Beam. RF antenna. RF cable

Similar documents
RF System Calibration Using Beam Orbits at LEP

FY04 Luminosity Plan. SAG Meeting September 22, 2003 Dave McGinnis

Operational Experience with HERA

The TESLA Dogbone Damping Ring

LHC operation in 2015 and prospects for the future

LHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1

Tools of Particle Physics I Accelerators

ELECTRON COOLING OF PB54+ IONS IN LEIR

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

LHC Luminosity and Energy Upgrade

Aperture Measurements and Implications

The Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory

Luminosity for the 100 TeV collider

Large Hadron Collider at CERN

LHC Collimation and Loss Locations

LEP PROGRESS AND FUTURE PLANS

LHC Commissioning in 2008

LHC Commissioning and First Operation

2008 JINST 3 S Main machine layout and performance. Chapter Performance goals

Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group

Status of linear collider designs:

Practical Lattice Design

LHC status & 2009/2010 operations. Mike Lamont

Longitudinal Dynamics

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

On-axis injection into small dynamic aperture

Raising intensity of the LHC beam in the SPS - longitudinal plane

2 Closed Orbit Distortions A dipole kick j at position j produces a closed orbit displacement u i at position i given by q i j u i = 2 sin Q cos(j i ;

Accelerator Physics. Accelerator Development

Overview of LHC Accelerator

First propositions of a lattice for the future upgrade of SOLEIL. A. Nadji On behalf of the Accelerators and Engineering Division

Status of the LHC Beam Cleaning Study Group

Status and Outlook of the LHC

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

LHC Run 2: Results and Challenges. Roderik Bruce on behalf of the CERN teams

Note. Performance limitations of circular colliders: head-on collisions

Run2 Problem List (Bold-faced items are those the BP Department can work on) October 4, 2002

Low Energy RHIC electron Cooling (LEReC)

SPIRAL 2 Commissioning Status

LEP Operation and Performance

Main aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5)

A Luminosity Leveling Method for LHC Luminosity Upgrade using an Early Separation Scheme

Plans for 2016 and Run 2

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

Der lange Weg zu 200 GeV : Luminosität und höchste Energien bei LEP

Construction Status of SuperKEKB

ELIC Design. Center for Advanced Studies of Accelerators. Jefferson Lab. Second Electron-Ion Collider Workshop Jefferson Lab March 15-17, 2004

Status of Proof-of-Principle Experiment of Coherent Electron Cooling at BNL

Accelerators. Lecture V. Oliver Brüning. school/lecture5

LHC ORBIT SYSTEM, PERFORMANCE AND STABILITY

NEXT GENERATION B-FACTORIES

Commissioning of PETRA III. Klaus Balewski on behalf of the PETRA III Team IPAC 2010, 25 May, 2010

Statusreport. Status of the GSI accelerators for FRS operation. Jens Stadlmann (FAIR Synchrotrons)

Plans for ions in the injector complex D.Manglunki with the help of I-LHC and LIU-PT teams

On behalf of: F. Antoniou, H. Bartosik, T. Bohl, Y. Papaphilippou (CERN), N. Milas, A. Streun (PSI/SLS), M. Pivi (SLAC), T.

Much of this material comes from lectures given by Philippe Lebrun (head of CERN's Accelerator Technology Department), at SUSSP, Aug

The LHC Collider. STOA lecture, Brussels, 27 th November 2012 Steve Myers Director of Accelerators and Technology, CERN

e + e Factories M. Sullivan Presented at the Particle Accelerator Conference June 25-29, 2007 in Albuquerque, New Mexico e+e- Factories

Lattice Design and Performance for PEP-X Light Source

Modeling CESR-c. D. Rubin. July 22, 2005 Modeling 1

Turn-by-Turn Beam Position Measurements at ANKA with LIBERA ELECTRON

ELIC: A High Luminosity And Efficient Spin Manipulation Electron-Light Ion Collider Based At CEBAF

+ EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN PS DIVISION. The CERN Antiproton Decelerator (AD) Operation, Progress and Plans for the Future

6 Bunch Compressor and Transfer to Main Linac

The Large Hadron Collider Lyndon Evans CERN

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

Emittance preservation in TESLA

Commissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department

Beam Loss Monitors, Specification

Physics 610. Adv Particle Physics. April 7, 2014

STATUS OF BEPC AND PLAN OF BEPCII

ERL FOR LOW ENERGY ELECTRON COOLING AT RHIC (LEREC)*

LHC Commissioning The good, the bad the ugly

LHC. LHC Crabs, Status. Brief Overview. Status of Technology R&D. Status of Simulations & Experiments. Rama Calaga RFTECH, Dec 2-3, 2010

