Power Cavern Design & Back Analysis Using Phase 2

Similar documents
M. Kellaway, D. Taylor and G.J. Keyter Braamhoek Consultants Joint Venture. Abstract. Introduction

Is Stress Important to the Stability of Underground Wedges?

Structurally controlled instability in tunnels

Geotechnical Monitoring for Safe Excavation of Large Rock Cavern: A Case Study

Successful Construction of a Complex 3D Excavation Using 2D and 3D Modelling

ROCK ENGINEERING ASPECTS OF THE INGULA POWERHOUSE CAVERNS. Mr Gerhard J Keyter Ms Monique Ridgway Dr Paul M Varley

Available online at ScienceDirect. Procedia Engineering 191 (2017 )

MEMORANDUM SUBJECT: CERTIFICATE IN ROCK MECHANICS PAPER 1 : THEORY SUBJECT CODE: COMRMC MODERATOR: H YILMAZ EXAMINATION DATE: OCTOBER 2017 TIME:

Geotechnical & Mining Engineering Services

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE COAL MINING OPTION

10. GEOTECHNICAL EXPLORATION PROGRAM

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE. METALLIFEROUS MINING OPTION Updated November 1998

Influence of foliation on excavation stability at Rampura Agucha underground mine

The effect of discontinuities on stability of rock blocks in tunnel

DESIGN AND CONSTRUCTION OF LARGE


Underground Excavation Design Classification

Introduction and Background

Roadway Support Technology with Sliding Cracking Surrounding Rock under Tectonic Stress

The Mine Geostress Testing Methods and Design

Explicit representation of rock reinforcement in 3D DEM models for foliated ground

Further Research into Methods of Analysing the October 2000 Stability of Deep Open Pit Mines EXECUTIVE SUMMARY

EOSC433: Geotechnical Engineering Practice & Design

Progress with the excavation and support of the Mingtan power cavern roof

Flin Flon Mining Belt

Kinematic Analysis Underground Wedges

A circular tunnel in a Mohr-Coulomb medium with an overlying fault

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS

Unwedge Geometry and Stability Analysis of Underground Wedges. Sample Problems

Characteristics on Rock Fractures Induced by Different Excavation Methods of Deep tunnels

Coal Loss and Dilution Considerations for Western Canadian Foothills Open Pit Coal Projects

INFLUENCE OF LOCAL PERTURBATION ON REGIONAL STRESS AND ITS IMPACT ON THE DESIGN OF MAJOR UNDERGROUND STRUCTURE IN HYDROELECTRIC PROJECT

Prevention and Control of Rockbursts in Dongguashan Copper Mine

SLOPE STABILITY EVALUATION AND ACCEPTANCE STANDARDS

Table of Contents Development of rock engineering 2 When is a rock engineering design acceptable 3 Rock mass classification

A Unique Metro Accident in Brazil Caused by Multiple Factors

The importance of both geological structures and mining induced stress fractures on the hangingwall stability in a deep level gold mine

Stability Analysis of A Railway Trench By Using Stereographical Projection

Evaluation of Structural Geology of Jabal Omar

Influence of the undercut height on the behaviour of pillars at the extraction level in block and panel caving operations

Springshed Springshed Management Training Curriculum

Some Aspects on the Design of Near Surface. Tunnels - Theory and Practice. Thomas Marcher¹, Taner Aydogmus²

ITASCA Consulting Canada Inc.

Analysis in Geotechnical Engineering

Geological and geotechnical approach for excavation of large unlined rock cavern

HOOVER DAM: Grout Curtain Failure and Lessons Learned in Site Characterization

A new design approach for highway rock slope cuts based on ecological environment protection

Waterview Connection Tunnels

Taming the Soutpansberg SACMA Presentation - Exxaro Tshikondeni Coal November 2011

Gotechnical Investigations and Sampling

24 September Best results achieved at U40 Prospect (West Arnhem JV with Cameco Australia): o 1.34% eu 3 O 8

Study of Soft Rock Roadway Support Technique

EAS 233 Geologic Structures and Maps Winter Miscellaneous practice map exercises. 1. Fault and separation:

Ground support modelling involving large ground deformation: Simulation of field observations Part 1

Moglicë HPP - Albania. Jorge Terron

25th International Conference on Ground Control in Mining

Design of large underground caverns

STRESSES AROUND UNDERGROUND OPENINGS CONTENTS

Behaviour of Blast-Induced Damaged Zone Around Underground Excavations in Hard Rock Mass Problem statement Objectives

