground fault in which some transient came in contact with the earthting and the fault occurred. This breakdown was again in one of the months of rainy season. From the comparison it can be concluded that AIS is more prone to breakdown due to environmental disturbances. 5. Maintenance In concern with the maintenance of GIS and AIS, maintenance is classified as routine maintenance, preventive maintenance and breakdown maintenance. As seen in the previous section no serious breakdown occurs in GIS unit in the past 10 years. Table 4. Routine maintenance in AIS in the year 2017 Sr. no. Month Routine Maintenance 1 March CT tan-delta and relay testing 2 June Replacement of R- Phase PT due to high tan-delta value 3 August CT and PT tan-delta measurement GIS is less prone to faults which occur due to environmental disturbances. Also the GIS unit is a completely metal clad enclosure where it uses fixed mounted circuit breakers, whereas in AIS unit Circuit breaker can be removed for maintenance and troubleshooting. AIS unit is inspected every year to two year in which all the

186 Dipali Kamthe, Dr. N. R. Bhasme equipments are checked. Table 4 shows the maintenance carried out on 220kV AIS and 132kV. The maintenance is based on the equipment of AIS. A quarterly maintenance is carried out which mostly consists of relay testing. Whereas in GIS no such maintenance are done. II. PERFORMANCE ANALYSIS Sr. No. Parameters AIS GIS 1 Design Standards IEC 62271 IEC 62271 2 Medium used for insulation Air SF6 3 Medium used for switching 4 Dimensions Air, oil, SF6 or vacuum Length: 45.3 m Height: 12.0 m Width: 30.0 m SF6 Length: 3.37 m Height: 2.55 m Width: 6.77 m 5 Area of installation 1359 m 2 23.81 m 2 6 Sensitivity to environment 7 Maintenance requirement Moderate 8 9 Need for gas pressure monitoring Type of execution with switching devices Moderate, pollution and humidity can have some effects on insulation that is exposed to air. Might be required only for switching devices incorporating SF6 Fixed but can be drawn out according to need. Excellent gas tank with high protection with very little sensitivity to environment, humidity, even altitude Minimal, because the busbar and switching units both are completely sealed. Might be required only for busbar. Fixed and sealed

Modeling and Simulation of Air Insulated and Gas Insulated Substations 187 III. CONCLUSION The study based on air insulated substation and gas insulated substations shows that basic working operation of both the substations are same, though they differs in some aspects. A MATLAB SIMULINK model is developed for the prediction of VFTO phenomenon in the substation. The inductance and capacitance of the bus bar are calculated from the diameters of conductor. Performance analysis on the basis of insulation medium, space requirement, environmental impact and maintenance is carried out. It is concluded that GIS is significantly more advantageous than AIS. Insulation medium of GIS has dielectric strength 3 times more than that of insulation medium of AIS. Space required by GIS is almost 1/4 th of the space required by AIS. GIS is significantly very less prone to the environmental impacts as all the components are mounted fix in metal clad, whereas in AIS unit lot of faults occurs due to environmental disturbances. Also maintenance required for the GIS is less as compared to AIS. Frequency of routine maintenance is more in AIS as compared to GIS. As the frequency of fault occurrence and maintenance in GIS is less as compared to AIS, the frequency of switching is less; therefore, generation of VFTO is less in GIS. REFERENCES [1] R. Samikkannu and S. Annadurai, Estimation and Analysis of VFTO in 420kV Gas Insulated Substation, International Conference on Circuit, Power and Computing Technologies (ICCPCT), IEEE 2014. [2] N. Malik, A. Al-Arainy and A. Mohammad, Electrical Insulation in Power System, Marcel Dekker, Inc, NewYork, 1998. [3] J. Bickford and A. Heaton, Transient Overvoltages on Power Systems, Proc. Inst. Electrical Engineering, Vol. 133, pp. 201-225, May 1986 [4] P. Bolin, Gas Insulated Substations, Mitsubishi Electric Power, CRC press LLC, 2003. [5] B. Ram and D. Vishwakarma, Power System Protection and Switchgear, Mcgraw-hill Education, Second Edition. [6] J. V. Rama Rao, J. Amarnath and S. Kamakshaish, Simulation and Measurement of Very Fast Transient Overvoltages in a 245kV GIS and Research on Suppressing method using ferrite rings, ARPN Journal of Engineering and Applied Sciences, Vol. 5, May 2010. [7] J. Meppelink and K. Feser, Very Fast Transients in GIS, IEEE Transactions on Power Delivery, Vol. 4, No. 1, January 1989. [8] V. Himasaila, M. Nagajyothi and T. Nireekshana, Review on Analysis of Very Fast Transient Overvoltage in Gas Insulated Substation, International Journal of Scientific Research Engineering & Technology (IJSRET), ISSN 2278-0882, Vol. 6, Issue 7, July 2017 [9] J. Holtzhausen and W. Vosloo, High Voltage Engineering Practice and Theory, ISBN: 978-0 - 620-3767 7

188 Dipali Kamthe, Dr. N. R. Bhasme