Comparison Of Blast-Induced Ground Vibration Predictors In Case Of Tulu-Plain Open Pit Colemanite Mine Of Eti Mine

Similar documents
A new predictor for ground vibration prediction and its comparison with other predictors

Evaluation of Ground Vibration Induced by Blasting During the Excavation of a Transportation Tunnel in Istanbul Metropolis

Local ground parameters of blasting vibration models for different geological structures at Mae Moh lignite mine, Thailand

Importance of blast-design in reduction of blast-induced vibrations

Data in Brief. Peak particle velocity data acquisition for monitoring blast induced earthquakes in quarry sites

Magnitude of Vibration vis-a-vis Charge per Delay and Total Charge

Assessment of Maximum Explosive Charge Used Per Delay in Surface Mines

Protection of Underground Mine Structures Due to Adjoining Open-pit Mine Blasting

GROUND VIBRATIONS IN OPENCAST MINE BLAST ON STRUCTURES VIS-À-VIS A LOCAL ENVIRONMENTAL EFFECT AND ITS MITIGATION THROUGH MINING TECHNOLOGY

Mathias Jern nitroconsult.se)

MEASUREMENT AND EVALUATION OF BLASTING GROUND VIBRATIONS AND AIRBLASTS AT THE LIMESTONE QUARRIES OF ASSIUT CEMENT COMPANY (CEMEX)

Evaluation of blast-induced ground vibration predictors

Ground vibrations level characterization through the geological strength index (GSI)

A gas pressure-based drift round blast design methodology

Engineering Letters, 25:3, EL_25_3_15. Yongqing Zeng, Haibo Li, Xiang Xia, Bo Liu, Hong Zuo, and Jinlin Jiang

Appendix D Rock Blasting Report

Blasting Design. Explosion A chemical reaction involving an extremely rapid expansion of gasses usually associated with the liberation of heat.

ASSESSMENT OF POWDER FACTOR IN SURFACE BENCH BLASTING USING SCHMIDT REBOUND NUMBER OF ROCK MASS

4) Ash, R.L., Blasting characteristics of large diameter boreholes. 6 th Annual Drilling and Blasting Technology, Houstan, 1977.

MAD345 - Mining II INTRODUCTION. 10 October Hacettepe University. Introduction Prospecting Mining Dilution Resource and Reserve Estimation

Do Now - APES. Due Next Class. Mining HW. Work on QSC using today s notes

Predictions of Experimentally Observed Stochastic Ground Vibrations Induced by Blasting

Effect of in-situ block size and rock properties on blast induced rock fragmentation in surface mines

Causes of Dynamic Overbreak and Control Measures Taken at the Alborz Tunnel, Iran

Blast design parameters and their impact on rock fragmentation

BLAST MONITORING REPORT. HG12 Hard Stone Quarry at Ta Klement, l/o Qala Gozo 1st March 2013

Planning and evaluation for quarries: case histories in Thailand

Blasting damage in rock

List of Abstracts. Automation and Introduction of New Technologies in Blasting Operations (9)

List of Publications:

Rock mechanics related to mining: challenges and opportunities

For efficient blasting practice

Minimisation of Surface Mining Costs using Artificial Neural Network

Hybrid Finite-Discrete Element Modelling of Dynamic Fracture of Rock and Resultant Fragment Arching by Rock Blast

The Mine Geostress Testing Methods and Design

GROUND VIBRATIONS FROM ROCK BLASTING

Peak particle velocity prediction using support vector machines: a surface blasting case study

A STUDY ON THE BLASTING VIBRATION CONTROL OF CREEP MASS HIGH SLOPE

Blast optimisation with In Situ rock mass characterization by seismic profiling at an opencast coal mine in India

Innovative Blast Free Mining Methods for Aggregate Quarries " Ramesh Bhatawdekar, Edy Tonnizam Mohamad, Firdaus Azlan Department of Geoteknik and Tran

Patrick Andrieux Principal Engineer

SEISMIC PEAK PARTCILE VELOCITY AND ACCELERATION RESPONSE TO MINING FACES FIRING IN A LIGHT OF NUMERICAL MODELING AND UNDERGROUND MEASUREMENTS

Behaviour of Blast-Induced Damaged Zone Around Underground Excavations in Hard Rock Mass Problem statement Objectives

C. R. McKee and M. E. Hanson Lawrence Livermore Laboratory University of California Livermore, California 94550

BUREAU OF MINERAL RESOURCES, GEOLOGY AND GEOPHYSICS

Cushion Pad of Reducing Blasting Vibration Starting New Era of Decreasing Disaster in Civil Engineering