PIP-II Injector Test s Low Energy Beam Transport: Commissioning and Selected Measurements

LHC. Construction Understanding first the commissioning. Prospects for

Luminosity measurement in ATLAS with Diamond Beam Monitor

HL-LHC OPERATIONAL SCENARIOS

LHC Upgrade Plan and Ideas - scenarios & constraints from the machine side

Simulations of HL-LHC Crab Cavity Noise using HEADTAIL

Accelerator R&D Opportunities: Sources and Linac. Developing expertise. D. Rubin, Cornell University

Higgs Factory Magnet Protection and Machine-Detector Interface

Status of the LHC Machine

Electron Cloud Studies made at CERN in the SPS

LEP 2 Energy Calibration and the Spectrometer

Run II Status and Prospects

COMMISSIONING AND STATUS OF THE DIAMOND STORAGE RING

D. Brandt, CERN. CAS Frascati 2008 Accelerators for Newcomers D. Brandt 1

What have we learned from the LCLS injector?*

Energy Calibration of the LHC Beams at 4 TeV

FCC-hh Final-Focus for Flat-Beams: Parameters and Energy Deposition Studies

Status of the ESR And Future Options

Beam Dynamics. D. Brandt, CERN. CAS Bruges June 2009 Beam Dynamics D. Brandt 1

Plans for CESR (or Life Without CLEO)

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

Beam dynamics measurement during ALBA commissioning

Challenges and Plans for the Proton Injectors *

Introduction to Accelerators

Muon Front-End without Cooling

SUMMARY OF RECENT HIGH LUMINOSITY EXPERIMENTS AFTER THE HERA-II LUMINOSITY UPGRADE AND FUTURE PROSPECTS

Transcription:

Status of LEP2 J. Wenninger, SL Operation for the SL division LEPC September 1998 Outline Optics and RF for 1998 Beam current limitations Injection and ramp Performance at high energy Conclusions LEPC/15-09-98 page 1

A low emittance optics After 5 years of operation with the 90 =60 optics (1993-1997) we have switched to a low emittance 102 =90 optics following a successful test at the end of the 1997 run. Main visible dierences & advantages : + : Smaller horizontal emittance/beam sizes. + : Achievable beam energy is 0.3 GeV higher. (;) : Poorer performance at 45 GeV. ; : Shorter bunches. Note : I will always quote BEAM energies. LEPC/15-09-98 page 2

More RF The 1998 RF system consists of : 272 (16 Pure Nb) SC cavities 48 Cu cavities! nominal total voltage of 2870 MV (SC RF gradient of 6 MV/m) The physics energy is 94.5 GeV : Energy loss per turn = 2.33 GeV The minimum RF voltage is 2600 MV for a horizontal damping partition number J x = 1.6. Loss of 0.6 GeV compared to J x = 1. RF margin : 1 Power Conv. trip (160 MV) 4% reserve LEPC/15-09-98 page 3

Cryogenic cooling power limitations The required dynamic cooling power depends on : the accelerating eld gradient E a : Q(E a ) = cavity Q-value P rf cryo E 2 a =Q(E a) the beam (\discovered" in 1996!) : Z( s ) 2 n Ib 2 I b = bunch current, n = # of bunches/beam, s = bunch length P beam cryo With the presently available cooling power, I b is limited to : Maximum I b ' 850 A (I tot ' 6.8 ma) with 2 beams of 4 long bunches ( s > 10 mm). The LEP cryoplants will be upgraded for 1999 to allow higher currents and gradients. LEPC/15-09-98 page 4

RF cable limitations Each 4-cell cavity has 2 pick-up antennas to sample the eld. The signals are used for cavity tuning... Unfortunately the port used to insert the RF antenna acts as a resonator for Higher Order Modes (HOM) induced by the beam (2-3 GHz). Consequences : Beam RF antenna RF cable Energy dissipation! contribution to P beam cryo (Bellows between cavities may also contribute) The well insulated antenna cable heats up and can be damaged by (too) high temperatures. Short bunches excite more high frequency HOMs! keep bunches long! LEPC/15-09-98 page 5

