Relaunching Agriculture: Strengthening Agriculture Public Services II Project (GAFSP - IDA) (P126744)

Similar documents
Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report AGRICULTURAL COMPETITIVENESS IMPROVEMENT PROJECT (P122812)

Public Disclosure Copy

The World Bank OECS Regional Tourism Competitiveness (P152117)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Zambia Water Resources Development Project (P114949)

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

Public Disclosure Copy. Implementation Status & Results Report Emergency Agricultural Livelihoods and Climate Resilience Project (P166328)

Public Disclosure Copy

The World Bank Local and Regional Competitiveness Project (P154263)

Public Disclosure Copy

The World Bank Livestock Sector Development Support Project (P159476)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Zambia Water Resources Development Project (P114949)

Public Disclosure Copy. Implementation Status & Results Report UGANDA North Eastern Road-corridor Asset Management Project (NERAMP) (P125590)

Public Disclosure Copy

Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund (P126180)

The World Bank Uganda Energy for Rural Transformation III (P133312)

The World Bank Cusco Regional Development (P117318)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

EC Ibarra Transport Infrastructure Improvement Project (P147280)

Public Disclosure Copy

The World Bank BiH Floods Emergency Recovery Project (P151157)

Public Disclosure Copy

Urban Water Supply Project (P156739)

NI - INTEGRATED PUBLIC PROVISION OF HEALTH CARE SERVICES (P164452)

The World Bank Georgia National Innovation Ecosystem (GENIE) Project (P152441)

Public Disclosure Copy

The World Bank Earthquake Housing Reconstruction Project (P155969)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report Girls Education and Womens Empowerment and Livelihood Project (P151451)

Public Disclosure Copy. AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power

The World Bank Regional Infrastructure Development Fund (P154947)

Public Disclosure Copy. Implementation Status & Results Report Small Town Water Supply and Urban Septage Management Project (P156738)

The World Bank. Kenya: Off-grid Solar Access Project for Underserved Counties (P160009) Key Dates. Project Development Objectives.

PAMSIMAS Support Trust Fund (P116236)

The World Bank Haiti Business Development and Investment Project (P123974)

Public Disclosure Copy. Implementation Status & Results Report KH - Livelihood Enhancement and Association of the Poor Project (LEAP) (P153591)

The World Bank Ethiopia: National Quality Infrastructure Development Project (P160279)

The World Bank Mali Reconstruction and Economic Recovery (P144442)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Dam Operational Improvement and Safety (P096532)

The World Bank Greater Maputo Water Supply Expansion Project (P125120)

SÃO PAULO METRO LINE 4 (PHASE 2) (P106390)

The World Bank Transport Connectivity and Asset Management Project (P132833)

Public Disclosure Copy

Public Disclosure Copy

The Agriculture Investment and Market Development Project (P143417)

The World Bank Senegal Tourism and Enterprise Development Project (P146469)

The World Bank Mali Reconstruction and Economic Recovery (P144442)

Implementation Status & Results Report Croatia & Bosnia & Herzegovina GEF Adriatic Sea Environmental Pollution Control Project (I) (P143921)

Public Disclosure Copy

Climate Adaptation and Mitigation Program for Aral Sea Basin CAMP4ASB (P151363)

The World Bank Ghana - Maternal, Child Health and Nutrition Project (P145792)

The World Bank JM Youth Employment in Digital and Animation Industries (P148013)

The World Bank Swaziland Health, HIV/AIDS and TB Project (P110156)

Public Disclosure Copy

The World Bank Local and Regional Competitiveness Project (P154263)

Public Disclosure Copy. Implementation Status & Results Report Haiti - Urban Community Driven Development Project / PRODEPUR (P106699)

The World Bank Integrated Forest Ecosystem Management (P151102)

Public Disclosure Copy

Sri Lanka Strategic Cities Development Project (P130548)

Public Disclosure Copy

The World Bank MA- Noor Ouarzazate Concentrated Solar Power Project (P131256)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Bangladesh Weather and Climate Services Regional Project (P150220)

The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

The World Bank CG Rep. LISUNGI Safety Nets System Project (P145263)

Public Disclosure Copy. Implementation Status & Results Report Tanzania: Resilient Natural Resource Management for Tourism and Growth (P150523)