Blasting damage in rock

Blast Fragmentation Modelling of the Codelco-Andina Open Pit Expansion

Control of surface settlements with Earth pressure balance method (EPB) for Istanbul metro

BUREAU OF MINERAL RESOURCES, GEOLOGY AND GEOPHYSICS

Effect of Stemming to Burden Ratio and Powder Factor on Blast Induced Rock Fragmentation A Case Study

DESTRESS BLASTING AS A PROACTIVE MEASURE AGAINST ROCKBURSTS. PETR KONICEK Czech Academy of Sciences, Institute of Geonics

BLAST MONITORING REPORT. Four blasts were carried out between 10:56 and 11:09 at the points as approximately indicated on the attached site diagram.

A Study of Mine Blasts and Rockbursts in the Pacific Northwest. Abstract

APPENDIX Q BLASTING IMPACT ASSESSMENT REPORT

M035 High Resolution 3D Tunnel Seismic Reflection at Olkiluoto, Finland

Seismic Sources. Seismic sources. Requirements; Principles; Onshore, offshore. Reading: Telford et al., Section 4.5 Sheriff and Geldart, Chapter 7

Research Article Research on Effects of Blast Casting Vibration and Vibration Absorption of Presplitting Blasting in Open Cast Mine

NZQA unit standard New US6 to replace and version 1 Page 1 of 5

Blasting, fragmentation and wall quality result at West Wanagon slope stability project on Grasberg Mine

Oil Shale, 2009, Vol. 26, No. 4, pp ISSN X OIL SHALE MINING-RELATED RESEARCH IN ESTONIA

Mining. Comparing blast-induced ground vibration models using ANN and empirical geomechanical relationships. Mineração. Abstract

Correlation of Blast-hole Deviation and Area of Block with Fragment Size and Fragmentation Cost

Strong Weighting Events in Shallow Multi-seam Longwall Mining

FOR Sand Stone Quarry Village : Chhirraleva Tehsil : Basna District : Mahasamund

Micro Seismic Monitoring Technique and Practice of Rock Blast in Deep Mining

UNDERGROUND BLASTING. There are two reasons to go underground and excavate:

ESTIMATING THE EFFECTS OF BLASTING VIBRATIONS ON THE HIGH-WALL STABILITY

SMALL-SCALE TESTING ON GROUND SHOCK PROPAGATION IN MIXED GEOLOGICAL MEDIA

Development of a predictive model of fragmentation using drilling and blasting data in open pit mining

ENGINEERING GEOLOGY AND ROCK ENGINEERING ASPECTS OF OPERATION AND CLOSURE OF KBS-3

2 Aggregates in Indiana

Coal Loss and Dilution Considerations for Western Canadian Foothills Open Pit Coal Projects

DAMAGE ZONE PREDICTION FOR ROCK BLASTING. Changshou Sun

BLOCK SIZE AND BLOCK SIZE DISTRIBUTION

Fragment Size Distribution of Blasted Rock Mass

Role of Blast Design Parameters on Ground Vibration and Correlation of Vibration Level to Blasting Damage to Surface Structures

BLAST MONITORING REPORT. HG12 Hard Stone Quarry at Ta Klement, l/o Qala Gozo 22nd January 2016

A new mining method T. GOSWAMI G.F. BRENT

Shaft Sinking with Electronic detonators at the Gautrain Rapid Rail Link Project

Fragmentation Management for the Downstream Value Chain. Scott G. Giltner

TIMING OF QUARRY BLASTS AND ITS IMPACT ON SEISMIC EFFECTS

An Introduction to Field Explorations for Foundations

COMPARING LABORATORY AND FIELD DURABILITY TESTING OF STONE Accelerated Weathering Testing of Stone

Application of Ground Penetrating Radar for hydro-geological study

Managing Muckpile Fragmentation. Scott G. Giltner

Study of Blast-Induced Damage in Rock with Potential Application to Open Pit and Underground Mines

Evaluation of the Environmental Impacts of Blasting in Okorusu Fluorspar Mine, Namibia.