ON THE FACE STABILITY OF TUNNELS IN WEAK ROCKS

Geotechnical Engineering and Dams

Canada Line Project. Stability of the Twin Bored Tunnels Under False Creek. Vancouver, British Columbia

Mining the South Reef at Doornkop

NNN99. Rock Engineering for the Next Very Large Underground Detector. D. Lee Petersen CNA Consulting Engineers

Rock Scour: Past, Present and Future. George W. Annandale, D.Ing, P.E. Engineering and Hydrosystems Inc. Denver, Colorado

ROCK MASS CHARACTERISATION IN ENGINEERING PRACTICE

ISMS Paper No Influence of weak planes on rockburst occurrence. Amin Manouchehrian, Ming Cai *

EXAMINATION PAPER MEMORANDUM

LAB 1: ORIENTATION OF LINES AND PLANES

Geotechnical & Structural Geology

Some issues in modelling of ground support using the three-dimensional distinct element method

ontribution of Geotechnical and Rock echanics design to vertical shaft nking and design

Stress arch bunch and its formation mechanism in blocky stratified rock masses

Crags, Cracks, and Crumples: Crustal Deformation and Mountain Building

CNSC Review of the Long-Term Safety Case for a Deep Geologic Repository

Rock slope rock wedge stability

Ground Support in Mining and Underground Construction

P16 Gravity Effects of Deformation Zones Induced by Tunnelling in Soft and Stiff Clays

Application of Core Logging Data to generate a 3D Geotechnical Block Model

Building on Past Experiences Worker Safety

Application of Rock Mass Classification Methods to the Klong Tha Dan Project Tunnels

Investigating rock mass conditions and implications for tunnelling and construction of the Amethyst Hydro Project, Harihari

Rockburst mitigation experiences on underground projects in the Cheves Hydropower project in the Peruvian Andes

Borehole Camera And Extensometers To Study Hanging Wall Stability Case Study Using Voussoir beam - Cuiabá Mine

Rock slope stability problems in Gold Coast area, Australia

Theme 7. Metamorphic rocks. Distinguishing rock types

Section 19.1: Forces Within Earth Section 19.2: Seismic Waves and Earth s Interior Section 19.3: Measuring and Locating.

Strengths and weaknesses of using elastic numerical modelling in mine design at the Callie underground mine

Open Pit Rockslide Runout

Establishing geotechnical processes for improved mine design at Bulyanhulu

Curriculum Document Mining Technician: Strata Control Practitioner (Surface) Occupational Curriculum

Geotechnical issues in seismic assessments: When do I need a geotechnical specialist?

Cavity Expansion Methods in Geomechanics

Application of a transversely isotropic brittle rock mass model in roof support design

Pit Slope Optimization Based on Hydrogeologic Inputs

Seismic analysis of horseshoe tunnels under dynamic loads due to earthquakes

Mt Owen Mine barrier pillar

Haulage Drift Stability Analysis- A Sensitivity Approach

REPORT ON THE ASSESSMENT OF TRENCHING INTHE ROAD RESERVE OF THE ROAD BETWEEN BEAUFORT WEST AND CARNAVON.

Dark Art. Ian de Bruyn

Transcription:

Power Cavern Design & Back Analysis Using Phase 2 A Look at the Ingula Power Cavern Project This summary is based on the published paper, The Use of Geotechnical Instrumentation to Monitor Ground Displacements During Excavation of the Ingula Power Caverns for Model Calibration and Design Verification Purposes, authors M. Kellaway, D. Taylor, and G.J. Keyter of Braamhoek Consutants Joint Venture, published in The Southern African Institute of Mining and Metallurgy, South African Tunnelling 2012, Lessons Learnt on Major Projects. Geomechanics software used worldwide by geotechnical engineers software tools for rock and soil Article prepared for RocNews Fall 2013

Power Cavern Design & Back Analysis using Phase 2 A Look at the Ingula Power Cavern Project The construction of the Ingula hydro power caverns in South Africa began in 2004 and is scheduled to end in 2015. Monitoring was in place throughout the construction process. Numerical models were then updated based on the collected field data and the calibrated models were used to investigate the effects of potential construction defects. Figure 1 Location of Ingula Power Cavern Project (Google Maps)

Project Description The Ingula power complex is located approximately 400 m below ground level, under a mountain ridge off the Drakensberg escarpment between the Free State and KwaZulu Natal provinces, South Africa. The complex, which is up to 50 m deep, consists of a 184 m long and 26 m wide hall, with a span:height ratio of 2.5. The transformer hall, which is up to 21 m in height, is 176 m long and 19 m wide. A pipe gallery runs alongside the transformer hall 6 m below floor level. Figure 2 Plan View of Power Cavern Complex Other installations include 11 m diameter appurtenant busbar tunnels, 5 m diameter high pressure penstocks, a 9 m diameter main access tunnel, and other minor shafts.