Rio de Janeiro Strengthening Public Sector Management Technical Assistance Project (P127245)

Public Disclosure Copy. Implementation Status & Results Report Cambodia Global Partnership for Education Second Education Support Project (P144715)

The World Bank EGYPT-Farm-level Irrigation Modernization (P117745)

The World Bank Earthquake Housing Reconstruction Project (P155969)

The World Bank Decentralized Community Driven Services Project (P117764)

The World Bank PE Water Resources Management Modernization (P107666)

Public Disclosure Copy. Implementation Status & Results Report Tanzania Education and Skills for Productive Jobs Program (ESPJ) (P152810)

The World Bank Community Development Program Support Project-Phase III (P144637)

The World Bank Ecuador - Sustainable Family Farming Modernization Project (P151963)

Name Previous Rating Current Rating

Key Dates. Project Development Objectives. Components. Overall Ratings

Ecuador - Sustainable Family Farming Modernization Project (P151963)

The World Bank Third Northern Uganda Social Action Fund (NUSAF 3) (P149965)

Transcription:

Public Disclosure Authorized LATIN AMERICA AND CARIBBEAN Haiti Agriculture Global Practice IBRD/IDA Specific Investment Loan FY 2012 Seq No: 9 ARCHIVED on 17-Jun-2016 ISR23358 Implementing Agencies: Public Disclosure Authorized Key Dates Key Project Dates Bank Approval Date:01-Dec-2011 Planned Mid Term Review Date:30-Jan-2015 Original Closing Date:30-Nov-2016 Project Development Objectives Effectiveness Date:03-Apr-2012 Actual Mid-Term Review Date:26-Jan-2015 Revised Closing Date:30-Jun-2018 Public Disclosure Authorized Project Development Objective (from Project Appraisal Document) The PDOs are to strengthen the Ministry of Agriculture, Natural Resources and Rural Development's (MARNDR) capacity to define andimplement the National Agriculture Extension Strategy, to increase access of small farmers to agriculture extension services andtraining on animal and plant health in priority regions, and to provide financial assistance in the case of an agriculture sectoremergency. Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured)phrpdodel The development objectives of the Project are to: (a) reinforce the capacity of the Ministry of Agriculture, Natural Resources and Rural Development to provide or facilitate access to services in the agricultural sector; (b) increase market access to small producers and food security in Selected Areas; and (c) provide financial assistance in the case of an Agriculture Sector Emergency. Components Public Disclosure Authorized Name Component 1: Agricultural Support Services:(Cost $11.00 M) Component 2: Direct Support to producers and associations:(cost $25.00 M) Component 3: Emergency Response Contingency Reserve:(Cost $1.50 M) Component 4: Institutional Strengthening, Monitoring and Evaluation, Project Management and Studies:(Cost $6.95 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory 6/17/2016 Page 1 of 9

Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The Level 1 restructuring of the Project, approved by the World Bank Board of Executive Director on July 5, 2015, was declared effective October 29, 2015. The project has now completed a successful rabies vaccination campaign, and has initiative the renovation of the Agriculture School of the Artibonite, which should be completed in the fall of 2016. In the North, RESEPAG has selected 51 sub-projects for financing, representing 10,116 beneficiaries, including 4,704 women. These sub-projects represent about HTG 230 million of investments, HTG 168 million of which are financed by the Project. As of May 31, 2016, 29 of these sub-projects have received financing for about HTG50 million and are expected to receive the balance before the end of the calendar year. Meanwhile, the formulation and selection of the final sub-projects is still on-going, and is expected to be completed by September 2016, with 70 sub-projects approved. Under the Sanitary and Phytosanirary Reform component, agreement has been reached on the role of the "Centres Polyvalents", and the bidding for the design of these centers and of the Central Office of the "Unite de Protection Sanitaire" is expected to be completed in July 2016. Contracts for three operators for the voucher initiative in the Center/South and for the matching grant in the South have been completed and the contracts are expected to be signed shortly. A implementation support mission has been scheduled for the week of July 11, as well as a mission with field visit for October 2016. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial High Macroeconomic -- Moderate Substantial Sector Strategies and Policies -- Substantial High Technical Design of Project or Program -- Substantial Substantial Institutional Capacity for Implementation and Sustainability -- High High Fiduciary -- Substantial Substantial 6/17/2016 Page 2 of 9