IMPROVED BLAST VIBRATION ANALYSIS USING THE WAVELET TRANSFORM

Seismic monitoring of a simulated rockburst on a wall of an underground tunnel

IMPACT ASSESSMENT OF BLASTING ON VULNERABLE LANDSLIDE AREA. Hari Dev, Birendra Pratap, Rajbal Singh and Shashank Pathak

Hijiori HDR Reservoir Evaluation by Micro-Earthquake Observation

Update on Acton Extension Application

BLAST MONITORING REPORT. HM22 Hard Stone Quarry at Wied Filep, l/o Naxxar 8th August 2016

ANNEXURE I Site Location map of M/s. Stone Plus quarry lease A-1

Dynamic Stability Analysis and Forecast of Surface Mine Dump

Facing the Drilling and Blasting Difficulties at Helwan Quarry, Egypt.

Title: Effect on surface deformation resulting from mining activity on value of property valuation : a case study from Jastrzębie-Zdrój region

New Generation Rotary Drill Bits: Klaw Bit Performance Analysis and Compared with Tricone Bit

THE UNITED REPUBLIC OF TANZANIA NATIONAL EXAMINATIONS COUNCIL CERTIFICATE OF SECONDARY EDUCATION EXAMINATION

Transcription:

1 Comparison Of Blast-Induced Ground Vibration Predictors In Case Of Tulu-Plain Open Pit Colemanite Mine Of Eti Mine K. GÖGÜLÜ 1, E. APAZ, Ö. UYSAL*, Y.S. DUUTUK 1, A. DEMİCİ 1, M.K. DİLMAÇ 4, A. KOÇASLAN 1 1 Cumhuriyet University, Faculty of Engineering, Department of Mining Engineering, Sivas, Turkey Kocaeli University, Kocaeli Vocational School, Kocaeli, Turkey Dumlupınar University, Faculty of Engineering, Department of Mining Engineering, Kütahya, Turkey 4 Atatürk University, Oltu Faculty Of Earth Sciences, Department of Mining Engineering, Erzurum, Turkey ABSTACT In order to be able to model the blast induced ground vibrations and to prevent the occurrence of damages in the site different researches have proposed varying approaches. These approaches use blasting energy (maximum charge per delay) and absorbing effect (distance between explosion point and measurement point) as base. ithin the context of this research work the blast-induced ground vibrations in Tülü-plain open pit colemanite mine of Eti Mine have been monitored and could have been tried to determine the performance of pick particle velocity prediction methods (11 methods) as given in literature. To this end 6 blasting activities have been carried out for overburden removal and the related parameters have been measured with 7 devices. During the operating, 69 vibrations have been triaxially recorded (longitudinal, transversal and vertical). The components of pick particle velocities (PPVT, PPVV, PPVL, PVS and PPV) have been assessed according to the methods given in literature. Key ords: Blast, Ground vibration, Blast induced vibration, Blast vibration prediction 1. INTODUCTION Environmental problems caused by the ground vibrations, rock ejections, poisonous gases and smokes, dust and air cannons are frequently encountered in different sectors such as mining, construction, quarrying, tunnel and pipe lining where blasting is inevitable. For this reason, it is necessary to consider the remedies of the possible environmental problems in addition to technical and economic factors such as fragmentation degree, size distribution and cost while determining the blasting conditions. The measurement and prediction of the blastinduced parameters are of great importance to prevent the environmental problems (Arpaz, 000). The literature research shows that the relevant studies are intensely continuing; however reveals a lack of consensus on neither predicting and nor preventing these problems was reached. It is possible to explain this situation with the different environment and design parameters that have completely different features.

In this study, the results of a series of the field surveys conducted in Eti Mine Tülü Boron Enterprise will be given to test the performance of the equations obtained in the literature to be used in the estimation of the blastinduced ground vibrations.. PATICLE VELOCITY ESTIMATION METHODS Many people and institutions conducted various research studies about estimating blast-induced ground vibrations and the scaled distance-dependent estimation of the peak particle velocity was accepted in most of the literature. The results of some studies conducted for estimating the peak particle velocity are chronologically given below (Arpaz 000; Ghosh&Daemen 198; Gupta et al. 1988; oy 1991). i. Ambraseys and Hendron (1968) = K PPV [1] ii. Nicholls, Johnson and Duvall (1971) = K PPV [] iii. Langefors and Kihlström (197) PPV = K [] iv. Indian Standards Inst.(197) PPV = K v. Davies vd., (1964), Attewell vd., (1965), Shoop and Daemen (198), Birch and Chaffer (198) PPV = K [5] vi. Ghosh and Daemen (198) PPV = K e [6] vii. Ghosh and Daemen (198) PPV = K viii. Gupta vd., (1987) e PPV = K e [8] ix. Gupta vd., (1987) PPV = K e [4] [7] [9]