Geological Setting The cavern complex was constructed in horizontally bedded siltstones, and is located approximately 25 m below a 40 m thick dolerite sill. The intact rock strength and stiffness decreases with depth below the sill, and there were also a number of faults intersecting the caverns and tunnels. Cavern Support Design While the initial design was based primarily on experience, the final support design was based on geological evaluations and numerical modeling in UDEC, Phase 2, and FLAC3D. Numerical models were used to estimate cavern convergence on the crown and sidewalls, and the time of support installation was also investigated. Figure 3 Rock material properties

Comparison of Phase 2 Results to Cavern Measurements Instrumentation was placed in areas of concern, based on the initial modeling results. Compared to the numerical results, the following observations were made with regard to displacements: In particular, the dyke with sheared contacts was incorporated into the model. Secondly, the staging was revised to reflect the actual sequence of excavation and support installation. Measured displacements were generally lower than expected Sidewall displacements were generally larger than crown displacements The rate of displacement slowed more quickly than anticipated as the excavation progressed Back-Analysis and Remodeling in Phase 2 Phase 2 models were constructed in the design phase of the Ingula project. These models were finetuned towards the end of the excavation of the main caverns for three primary reasons. Firstly, Phase 2 models were updated to reflect the actual geology. Finally, the Phase 2 models were recalibrated using the available monitoring data from the excavation. The models were calibrated using the Phase 2 model for a geotechnical cross-section through Units 1&2 in the Machine Hall and the calibrated parameters were then used in the models for Machine Hall Units 3&4 as well. Figure 4 Section of Units 1&2 Geology

Figure 5 Calibration of Material Parameters for Units 1&2 One particularly interesting revision to the Phase 2 model was the assumption that there was the same percentage of rock bridges in the strike direction of bedding planes and joints as in the dip direction. This adjustment to the bedding and joint strength balanced the effect of infinitely long bedding planes and joints in the strike direction in Phase 2. Prior to the adjustment, large rock wedges were formed in the crown and sidewalls of the model. After revision, rock wedge were more typical sizes. The results obtained from the calibrated Phase 2 models are compared to the actual crown and sidewall displacements up to the end of construction of the caverns. The numerical results were generally within 5-10 % of field measurements. Figure 6 Comparison of numerical results and field measurements for calibrated Phase 2 models

Modeling of Construction Defects While differences exist between the Phase 2 models and the cavern measurements, the results were good enough to merit the influence of construction defects to be modeled and analyzed in Phase 2. The first defect investigated was the corrosion of invert floor dowels. This was investigated by removing all floor dowels in certain locations in the calibrated Phase 2 models. The second deviation modeled was cable anchor hole deviation, which was actually noted during construction. To model this defect in Phase 2, staged cable anchor removal was implemented. In the calibrated Phase 2 models for Units 1&2 it was found that staged anchor removal resulted in steady convergence increases, most significantly in the transformer sidewalls. In Units 3&4 models, removal of an anchor resulted in rock wedge mobilization and subsequent failure of the anchors retaining the wedge. Convergence of the Phase 2 model was not obtained for the final stage. Observations and Conclusions From the model calibration, it was observed that the presence of local rock wedges have a large effect on both the modeling results and the field measurements. In general, if a rock wedge exists in the field, there needs to be one in the model in order for comparable results to be obtained. With regard to the modeling of construction defects in Phase 2, the numerical results showed that the long term yield failure of some damaged cable anchors may have little effect on cavern excavation stability. However, the models also showed that the long term yield failure of damaged anchors at critical locations may result in rock wedge mobilization and progressive failure. Based on these Phase 2 results, it was recommended that cavern instrumentation be maintained and stability monitoring continued long term. To read the original article by M. Kellaway, D. Taylor and G.J. Keyter, please click here. 7