Environment and Social -- Moderate Moderate Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Substantial Substantial Results Project Development Objective Indicators Performance of MARNDR in Sanitary and Phytosanitary (SPS) measures (Index Rating from gap analysis using methodology of World Organization for Animal Health (Percentage, Custom) Value 30.00 30.00 30.00 60.00 Date 01-Apr-2012 31-Oct-2015 30-Apr-2016 30-Apr-2018 Direct project beneficiaries (Number, Core) Value 0.00 6375.00 8449.00 19000.00 Female beneficiaries (Percentage, Core Supplement) Value 0.00 36.00 33.46 28.00 Production increase by voucher beneficiaries (Percentage, Custom) Value 0.00 0.00 0.00 30.00 6/17/2016 Page 3 of 9

Increase in sales of the supported producer organizations (Aggregated million US$) (Amount(USD), Custom) Value 0.00 0.00 0.00 10.00 Overall Comments Intermediate Results Indicators a) Central Building; b) Polyvalent centers; c) Quarantine stations; and d) Laboratories; are built / rehabilitated, equipped and operational (Text, Custom) Value a) 0 b) 0 c) 0 d) 0 a) 0 b) 0 c) 0 d) 0 a) 0 b) 0 c) 0 d) 0 a) 1 b) 4 c) 5 d) 3 Number of client days of training linked to SPS provided to epidemiological volunteers and private veterinarians. (Number, Custom) Value 0.00 5786.00 8986.00 6600.00 6/17/2016 Page 4 of 9

Number of samples analyzed for the detection of the presence of diseases. (Number, Custom) Value 0.00 1042.00 6000.00 96000.00 Number of cattle identified by the Project and included in the information system. (Number, Custom) Value 0.00 0.00 0.00 250000.00 Number of Departments where producers have access to market information by SMS, community radio and/or by publication at all DDA and BACs. (Number, Custom) Value 0.00 0.00 0.00 4.00 Number of didactical material elaborated and diffused in the Project zone, classified by themes. (Number, Custom) Value 0.00 0.00 0.00 20.00 6/17/2016 Page 5 of 9

Agricultural Middle School is operational for at least 30 students. (Text, Custom) Value No No No Yes Number of producers adopting improved technologies promoted by the Project. (Number, Custom) Value 0.00 0.00 0.00 8000.00 Number of producers adopting improved technologies promoted by the Project (disaggregated by gender). (Number, Custom Breakdown) Value 0.00 0.00 0.00 2400.00 Number of accredited suppliers of inputs and services in the targeted areas. (Number, Custom) Value 0.00 0.00 0.00 200.00 6/17/2016 Page 6 of 9

Increase in productivity of the voucher beneficiaries. (Percentage, Custom) Value 0.00 0.00 0.00 25.00 Number of client days of extension services provided to producers, members of producer organizations, different than SPS training. (Number, Custom) Value 0.00 0.00 0.00 13000.00 Satisfaction rate of participants of the farmer field schools. (Percentage, Custom) Value 0.00 0.00 0.00 75.00 Percentage of producer organizations having an operational investment at least 12 months after its completions. (Percentage, Custom) Value 0.00 0.00 0.00 75.00 6/17/2016 Page 7 of 9

Percentage of sub-projects that are sensitive to a) gender; b) environment; or c) nutrition. (Percentage, Custom) Value 0.00 85.71 83.00 60.00 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P126744 IDA-H7410 Effective USD 40.00 40.00 0.00 12.93 22.59 32% P126744 TF-11396 Effective USD 10.00 10.00 0.00 2.86 7.14 29% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P126744 IDA-H7410 Effective 01-Dec-2011 11-Jan-2012 03-Apr-2012 30-Nov-2016 30-Jun-2018 P126744 TF-11396 Effective 11-Jan-2012 11-Jan-2012 03-Apr-2012 30-Nov-2016 30-Jun-2018 Cumulative Disbursements 6/17/2016 Page 8 of 9

Restructuring History Level 1 Approved on 02-Jul-2015 Related Project(s) There are no related projects. 6/17/2016 Page 9 of 9