x. Gupta vd., (1988) PPV K = [10] xi. CMS (oy, P.P., 1991) = n + K e 1 PPV [11] Here; PPV: Peak particle velocity (mm/s) : Distance from the blasting point (m) : Maximum amount of explosives per delay (kg) K,,, n: Field constants e - e -(/) : Inelastic dilution factor : Inelastic absorption factor. OKING FIELD The study was conducted in Bigadiç Directorate for Tülü Open Pit Mine Enterprise that belongs to Eti Mine Directorate General. The enterprise is approximately 8 km away from Balıkesir which is located in westward Turkey. However, there are many villages in close vicinity around the enterprise. The borders of the enterprise are getting close to these villages day by day. These villages are affected by the blasts and problems arise frequently between villagers and the enterprise. These problems sometimes affect the production plans of the enterprise. The study was conducted in agricultural areas and regions close to residential areas. The blasts are shots for loosening the top layer of the boron. The formation consists of clay stone, limestone and tuff. The bore holes are in 8 m length and 170 mm diameter. Burden distance and spacing range between and 5 m. ANFO is used as an explosive, power gel dynamite is used for priming and nonel capsule is used for firing. 4. FIELD SUVEYS AND EVALUATIONS ithin the framework of the field surveys, the blast-induced vibrations in Etibank Bigadiç Tülü open-pit mine were followed and the success degree of the estimation methods (11 methods) of the particle velocity in literature was determined. For this aim, 6 shots made during the stripping activities between the dates 14 July- 8 August 011 were measured by 7 blast seismograph and 69 values of data belonging the blast vibration were recorded triaxially (longitudinal, latitudinal and vertical) (Table 1). The obtained components of the particle velocities bileşenleri (PPVT, PPVV, PPVL, PVS and PPV) were evaluated according to the methods in the literature and it was seen that the methods resulted in different success rates according to the correlation coefficients (Table ).

4 Table 1. esults of the measurements Charge Particle Velocity Distance per delay Transverse Vertical longitudinal esultant ()(m) () (kg) (PPVT) (PPVV) (PPVL) (PVS) mm/s mm/s mm/s mm/s mm/s 1 60 144 1.5 14. 16.9 18 16.9 60 148 4.8 7.6 6.1 8.8 8.8 Event No Maximum (PPV) 5 60 96 8.5 11.9 9.91 1. 11.9 6 60 4 1.65 9.65 7.49 0 9.65 Table. The evaluation of the particle velocity components and air cannon values according to the estimation methods in the literature. 1. Method V = K * K 67,84 15, 765,06 175,44 1,87 661,61-1,00-1,8-1,1-1,9-1,9-1,17 r 0,1 0,61 0,48 0,55 0,5 0,14. Method V = K * K 1,58 51,15 0,58 558,60 497,41 989,15-1,00-1,8-1,1-1,9-1,9-1,17 r 0,1 0,61 0,47 0,54 0,5 0,14. Method 4. Method V = K * K 65,60 199,8 14,09 5,9 01,44 1,7 1, 1,8 1,60 1,71 1,71 1,57 r 0,1 0,60 0,47 0,54 0,5 0,14 V = K * K 65,60 199,8 14,09 5,9 01,44 1,7 0,99 1,7 1,0 1,9 1,8 1,17 r 0,1 0,60 0,47 0,54 0,5 0,14

5 Table.Continuation V = K * * 5. Method 6. Method 7. Method 8. Method 9. Method K 1597,8 8568,65 5765,0 64,41 0578,6 01,9-1,00-1,7-1,0-1,8-1,8-1,17-0,098 0,004-0,096-0,99-0,67 0,585 r 0, 0,6 0,48 0,55 0,54 0,14 V = K * * K 10,14 8,,58 6,8 6,9 7,94 0,09-0,8-0,09-0,0-0,06-0,59-0,004-0,004-0,005-0,005-0,005-0,00 r 0,6 0,66 0,5 0,61 0,58 0,15 V = K * * K 9,5 47,0 4,85 7,95 8,5 1059,9 0,09-0,8-0,09-0,0-0,07-0,58-0,004-0,004-0,005-0,005-0,005-0,00 r 0,6 0,66 0,5 0,61 0,58 0,15 V = K * * e * K 10,8 1,04, 6,07 4,88 488,5-0,1 0,6 0,1 0,0 0,07 0,78-0,004-0,004-0,005-0,005-0,005-0,00 r 0,6 0,66 0,5 0,61 0,58 0,15 V = K * * K 10,8 1,04, 6,07 4,88 488,5-0,09 0,7 0,09 0,01 0,05 0,58-0,004-0,004-0,005-0,005-0,005-0,00 r 0,6 0,66 0,5 0,61 0,58 0,15