Antenna cable power Laboratory tests have been used to dene a limit for the power transmitted by the antenna cables : Cable Temperature (K) 600 500 400 300 Cable T limit Warm Cavity (measured) Cold Cavity LEP Measurement Power Limit 200 0 2 4 6 8 10 Power (W)! Maximum transmitted power = 8 W The power is monitored in the LEP Control Room for 2 RF cables. Critical parameters : Bunch currents Bunch length LEPC/15-09-98 page 6

Antenna cable damage and repair Antenna cable status : For RF modules installed in 1997 most cables were found \damaged" (modied electrical properties). 6 cables have been destroyed in 1998. 1 cavity has both cables destroyed, but it was recovered by tuning it on the forward and reected RF power! Fall-back solution! The next technical stop will be extended up to a maximum of 6 days for the RF group to test the replacement of the cables. This operation is delicate because the cables are inside the insulation vacuum. It is planned to replace all RF cables in the coming winter shutdown. LEPC/15-09-98 page 7

1998 Startup The LEP startup was smooth : 6th May : Circulating beam with the 60 =60 optics (problem with a SC quadrupole in IP2) 9th May : First beam with the 102 =90 optics 14th May : Z calibration run! 24th May 19th May : Single beam at 94.5 and 96.5 GeV 25th May : First physics at 94.5 GeV LEPC/15-09-98 page 8

Z calibration run The Z calibration run : Each beam had 4 trains of 2 bunches. The maximum bunch current was 250 A. L = 6 ; 7 10 30 cm ;2 s ;1 2.5 pb ;1 were delivered in 11 days. A large fraction of this period was used to prepare the RF system and optics for the high energy run. This modest performance was expected : The low emittance 102 =90 optics is not suited for physics at 45 GeV. Commissioning a dedicated optics for the calibration run would not have gained any time. LEPC/15-09-98 page 9

Injection and ramp Injection at 22 GeV : No major problems. All RF ON (530 MV, Q s = 0:133)! oscillating RF units (sometimes) Routinely accumulate I b 760 A (I tot I b = 870 A obtained with a single beam. Ramp : It took time to develop a ramp with good transmission and long bunches! = 6.2 ma) The ramp is now stable for the present currents. The bunches are lengthened by : { Keeping the wigglers on at higher energies. { Shifting the RF frequency by +100 Hz. { Tuning the RF voltage while maintaining space between machine resonances to avoid beam losses. LEPC/15-09-98 page 10

The (powerful) ramp Power transmitted by one antenna cable : Cable power (W) or Total Current (ma) 10 8 W Power Limit 8 6 4 Ramp Total Current 2 0 0 20 40 60 80 Time (minutes) The power is (anti) correlated to bunch length. The power uctuates from ramp to ramp for the same current ($ orbit). 8:5 W! BEAM DUMP (red once!) To push the current further we need to control the bunch length even better... LEPC/15-09-98 page 11

RF system at high energy The RF system performance was good : Many RF units can run at 6.3 MV/m. More margin! good for eciency. 6.5% of the lls were lost due to RF. All luminosity was delivered 94.5 GeV. In 1997 : 5% of the luminosity was delivered below 91.5 GeV (the target energy was 92 GeV). HOM couplers : a recent worry... Some SC HOM couplers show an increase of the outlet He gas temperature $ dissipation?! triggers RF trips (interlock) One HOM coupler quenches. Related to the beam (current). This \phenomenon" is monitored by the RF group! LEPC/15-09-98 page 12

Luminosity optimisation For head-on collisions : L = ni 2 b 4e 2 f x y L optimisation involves a lot of work on the beam sizes u (u = x y) : where : u " u 2 u = u " u + (D u ) 2 : optical (betatron) function at the IP. : beam emittance. D u : local dispersion, ideally D u = 0, not measurable at the IP (with good accuracy). : relative energy spread (' 0.17%). Assumes no coupling between the planes. LEPC/15-09-98 page 13

Horizontal beam size optimisation Optics : " x (102 =90 ) = 0:78 " x (90 =60 ) RF frequency +100 Hz (+120 Hz at end of lls) : Redistribution of the damping (Hor. damping partition number J x shifted from 1 to 1.6) " x! " x =1:6 Note associated energy shift of -0.17 GeV! 94.5 GeV! 94.33 GeV Squeeze x : 2 m! 1.5 m (May 29th) 1.5 m! 1.25 m (Sept 8th) Limited by momentum aperture and background. D x : negligible. LEPC/15-09-98 page 14