6 Table.Continuation 10. Method 11. Method V = K * * K 16,1 95,56 5,7 8,05 77,7 76,0-0,11-0,66-0,4-0,49-0,51-0,17-0, -0,181-0,0-0,199-0,194-0,47 r 0,4 0,6 0,49 0,57 0,55 0,16 1 V = K * + n K 97,14 17,1 17,76 179,80 16,14 1489,94 n,09 0,8 1,6 1,8 1,6 6,7 r 0,1 0,7 0,6 0,7 0,6 0,09 5. ESULTS AND SUGGESTIONS The drilling and blasting comes to the forefront as the most economic excavation methods in sectors such as mining, construction and quarrying where the rock excavations are inevitable. However, ground vibrations that are formed due to the nature of the blasting can put the enterprises into difficult positions. Contemporarily, the research studies for the solution of these problems are based on the idea of estimating the blast-induced ground vibrations and getting them under the control according to these estimations. In this study, the performance of the estimation methods used to minimize the blast-induced ground vibrations in Bigadiç Enterprise Tülü colemanite open-pit mine enterprise that belongs to Eti Mine Directorate General was tried to be tested. For that purpose, 69 measurements were obtained from 6 blasts and they were evaluated according to 11 different methods in the literature. As a result of these evaluations, i. All methods result in different safety limits. ii. The evaluation based on the scaled distance, which is commonly accepted in the literature does not exhibit any significant difference in any evaluation. iii. No method comes to the forefront by giving the highest regression coefficient in every table. iv. It is revealed that there is not any method to be used in order to predict and control the blast-induced ground vibrations fully. v. It is seen that it is more suitable to get the shots under control according to the method that exhibits the highest regression on the basis of the regions by evaluating according to all methods for the prediction and control of the blast-induced ground vibrations.

7 6. ACKNOLEDGEMENTS This study was supported by TÜBİTAK (The Scientific and Technological esearch Council of Turkey) with the project numbered 110M94. Authors separately thank employees of Eti Mine. EFEENCES Ambraseys, N.., Hendron, A.J., Dynamic Behaviour of ock Masses, ock Mechanics İn Engineering Practices, London: iley, 1968. Arpaz, E., Monitoring and evaluation of blast induced vibrations in some open-pit mines in Turkey: Ph.D Thesis Cumhuriyet University Graduate School of Natural and Applied Sciences Department of Mining Engineering, Sivas, 000. Attawell, P.B., Farmer, I.. and Haslam, D., Prediction of Ground Vibration Parameters From Major Quarry Blasts, Mining and Minerals Eng., December, 1965, pp. 61-66. Birch,.J. and Chaffer,., Prediction of Ground Vibration from Blasting on Open Cast Sites, Trans. Inst. Min. Metall, Sec. A: Mining Industry, April, 198, Davies, B., Farmer, I.. and Attewell, P.B., Ground Vibration from Shallow Sub-Surface Blasts, The Engineer, 1964, vol. 17, pp. 55-559. Ghosh, A., Daemen, J.K., A simple new blast vibration predictor, In: Proceedings of the 4th US symposium on rock mechanics, College Station, Texas, 198, p. 151 61. Gupta,.N., oy, P.P. Bagachi, A. and Singh, B., Dynamics Effects in Various ock Mass and Their Predictions, j. Mines, Met. Fuels, 1987, pp. 455-46. Gupta,.N., oy, P., Singh, B., On a blast ınduced blast vibration predictor for efficient blasting, Proceedings of the nd International Conference of Safety in Mines, 1015-101, Beijing, China, 1988. Langefors, U., Kihlström, B., The modern technique of rock blasting, Third Edition, Stockholm, Sweden. (1978). Nicholls H, Johnson CF, Duvall I., Blasting vibrations and their effects on structures. United States Department of Interior, USBM, Bulletin 656, 1971. oy, P.P., Vibration control in an opencast mine based on improved blast vibration predictors, Mining Science and Technology, 1, 1991. Shoop, S.A. and Daemen, J.J.K., Sire-Specific Predictions of Ground Vibrations Induced by Blasting, AIME Spring Meeting, March, Atlanta, 198.