Horizontal In August the OPAL L increased to 10-20% above the average following a drift of x from 1.5 to 1.2 m. σ x (µm) 40 20 L3 ALEPH OPAL DELPHI 0-20 -40 β * 1.5m σ x = 185 µm 150 200 250 β * 1.25m σ x = 162 µm x : dierence of x wrt the average. Following this \accidental success" x to 1.25 m in all IPs. Day was reduced The main gain in performance seems to come (for the moment) in the second half of lls. LEPC/15-09-98 page 15

Vertical beam size optimisation Key parameter for the vertical plane : Orbit " y and D y depend strongly on the orbit. L is optimised empirically by nding a \Golden Orbit" using well chosen orbit correction algorithms. Golden Orbits need constant retuning. Optimum y ' 3:5 ; 4:5m. The coupling with the horizontal plane must be well corrected (solenoids). A strong beam-beam interaction at the IP can also blow up to beams. We actually have some evidence (specic luminosity, vertical beam size) of blowup. LEPC/15-09-98 page 16

Golden Orbits and dispersion For weeks the DELPHI luminosity was 10% low. was 10% larger in DELPHI and it was not related to... y The problem was cured on July 20th by a small orbit and D y change. Eect on the DELPHI L of the orbit and D y change : Luminosity (10 30 cm -2 s -1 ) 80 60 40 Vertical Orbit Change DELPHI L3,ALEPH,OPAL 20 0 16:00 18:00 20:00 22:00 24:00 Daytime LEPC/15-09-98 page 17

Performance at 94.5 GeV Operation at 94.5 GeV is very smooth. The 102 =90 optics is performing very well! Peak performance : Year L (cm ;2 s ;1 ) I b (A) Max. y 1996 3.4 10 31 520 0.040 1997 5.0 10 31 650 0.055 1998 7.4 10 31 740 0.062 Note : beam-beam tune shift y L=I b. Eciency (physics/total time) : 47% Contributions to the down-time : { SPS & CPS : 50%. { RF : 13%. {... Typical turn-around time : 70 minutes record time : 48 minutes LEPC/15-09-98 page 18

Approaching 3 pb ;1 /day! Best integrated luminosities : 2:9 pb ;1 over 24 hours 2:5 pb ;1 in a single day (00:00 to 24:00) Luminosity (10 30 cm -2 s -1 ) I tot (ma) E (GeV) 100 50 0 5 2.5 0 80 60 40 20 0 04:00 12:00 20:00 04:00 12:00 Daytime! maximum eciency of 80%! LEPC/15-09-98 page 19

The Beam-beam Limit Beam-beam interaction regimes, characterised by the maximum beam-beam tune shift max y : Below limit : L I 2 b ( y I b ) Above limit : L I b ( y I b, y = max y ) At 94.5 GeV the beam size increases slightly with I b (data from August). Spec. Lum (10 30 cm -2 s -1 ma -2 ) 11 10 9 8 Norm. to σ y at 700 µa 400 500 600 700 Bunch Current (µa) LEPC/15-09-98 page 20

Beam Lifetime The beam lifetime in collisions is dominated by beam-beam Bremsstrahlung : 1= L=I b y (1) The better the performance, the faster it decays! Lifetime (h) 50 40 Ramp, beam adjustment 30 20 10 Collisions 0 0 1 2 3 Time (h) Luminosity lifetime is =2 ' 3 hours. The typical ll length is 3.5 hours. LEPC/15-09-98 page 21

Backgrounds Baseline background situation is good. Periodic \background storms" : related to particles hitting resonances. Tune changes are the usual cure. With x = 1.25 m situation is more delicate. OPAL : O-momentum background due to poor vacuum in Cu cavities at the start of the run. DELPHI (ALEPH) : Most sensitive IP! Most sensitive to background storms. Related to the mask-protecting QS3/4 quadrupole collimators which cannot be closed as tightly as in IPs 2 and 6. LEPC/15-09-98 page 22

Conclusions 1998 \Hot" topic : antenna cables! Good ramps with high currents and long bunches were dicult to set up! The 102 =90 optics and LEP perform well. The integrated L should exceed 150 pb ;1. The future is in the hands of the LEP RF group... LEPC/15-09-98 page 23